Documente Academic
Documente Profesional
Documente Cultură
TABLE OF CONTENTS
ABBREVIATION AND ACRONYMS 1-7
DSEPHR DEMOGRAPHIC AND SOCIO- ECONOMIC PROFILE OF
HARARI REGION, 1-7
HARARI PEOPLE AND NATIONAL REGIONAL STATE STATISTICAL
ABSTRACT DOCUMENT, DECEMBER 2003EXECUTIVE SUMMARY 1-7
EXECUTIVE SUMMARY 1-8
1 INTRODUCTION 1:1
1.1 BACKGROUND INFORMATION...........................................................................................................1:1
1.2 JUSTIFICATION OF THE PROJECT......................................................................................................1:1
1.3 PROJECT OBJECTIVE.............................................................................................................................1:2
1.4 THIS REPORT...........................................................................................................................................1:3
2 THE PROJECT AREA 2:5
2.1 LOCATION................................................................................................................................................2:5
2.2 CLIMATE..................................................................................................................................................2:6
2.3 GROUND WATER RESOURCES............................................................................................................2:7
2.4 GROUND WATER QUALITY..................................................................................................................2:8
3 SOCIO-ECONOMY DEVELOPMENT 3:9
3.1 POPULATION PATERN...........................................................................................................................3:9
3.2 HOUSEHOLD SIZE..................................................................................................................................3:9
3.3 HOUSING................................................................................................................................................3:10
3.4 EDUCATION...........................................................................................................................................3:11
3.4.1 Traditional system of education.....................................................................................................3:11
3.4.2 Modern Education.........................................................................................................................3:12
3.5 HEALTH..................................................................................................................................................3:13
3.6 INDUSTRY..............................................................................................................................................3:14
3.7 WATER AND SANITATION...................................................................................................................3:15
4 EXISTING WATER SUPPLY SITUATION 4:16
4.1 SERVED/UNSERVED POPULATION THE MDG REQUIREMENTS................................................4:16
4.2 SOURCE..................................................................................................................................................4:17
4.3 TREATMENT PLANTS..........................................................................................................................4:17
4.4 STORAGES TANKS...............................................................................................................................4:18
4.5 TRANSMISSION LINES........................................................................................................................4:18
4.6 ON- LINE TOWNS.................................................................................................................................4:18
4.7 SERVICE RESERVIRS...........................................................................................................................4:18
4.8 DISTRIBUTION SYSTEM.....................................................................................................................4:19
4.9 PIPED CONNECTION............................................................................................................................4:19
5 POPULATIOON PROJECTION 5:22
5.1 GENERAL...............................................................................................................................................5:22
5.2 DESIGN PERIOD....................................................................................................................................5:22
5.3 SOURCES OF INFORMATION.............................................................................................................5:22
5.4 DESIGN POPULATION.........................................................................................................................5:23
5.4.1 Previous Consultants Design Projections.....................................................................................5:23
5.4.2 Satellite Towns...............................................................................................................................5:23
5.4.3 Detailed Kebele Level Growth Rates.............................................................................................5:24
5.4.4 Revised Design Projections...........................................................................................................5:24
5.4.5 HARAR CITY.................................................................................................................................5:24
5.4.6 Harar City Kebeles........................................................................................................................5:25
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 1
HARAR WATER SUPPLY AND SANITATION PROJECT
TABLE OF PICTURES
LIST OF TABLES
WWDSE
MWR
CECE
BECOM
1 EXECUTIVE SUMMARY
Harar city is the capital city of the HRS in Ethiopia. Due to the rapid
population aggregate growth rate estimated at 2.5- 3.5 percent per annum,
the old age of the existing water supply network, depletion of the water
source; the network failing to meet the demand by the population and
future development plans which opens the opportunity for investors to
invest in various industries in the city
Lake Alemaya, the town's principal source of water since 1960, lies
exhausted, no longer able to supply the pipes with even ration levels. The
Alemaya water treatment facility originally designed to serve a population
of 70,000. Annual deposits of close to 8,000 metric tons of silt have
compounded the problem reducing the lake's water capacity by
approximately 7,500 cubic meters per year. Unregulated irrigation, with
farmers pumping water to reach fields up to 12 kilometres away, has
depleted already strained resources even further.
The present project shall implement the Water Supply of Harar City & On-
Line Towns and villages of Oromia Region located along the new supply
main namely: Alemaya, Adele, Aweday, and Dengego.
The sources to be exploited are well fields in the Rift Valley, some 20 km
West of Dire Dawa, on the road to Hurso, near Hasseliso village. From the
groundwater level (around 1160-80 masl.) to the reservoir above Dengego
(at 2135 masl), in top of the 42 km of pressure main, there are 980m
difference of height. The distance from the well fields to Harar’s main
reservoir R6 is 71 km.
DEMOGRAPHIC EVOLUTION
The demographic evolution of Harar City & On-Line Towns and villages of
Oromia Region that are included in the Water Supply Project is based on the
national Census conducted in 1994 by CSA and the forecast by DSEPHR,
2001 & 2003.
For Harar City, a varying population growth over the project area was
applied, in order to take into account the development of the modern part
of the city of the outer sectors of the town. The review of the localities of
Oromia Region: Alemaya, Aweday, Adele and Dengego, is mainly based on
the December 2003 document.
Chapter 5 deals with the Demographic Evolution of Harar City Harar City &
On-Line Towns. Find detailed calculations in Annex 1.
The topographic survey of the whole Supply Main shall be conducted at the
beginning of the civil contract works.
O&M equipment (see chapter 10) is included in the tenders for
Electromechanical Equipment and SCADA System, this material being
dependent of the type of equipment purchased.
WATER STORAGE
At the 4 main pumping stations twin 500m3 collection tanks (wet wells) are
proposed, a total of 8 units. These tanks are needed for smooth operation
of the pumps. The Consultant recommends to construct all 8 tanks during
the first phase of construction. The rational explanation is given in chapter
4.
The projected capacity of the distribution reservoirs by the previous design
is acceptable for daily compensation of consumption, at the condition that
an efficient SCADA System (Telemetry) is guiding the operation.
In case of major interruptions however, additional storage capacity is
needed. The Consultants recommend therefore to construct an additional
reservoir in Harar City and to increase the capacity in Dengego in the near
future.
WATER TREATMENT
WATER DISTRIBUTION
The distribution of all concerned localities has been analysed. The general
layout is based on the respective urban development plans. A topographic
survey of the distribution of Alemaya and Aweday has been made, along
with a certain number of GPS points.
Sites for public fountains have been individuated, but those of the Oromia
Region need official confirmation. All sites for installations and reservoirs
have also to be given officially to the project.
ADMINISTRATIVE COMPOUND
The sites in Harar City have been identified. For the sites in On-Line Towns
official confirmation has not been received. This sanitation with water
supply linkage is appreciated by the local population, as most do not have
private showers.
2 INTRODUCTION
Harar City is one of the oldest towns in the country. The water supply to
Harar first commenced approximately one hundred years ago with the
capping of Sophie Spring and the laying of gravity main to convey water to a
reservoir located in old part of the town. The system was expanded during
Italian occupation of 19361 to 1941 by the capping of two additional springs
and construction of four service reservoirs. In 1983, the water supply has
been further expanded with construction of Lake Alemaya intake and
treatment plant with water being delivered to the newly constructed Aboker
reservoir. Since then Lake Alemaya has been used as the sole source of
water supply for Harar, Alemaya, Aweday and Hamaressa.
In the past few years, Harar City has experienced a fast population growth
and with the development of the town the demand for piped water supply
has also significantly increased, as a result the existing Alemaya source
could not satisfy even the existing demand with out including the new
developments. The amount of water in the lake has decreased to such an
extent that it is no more able to draw water from the lake and supply the
town. The reason for the fast decrease of the level of the lake is mainly due
to silting, and the increasing usage of the water by the surrounding farmers
for irrigation.
In 1983, a consulting firm GWE had studied as part of the Feasibility study for
34 Towns Water supply Project. This report proposed that the future source to
be ground water from Lake Alemaya basin & impoundments on the
Hamaressa & Maya Gudo rivers, in addition to the existing Alemaya intake,
however, it was not implemented.
1
Great Harar CityWater Supply Project Design Report, WWDSE,2002
Again, in 1994, a consulting firm Sir Alexander GIBB studied in depth the
water supply of Harar City and On-Line towns, in the package of Twelve
Towns water supply and Sanitation study, entitled feasibility/ preliminary
design report Harar. In this report, a Dam, at Maya Gudo for first phase and
at Errer for second phase was proposed to be a source of water supply. In
addition, the rehabilitation of existing Alemaya treatment plant & installation
of high lift pumping station on Alemaya Lake to be used in the first phase
were also proposed. However, this was also could not be implemented due to
high investment cost, which was estimated to be Eth.Birr 834 million.
The problem of potable water in Harar City, which has been persisting for
more than a decade, has now reached a critical stage. The Harar City water
supply has virtually collapsed after decades of poor maintenance and high
population growth.
The objective of the Harar2 Water Supply and Sanitation project is to provide
a better access to water supply and sanitation services to the population of
the city and nearby Alemaya, Aweday, Adele and Dengego "through
improved water production, distribution and sanitation."
To this end, the project will:
I. involve the "rehabilitation and extension of water supply and
sanitation systems in high-density low-income areas."
2
Harar City WSP Fund, Water Resources Equipment/Services Abidjan, 4 September 2002
This ADB-funded contract is due to last three years and comprises the
following services:
a. Review and revision of the existing drawings, studies, designs,
projects in various sectors (water, electromechanical facilities,
sanitation, civil works, etc.).
b. Detailed designs and preparation of tender documents for the
selected projects.
c. Administration of contracts and construction supervision.
d. Training in operation and maintenance of staff of the Harar City
Water Supply and Sewerage Services Authority.
e. Preparation of terms of reference for sanitation study, institutional
support component and audit services.
In this report based on the analysis options and recommendations, the water
supply for Harar City and On-Line Towns up to the year 2025 has been
reviewed.
3.1 LOCATION
Harar City
Harar City is the Administrative center of the Harari Region and one of the
oldest towns in the country.
Harar City lies 51 kilometres to the southeast of Dire Dawa. It is located in the
eastern wall of the Great Rift Valley looking over the vast Danakil desert to
the north, the cattle rich savannas to the south and fertile lands of the Harar
City Mountains to the east. It lies between two rivers, tributaries of the Errer,
on the southern edge of a vast plateau. The surrounding mountains divide the
Great Rift Valley from the plains of the Ogaden. The elevation of Harar Town
ranges between 1754 to 2098 m.a.s.l..
THE WATER
SUPPLY
PROJECT AREA
On-Line Town
These are (formerly notified as satellite) town and villages were lately
incorporated into the Harar water supply and sanitation project based on the
Harari and Oromia regional states negotiation and agreement to include
them in the project WWDSE’s 2002 report has included these satellite town
and villages with out any detail study with limited water stand point supply..
The relative location to the water source for the supply system of Harar city
coupled with the acute shortage of drinking water were the main reasons for
these areas to be included in the Great Harar water supply system.
Alemaya is 21 km and Adele 5 km, are north of the Harar city on the main
Harar-Diredawa Asphalt road. All towns are located within the East Harerghe
Zone of Oromia Regional State. The Lakes Alemaya (472 ha) now drained and
Adele (300 ha) are in Haramaya Woreda.
Aweday is north of the Harar city on the main Harar-Diredawa Asphalt road.
Dengego Village: - It is located at the highest pick on the road from Dere
Dawa to Harar along which the transmission main to be laid.. It is about 23
km from Dere Dawa where the proposed 2000 m 3 collecting reservoir is
located.
Adele Town: - Adele is a comparatively smaller rural town than other On-Line
towns. The town is located at about 9.5 Km on the right side of the main road
from Dengego to Harar. Further, the town is stretched on the left and right
side of the road to Gara Mulata town.
All towns are located within the East Harerghe Zone of Oromia Regional State.
Geographic location of each town is stated in the table 2.1 above.
3.2 CLIMATE
Climate is the average state of the atmosphere over an area during a period
of time. Climatic elements include rainfall, precipitation, humidity,
temperature, sunshine, wind and frost, fog, lightning, thunder, flood, drought
etc. Climate influences all human endeavours and thus it is an important
resource.
There is no available weather station data that describes the specific climate
condition of the Hasselisso area, where the deep well exist. Howeveer the
Diredawa station with similar altitude and topography is believed well to
represent the Haseliso area as presented below in table 2.2. eve though the
record almost incomplete, it will be helpful for the various pumps generators
and remote system equipments specification.
The hararmeda weather station collects data useful for and the vicinity,
however the frequency of the record within the day and for each month one
day for a montth and upto two months for a year. Thefore the information can
helop only to get glimpse of the area and canot be used for engineering
design and the various important data are Harar is very well known and
admired for its healthy and favourable weather temperature that enabled
development of the various medeterian and unique fruits and these together
with its weather found to be one factor for the exodus of migrants and settles.
Dire Jara well field is found approximately about 20 km west of Dire Dawa
town between longitude 41o42’-41o47’ and latitude 9o32’-9o36’. The well field
is located at the foot of the eastern part of the Ethiopian rift valley
escarpment in Kulf Gosha river basin. The streams around the well field are
flowing from the escarpment south-north direction to the plains.
The surface water catchment of Kulf Kosha River is about 125 km2 with
elevation varying from 2350 to 1220 m.a.s.l.
The Dire Jara areas have high groundwater potential. At Dire Jara well field,
totally 17 boreholes of a real distribution were drilled. Out of the 17 wells, 12
boreholes were found productive and recommended for Harar City water
supply source.
4 SOCIO-ECONOMY DEVELOPMENT
Harar City
According to the result of the recent population census, (2005) the total
population of Harari region is indicated to be 188,952 of which the
percentage share of female and male is 50%. The residents of Harar City are
estimated to be 116,924, while the rural residents number 72,028.
On-Line Towns
Population figures are based on CSA, 1994 census and detailed below.
Harar City
According to the results of the socio-economic baseline survey conducted the
average household size of the sampled households is 4.9 and 5.1, Rural town
and rural respectively. Therefore, the average household size is assumed to
be five similar to the household size of the most rural house holds else where
in Ethiopia.
T able 3.2 Housing Units and Population Growth from 1984 to 1994On-Line
Towns
For the On-Line Towns of Alemaya and Aweday, current population and
housing figures were obtained from the Municipalities. The main source of
information is the Population and Housing Survey 2003, conducted in
September 2003 by the Central Statistics Authority, Harar City branch office:
Table 3.3 Population and housing number for the year 2004.
4.3 HOUSING
Harar
Most of the housing units are in a poor condition, and living standard of most
of the households of the Woreda is relatively low. The field observation
revealed that most of the buildings are masonry walls and corrugated sheets
roofs houses are
Table 3.4 Urban Housing Units by Type of Building, Harari Region, 1994.
The need for new housing units increasing each year as the new construction
do not met the demand of the population. The urgent need for housing units
is demonstrated by the number of development plans and housing
associations.
4.4 EDUCATION
4.4.1 Traditional system of education3
Traditional institution for education that have enabled the ancient Harari's to
attain it's status of being center at learning in the horn of Africa are
attributed to traditional institution as 'Qurangey' and 'Kabir' Gaar! It is known
that there were about 2-3 Quran Geys in every zone (i.e. in 5 gates) and
3 Harari people national Regional tate Conservation Strategy of Harari Region volume III : Resource Base And Its Utilization
shrines in rural area which comprises about 10-15 and almost in all peasant
villages in Hundene had at least one. All the holly places, Shrines like Awe
Umer, Ziad, Sheike Ibrahin in Miayay; Awe Jailan, Awe Sofi yahya etc... Were
all centers at learning for the rural area.
Higher Education , there are three schools (Nursing School, Teacher's training
institute and Technical School built by Menschen für Menschen Foundation.
The Primary School (7 - 12 years) in the region there were about 18,823
children (11.7 percent of the total population) of primary age in medium
variant projection of CSA. This figure is projected to reach 42,947 and 46,746
children of primary age in the year 2025 and 2030 respectively.
4.5 HEALTH
The coverage and quality of health service together with other development
components has a key role in sustaining a given society.
Table 3.11 Harar’s Hospitals and Health Centers:
4.6 INDUSTRY
The average house in Harar City as per the 1994 census was: non-storied,
attached or detached, with one to three rooms. Sanitation, if existing, was
based mainly on latrines.
The Objective for water (Goal 7, Target 10) 4 is to: "Halve by 2015 the pro
portion of people without sustainable access to safe drinking water” . The
international community added a new goal of halving by the year 2015 the
proportion of people without access to basic sanitation.
4
UNDP 2003
5
United Nations 2002)
5.2 SOURCE
Alemaya Lake, 21 km from the town served as a raw water source until its
level lowered to the minimum in February 2004. Over exploitation of this
precious resource by uncontrolled irrigation of chat fields has decreased the
depth of Lake Alemaya from 14 meters in 1980 to 1.8 meters. Presently the
intake of the treatment plant is dry most of the year and the city gets its
drinking water from wells nearby the lake, as does Harar Brewery and
Alemaya University.
Pre-chlorination:
No longer used as the dosing pumps are out of order. This was required due
to the pollutions and contamination, algal growth and high pH of the Lake
Alemaya Water.
Clarifier:
it is of the Degremont pulsator type. The pulsator control equipment has not
worked properly for the last 13 years. As originally constructed, aluminium
sulphate was added directly to the raw water main by injection, but as with
the pre-chlorination unit the system is no longer functioning due to the
failure of the dosing pumps. As a substitute, aluminium sulphate was added
via a bucket/drip system, which is clearly inadequate. To improve the
situation HTWSSA established a manual gravity dosing system, which is also
inadequate. Because of the failure of the pulsator control system and the
poor aluminium dosing system, it is noticeable that the carry-over water is
still very turbid.
10 m long and 3 m wide with 1 m high which has three compartments each
having 21-baffle wall to pass water through this chamber, this will give time
to mix aluminium sulphate properly and make flock. This has improved a
little bit the quality of water but not as the desired level.
From the 200m3 tank water flows by gravity to Harar City via a 350 mm/300
mm/250 mm diameter steel pipeline having a total length of approximately
14,1409.8 m (5285.5m/5285.5m/300m).
There are five water service reservoirs, which are in order service as refered
in table 4.2.
Two other reservoirs, Ginella Alta and the old town reservoir, have been
taken out of operation due to their poor condition. Of the above listed
reservoirs only the Aboker terminal reservoir and the Alemaya reservoir are
in a reasonable condition. Both these were constructed in concrete whereas
the others are masonry build.
The Aboker terminal reservoir is fed directly by the transmission main from
the Alemaya treatment plant while the Tassinari, Neguscira and Ginella Bassa
reservoirs are located within the distribution system and are linked by a
series of old asbestos cement pipes. The Alemaya reservoir is connected to
80mm diameter galvanized inlet pipeline from the break pressure tank on
the Alemaya to Aboker transmission main.
The Harar City water supply system consists of over 38,500meters of various
diameters ranging from 300-25mm in its design life.
The system was characterized by high rate of leakage amounting to 40% and
contamination due frequent breakage aged pipes. Except in certain key
locations such as the service reservoirs, no gate-valves, air-release valves or
washouts could be identified. Many of the distribution lines have been laid at
a shallow depth, as little as 200 to 300 mm. In some cases, storm water
erosion has caused sections of pipeline to be exposed. All the 13 water
points require standard maintence to bring to the new system service level.
The present major customer type in Harar City is private connection given on
covering 50% of the system.
Harar City
Table
4.5
Aweday Town Piped Water Connections October 2004:
6 POPULATIOON PROJECTION
6.1 GENERAL
The population forecast of this study bases the 1994 Population and Housing
Census of Ethiopia. For all zone, sub zone and Kebele level projections CSA
1994 census report are the bases for the design of this report.
The consultant has a strong feeling that a design life of 15 years is short,
bearing in mind that the construction speed is not expected to be very fast
due to conditions existing in the project area. The consultant would
recommend a design life of 20 years with a design horizon 2005 – 2015 as
phase one and 2015- 2025 as phase two taking in to consideration the pre-
tender and the construction period of the project.
The initial design of Harar Water Supply and Sanitation Project was
conducted in 1993-94 by Alexander Gibb, with a population forecast based
on the specific situation due to the aftermath of Siad Barre's downfall in 1991
in Somalia resulting in migration of Somalians to the east Harerghe zone. As
can be seen from the following table, this estimation was very high.
6
Report by WWSDE 2000
Population growth rates per Kebele are not available in the CSA analysis. The
design report of WWDSE of 2000 has adopted the same growth rates for all
Kebeles, without distinction between the fully crowded and walled city centre
“Jegol” and outer development areas. If as a whole the forecast is
acceptable, its repartition over the city area has to be reconsidered.
The total population of urban area derived from 1994 census is said to be
72,028, where as the areas of the Harar town is said to be 1,720 ha and the
population density is 41.87 people/ha. Based on CSA the following growth
rate and projected population have been tabulated. The urban portion is
meant fully to Harar city and will be used consistently throughout the design
process.
Table 5.3 Population Growth Rates and projection for Harari Region/1995–
2030 Percentage, MV
Harar city (Jegol) is one of the eight attractions declared as world heritage by
UNESCO.
In 1994, the population of Jegol was 26,324, 1/3 of the total population of the
town. Presently it is estimated to be 34,000 inhabitants and this number
expected to remain constant or decrease due to the following reasons:
a. presently richer wholesale and retailers now residing in the
historical centre are expected to build and shift their dwellings in
new development zones. The business area will remain to be where
it exists now at the heart of the walled town.
b. Younger generation are also expected to follow the same trend,
when got married.
c. Elder persons remain in Jegol, equipping and renewing their houses,
and this will not affect the density of the design population.
7
This evaluation of development of each Kebele was introduced by the present design review and represents a main difference with the
previous design. It considers that the future development of Harar City is differentiated for each sector. While the overcrowded historical city
centre will stabilise and improve its historical character and its attraction for tourists, maintaining as well its
commercial vocation, outer development zones will grow progressively
The population density for the walled town (Jugal) which is too high for the
area. Compared to the density of the town, which led to the degradation of
cultural heritage and creation of sanitation problem. Thus it needs proper
attention and formulation of appropriate policy to restore the natural
resource.
In Kebele 1, 2, 4 and 5, which cover parts of Jegol, but include also zones
outside the city’s walls, a moderate development outside the walls shall be
taken into account.
Harar’s distribution system was subdivided by the Design Study into seven
pressure zones (zone 1 to 8, zone 4 does not exist). This system, based on
maximum pressures, is maintained. The population of the seven pressure
zones of Harar’s distribution system is based on the Kebele forecast
presented on table 5.9. The total base-population of each Kebele is detailed
in table 5.8
Table 5.7 Summaries of Zonal and Sub-Zonal Population & Density
For the On-Line Towns of Alemaya and Aweday, current population and
housing figures were obtained from the Town Administrations. The main
source of information is the Population and Housing Survey 2003, conducted
in September 2003 by the Central Statistics Authority, Harar City Branch
office. The projection is made with growth rates similar to those of Harar City
For Aweday the base value is the revised value of 2004, that is 12000
inhabitants.
For Aweday we note a drastic change between the figures of 1994 and the
new ones. This is due to the recent rapid growth of the locality, which has
developed as the main production and trading centre of chat.
The Aggregate population of Harar City & the On-Line towns is presented in a
summary table.
More detailed tables showing the forecasted development in the towns and
the repartition per Kebele are reported in Annex 1.
7 WATER DEMAND
7.1 GENERAL
Estimating water demands (i.e., average day, maximum day, and peak
hourly demands) involves consideration of a number of factors such as:
climatic influences, socioeconomic influences; degree of recreational or
seasonal uses and historic water uses for the development or the area, For
the historical city centre Jegol an important portion of mixed domestic +
commercial water demand is added to the consumption of the projected
population of that part of the town.
The water demand for Harar City and On-Line Towns belonging to Oromia
Region: Alemaya, Aweday, Adele and Dengego, cannot be based on passed
experience, as since over ten years these localities experience a water
shortage. The present situation of housing, industries, hospitals, schools,
military camps and other institutions are considered. Future developments,
like the partial implantation of Alemaya University, small scale industries and
housing associations development plans have been taken into account. The
respective water consumptions are calculated for each sub-zone. The total
water consumption is the sum of direct human consumption plus all other
water needs.
Table 6.1 Harar Town Water Demand Statistics
Table 6.2 Harar town Water Demand Statistics (Continuation of Table 6.1)
The high project cost coupled with operation & management cost, the price
per m3 of water at delivery spot might not encourage users to take water
frequently. Specific consumptions will therefore be rather lower than other
same level Ethiopian cities/towns.
Table 6-3 Per capita water demand by residential categories in major cities of
Ethiopia, (Mesfin 198810).
The urban structure of Harar Cityis of a mixed type. High income housing, a
very reduced area, is located next to informal dwellers. Therefore the
analyses consider major dwelling areas with medium, intermediate and low
10
His Excellency Ato Mesfin Tegene Former, Deputy Minister of WRM
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 34
HARAR WATER SUPPLY AND SANITATION PROJECT
Table 6-4: Average Per Capita water consumption and house occupancy in
major Ethiopian Cities (Mesfin 198811).
The main modes of service considered especially for the On-Line (online)
towns under this design review are; Public tap users – (PTU) Yard tap users –
(YTU) House tap users – (HTU) and Non-users.
At present, for washing and cleaning, alternative sources of water are used,
especially rainwater harvesting during the rainy seasons, springs in certain
parts of Harar City and wells in Aweday. These sources will certainly be
maintained.
11
Ditto,
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 35
HARAR WATER SUPPLY AND SANITATION PROJECT
On-Line Towns
The forecast envisages decrease in public tap users on the assumption that
more and more people will have yard connections. Due to this a substantial
increase of yard connections and house connections is anticipated.
Water requirements in these cases depend on such factors as the use of the
building, number of employees and/or residents, number of visitors and
other users.
The figures in Table 4.6 are used as a guide for estimating water
requirements for Commercial and Institutional establishments under this
design review. The Water Demand Analysis was made in straight
collaboration with the Urban Bureau and local offices.
Out of the average water demand of each zone and-sub zone, the total water
demand is calculated, introducing the unaccounted quantity of water for
losses in the system, street and sewer flushing, operation and maintenance.
This unaccounted quantity of water is introduced with 15% for the year 2015
and 25% for 2025.
7.11 PEAKING
FACTORS
The incidence of varying peak hour factors for Harar City is not very
significant: taking a uniform peak hour factor of 1.6 increases the peak hour
consumption of the City only by a 3%.
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 40
HARAR WATER SUPPLY AND SANITATION PROJECT
NB.
For On-Line Towns the peak hour factor is taken to be 1.6 for all activities.
12
For detail of the demand calculation refer in annex III
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 41
HARAR WATER SUPPLY AND SANITATION PROJECT
The respective water consumptions are calculated for each sub-zone. The
total water consumption is the sum of direct human consumption plus all
other water needs. For the historical city centre Jegol an important portion of
mixed domestic + commercial water demand is added to the consumption of
the projected population of that part of the town. Specific and typical water
consumption figures are annexed
The water demand in zone 5 includes an estimated three hour fire fighting
and 200 m3 emergency water reserve in addition to the zone domestic and
non-domestic demand. As presently most connected
houses and public water taps have their own water
tank, generally sufficient for a 24 to 72 hours reserve,
the actual peak factor is lower.
Special consideration was given to the Babile Mineral Water Bottling Factory,
the abattoir, Fuel stations, future industrial zone, future Alemaya University
Medical Faculty campus and the existing small scale industries where
demand variations are not similar to other areas.
7.18
The main considerations and principles in the review and designing the
system have been:
Source
All ground water from Dire Jara well fields shall be exploited to the
maximum, i.e., 43,500 m3/day of the maximum day demand of the
second phase.
Population
All basic data required for the preparation of forecasts by WWDSE in
their 2000 and September 2002 report have been thoroughly reviewed
and those found to be outdated were updated with current and latest
data.
As much as possible, design factors specific to the actual project
demand and population forecasts shall be adopted as general
standards for the different projects will have some drawbacks and
mostly give a result of over design of some or all areas and the vise
versa.
Demand
the per capita consumption in the different residential categories and
different sub-zones factors for the preparation of the forecasts of the
water demand is presented as in the following tables and will be
adopted in the design of the water supply distribution system of Harar
town.
The domestic and non-domestic demand calculation or factors used in
the previous report were not specific to zones and sub-zones of the
project rather than the general norms, applied in feasibility /project
general inception report.
For almost all data in addition to the current and latest information and
data collected from the concerned government institutions and local
agencies.
Pressure zones
The necessary pressure, i.e. at least 6 -10 m pressure during the peak
hour demand in all points of the distribution system is provided by the
200m3 break pressure tanks in each zone that are also serving as
storage tanks.
Calculation of design parameters for different pressure zones shall be
done separately as conditions in the different zones and sub-areas
differ as well.
The main criteria adapted for the design of the water supply system are:
Design period is 20 years with design horizon from 2005 to 2025
including construction period of 2 years.
Drinking Water Quality Standard is the WHO Guidelines,
Max water pressure for static water head is 75 meters,
Min water pressure is 6-10 meters,
Min velocity is 0.4 m/sec, and
Max velocity is 1.5 m/sec.
Scheme components like Collection Tanks (wet wells), reservoirs and
conveyance units will be designed as per the accepted MWR standards.
In general, the pipe material for the distribution network will be PVC, while in
the areas where there are rivers or road crossing and areas with pipe
diameter greater than 300 mm shall be ductile cast iron (DCI).
Harar City
Public water taps in certain parts of Harar are still a social need, as a
majority of the population is not connected to piped water due to low
income. Once the new water supply will be realised, a very aggressive policy
of connections has to increase drastically the number of house connections.
During the design review period, a certain number of big water tanks have
been installed in Harar by the Iranian Cooperation, in addition to the existing
public water tabs. Therefore, the number of needed public fountains is Harar,
list of which we have received from the Municipality at the beginning of
December 2004, is reduced to 14. The existing average daily per capita
supply provides a guide to the type of connections to be provided in a
scheme.
On-Line Towns
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 45
HARAR WATER SUPPLY AND SANITATION PROJECT
In this case, water points are the primary choice in the first instance. House
connections are expected to increase in number over time making advisable
to design for mains even though water points are provided initially.
Layout
Pipe distribution networks in most zones are designed to be
constructed only in the first phase of the project to economically utilize
the investment loan in its grace period.
Network analysis covering minimum and peak hour consumption in
both design phases are carried out independently for each pressure
zone.
The layout of the revised pipe network, which includes all extension
areas, has also been prepared based on the latest urban development
master plan following the road network.
Though it is very difficult to make looped distribution system,For Harar
city effort has been made to avoid dead end water supply network,
however, at some places, due to the ragged topography, the system
left dead ended.
Nodal Demands
In the simulation of the pipe network system, the demand at each
node was calculated or updated based on newly calculated nodal
demands as shown in Annex-D.
In this review work, the nodal demand is further adjusted based on
specific Sub-Zonal demands distributed to each supply nodes
according to specific demand pattern in each sub-area for the phase I
and II of the project.
Peaking factors
Design Aid
Hydraulic analysis of the whole water supply system has been
controlled by the “WaterCAD 6.1” by HEASTAD METHODS, computer
aided soft ware. However, the initial design calculations were carried
out based on the Hardy-cross analysis. The equation utilises the
iteration principle to calculate the flow through a pipe of given
characteristics under defined head loss and flow variation conditions.
The pipe sizing procedure by manual calculations using the Hardy-
cross method has not been done at this time. The soft copies of the
previous design have been used as an input data for the analysis.
Pre-selection of pipe diameters was done using the Hazen - Williams’s
equation.
The distribution main is designed to cater the peak hourly demand of
year 2025.
Results of the design analysis with Water CAD software are given in
appendix 6. Forty (40) Iterations were made and the unbalances flow is
0.000015 L/s.
Results of the computer calculations are given in Appendix 7.
8.3.2
The system was designed such that during the peak hour, the pumps would
be delivering the maximum daily demand, while the additional demand
requirement would be balanced by the reservoirs. Although this situation was
achieved (Appendix 7A), the provided pipe network do not optimise the
capacities of the reservoirs. Ideally, the larger reservoir (4000 m3 at node N-
300) should be supplying about 67.67 % of the additional demand (about
75.92 L/s).while the smaller existing reservoir (R-5), 1000 m3 at nodes N-
150) should be supplying 16.67% (about 18.70 L/s). In the provided system,
the smaller break pressure tank provides only 16.67% of the additional
demand during the peak hour.
During minimum consumption i.e. at night, both the two reservoirs and the
break pressure tanks should be filling. Generally, it should be possible to
arrange the pipes to achieve these desired situations.
8.3.4 Velocities
8.3.5 Pressures
Are generally kept under 6 bar for distributions. They never overpass 10
bars. Where pressure is higher than 6 bar, a reducer is foreseen at house
level.
Pipes in zones with higher pressures than 7-8 bar are foreseen in pressure
class 16.
Minimum pressures are generally over 1.5 bar, exception made for some
extreme cases.
For more details, see Annex 2 of this Volume 1, and Volumes 3 and 4.
Please find in Annex 2 detailed figures and calculations of the water
demand of the city and of Harar City & On-Line Towns and in Volume 3 the
respective analyses by WaterCad.
The minimal diameters of the pipes take into account fire fighting
and the need of changes of flow during repairs.
Each loop of the system is separated by valves to allow works or
repairs on it without interruption of the supply to the other parts of
the system.
The number of valves is minimised for economical and practical
reasons. Valves which are not operated every 3 months remain
easily blocked
Wherever there is power from EEPCO, pumps will be driven by electric power
from transformer. A standby generator will be installed for power supply
during electric power failure.
The power needed to start the pump is assumed to be 1.75 times its steady
state value. The diesel generator (standby during power failure) is made to
have the same rating as the transformer.
The operation of break pressure tanks, reservoirs and the whole system must
be monitored with a remote control telemetric system. The operational
problems experienced with use of float valves in such type of facilities is
unbearable and therefore having considered the distance between each unit
and the design to control from one center will derive us to the use of a
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 49
HARAR WATER SUPPLY AND SANITATION PROJECT
Typical Uses:
When lightning, gophers and excavating shorten wire life
Where installation of conduit and wire is too expensive or
impractical
When obstacles such as parking lots, roads, or ponds must be
crossed
When there is too much electrical interference in the area
Advantages
Eliminates man-hours needed for on-site data collection and/or
visual inspections
Monitors and controls remote processes from a single master
location
Generates reports to meet compliance issues
Saves time and reduces maintenance/construction costs
Replaces buried cable systems
Easy to configure & use
Future expandable
Gate valves:
are used to subdivide the distribution system, allowing operators to
allocate between areas and to shut down sections of the system to
facilitate maintenance or cones and sub zones conduct repairs.
All valves are kept open and enclosed in safe appropriate box.
Washouts:
should be provided at low points in the distribution system to enable
mains to be drained or maintenance and repair purposes.
Air Valves:
air valves are not required in distribution mains as the air collected
will be vented through house connections or water points.
For transmission pumped/gravity mains double air valves are to be
provided at all high points with respect to the pipe profile and
hydraulic gradient and at a maximum spacing of 2000m. .
Flushing Device:
dead ends if any shall be provided with an acceptable flushing
device with sufficient flushing velocity usually greater than in the
water mains.
It is recommended that the dead ends be equipped with a proper
flushing chamber for regular cleaning of the stretch so as to avoid
the stagnation of water in the pipes.
No flushing device shall be connected to sewer nor be subjected to
flooding o plugging
Private Connections
The private connections should not include cast iron surface boxes
since most of the roads are not asphalted.
The corporation cock will therefore be generally buried in the
ground except in places where concrete manholes will be built.
The tees currently used for the connection to the main pipe will be
replaced by saddles that will allow a connection under pressure.
Water Meters:
Given the high value of the water delivered by pumping to Harar,
precise volumetric water meters are proposed.
System Appurtenances
Where appropriate, at low nodes, roads & river crossings, flush
outlets and other necessary system appurtenances shall be
provided.
At each node, valves with the standard surface boxes shall be
provided.
all site spots with Major fittings/ other facilities or junction points
between two pipes with different nominal pressures, materials and
sizes should be clearly marked on the ground using concrete blocks.
Such provisions are quite helpful for operation, maintenance and
further extension purposes.
It has been found that the existing pipes are generally either
inadequate or over designed. There was an intention to utilise the
old pipes in some parts of the new network. However, it has been
assumed that the useful life of the old pipes in the existing network
has almost expired. It is therefore recommended not to consider the
re - use of these pipes. Future additional water assumed to come
from the additional wells in Hurso area.
The existing parts of the present water supply system except some
newly built in Alemaya town and the tertiary house connection
pipes in Harar city will not be fully considered as part of the new
distribution network, as most of it is already deteriorated due to old
age.
The Alemaya, Aweday, Adele and Dengego water supply pipe
systems are included in the new system.
The reservoir in Harar town, Alemaya, Dengego, Aweday and the
transfer main and distribution lines are designed to meet the year
2025water demand of the great Harar.
The Hasseliso and all booster pumping stations and the
transmission line from Hasseliso - Dengego and Dengego - Harar
town are designed for the maximum yield of the Dire Jara aquifer,
i.e., .
The pumping systems is so designed that they are if necessary,
capable of pumping maximum daily demands which means; Harar
town and all the satellite towns' demand beyond 2025.
The reservoirs and break pressure tanks are designed to balance
the daily variations assumed to require a reservoir capacity
equivalent to about 30% of the maximum daily consumptions.
For fire fighting purpose for the city of Harar, a reservation of 200
m3 has been made in the existing 1000 m3 capacity break pressure
tank and reservoir designated as R-5 in addition to supplying Zone 5
and storage
Systematic reviews as shown in table 7.1 indicated that better water and
sanitation is associated with decreased diarrheal morbidity, improved
nutritional status, lower childhood mortality and less morbidity from
ascariasis, guinea worm, schistosomiasis, and trachoma.
13
Source: Esrey, S.A. et al (1991). “Effects of Improved Water Supply and Sanitation on Ascariasis, Diarrhoea,
Dracunculiasis, Hookworm Infection, Schistosomiasis and Trachoma,” in WHO Bulletin, 69(5): 609-621.
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 54
HARAR WATER SUPPLY AND SANITATION PROJECT
9 PROJECT COMPONENTS
Details dealing with hydrogeology, ground water resources and drilling are
presented in a separate report.
The previous Design has proposed two wet wells of 500 m3 each, one to be
constructed during Phase I, the second for Phase II. However, the need for
the second 500m3 tank is crucial in Phase I, because the differences of flow
between pumps are bigger. Details of wet well accommodations are stated in
the table below:
During the initial phase of the project, most of the time the running of one
pump in pumping station PS 1 (CT) will be sufficient. however for the reasons
stated below Two wet wells of 500 m3 can be considered as a minimal
requirement. Recommendation of two wet wells:
o The best way to operate electrical driven pumps is continuous
operation without interruptions.
First scenario:
With one pump, functioning in PS 1 the wet well WW1 in P 2 will be filled up
in 39 minutes. Normally, after 5 to 10 minutes, pump 1 in PS 2 will begin to
work. At that moment, 63 to 127 m3 are filled up in WW1. The difference of
capacity between the pumps in the two stations is 52 l/s. After 1.73 hours,
the wet well WW1 is full and a second pump has to start to avoid overflow.
After 1.4 hours, this second pump has to be stopped to avoid complete
emptying of WW1.
Second scenario:
With two wet wells of 500m 3 capacity, the scenario is consistently better: The
first pump needs 1 hour and 18 minutes to fill up the twin wet wells. When
the pump in PS 2 begins to work, it needs nearly 5 hours before the second
pump has to lower down the volume, and it will work for 3.2 hours.
In the second part of Phase I, when 3 pumps are working continuously, with
only one wet well of 500 m3, the reaction time becomes very short. 3 pumps
in PS 1 will empty the collection tank CT and fill up the well WW1 in 18
minutes. That is too short. Scenario 1 does not change, but the initial
reaction times are very short. In this case, to avoid overflow, one pump in PS
1 has to be stopped after 1.73 hours, for 4 hours. This may affect the
functioning of the borehole pumps of the well fields.
At Hasselisso Well field, four identical booster pumping stations are foreseen,
each with 2 twin water tanks of 500 m3. The ground elevations of these
pumping stations and of Dengego Reservoir, in top of the pressure main, are:
The locations of all pumping stations are new, in order to install the same
pumps in all three pumping stations 2, 3 and 4 for Phase I, and in all 4
stations in Phase II. This will facilitate operation and maintenance of the
equipment.
The proposed System (see volume 2 of this report) shall also solve the water
reserve for fire-fighting.
The supply main of total length 71km is subdivided into two sections:
Pressure Main section, length 42 km: connection from Hasseliso well
field to Dengego 2000m3 reservoir
Gravity Main section: connection from Dengego reservoir to R6 main
Reservoir 4000m3 in Harar: length 29 km.
However, the dimension of the DCI pipes, Ø 600 mm, purchases 4 years ago,
is not sufficient to reach the main reservoir R6 of Harar City in Phase II of the
project, due to high friction losses. Therefore, a booster pumping station in
Alemaya is proposed. The respective area shall be reserved, because
otherwise it will not be available when needed.
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 58
HARAR WATER SUPPLY AND SANITATION PROJECT
Initial Remark:
''The survey of 2002 was made by Total Station instruments
starting from Dire Dawa, and surveying to Hasseliso on one side,
and to Harar Cityon the other side. However, it was not
connected to the survey made by another surveying team in
Harar, that took a bolt in top of reservoir R5 as a reference point.
Therefore the two surveys traverse are not closed and connected
by a common control point in Harar.''
9.4 STORAGE
9.4.1 General
The service reservoirs and all pressure tanks proposed in the WWDSE
September 2002 report have been properly analyzed and controlled for the
following design factors; numbers, sizes, topographic suitability, the site for
their construction and their capacity to store water for the different demand
fluctuation periods. Minimum hour demand and hourly variation data/ record
were not available for the city of Harar. For this reason the average demand
factors and consumption values of Addis Ababa, Awassa and Dire Dawa has
been adopted.
One of the reservoirs named ABOKER terminal square shaped concrete under
ground reservoir with a capacity of 1000m3 constructed in 1966( EC), At an
average elevation of 2007 m.a.s.l was considered to be incorporated in the
new water supply system with only some rehabilitation work on the civil
structure and change and replacement of the elector mechanical parts.
The following reservoirs have been proposed in this Design review report:
In Phase II (2025),
For normal daily compensation, Harar City & On-Lines needs at minimum a
total volume of storage, i.e., from Dengego to Harar City of: 36794 x 0.3 =
11000 m3, and Harar City: 30179 x 0.3 = ’000 m3
Ideally, for a pumped water supply, the storage capacity should be equal to
the water demand during an unforeseen interruption of pumping (major
repair, power failure).
If this interruption can last 1 day, in 2015 the storage capacity of Harar City&
On-Lines should be 24’000 m3. If it lasts 3 days, it should be in the order of
60,000 m3 for Phase I.
The stored volume is considered sufficient to serve the city for at least 4 to 6
hours pump stoppage or pump failure time and to balance the demand
fluctuation in 24 hours time.
The location of the newly proposed service reservoirs site for both to be
constructed in phases has been identified and selected based on the
following, but not limited to these:
The required elevation heads for the water to reach the proposed
reservoir by gravity directly from the transmission main from Dengego
reservoir
The availability and suitability of the area for the proposed reservoir
construction including future extension.
Considering maximum optimized alternatives (options) to avoid pump
fed area or zone with in the distribution network.
The storage capacity of the service reservoir has been determined as per the
hydraulic calculation (see Table 8.5 below) carried out to meet demand
variations during 24 hours. Based on the required storage capacity needed
i.e. 30% of the total maximum day demand for first phase and second phase
is determined to be 3,502 m3 and 6580 m3 respectively.
The reservoir could store during pump failure a maximum of 6 hours water
demand is stored to be supplied to the town with out any interruption.
The adopted option presented as follows have been modified to some extent
with the demand adjustment.
Option
To locate the reservoir at an elevation of 2070 where the water can flow by
gravity from Dengego,
through the transmission main for first phase, hydraulic calculation for first
phase. In this arrangement
the elevated areas or areas which have an elevation above 2055 will
be fed by boosting the water to smaller water tank to be distributed by
gravity for pressure zone above this elevation.
Furthermore, to meet the requirement of the second phase, a booster
pumping station at an elevation between 2012 and 2014 and at a road
distance between 13 to 15 km from Dengego or at a chain age of 390
to 393 on the profile of the rising main is required for the water to
reach the proposed reservoir site at an elevation of 2070.
The required head for this pump is about 145 m and a discharge
equal to the maximum daily demand of second phase.
Comparing the above two options, in option one the capacity of the
pump will be big that is, the discharge of the pump will be equal to the
maximum day demand which is 278 l/s for first phase and 418 l/s for
second phase.
In this option
No buster pumping station is required. only a small pump is required
in the service reservoir site to boost water from the main reservoir
(4000m3) to the 200 m3 water tank to distributed water to the
particular subsystem or (zone 7) located in a higher elevation than the
service reservoir.
The capacity of the pump shall be the maximum day demand of Zone
7, which are 2.98 l/s and 4.64 l/s for first and second phase
respectively. However, in the second phase of this 2 nd option a booster
pump for the water to reach the main reservoir is required on the
transmission main as a consequence of the anticipated head lose due
to increase in friction with age.
As per the attached hydraulic analysis for second phase maximum demand
the water will flow by gravity up to elevation of about 2015 and a road
distance of about 14 km from Dengego. Therefore, the pump station shall be
located at this place and will have a capacity of about 145 m head and a
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 63
HARAR WATER SUPPLY AND SANITATION PROJECT
discharge equal to the maximum day demand of second phase for Harar and
Aweday (374.30 l/s).
Based on the size of pump which directly related to the volume of work,
easiness of implementation, operation and maintenance as well as
investment cost, option 2 requires lower capacity pump and therefore it is
recommended. The details of the pumps, and in general the electro
mechanical component is covered in the Electro Mechanical Design Review
Report in different section.
From the recommended option, it is anticipated that for the first phase one
pumping station inside the compound of the service reservoir site shall be
constructed to serve the elevated areas or zone 7.
Even though this pump is within the distribution system the capacity is
determined using the maximum day demand of zone 7, whereas, the peak
hour demand shall be taken care by the collecting tank provided (see section
4.1.7). Thus, for the first phase, two pumps one operating and one standby
with a characteristics of H = 40 m and discharge Q = 2.98 l/s shall be
installed.
For the second phase two pumps one functional and one standby each with
Q = 4.96 l/s and H = 40m shall be employed. Therefore, the pump house to
be constructing in the first phase shall have the capacity to accommodate
and satisfy the second phase requirement.
For the second phase of this project a pumping station at about 13 km from
Dengego at an elevation of 2015 is required. This pump house will be
constructed in second phase of the project. The pump capacity will be Q
=374.30 l/s (maximum day demand for Harar and Aweday) 145 m head
lifting capacity.
Ground level within Harar ranges from 1754.12 m.a.s.l. at the Police Training
Center to 2098 m.a.s.l. at St. Georges Church. To limit the maximum and
minimum head within the distribution system, the proposed pipe distribution
network is divided into 7 distinct pressure zones or sub- systems. Each
pressure zone is supplied from the 200 m3 break pressure water tank which
also serves as break pressure chamber. The maximum day demand, peak
hour demand and range of elevation for each zone are presented on Table
4.1.5 and 4.1.6.
Zone 1:
This zone is one of the smallest pressure zones with in the elevation range of
1762.5 and 1819.03 (m.a.s.l.).
The elevated place (1824.39m.a.s.l) is where the 200 m3 water tank
called T-1 is situated to feed the distribution network with in this zone
by gravity.
The location of zone 1 is in the eastern tip of the city, out side Jugal,
stretching from Felana- Ber up to Senga-ber including the Grand
Mosque (Abdal).
This zone covers the area; small part of the old city centre (Jugal) and
the area out side Jugal fence on the South eastern side tip of the city,
the police training centre, future residential plots for housing
cooperatives, religious gathering areas, cemeteries, abattoir, some
public services and agricultural land.
Most of the houses inside Jegol are attached resulting to a density of
140 inhabitants per hectare. Categorised as medium income area and
most houses in this zone will be connected to the public water supply.
the water demand can be based on total population equivalent of
14,000 persons and on an average specific consumption of 95 lpcd.
Zone 2
This zone has elevation range between 1779.02 and 1881 m.a.s.l.
The 200m3 break pressure tank (T-2) is situated at the maximum
elevation (1881 m.a.s.l.) to supply the distribution network of the zone
by gravity.
Zone 2 have got an estimated area of 246 Hectares and
covers part of Jugal, Kebeles 7, 6, 5 and 3 in full and parts of Kebeles 1,
2 and 4 which are highly densely populated areas of the city with an
average of more than 300 inhabitants/hectare and Kebele 8 which is a
medium and low income area partial covered by medium and low cost
houses, future residential and agricultural land , and part of Kebele 15
and extends up to Dekar (Suburb) on the Jijiga road which is a future
development and expansion area of the city.
Babile mineral water bottling factory and The Misrak Arbegnoch high
level Water demand
Zone 3
Zone 5
Zone 6
The minimum and maximum elevations of this area are 1980.14 and
2068.58 m.a.s.l respectively.
covers northern part of the town, encircling the Aboker Mountain where
St. George Church and the Cuban patriot’s cemetery is situated, most
of Kebele 18, half of Kebele 12, and some part of Kebele 11.
Extends to Fedis Road including Harar Radio Station and on the
Hamarresa side up to the Oromia Rural Roads Authority and Menschen
fur Menschen Agricultural technical training Institute.
Currently this is the less densely populated zone except in some part,
however, is the future development area and industrial zone as per the
city council development plan.
The water distribution network of the zone is supplied directly from the
4000 m3 capacity service reservoir situated at an elevation of
2076m.a.s.l. Zone 6 covers an area of roughly 500hectares.
The total future water demand of the industrial zone, the agricultural
Institute, and two Total fuel stations in this sub zone are the major
inputs.
Zone 7
The maximum and minimum elevations of this zone are 2098 and
2051.98 m.a.s.l respectively situated on the north most elevated part
of the city where St. Gorge Church and the Cuban patriot’s cemetery
are located.
This zone is designed to be supplied by gravity from collecting
chamber R-7 located at an elevation of 2098.19, m.a.s.l.
R-7 will be fed by a buster pump situated next to the 4000 m 3 service
reservoir.
This zone currently has very few inhabitants and with only few
hectares reserved for future residential plots, a reasonably large part is
allocated as a preserved historical, and recreational area in the city
council development plan.
Zone 8
In this revised distribution network for Harar city there are 5 break pressure
tanks. Except the existing Aboker reservoir with a capacity of 1000 m3
rectangular in shape (R-5) incorporated in this project to serve as a supply
source and break pressure tank for Zone 5, each have 200 m3 capacity and
circular shape concrete tanks and will be constructed on ground. These
tanks are named T-1, T-2, T-3 and T-8, after the pressure zone they serve by
gravity. In order to consistent with the default annotation of Water CAD
program, the abbreviation will be used through the design report.
Table 8.7 Discharge From Each Break Pressure Tanks & Reservoirs
BCEOM/WWDSE/CECE Design Review Report, Volume I, Edition December 2005 67
HARAR WATER SUPPLY AND SANITATION PROJECT
The main purpose of these tanks is to maintain the pressure head in the
distribution network of respective zones to be in the recommended range (15
– 75 manometer head). This is accomplished by selecting the break pressure
tanks site with respective to the pressure zones maximum and minimum
elevation. This break pressure tanks should be constructed as per the
specified elevation on Table 4.3.
The chamber has a capacity of storing for 12 hours of the maximum day
demand capacity of the zone 7 for phase II. it serves as storage in times of
pump failure and supports the life of the pump giving ample break time.
Under this revised scheme all waters reaching Harar is collected in Service
Reservoir (R-6), from where it flows by gravity to the lower pressure zones
break pressure tank (T-1, T-2, T-3, R-5, T-8) and is pumped to collecting
chamber T-7.
Pipe pressure classes are determined by the maximum possible pressure that
may occur in the system. Accordingly the transfer system,
from the service reservoir to T-8, T-7 & R-5 will be PN 16 and
the transfer main that feeds the lowest points to T-3; T-2 & T-1 will be
PN 25.
The water transfer mains required are summarized in Table 4.1.8 and the lay
out of the water transfer main is presented on Figure 4.1 and 4-2. This water
transfer mains are to be laid to profile, having due regard to the range of
hydraulic gradients.
The length of the pipe with respect to their diameter for distribution network
and the transfer main is presented in Table 4-7 & 4-8 respectively. As per the
finding from the hydraulic calculation and summary on Table 4.9, except at
one Node (Node 158) where the maximum pressure at minimum hourly
demand (night time flow) is 100m (10 bar), all nodes in the distribution
network has a pressure lower than 100m (10 bar), Therefore, the nominal
pressure of the pipes in the distribution network shall be PN 10.
Table 8.10 Length and Diameter of pipes for the distribution network of
Harar city.
Table 8.11 Length and Diameter of Distribution Main for Harar City
The lay out of the revised pipe distribution network which shows all phase I
and phase II pipes with type, size and length alongside with the other major
physical units like service reservoirs, break pressure tanks, booster pump
stations is presented in separated drawings.
have been installed in each public fountain sites to re-fill them from the
existing water supply network and using water trucks to distribute water in
ration to the people in the city.
9.6.1.1 Distribution
The water distribution system for Alemaya was completely new study with
respect to its components as there was no design of the same in the earlier
report
The maximum day demand that is important mainly for source
determination is 19.88l/s for first phase (2015) and 33.77l/s for second
phase (2025).
The peak hour demand that is useful for sizing distribution network is
31.81l/s and 54.03 l/s for first phase (2015) and second phase (2025)
respectively. In new of these change and available data only the
reservoir capacity and diameter of transfer main is changed from what
Gibb’s recommended for Alemaya town.
The reservoirs capacities are designed as per the new demand based on the
new factors for projection. The previous phase II demand is about 53% higher
than the new revised demand.
Transfer Main for Alemaya town branching out from the Dengego Harar line
(600 mm DCI) are:
To 200m3 new Reservoir located at the hill north of the town at an
elevation of 2075.35 m.a.s.l., inside the compound of the Muslim
Medressa (school),
To existing and new reservoir, a second main line along the road to the
Alemaya University.
The diameters of these transfer mains are proposed to be DN 200mm
based on the second phase maximum day demand for
In Phase I water can reach the two reservoirs by the available
gravitational head. The hydraulic calculation that shows, available
head is presented in the Annex at Table H-1.1 for the first phase and in
Table H.1.2 for the second phase.
In phase II, the available head in the system remain to be only 31.6
meters. To reach the new reservoir at 2075 m.a.s.l, additional head of
25 m is required.
for the second phase a pump having a discharge capacity of 57.8 l/s
and a head of about 30 m shall be constructed at an Alemaya Town
(33.77l/s).
The lengths are 1000 m to the new reservoir and 1500m to the existing
reservoir respectively.
The calculated maximum head including friction loss during phase II is
about 60m35m and 30 m to the old and new reservoirs respectively;
thus a pipe with nominal pressure of 10 bars (PN 10) is assumed
sufficient.
Ground Elevation the new reservoir is 2014 m.a.s.l, and existing
reservoir is 2013 m.a.s.l,to having an available head of 81 meters and
82 meters respectively. Both operate separately.
From the survey, the ground elevation of Alemaya town found out to
have an elevation variation of about 83 m and forced to the
requirement of two pressure zones.
most of the existing pipe network are reconsidered in the new design.
The Water demand forecast have been revised based on the revised
population figure and growth rate factors.
Accordingly, the nodal demand distribution has also been distributed
following the settlement and development trend of the town.
9.6.5.1 General
The town of Aweday is one of the fast growing among the On-Line Towns. The
town has continued to build its name associated with chat trading high-level
income generating plant.
The off take from the Harar transmission main to the proposed Aweday
reservoir site at 2081masl which is designated as transfer main No1
and the length is about 1000 m.
The pipe diameter of this main have been designed to carry the phase
II maximum day demand (2769m3/day) and sized to be 200 mm.
The 75m head difference between the 200 m 3 lower and the upper
(100m3) reservoir used in the selection and design of the pump.
Accordingly, the pipe nominal pressure can be sized to be ten bars (PN
10).
However, in this new system the result from Hydraulic calculation, table H-1-
1 in the annex for the transmission main,
pipe will branch out at an elevation of 2027 m.a.s.l and the available
head at this point is 54.2 meter and negative (-) 23 m for first and
second phase respectively.
Therefore the proposed pump head by WWDSE for first and second
phase demand were revised.
Further, the requirement of pumps and the capacity have been decided
along with the detail survey and design of distribution network.
WWDSE’s September 2000 report stated that “Like for the other Satellite
towns the diameters and length of the Distribution network for Aweday is
directly accommodated from Gibb’s proposal in this report. However for
Aweday also there was neither a Master Plan nor adequate base mapping, for
Gibb’s to present the future water supply system”.
It was a huge burden imposed to this consultant when the contract for the
current review work was prepared with out checking the above condition of
the said final design report and considering being a final design report during
the preparation of the terms of reference for a design review while there was
no design to be reviewed.
9.6.6.1 General
These town and villages were lately incorporated into the Harar water supply
and sanitation project based on the Harari and Oromia regional states
agreement to include them in the project. WWDSE’s 2002 report has
included these On-Line town and villages with out any detail study with
limited roadside water point's supply.
10 WATER TREATMENT
10.1 HASSELISO WATERS
However, it has to be pointed out that the water is quite hard with respect to
calcium and can thus have a tendency to settle out, especially at higher
temperatures. Moreover, since the pH of the groundwater is close to 8.2,
which is nearly the optimum range for the precipitation of CaCO 3, this
situation may further be aggravated by the addition of chlorine during actual
plant operation and may thus contribute to possible scaling.
Due to the reasons stated below, it has been necessary to move the site:
a. before the review is complete Hasseliso has managed to get a a new
and complete water supply system from a separate borehole equipped
with pump and a reservoir located on the hill above the village. This
system supplies also water to another nearby village.
b. Incase the system needs expansion in the future one of the observation
wells can be used as additional source without connecting to the new
hara scheme. at present there is no need of drinking water between the
well field near Hasseliso and Dengego reservoir, on top of the pressure
main, at 42 km from Hasseliso.
c. The drinking water for the operators and guards of the pumping stations
can be obtained by much cheaper methods.
d. Fundamentally, the water from the boreholes do not contain pathogens,
and the risk of pollution in the pressure main is nearly nil.
e. For the pump impellers it is an advantage if the water is not chlorinated.
Criteria used to determine the amount and type of disinfectant needed are:
Amount of water to be treated.
Quality of water to be treated, particularly with regard to disinfectant
consuming substances and pH.
Age of the distribution network and possible risk of pollution.
Safety requirements during transport, storage and application.
Wastage due to potential loss of available chlorine during preparation.
Cost and effectiveness of the specific disinfectant.
All three forms of chlorine are considered i.e. sodium hypochlorite, chlorine
gas and calcium hypochlorite.
The dosing rates for a 1% (w/v) calcium hypochlorite solution with 65%
active chlorine is indicated for the maximum day demand for Harar &
atellites (Dengego reservoir) and Harar city, for the years 2015and 2025.
A cool dry storage area to stockpile the calcium hypochlorite powder in its
shipping containers.
The storage room should thus be designed to meet this specification with
enough room for ventilation due to the irritating nature of chlorine gas
emanations. The 9m2 room shown in the previous Design Report drawing is
not sufficient to stock the disinfectant: 400 bags of 50 kg capacity or drums,
needed at Dengego reservoir for a six-month period in the year 2022.
The two treatment facilities at Dengego and Main Harar (R6) reservoirs have
differing chemical consuming capacities (as shown in the table with respect
to chemical use) and due consideration in this regard will thus be needed to
determine the respective storage capacity.
A mix and solution tank. After mixing Ca(OCl)2 in water, impurities and not
dissolved chemicals settle to the bottom of the solution tank. The clear
solution in this tank is then transferred to the
Clear solution tank, to prevent non-dissolved material from reaching and
plugging the hypo-chlorinator or rupturing the diaphragm.
Chlorine injector, fitted on the inlet pipe to the reservoir.
Automatic chlorine detector and pH detector at the outlet of the reservoir.
Command at distance of the chlorinator, regulating the chlorine dose.
The chemical feed room shall accommodate a twin disposition of twice two
containers and two feed pumps (one being stand-by). The arrangement of
the two tanks to each other and to the feed pump shall ensure a correct
operation of the chlorinator.
1.2 m diameter fibreglass tanks, 1.6 m high, are proposed.
The mix-tank shall be equipped with an electrical mixer. Its outlet shall be
positioned 50 cm above the base-level, to allow settling of the non soluble
components. At its base, a wash-out shall allow to dispose off this settled
material.
The tanks (1.4 m3 capacity + free rim) are capacity-wise designed for a daily
three-shift operation in the year 2012. Both tanks, feed pump and all other
fixtures shall be of corrosion resistant materials.
Complete sets of new standard & special tools, necessary for the operation,
maintenance and dismantling of the various facilities shall be provided in
strong steel or wooden boxes each fitted with a suitable pad lock. They will
mainly include the following :
Since these tools will mainly be used during the commissioning period of the
E & M works and for maintenance of the latter we propose to include them in
the related E-M contract instead to launch a separate one.