Documente Academic
Documente Profesional
Documente Cultură
2. Surface preparation (Cutting ,Filling, Drilling & Updated drawings with existing facilities marked must be available prior to start
the activity.
Leveling) on existing contruction area.
Close supervision must be done by competent supervisor.
All the existing live utilities must be clearly marked and information must be
passed to the operators.
Pre-job meeting to be conducted prior to start the activity.
All the lifting beams must be third party certified and color coded as per the BNPP
3. .Installation of pretied reinforcement bars by using
procedure.
spreder beam/lifting beam. Store and handle lifting beam correctly.
Include the self-weight of the beam and attachments when calculating the load
imposed on the crane hook.
Ensure the load will remain stable when lifted.
Ensure no single lifting point becomes overloaded by the slinging or handling
methods.
Pre-job meeting to be conducted to the operators& workers prior to start the
activity by immediate supervisor.
Ensure that the pile case vibro hammer head is properly aligned on top of the steel
4. Pile case driving by using vibro hammer
case.
The area must be barricaded and adequate warning signages to be placed.
Ensure strict compliance of safe buffer zones along the perimeter of piling
operations.
Prohibit entry of other personnel not involve in the task.
Compliance with PPE requirements use eye/face protection, hand gloves,
helmets and safety shoes.
5.Steel Casing Lifting When casing not in use, the casing is to be parked into the ground in a way that a
third of its length is inserted into the ground.
Proper checking and installing of casing pin to connect the casing with the rig turn
table. Rigger to install the pin at the high level or remove it when required using man
basket or man lift vehicle. If area is too narrow to occupy the rig along with a crane for
man basket or man lift so rigger is to mount the rig using the rig winch rope and safety
harness.
Page 1 of 1