Sunteți pe pagina 1din 10

Project : E-7501A COMPLETE HEAT EXCHANGER

Manufacturer :
P.O. : 5558163
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05
PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED
ITP 01 28/4/2018 THK AT

LEGEND SHELL SIDE TUBES SIDE


HC+H2+H2S+H2O+NH3
A = Approval Required FLUID / PRODUCT / MEDIUM: H2+HC+H2S+H2O (FEED) (EFFLUENT)
R = Review of Documentation FLUID GROUP: 1 1
M = Monitoring FLUID PHASE: GAS+LIQUID GAS+LIQUID
W = Witness Inspection DESIGN PRESSURE (kg/cm2 g): F.V./122,5 FV/104,2
H = Hold Point (Notification for Inspection required) DESIGN TEMPERATURE (oC): 305 355
SW = Spot Witness Inspection VOLUME (m3): 11,32 5,82
DESIGN CODE: ASME VIII DIV.2 + TEMA "R"
MDMT (oC): -4
JOINT EFFICIENCY: 1 1
DIRECTIVES: PED 2014/68/EU - ATEX 2014/34/EU
EQUIPMENT CATEGORY: IV
INSPECTION MODULE: G
NOTIFIED BODY: MOODY TOTTRUP HELLAS
NOTIFIED BODY NUMBER: 656
HEAT EXCHANGER TYPE (TEMA): DEU
ATEX CATEGORY: ZONE II GAS GROUP IIB TEMPERATURE T3
NA = NOT APPLICABLE SPECIAL SERVICE: HYDROGEN HYDROGEN
ASME VIII Div.2 CLASS / TEST GROUP: 2 / 1A
PO = PURCHASE ORDER
MR = MATERIAL REQUISITION
DWG = CONSTRUCTION DRAWING

REVISION INDEX
EKME CLIENT TPI NO.BO.

1 18/6/2018 NoBo comments incorporated THK AT


0 28/4/2018 First Issue THP AT
REV DATE DESCRIPTION ISSUED CHECKED SIGNATURE SIGNATURE SIGNATURE SIGNATURE

Page 1 of 10
Project : E-7501A COMPLETE HEAT EXCHANGER
Manufacturer :
P.O. : 5514531
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05

PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED


ITP 01 28/4/2018 THK AT
I&T CODES-SPECIFICATIONS- ACTION
INSPECTION & TEST DESCRIPTION EXTEND
DOCUMENTATION
REQUIREMENTS EKME CL/TPI ΝΟ.ΒΟ
BEFORE FABRICATION

1 PRE INSPECTION MEETING 100% P.O. MINUTES OF MEETING H H H

2 REVIEW OF INSPECTION REQUIREMENTS 100% P.O. NA H R H

3 CHECK OF MATERIALS SUB-ORDERS 100% EN 10204 3.1, P.O., ASME II - PART A MATERIAL SUB-ORDERS H R R

4 CHECK OF MATERIAL CERTIFICATES 100% EN 10204 3.1, P.O. MATERIAL CERTIFICATES H R R

5 CHECK OF MECHANICAL CALCULATIONS 100% ASME VIII Div.2, TEMA R APPROVED CALCULATIONS H H H
P.O.
6 CHECK OF CONSTRUCTION DRAWINGS 100% APPROVED DRAWINGS H H H
DATA SHEET
APPROVED
7 CHECK OF WPS / WPQR / WMAP 100% ASME IX H H R
WPS / PQR / WMAP
8 CHECK OF WPQ 100% ASME IX WPQ H R R
CONSUMABLES
9 CHECK OF CONSUMABLES CERTIFICATES 100% ASME II - PART C, EN 10204 3.1/2.2 H R R
CERTIFICATES
CHECK OF INSTRUMENTS CALIBRATION INSTRUMENTS
10 100% INTERNAL PROCEDURE Δ22 H R R
CERTIFICATES CERTIFICATES
11 CHECK OF NDT PROCEDURES 100% MR, ASME V, WRITTEN PRACTICE NDT PROCEDURES H (1) H R
CHECK OF NDT PERSONNEL
12 100% ASNT-SNT-TC-1A LEVEL II CERTIFICATES H (1) R R
QUALIFICATIONS
13 CHECK OF PWHT PROCEDURE 100% PO, PED 2014/68/EU, ASME VIII Div.2 T18 H R M

Page 2 of 10
Project : E-7501A COMPLETE HEAT EXCHANGER
Manufacturer :
P.O. : 5514531
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05

PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED


ITP 01 28/4/2018 THK AT
I&T CODES-SPECIFICATIONS- ACTION
INSPECTION & TEST DESCRIPTION EXTEND
DOCUMENTATION
REQUIREMENTS EKME CL/TPI ΝΟ.ΒΟ
14 CHECK OF HYDRAULIC TEST PROCEDURE 100% PO, ASME III Div.2 T22 H H R

RAW MATERIAL (INCOMING OR FROM STOCK)


VISUAL AND DIMENSIONAL CHECK OF MATERIAL SUBORDERS
15 100% NA H R R
MATERIALS (INCL SUBORDERS) MATERIAL CERTIFICATES
CHECK OF HEAT NUMBERS (INCL
16 100% MATERIAL CERTIFICATES NA H R R
SUBORDERS)
MATERIAL SUBORDERS, ASME VIII
17 THICKNESS CHECK OF SHELL 100% NA H W R
MATERIAL CERTIFICATES, DWG
18 VISUAL CONTROL OF CONSUMABLES 100% ASME II - PART C, Δ35 F44 H R R
PMI ON INCOMING ALLOY MATERIALS AN
19 100% EK-PMI, ASME II F44 H R R
WELDING CONSUMABLES
FABRICATION (GENERAL)
CONTROL OF MATERIALS, TRANSFER OF
20 100% ASME VIII Div.2 NA H W R
MARKING (IF REQUIRED)
21 CHECK OF CONSUMABLES HANDLING SPOT ASME II - PART C, Δ35 NA H M M

DURING FABRICATION
CHECK OF MATERIALS TRACEABILITY (INCL.
22 100% ASME VIII Div.2 NA H R R
CONSUMABLES)
CHECK OF SHELL & CHANNEL PLATES
23 100% DWG NA H M M
CUTTING AND ROLLING
CHECK OF SHELL & CHANNEL PLATES
24 100% WPS NA H M M
BEVELS PREPARATION (V&D CHECK)

Page 3 of 10
Project : E-7501A COMPLETE HEAT EXCHANGER
Manufacturer :
P.O. : 5514531
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05

PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED


ITP 01 28/4/2018 THK AT
I&T CODES-SPECIFICATIONS- ACTION
INSPECTION & TEST DESCRIPTION EXTEND
DOCUMENTATION
REQUIREMENTS EKME CL/TPI ΝΟ.ΒΟ
EK-MT-1, EK-PT-1, ASME V, ASME VIII
25 MT/PT ON BEVELS 100% RT REPORTS H (1) R R
Div.2
CHECK OF FORGINGS MACHINING
26 100% DWG NA H M M
(CHANNEL, NOZZLES, FLANGES)
CHECK OF SHELL & CHANNEL PLATES
27 100% DWG, WPS, ASME VIII Div.2 NA H W/M M
LONGITUDINAL WELDS FIT UP AND ALIGNMENT
CHECK OF PREHEATING (APPLICABLE FOR
28 100% WPS NA H M M
ALL ACTIONS HEREAFTER)
LONGITUDINAL WELDS WELDING
29 100% WPS F44 H M M
MONITORING AND PARAMETERS CHECK
30 PT ON ROOT PASS 100% EK-PT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
VISUAL CHECK OF COMPLETED
31 100% EK-VT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
LONGITUDINAL WELDS
CHECK OF DHT ON COMPLETED
32 100% WPS RT REPORTS H (1) R R
LONGITUDINAL WELDS
RT OF LONGITUDINAL WELDS PRIOR TO
33 100% EK-RT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
PWHT
MT OF LONGITUDINAL WELDS PRIOR TO
34 100% EK-MT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
PWHT
CHECK OF WELD OVERLAY APPLICATION ON
35 100% WPS F44 H M M
SHELL & CHANNEL PLATES (PER COURSE)
CHECK OF WELD OVERLAY APPLICATION ON
36 HEMISPHERICAL HEAD, FORGINGS AND NOZZLES
100% WPS F44 H M M
PT ON WELD OVERLAY (PER LAYER AND
37 100% EK-PT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
FINAL LAYER)
VISUAL CHECK OF COMPLETED WELD
38 100% EK-VT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
OVERLAY
39 F Nr ON WELD OVERLAY 100% F Nr 3-10 RT REPORTS H (1) R R
Page 4 of 10
Project : E-7501A COMPLETE HEAT EXCHANGER
Manufacturer :
P.O. : 5514531
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05

PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED


ITP 01 28/4/2018 THK AT
I&T CODES-SPECIFICATIONS- ACTION
INSPECTION & TEST DESCRIPTION EXTEND
DOCUMENTATION
REQUIREMENTS EKME CL/TPI ΝΟ.ΒΟ
39 F Nr ON WELD OVERLAY 100% F Nr 3-10 RT REPORTS H (1) R R

Page 5 of 10
Project : E-7501A COMPLETE HEAT EXCHANGER
Manufacturer :
P.O. : 5514531
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05

PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED


ITP 01 28/4/2018 THK AT
I&T CODES-SPECIFICATIONS- ACTION
INSPECTION & TEST DESCRIPTION EXTEND
DOCUMENTATION
REQUIREMENTS EKME CL/TPI ΝΟ.ΒΟ
40 PMI ON WELD OVERLAY 100% EK-PMI, ASME II RT REPORTS H (1) R R
CHECK OF SHELL & CHANNEL PLATES
41 CIRCUMFERENTIAL WELDS FIT UP AND ALIGNMENT
100% DWG, ASME VIII Div.2 NA H W/M M
CIRCUMFERENTIAL WELDS WELDING
42 100% WPS F44 H M M
MONITORING AND PARAMETERS CHECK
43 PT ON ROOT PASS 100% EK-PT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
VISUAL CHECK OF COMPLETED
44 100% EK-VT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
CIRCUMFERENTIAL WELDS
CHECK OF DHT ON COMPLETED
45 100% WPS RT REPORTS H (1) R R
CIRCUMFERENTIAL WELDS
RT OF CIRCUMFERENTIAL WELDS PRIOR TO
46 100% EK-RT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
PWHT
MT OF CIRCUMFERENTIAL WELDS PRIOR TO
47 100% EK-MT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
PWHT
WELDS REPAIRS (IF ANY) AND REPETIOTION
48 100% NDT REPORTS, ASME V, WPS NDT REPORTS H R R
OF NDT ON REPAIRED WELDS
CHECK OF WELD OVERLAY APPLICATION ON
49 100% WPS F44 H M M
SHELL & CHANNEL CIRCUMFERENTIAL WELDS
CHECK OF WELD OVERLAY APPLICATION ON
50 100% WPS F44 H M M
CIRCUMFERENTIAL WELDS
PT ON WELD OVERLAY (PER LAYER AND
51 100% EK-PT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
FINAL LAYER)
VISUAL CHECK OF COMPLETED WELD
52 100% EK-VT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
OVERLAY
53 F Nr ON WELD OVERLAY 100% F Nr 3-10 RT REPORTS H (1) R R

Page 6 of 10
Project : E-7501A COMPLETE HEAT EXCHANGER
Manufacturer :
P.O. : 5514531
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05

PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED


ITP 01 28/4/2018 THK AT
I&T CODES-SPECIFICATIONS- ACTION
INSPECTION & TEST DESCRIPTION EXTEND
DOCUMENTATION
REQUIREMENTS EKME CL/TPI ΝΟ.ΒΟ
54 PMI ON WELD OVERLAY 100% EK-PMI, ASME II RT REPORTS H (1) R R

55 V&D CHECK OF OPENINGS FOR NOZZLES 100% WPS, DWG NA H W/M M


NOZZLES DIMENSIONAL CHECK OF FIT UP
56 100% WPS, DWG NA H W/M M
AND ALIGNMENT
NOZZLES WELDING MONITORING AND
57 100% WPS F44 H M M
PARAMETERS CHECK
CHECK OF BACK GOUGING (WHERE
58 100% WPS F44 H M M
APPLICABLE)
59 PT ON GOUGED ROOT PASS 100% EK-PT-1, ASME V, ASME VIII Div.2 PT REPORTS H (2) R R

60 COMPLETION OF THE WELD FROM INSIDE 100% WPS F44 H M M


VISUAL CHECK OF COMPLETED NOZZLES
61 100% EK-VT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
WELDS
CHECK OF DHT ON COMPLETED NOZZLES
62 100% WPS RT REPORTS H (1) R R
WELDS
PHASED ARRAY ON NOZZLES WELDED TO
63 100% EK-UT-1, ASME V, ASME VIII Div.2 UT REPORTS H (1) R R
SHELL OR CHANNEL (Φ≥ 100mm)
64 MT ON NOZZLES 100% EK-MT-1, ASME V, ASME VIII Div.2 PT/MT REPORTS H (2) R R
V&D CHECK OF EXTERNAL ATTACHMENTS (SADDLES
65 TRANSITION PLATES, NAMEPLATE SUPPORT, ETC)
100% DWG NA H W/M M
EXTERNAL ATTACHMENTS (SADDLES TRANSITION
66 PLATES, NAMEPLATE SUPPORT) DIMENSIONAL CHECK 100% WPS, DWG NA H W/M M
OF FIT UP AND ALIGNMENT

Page 7 of 10
Project : E-7501A COMPLETE HEAT EXCHANGER
Manufacturer :
P.O. : 5514531
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05

PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED


ITP 01 28/4/2018 THK AT
I&T CODES-SPECIFICATIONS- ACTION
INSPECTION & TEST DESCRIPTION EXTEND
DOCUMENTATION
REQUIREMENTS EKME CL/TPI ΝΟ.ΒΟ
EXTERNAL ATTACHMENTS WELDING
67 100% WPS F44 H M M
MONITORING AND PARAMETERS CHECK
68 MT ON EXTERNAL ATTACHMENTS WELDS 100% EK-MT-1, ASME V, ASME VIII Div.2 PT/MT REPORTS H (2) R R
CHECK OF TEMPORARY ATTACHMENTS EK-MT-1, EK-PT-1, ASME V, ASME VIII
69 100% F44 H M M
REMOVAL AND MT/PT CHECK Div.2
CHECK OF PWHT ON SHELL/CHANNEL
70 100% WPS NA H M M
BARREL
HARDNESS TEST OF BUTT AND BRANCH
71 100% EK-HT-1 RT REPORTS H (1) R R
WELDS AFTER PWHT
UT OF BUTT AND BRANCH WELDS AFTER
72 100% EK-UT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
PWHT
MT OF BUTT AND BRANCH WELDS AFTER
73 100% EK-MT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
PWHT
74 PT ON WELD OVERLAY AFTER PWHT 100% EK-PT-1, ASME V, ASME VIII Div.2 RT REPORTS H (1) R R
CHECK OF TUBESHEET MACHINING,
75 100% DWG NA H M M
DRILLING
76 V&D CHECK OF FABRICATED TUBESHEETS 100% DWG NA H W/M M
CHECK OF TUBE BUNDLE ASSEMBLY
77 100% DWG NA H M M
(BAFFLES, TIE RODS, ETC)
78 CHECK OF TUBES INSERTION TO BUNDLE 100% DWG NA H M M

79 CHECK OF TUBES LIGHT EXPANSION (V&D) 100% DWG NA H M M


TUBES-TO-TUBESHEET WELDING
80 100% WPS F44 H M M
MONITORING AND PARAMETERS CHECK

Page 8 of 10
Project : E-7501A COMPLETE HEAT EXCHANGER
Manufacturer :
P.O. : 5514531
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05

PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED


ITP 01 28/4/2018 THK AT
I&T CODES-SPECIFICATIONS- ACTION
INSPECTION & TEST DESCRIPTION EXTEND
DOCUMENTATION
REQUIREMENTS EKME CL/TPI ΝΟ.ΒΟ
PT ON TUBE-TO-TUBESHEET STRENGTH
81 100% EK-PT-1, ASME V, ASME VIII Div.2 MT REPORTS H (2) R R
WELDS
PMI ON TUBE-TO-TUBESHEET STRENGTH
82 100% EK-PMI, ASME II MT REPORTS H (2) R R
WELDS
F Nr ON TUBE-TO-TUBESHEET STRENGTH
83 100% F Nr 3-10 MT REPORTS H (2) R R
WELDS
VERIFICATION OF WELDERS ID ON WELDS
84 100% ASME VIII Div.2 WELDING MAP H R R
AND WELDING - NDT MAP
CHECK OF TUBE BUNDLE INSERTION TO
85 100% DWG F37 H R R
SHELL/CHANNEL BARREL - V&D CHECK
CHECK OF BOLT TIGHTENING ON
86 100% DWG, PROCEDURE F37 H R R
TUBESHEET, CHANNEL COVER, NOZZLES
FINAL TESTS, CLOSING

87 FINAL VISUAL AND DIMENSIONAL CHECK 100% DWG F37 H R R

88 HYDROSTATIC TEST OF SHELL 100% T22, ASME VIII Div.2 F01 H H H

89 HYDROSTATIC TEST OF TUBES 100% T22, ASME VIII Div.2 F01 H H H

90 CHECK OF DRAIN AND DRYING 100% T22, ASME VIII Div.2 NA H H H

91 CHECK OF SURFACE PREPARATION 100% T15 F30 H W W

92 VISUAL & DFT CHECK OF PAINTING 100% T15, PO F30 H R R

93 CHECK OF ACTIONS PRIOR TO SHIPMENT 100% PO NA H H H

Page 9 of 10
Project : E-7501A COMPLETE HEAT EXCHANGER
Manufacturer :
P.O. : 5514531
Client : INSPECTION & TEST PLAN
Item : E-7501A
Document No : E05-E7501A-00

R0-2/10/02 E05

PROJ No DWG No CONTRACT DOC TYPE REV DATE ISSUED CHECKED


ITP 01 28/4/2018 THK AT
I&T CODES-SPECIFICATIONS- ACTION
INSPECTION & TEST DESCRIPTION EXTEND
DOCUMENTATION
REQUIREMENTS EKME CL/TPI ΝΟ.ΒΟ
DOCUMENTATION

94 GENERAL REVIEW OF DATA BOOK 100% PO DATA BOOK H H H


PHOTOCOPY OF
95 CHECK OF NAMEPLATE AND CE STAMPING 100% PO H W W
NAMEPLATE
96 INSPECTION RELEASE NOTICE 100% PO IRN H H H

NOTES
(1) ACTION BY DT/NDT SUB-CONTRACTOR
(2) ACTION BY NDT SUB-CONTRACTOR OR EKME
* WITNESS AT START OF RELEVANT ACTIVITIES

Page 10 of 10

S-ar putea să vă placă și