If your work center capacity 8 hours and there are 4 persons then total capacity at your
work center is 32 hours if your capacity utilization is 100%.
If you using this work center in order then total capacity of this work center in a day is 32
hours.
Standard SAP as predefined formulas for calculating the work center capacity.
In capacity Tab
Capacity category - Person
Other formula - SAP008 (Actual Work)
In capacity header
Maintain the hours and capacity you require
In scheduling tab
Maintain other formala as - SAP004
Work Dimension - Time
Unit - Hrs
In costing sheet
Maintain Cost center
Activity type and SAP008
(2)
They are very significant for capacity planning and scheduling of work.These form the basic
requiremnts for execution of these activities.
If you dont enter a capacity formulae (Ex AP008) in the capacity tab of the work center,
then capacity requirement records are not entered by the system for the work order
associated to this work center. Have a look at Capacity Requirements planning for detailed
information.
If you dont enter sceduling formulae, then when you schedule the work order,Nothing
happens and the operation start and end dates remain the same. The values entered here
are calculated based on the formulae entered in the scheduling tab of the work center.