Documente Academic
Documente Profesional
Documente Cultură
Let’s see now the general guidelines for high potential (Hi-Pot) DC testing of
medium voltage cables:
1. Pre-test guidelines
a. Testing equipment
b. Recommended testing procedures
c. Preparation for testing
2. Hi-pot testing procedures
a. Continuous method
b. Step method
c. Recommended testing procedure
Acceptance testing
Maintenance testing
3. Common testing problems
4. Fault locating
5. Checklist
1. Pre-test guidelines
a. Testing equipment
Before conducting any Hi-Pot testing, the following steps should be taken.
a. Continuous method
b. Step method
Maintain the test voltage at the prescribed value for the time specified in the
applicable specifications. At the end of the test period, set the test set voltage to
zero, allow the residual voltage on the circuit to decay, disconnect the power
supply and then ground and “drain” the conductor just tested.
After testing, maintain solid grounds on the cable for at least 4 times
the duration of the test since DC charges can build up on the cable to
potentially dangerous levels if grounds are removed too quickly.
After installation and before the cable is placed in regular service, the test
voltages specified in Table c.1. should be applied for 15 consecutive minutes.
Record the leakage current at one minute intervals for the duration of the test.
At any time during the warranty period, the cable circuit may be removed from
service and tested at a reduced voltage (normally 65% of the original
acceptance value) for 5 consecutive minutes. Record the leakage current at one
minute intervals for the duration of the test.
Some common problems that may be encountered during testing are listed
below.
Erratic readings:
Environmental influences:
4. Fault locating
5. Testing checklist
Reference // Cable Installation Manual for Power and Control Cables by General
Cable
Edvard Csanyi