BANGLADESH INLAND WATER TRANSPORT AUTHORITY (BIWTA)

BIWTA Bhaban,141-143,Motijheel, Dhaka, Bangladesh

INCEPTION REPORT
ON
CONSULTING SERVICES FOR DESIGN REVIEW
AND CONSTRUCTION SUPERVISION OF
CONSTRUCTION & INSTALLATION OF
DEMARCATION PILLAR, WALKWAY, BANK
PROTECTION, JETTY WITH ALLIED WORK ON
EVICTED FORESHORE LAND OF THE RIVER
BURIGANGA, TURAG, BALU AND SITALAKHYA
(2ND PHASE)

CONSULTANT :
Inter Space & Dcon Design Studio, JV
House-6/10, Block-A, Lalmatia, Dhaka-1207
Prepared for:

The Government of Bangladesh (GoB) through

Bangladesh Inland Water Transport Authority (BIWTA)

INCEPTION REPORT FOR CONSULTING SERVICES FOR DESIGN


REVIEW AND CONSTRUCTION SUPERVISION OF CONSTRUCTION &
INSTALLATION OF DEMARCATION PILLAR, WALKWAY, BANK
PROTECTION, JETTY WITH ALLIED WORK ON EVICTED FORESHORE
LAND OF THE RIVER BURIGANGA, TURAG, BALU AND SITALAKHYA
(2ND PHASE)

Version: 1.0 (Draft)


10 February, 2019

DISCLAIMER - This document may not be disclosed to any person other than the addressee or any duly authorized person within
the addressee's company or organization and may only be disclosed so far as is strictly necessary for the proper purposes of the
addressee which may be limited by contract. Any person to whom the document or any part of it is disclosed must comply with
this notice. A failure to comply with it may result in loss or damage to Inter Space & Dcon Design Studio JV or to others with
whom it may have contracted and the addressee will be held fully liable therefor.

Care has been taken in the preparation of this report, but all analysis, calculations, information are supplied for the assistance of
the relevant client and are not to be relied on as authoritative or as in substitution for the exercise of judgment by that client or
any other reader.

All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means electronic,
mechanical, photocopied, recorded or otherwise, or stored in any retrieval system of any nature without the written permissio n
of the copyright holder.

© Inter Space & Dcon Design Studio JV


House No. 6/10, Block-A, Lalmatia, Dhaka-1208

i
TABLE OF CONTENTS

1.1 INTRODUCTION..............................................................................................................................1
1.2 PROJECT BACKGROUND .............................................................................................................1
1.3 STUDY AREA .....................................................................................................................................2
1.4 SCOPE OF WORK ............................................................................................................................5
2.1 INITIATION OF STUDY ..................................................................................................................7
2.2 STUDY TEAM ........................................................................................................................................7
2.3 MEETING MINORS .........................................................................................................................7
2.4 FIELD VISIT & RECONNAISSANCE SURVEY........................................................................ 10
2.5 OBSERVATIONS ........................................................................................................................... 15
2.5.1 FROM FIELD VISIT ................................................................................................................... 15
2.5.2 FROM DESK STUDY ................................................................................................................ 15
3.1 TECHNICAL APPROACH AND METHODOLOGY............................................................... 17
4.1 WORK PROGRAM........................................................................................................................ 25
4.2 PREPARATION OF REPORTS .................................................................................................... 25
4.3 ORGANIZATION & STAFFING ................................................................................................. 25
4.4 PROJECT WORKFLOW ............................................................................................................... 28
LIST OF FIGURES

Figure 1.1: Map showing the project area .............................................................................................3

Figure 1.2: Georeferenced location of Ramchandrapur to Kamrangirchar ................................4

Figure 2.1: Georeferenced locations of six (6) jetties along the Hasanbad to Katoali ........ 11

Figure 2.2: Photos of field visit & reconnaissance survey ............................................................. 12

Figure 2.3: Photos of field visit & reconnaissance survey ............................................................. 13

Figure 2.4: Photos of field visit & reconnaissance survey ............................................................. 14

Figure 3.5: Main activities of the Methodology of Service ........................................................... 17

Figure 3.6: Schematic Diagram showing the Methodology of the Detailed Design Phase
(Activity 1) ........................................................................................................................................................ 22

Figure 3.7: Tentative View of Architectural Perspective 3D View (Part of Master Plan) ..... 23

Figure 3.8: Bidding Document Procedures ......................................................................................... 24

Figure 4.9: Project Organization Chart ................................................................................................. 27

Figure 4.10: Project Work Flow .............................................................................................................. 28

LIST OF TABLES

Table 1.1: General Project Information ....................................................................................................2

Table 3.1: Activity Group and Tasks arranged by the Consultant .............................................. 17

Table 3.1: Design standards proposed to be used in design ....................................................... 23

Table 4.1: Project Implementation Schedule...................................................................................... 26

3
This page is intentionally left blank
Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Chapter 1
1.1 INTRODUCTION

The Bangladesh Inland Water Transport Authority (BIWTA) on behalf of the Government of
Bangladesh (GoB) is aiming to construct and install demarcation pillars, walkway & bank
protection, and jetty with allied works on Evicted Foreshore Land of the Rivers Buriganga,
Turag, Balu and Sitalakhya.

In this inception report, documents feedback centered on design review, approach and
methodology shared and discussed with the stakeholders and sets out how the consultation
with and with approval from BIWTA, intends to proceed with the substantive project.
1.2 PROJECT BACKGROUND

Dhaka City is encircled by Buriganga, Turag, Balu and Sitalakhya rivers. There are three (3) river
ports located on the banks of these rivers for transportation of passengers and cargoes
through inland waterways. However, the banks of these rivers are encroached by illegal
occupants, and in some cases, the sand traders and industrialists have made their business by
the banks of the rivers encroaching the foreshore land. In many cases, they even constructed
structures to run their business. As a result, the width of the rivers and navigational depth are
reducing every year. A cross-section of people has a tendency to occupy public property. The
construction of unauthorized and unplanned structures has created constraints in the flow of
water in these rivers.

Dhaka Inland River Port, the biggest one irrespective of all characteristics, is situated on the
bank of the Buriganga River which acts as a gateway to the capital city. The port limit is about
42 km covers the foreshore land of the Buriganga and the Turag rivers which extends from
Ashulia to BG Mouth, the confluence of the river Buriganga and Dhaleshwari. The inland river
port of Narayanganj, situated on the bank of the Sitalakhya, once it was renowned as the
Dandy of Bangladesh, is one of the major river ports covering the port limit of 27 km. The
other port named, Tongi Inland River Port is situated on the bank of the Turag River and serves
the city which is also an important industrial and commercial center. Its port limit of about 38
km covers the foreshore area of the river Turag and Balu between Tongi and Demra.

It is pertinent to note that there are two important decisions taken in the special meeting
chaired by Honorable Prime Minister of GoB that was held on July 27, 2018. To prevent
unauthorized encroachment, especially form the rivers Buriganga, Turag, Balu & Sitalakhya
decisions of that meeting were to construct walkway, bank protection, garden etc.

BIWTA aims to construct demarcation pillars, walkway, bank protection, and jetty with allied
works on evicted foreshore land of the rivers Buriganga, Turag, Balu, and Sitalakhya as part of
the second phase of this project. The underlying objective is to protect the foreshore lands
from illegal occupation and thereby restoring and ensuring the natural river water flow along
the aforesaid rivers. BIWTA as a tenacity to the above issue has decided to build physical

INCEPTION REPORT Page | 1


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

infrastructure, e.g. reinforced concrete retaining walls, guide walls, walkways, steps and/or
jetties to secure the foreshore line with permanent structures to discourage and prevent
unlawful and illegal encroachment along the river edges.

The objectives of the project are as follows:


1) To prevent unauthorized encroachment of the foreshore land under Buriganga,
Turag, and Sitalakhaya (partly) rivers;
2) To augment the beauty of the said portion of these rivers;
3) To make an environmental improvement on both sides of these rivers; and
4) To utilize the foreshore areas of the said portion of river Buriganga, Turag and
Sitalakhaya by providing facilities.

Table 1.1: General Project Information

“Construction & Installation of demarcation pillar,


Walkway, Bank Protection, Jetty with allied work on
Name of the Project
Evicted Foreshore Land of the River Buriganga, Turag,
Balu and Sitalakhya (2nd Phase)

Sponsoring Ministry Ministry of Shipping (MoS)


Bangladesh Inland Water Transport Authority
Executing Agency
(BIWTA)
Total Estimated Cost Tk. 55,460.87 lac

1.3 STUDY AREA

The total length of the circular water way under the purview of this project scope is 110
kilometers. The total length of the rivers is divided into three segments, i.e. Sadarghat – Ashulia
30 Kilometers, Ashulia – Tongi – Kanchpur 40 Kilometers and Kanchpur - Naraynaganj –
Sadarghat 40 Kilometers. As such the route can be identified as Sadarghat – Ashulia – Tongi –
Kanchpur – Narayanganj – Sadarghat.

The project sites are located in 4 key areas. One at Keranigonj; 6 Kilometers up and down the
stream along Siddirgonj Silo to Kumiduni to Kanchpur Bridge to Sultana Kamal Bridge in the
vicinity of Narayangonj Sadar, Bandar, Sonargaon, and Siddirgonj; Tongi area; and Uttarkhan,
Turag, Muhammadpur, Kamrangirchar, Kotowali, Mirpur in Dhaka Metropolitan Area.

After scouring through the feasibility studies and impact assessments from 1st phase of this
project, the consultant team has already surveyed the Sadarghtat to Katoali, 11 km, area as a
part of commencement of the 2nd phase. A georeferenced location of a survey map on google
earth is shown in figure 1.1.1.

INCEPTION REPORT Page | 2


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and
Sitalakhya (2nd Phase)

Circular Waterways

Zone:12 ; Ashulia to Zone:10 ; Pagar Mouza to


Kamarpara (Gazipur side) – harbaid
3.75 Km. – 3.068 Km
Zone:11 ; Ashulia to Zone:9 ; Batulia to Uzanpur
Kamarpara (Dhaka side) – – 3.725 Km
3.56 Km.

Zone:8 ; Near
Zone:1 ; Ramchandrapur Sultanakamal and Kanchpur
to Basila – 3.55 Km. Bridge – 5 Km
Zone:2 ; Rayerbazar khal to
Kamrangir Char – 4.45 Km.

Zone:3 ; Near Sadarghat –


1 Km
Zone:7 ; Narayangonj Sailo
to Kumudini – 8.55 Km
Zone:4 ; Hasnabad to
Kawtail – 9.45 Km

Zone:5 ; Fatulla to
Dharmaganj – 3.50 Km Zone:6 ; DEPTC area – 2.50
Km

Figure 1.1: Map showing the project area

INCEPTION REPORT Page | 3


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and
Sitalakhya (2nd Phase)

Figure 1.2: Georeferenced location of Ramchandrapur to Kamrangirchar

INCEPTION REPORT Page | 4


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

1.4 SCOPE OF WORK

It is our understanding that the initial master plan has already been prepared for the entire
route as designated in the DPP. Our responsibility would be to review the DPP, master plan,
feasibility studies and schematic design drawings for planning, architectural, structural and
electro-mechanical point of view and the constructability. The review will include comments
on possible alterations for improvement from a master plan level, followed by architectural
and structural detailed drawings including electro-mechanical solutions with detailed drawings.
The consultant will issue good for construction (GFCs) drawings for inclusion in the tender
documents.

The consultancy services envisage the following scopes:

 Preparation of detail cost estimate, Standard Tender Document (STD), BoQ for each
package as per DPP;

 To provide necessary support in the evaluation process;

 The consultancy services envisage alignment of the walkway in the site, selection of landing
facilities with road linkage, review of the design of walkway, bank protection, quay wall,
reinforced concrete jetty, spuds, steps boundary wall as per site condition;

 Fixation of reinforced concrete jetty/ reinforced concrete steps for loading /unloading of
the vessel;

 Verify the survey and design, updating of design and working drawings, verification of
contractors’ detailed construction environmental health and safety (EHS) plans as per the
EMP;

 Review and approve contractor’s quality management plan, work program, method
statements, material sources, manpower and equipment deployment, construction EHS
plans etc.;

 Ensure the works in strict compliance with the design and specification, issue non-
compliance notification, if required;

 Review and approve the setting out of the works

 Prepare standard formats for recording site records and reporting purpose

 Reconfirm and prepare regular monitoring reports on site-specific environmental issues/


conditions and compliance and prepare and monitor implementation of necessary
mitigation and/or remedial action plans where required;

 Review and finalize the design/ drawing as per site requirement as well as preparation of
new drawing;

 Inspect and supervise the day to day operations and activities to ensure the quality of
material and workmanship;

INCEPTION REPORT Page | 5


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

 Review the progress and resources including key personnel, work plan, materials, and their
sources;

 Review and approve quality assurance plan, conduct the tests to ensure quality of works;

 Conduct regular site meetings to discuss issues and problems affecting the progress, keep
minutes and report the employer accordingly;

 Ensure that all activities and sites including spoil disposal, quarry, borrow, material
crushing, material stockpiling, compaction etc. are operated and reinstated according to
the IEE/ESIA, EMP and contractors’ detailed construction EHS plan requirements;

 Project progress report as per IMED requirement;

 Preparation of variation order and revised DPP as per standard guideline.

INCEPTION REPORT Page | 6


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Chapter 2
2.1 INITIATION OF STUDY
The work was started after a meeting held in the office of the Chief Engineer, BIWTA,
participated by the Executive Engineer (P&D) on behalf of BIWTA and Architect Abu Anas Faisal
(Authorized Representative of Consultant), Team Leader Dr. Ahmadul Hassan, Dr. Md. Monjur
Hossain (Structural Engineer), Abdullah Al Hossain Chowdhury (QCE), Babul Akter (Land
Record Specialist), Md. Salem (Procurement Specialist), Mohammad Rakibur Rahman (RE), Dr.
M. Hussainuzzman (ES), Md. Tarique Saifullah (Electrical Engineer), Mohammad Sayedur
Rahman (Plumbing Engineer), Md. Liakat Ali (Site Engineer-1).

The Project Director depicted the project objectives to enable all relevant team members about
the works to be done as per TOR adequately. Some suggestions have been given to the
followings (1) Detail survey of the portion of the subject river, (2) Boundary Pillar
measurements & effectiveness as per design, (3) Walkway, (4) Landing facilities, (5)
Development of Eco-park locations etc.

Consulting office:
Head Office : House No. 6/10, Block-A
Lalmatia, Dhaka-1208
Inter Space & Dcon Design Studio JV.
Field Office : Sadarghat VIP Lounge
BIWTA Office (adjacent).
2.2 STUDY TEAM
The Study Team comprised of Engineers, Architect, Designer, Land Record Experts, and
Environmentalist etc. who have been engaged from the consortium of Consultant. The key
personnel of the Team is Structural Engineer, Architect, Procurement Specialist,
Environment Specialist, Land Record Specialist, Electrical & Plumbing Engineers & Site
Engineers etc.

2.3 MEETING MINORS


After the commencement the client and the consultant went through several informal and
formal discussion meetings to give this project a head start.

INCEPTION REPORT Page | 7


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

MOM No.: 01

Subject: Immediate initiative to establish Boundary Pillars & other related

Venue: Ancillary WorksDirector’s Office


BIWTA Project

Date: 04 February, 2019 Time: 11.30 AM

Project: Consulting Services for the Construction & Installation of


Demarcation Pillar, Walkway, Bank Protection, Jetty with allied work on
Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya
(2nd Phase)”

Client: Bangladesh Inland Water Transport Authority (BIWTA)

Consultant: Inter Space & Dcon Design Studio JV

Participants:

Client
Project Director

Deputy Project Director

Chief Engineer (Dredging)

Chief Engineer (Civil)

Director (Port, Dhaka)

Joint Director (Land & State)

Superintending Engineer (Dhaka Circle)

Joint Director (Port, Dhaka/Narayangonj)

Executive Engineer (Dhaka/Narayangonj)

Consultant
Mohammad Rakibur Rahman (RE)

Abu Anas Faisal (Architect)

Dr. Md. Monjur Hossain (Structural Engineer)

Agenda:

 Establishment of Boundary Pillars along all the 4 (four) Riversides (i.e. Buriganga,
Turag, Balu and Shitalakya). [Ref. DPP Package No. 16, 17, 18 (page No. 32)]

 Land Development for Eco Parks. [Ref. DPP Package No. 13 (page No. 32)]

INCEPTION REPORT Page | 8


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

 Development works from Kamrangir Char to Basila. [Ref. DPP Package No. 1 (page No.
29)]

 Design and construction of Jetties. [Ref. DPP Package No. 14, 15 (page No. 32)]

 Design considerations from Buriganga to Babubazar area. [Ref. DPP Package No. 3
(page No. 30)
Decisions and Resolutions:

The Project Director welcomed all the participants of the meeting and thanked the
Consultants for attending the site visit program and reconnaissance survey.

The following decisions and resolutions came out from the discussions.
SL
Discussions Decisions & Resolution
No.

Establishment of Boundary Pillars along


all the 4 (four) Riversides

 Discussion took place regarding t h e


 Consultants shall provide t h e
Design Criteria of Pillars.
revised design of pillars within 3
 Structural Engineer (consultant) working days and revised
explained the stability importance of estimate within the next 2
the pillars. working days.
1
 All the high officials (BIWTA) took  BIWTA authority would
participation regarding the high land
cooperate the consultants to
and low land pillar’s top level, Tender
package of pillars and construction prepare tender documents in
methodology of pillars. this regard.

 Consultants asked for the GPS surveys


of the proposed high land and low land
pillars.

Land Development for Eco Parks Eco park’s land areas will be
There is an Instruction from Chairman developed as soon as possible with

2 (BIWTA) that Eco park’s land areas will be bank protection works and fencing.
developed as soon as possible with bank Consultants would provide the
protection works and fencing. The discussion necessary design and action plan with
went on regarding the matter. an estimate within February 2019.

Development works from Kamrangir Char to Consultants will take some more soil
3
Basila test results and topographic surveys

INCEPTION REPORT Page | 9


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

SL
Discussions Decisions & Resolution
No.
Project Director advised the consultants to for this part of the site within February
take some more soil test results and 2019.
topographic surveys for this part of the site.

Design and construction of Jetties  Consultants will visit all the


probable sites for jetties
Discussion held on the functional uses and
within 15 March 2019 and
hazard issues of the jetties. Consultants said
recommend for the jetties.
4 that they have visited almost all the probable
sites for jetties within t h e Dhaka part.  BIWTA will provide
High officials from BIWTA recommended for Bathymetric and
some more visits and studies in this regard. Hydrographic Surveys of the
probable sites.

Design considerations from Buriganga to


Babubazar area

The consultants explained to the BIWTA


authority that as per Chairman (BIWTA) and
Project Director’s instruction, this site is of a Consultants will provide a
5 very prosperous scope of aesthetic and presentation for this site within 30
functional facilities. So special attention to be March 2019.
paid to design this area. Consultants
mentioned that there is limited scope in the
DPP. Authority replied that DPP might be
revised if necessary.

As there was no other point of discussion, the Project Director announced the end of the
meeting with thanks. The meeting ended at 1.30 PM
2.4 FIELD VISIT & RECONNAISSANCE SURVEY
A team composed of engineers, architect, land record experts and BIWTA official visited
the Sadarghat to Babubazar Bridge Location on January 30th, 2019. The team took the GPS
reading of the six jetty locations along the Hasanbad to Katoali portion and studied the area.

INCEPTION REPORT Page | 10


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and
Sitalakhya (2nd Phase)

Figure 2.1: Georeferenced locations of six (6) jetties along the Hasanbad to Katoali

INCEPTION REPORT Page | 11


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and
Sitalakhya (2nd Phase)

Figure 2.2: Photos of field visit & reconnaissance survey

INCEPTION REPORT Page | 12


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and
Sitalakhya (2nd Phase)

Figure 2.3: Photos of field visit & reconnaissance survey

INCEPTION REPORT Page | 13


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and
Sitalakhya (2nd Phase)

Figure 2.4: Photos of field visit & reconnaissance survey

INCEPTION REPORT Page | 14


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

2.5 OBSERVATIONS
The consultant team after reviewing the documents and field visit made some observations
based on information, design, and implementation for each component of the project.

2.5.1 FROM FIELD VISIT


Demarcation Pillars:

 All existing pillars are in the high land area but the base of the pillar is below road
level.

 During rainy season there is a chance of the pillars to go underwater fully or


partially.

 Low land area is located around 5~7m down from road level. For low land
demarcation pillars, proper design consideration must be given for visibility during
monsoon.

 Driven piles might pose construction difficulties.

 The possibility of Erosion.

Jetty:

 A moot issue regarding access road found in “Aliganj Khelar Matth” location.

 To prevent river encroachment in some locations, there is a need for dredging to


construct jetty cum walkway and allow for the adequate draft for the vessels.

 Health & safety measures must be considered in design as some locations there is
an ongoing practice of hazardous material.

Walkway and Bank protection:

 In some locations, existing walkway may be used with some renovation.

 Existing walkways are not continuous throughout the surveyed area. In some
locations, the existing walkways are damaged due to soil subsidence.

 Damaged to walkway due to lack of bank protection.

 Walkway cum jetty may be possible in some locations. However, detail design
considerations are needed.

2.5.2 FROM DESK STUDY


 Material Selection: For the portions where the river is polluted special cement with
appropriate curing and mix ratio to be used for concrete.

 Design Parameters: A comprehensive hydrographical data is needed for the provided


design of the components. The consultant already bought data from government
authority to analysis the hydrographical parameters.

INCEPTION REPORT Page | 15


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

 Architectural Parameters & Beautification: Traditional and cultural spots will be


given special care so that the social aspects of the spots remain unchanged. It is
imperative to provide universal access with sitting arrangement for recreational
purposes along the Sadaghat to Babubazar area. In addition, a proper parking facility
must be provided to accommodate smooth traffic in Sadaghat to Babubazar area.

INCEPTION REPORT Page | 16


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Chapter 3
3.1 TECHNICAL APPROACH AND METHODOLOGY
Following the Terms of Reference (TOR), the whole scope of works can be kept into the main
two activities (Figure 1.1). To perform the assignment efficiently, these two activities have been
sub-divided into some activities as shown in the schematic diagram in Figure 1.2. All the
activities have the related tasks of work which have been listed in Table 1.1. A link between
tasks and the TOR Requirements also has been shown in the figure below.

Activity 2
Activity 1
Construction
Detailed Design
Supervision

Figure 3.5: Main activities of the Methodology of Service

Table 3.2: Activity Group and Tasks arranged by the Consultant

Activity 1 DETAILED DESIGN TOR Reference

Activity 1.1 Preparatory Works

Task 1.1.1 Review of DPP, Feasibility Study & Existing 3


Survey Documents

Task 1.1.2 Review the selection of location and alignment 3


of the proposed area/ bank of the river as per
existing Drawing

Task 1.1.3 Review of Existing Data and Preliminary 3, 11


Engineering Design/ Drawing of proposed
service as per site condition

Task 1.1.4 Preparation of Detailed Work Plan and -


Implementation Schedule

INCEPTION REPORT Page | 17


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Activity 1.2 Survey and Study

Task 1.2.1 Site Investigation, Verify, Collection or/ and 3, 5


Conduct of Topography Survey or
Geotechnical Survey or Hydrographic Survey
Data or further Necessary Survey Data as per
Site Requirements

Task 1.2.2 Propose and Collection of Soil Test & Material 07, 12
Survey Data as per Requirements

Activity 1.3 Detailed Design

Task 1.3.1 Verify or Suggest for any Modification of the 5


Existing Approved Design/ Drawing as per Site
Requirements

Task 1.3.2 Preparation of Detailed Master Plan with 3D 5, 11


Views and Architectural Design/ Drawing
(Plan, Section & Elevation) as per Approved
DPP

Task 1.3.3 Preparation of New Detailed Design/ 5, 11


Drawings (Structural Design) as per Site
Requirements & DPP

Task 1.3.4 Estimation of Quantities/ BoQ Preparation 1

Task 1.3.5 Preparation of Construction Management 06


Plan

Task 1.3.6 Preparation of Quality Assurance and Quality 12


Check Policy

Task 1.3.7 Review EIA, EMP, EMoP and Prepare 05


Environment, Health, and Safety (EHS) Policy

Task 1.3.8 Prepare Standard Formats for Recording Site 9


Records and Reporting purpose

Activity 1.4 Updating Economic/ Financial Analysis and Bid Assistance

Task 1.4.1 Review and Revision of Economic and 1


Financial Analysis

INCEPTION REPORT Page | 18


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Task 1.4.2 Preparation of Standard Tender Documents 1


(STD) as per DPP

Task 1.4.3 Evaluation of Tender 2

Task 1.4.4 Selection and Award of Contractor 2

Activity 1.5 Reporting in Design Phase

Task 1.5.1 Inception Report (end of the 1st month)

Task 1.5.2 Preliminary Design Report (end of 2nd week of 11


the 2nd month)

Task 1.5.3 Draft Final Design Report (i/c Soil Investigation 11


Report) (end of the 2nd month)

Task 1.5.4 Final Design Report (i/c Cost Estimate Report) 01, 11

(end of 3rd month)

Task 1.5.5 Environmental and Social Plan Report 05

Task 1.5.6 Bidding Document Report 01

Task 1.5.7 Bid Evaluation Report 02

Activity 2 CONSTRUCTION SUPERVISION TOR


Reference

Activity 2.1 Supervision Works

Task 2.1.1 Review and Approve Work Program, Quality 5, 6


Management Plan, Manpower & Equipment
Deployment Charter, Construction EHS
(Environmental, Health, and Safety) Plans as
per EMP submitted by the Contractor

Task 2.1.2 Review and Approve Method Statements, 6, 14


Material Source and Quality Assurance Plan
submitted by the Contractor

Task 2.1.3 Issuing Commencement Order to the 8


Contractor

INCEPTION REPORT Page | 19


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Task 2.1.4 Issuing Instructions and Necessary 7


Additional/Modified Drawings to the
Contractor

Task 2.1.5 Verification of the Contractor’s Surveys 5

Task 2.1.6 Review and Approve the setting out of the 8


Contractor’s works

Task 2.1.7 Assessment of the Contractor’s Inputs 16, 8

Task 2.1.8 Ensuring Material Testing and maintaining 7, 12, 14


Quality of Material and Workmanship

Task 2.1.9 Supervise Civil Works as per the Approved 7


Design/ Drawing and Technical Specification
and Issuing Non-Compliance

Task 2.1.10 Ensuring Health and Safety on site as per EHS 16

Task 2.1.11 Prepare and Maintain Site Activities’ Records 7, 9

Task 2.1.12 Liaison with related Services’ Authorities about 15


the progress and Reporting the Employer
accordingly

Task 2.1.13 Assistance and Direction to the Contractor 12

Task 2.1.14 Assistance in Preparation of Variation Order 18


and Revised DPP as per Standard Guideline

Task 2.1.15 Preparation of Monitoring Reports on Site 10


Specific Environmental Conditions and
Compliance and Prepare Mitigation and
Remedial Action Plan.

Task 2.1.16 Monitoring Physical & Financial Progress 13, 15

Activity 2.2 Completion and Taking Over

Task 2.2.1 Inspection, Specifying, arrangement and 7, 10


Supervising Remedial Works as required

INCEPTION REPORT Page | 20


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Task 2.2.2 Inspections/ Punch Lists Preparation and 7


Issuing Certification on Completion and
Taking Over

Task 2.2.3 Dispute Board Assistance 10

Activity 2.3 Guidance on O/M and Environmental & Safety Considerations

Task 2.3.1 Guidance on Operation and Maintenance Plan 13


of Eco Park & others

Task 2.3.2 Supervision and Monitoring of 5


Implementation of EMP after Construction

Activity 2.4 Report in Construction Supervision Phase

Task 2.4.1 Inception Report 15

Task 2.4.2 Quarterly Progress Report 15

Task 2.4.3 Progress Report as per IMED requirements 17

Task 2.4.4 Operation and Maintenance Manual 15

Task 2.4.5 Environmental Monitoring Report 15

Task 2.4.6 Construction Completion Report 15

Task 2.4.7 Service Completion Report 15

INCEPTION REPORT Page | 21


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Review DPP and Feasibility Study


Report

Review Survey & Soil If Not


Test Report Sufficient Conduct Survey
(Geotechnical,
Work/ Data
Hydrographic etc.)
Collection

Review Design/ Drawing & Design


Criteria

Modify Design/ Drawing Prepare Master Plan with


as per site condition 3D View & Architectural
Design

Prepare Cost Estimate


(BoQ)

Prepare Standard Tender Document


(STD)

Evaluation of
Tender

Prepare Format for


Site Monitoring
Records

Figure 3.6: Schematic Diagram showing the Methodology of the Detailed Design Phase
(Activity 1)

INCEPTION REPORT Page | 22


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Figure 3.7: Tentative View of Architectural Perspective 3D View (Part of Master Plan)

Initial Feasibility Study report will be reviewed in detailed and its technical feasibility and
economic viability in relation to project cost will be verified. However, the standards which are
to be taken into consideration of the design are outlined in the Table.

Table 3.3: Design standards proposed to be used in the design

Structural Components Design Standards

Walkway, Quay wall, RCC AASHTO, A Policy on Geometric Design of Highways &
Jetty, Boundary Wall, Bank Streets, 1990 or Geometric Design Guidelines AASHTO
Protection work
Road Design Standards

Design Manual of BWDB

Geometric Design Guidelines AASHTO

Bangladesh National Building Code (BNBC)

BIWTA Design Guideline (if any)

INCEPTION REPORT Page | 23


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Figure 3.8: Bidding Document Procedures

INCEPTION REPORT Page | 24


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Chapter 4
4.1 WORK PROGRAM
As stipulated in the TOR, the consulting services will be implemented within 36 months as
shown in Table 4.3. Accordingly, the consultancy services have been divided into four distinct
phases and have translated the TOR into a feasible, deliverable working plan as presented in
the Work Schedule. From the Work Schedule, the assignment of experts has been prepared.
The summary of the main activities of the whole assignment, content, and duration, phasing
and interrelations and report delivery dates are shown in the following Figure and Table. The
final Work Plan will be finalized after consultation with the client to produce the optimum plan
in order to ensure timely execution of the project within the budget.
4.2 PREPARATION OF REPORTS
Project work schedule is shown in Appendix-01

Manning Schedule is shown in Appendix-02.

Team Composition and Task Assignments shown in Appendix-03.


4.3 ORGANIZATION & STAFFING
As per the Contract Document, the structure and composition of the team for the consultancy
work has been formed. The main disciplines of the assignment, the responsibility of the key
experts and technical staffs have been determined. The organization and staffing have been
reflected in the Team Composition and Task Assignments in Appendix 03 and the Staffing
schedule in Appendix 04. An organization chart illustrating the team structure and its interfaces
with the client and other institutions involved in the project have been provided.

INCEPTION REPORT Page | 25


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and
Sitalakhya (2nd Phase)

Table 4.4: Project Implementation Schedule

Key Activities 2018 2019 2020 2021

N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O

Commencement of
Consulting Services

Completion of Detailed
Design, preparation of
Drawings, Cost Estimate,
BoQ, STD and assistance
in Evaluation Process

Commencement of Civil
Works

End of Civil Works

Termination of
Consulting Services

INCEPTION REPORT Page | 26


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

Figure 4.9: Project Organization Chart

INCEPTION REPORT Page | 27


Consulting Services for “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied work
on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)

4.4 PROJECT WORKFLOW

Figure 4.10: Project Work Flow

INCEPTION REPORT Page | 28


Appendix 01
Project work schedule
1.3.4
1.3.3
1.3.2
1.3.1
1.2.2
1.2.1
1.1.4
1.1.3
1.1.2
1.1.1
Task

Design
Survey
Survey

Modification
Work Plan and

BoQ Preparation
Task Name

as per site condition

Soil Test & Material

Activity 1.3: Detailed Design


Review of location and

Preparation of Detailed

& Architectural Design


Activity 1.2: Survey and Study
Review DPP, Feasibility

Preparation of Structural
Activity 1: DETAIL DESIGN

Study & Existing Survey

Implementation Schedule

Site Investigation, Verify,


Form 5A5: Work Schedule

Activity 1.1: Preparatory Works

Verify/ Suggest for Design

Preparation of Master Plan


Review of Existing Design
alignment of proposed area

Conduct Data Collection of


Start

1/4/19
3/2/19

15/2/19
10/2/19
15/2/19
30/1/19
24/1/19
22/1/19
18/1/19
10/1/19
Finish

1/5/19
9/2/19
9/2/19

16/4/19
30/4/19
17/3/19
20/2/19
31/1/19
25/1/19
25/1/19

6
7
7

30
60
79
30
21
18
15
(Days)
Duration

Month, Quarter,

F
F
F

C
C
C
C
C
C
C
Year
3/1/2019
6/1/2019
9/1/2019
12/1/2019
15/1/2019
18/1/2019
21/1/2019
24/1/2019
27/1/2019
30/1/2019
3/2/2019
6/2/2019
9/2/2019
12/2/2019
15/2/2019
18/2/2019
Q1

21/2/2019
24/2/2019
27/2/2019
3/3/2019
6/3/2019
9/3/2019
12/3/2019
15/3/2019
1 2 3

18/3/2019
21/3/2019
24/3/2019
27/3/2019
30/3/2019
3/4/2019
6/4/2019
9/4/2019
12/4/2019
15/4/2019
4

18/4/2019
21/4/2019
24/4/2019
27/4/2019
30/4/2019
3/5/2019
6/5/2019
9/5/2019
12/5/2019
15/5/2019
5

18/5/2019
21/5/2019
Q2

24/5/2019
27/5/2019
30/5/2019
3/6/2019
6/6/2019
9/6/2019
12/6/2019
15/6/2019
6

18/6/2019
21/6/2019
24/6/2019
27/6/2019
30/6/2019
3/7/2019
6/7/2019
9/7/2019
12/7/2019
15/7/2019
2019

18/7/2019
21/7/2019
24/7/2019
27/7/2019
30/7/2019
3/8/2019
6/8/2019
9/8/2019
12/8/2019
15/8/2019
8

18/8/2019
21/8/2019
Q3

24/8/2019
27/8/2019
30/8/2019
3/9/2019
6/9/2019
9/9/2019
12/9/2019
15/9/2019
9

18/9/2019
21/9/2019
24/9/2019
27/9/2019
30/9/2019
3/10/2019
6/10/2019
9/10/2019
12/10/2019
15/10/2019
18/10/2019
21/10/2019
24/10/2019
27/10/2019
30/10/2019
3/11/2019
6/11/2019
9/11/2019
12/11/2019
15/11/2019
18/11/2019
21/11/2019
Q4

24/11/2019
27/11/2019
30/11/2019
3/12/2019
6/12/2019
9/12/2019
12/12/2019
15/12/2019
18/12/2019
21/12/2019
24/12/2019
27/12/2019
30/12/2019
3/1/2020
6/1/2020
9/1/2020
12/1/2020
15/1/2020
18/1/2020
21/1/2020
24/1/2020
27/1/2020
30/1/2020
3/2/2020
6/2/2020
9/2/2020
12/2/2020
15/2/2020
18/2/2020
Q1

21/2/2020
24/2/2020
27/2/2020
3/3/2020
6/3/2020
9/3/2020
12/3/2020
15/3/2020
18/3/2020
21/3/2020
24/3/2020
27/3/2020
30/3/2020
3/4/2020
6/4/2020
9/4/2020
12/4/2020
15/4/2020
18/4/2020
21/4/2020
24/4/2020
27/4/2020
30/4/2020
3/5/2020
6/5/2020
9/5/2020
12/5/2020
15/5/2020
18/5/2020
21/5/2020
Q2
= Float Task

24/5/2020
27/5/2020
30/5/2020
3/6/2020
6/6/2020
9/6/2020
= Critical Task

12/6/2020
15/6/2020
18/6/2020
21/6/2020
24/6/2020
27/6/2020
30/6/2020
3/7/2020
6/7/2020
9/7/2020
12/7/2020
15/7/2020
2020

18/7/2020
21/7/2020
24/7/2020
27/7/2020
30/7/2020
3/8/2020
6/8/2020
9/8/2020
12/8/2020
15/8/2020
18/8/2020
21/8/2020
Q3

24/8/2020
27/8/2020
30/8/2020
3/9/2020
6/9/2020
9/9/2020
12/9/2020
15/9/2020
18/9/2020
21/9/2020
24/9/2020
27/9/2020
30/9/2020
3/10/2020
6/10/2020
9/10/2020
12/10/2020
15/10/2020
18/10/2020
21/10/2020
24/10/2020
27/10/2020
30/10/2020
3/11/2020
6/11/2020
9/11/2020
12/11/2020
15/11/2020
18/11/2020
21/11/2020
Q4

24/11/2020
27/11/2020
30/11/2020
3/12/2020
6/12/2020
9/12/2020
12/12/2020
15/12/2020
18/12/2020
21/12/2020
work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)”

24/12/2020
27/12/2020
30/12/2020
3/1/2021
6/1/2021
9/1/2021
12/1/2021
15/1/2021
18/1/2021
21/1/2021
24/1/2021
27/1/2021
30/1/2021
3/2/2021
6/2/2021
9/2/2021
12/2/2021
15/2/2021
18/2/2021
Q1

21/2/2021
24/2/2021
27/2/2021
3/3/2021
6/3/2021
9/3/2021
12/3/2021
15/3/2021
18/3/2021
21/3/2021
24/3/2021
27/3/2021
30/3/2021
3/4/2021
6/4/2021
9/4/2021
12/4/2021
15/4/2021
18/4/2021
21/4/2021
24/4/2021
27/4/2021
30/4/2021
3/5/2021
6/5/2021
9/5/2021
12/5/2021
15/5/2021
18/5/2021
21/5/2021
Q2

24/5/2021
27/5/2021
30/5/2021
3/6/2021
6/6/2021
9/6/2021
12/6/2021
15/6/2021
18/6/2021
21/6/2021
24/6/2021
27/6/2021
30/6/2021
3/7/2021
6/7/2021
9/7/2021
12/7/2021
15/7/2021
2021

18/7/2021
21/7/2021
24/7/2021
27/7/2021
30/7/2021
3/8/2021
6/8/2021
9/8/2021
12/8/2021
15/8/2021
18/8/2021
21/8/2021
Q3

24/8/2021
27/8/2021
30/8/2021
3/9/2021
6/9/2021
9/9/2021
12/9/2021
15/9/2021
18/9/2021
21/9/2021
24/9/2021
27/9/2021
30/9/2021
3/10/2021
6/10/2021
9/10/2021
12/10/2021
15/10/2021
18/10/2021
21/10/2021
24/10/2021
27/10/2021
30/10/2021
3/10/2021
6/10/2021
9/10/2021
12/10/2021
15/10/2021
18/10/2021
21/10/2021
Q4

24/10/2021
27/10/2021
30/10/2021
3/10/2021
6/10/2021
9/10/2021
12/10/2021
15/10/2021
18/10/2021
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

21/10/2021
Project Title: Consulting Services for Design review and Construction Supervision of “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied

24/10/2021
27/10/2021
30/10/2021
Project Title: Consulting Services for Design review and Construction Supervision of “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied
work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)”
= Critical Task
Form 5A5: Work Schedule = Float Task

Month, Quarter,
2019 2020 2021
Duration

Year
Task Task Name Start Finish Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
(Days)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
1.3.5 Preparation of 9/5/19 24/5/19 15 F
Construction Management
Plan

1.3.6 Preparation of Quality 10/5/19 9/6/19 30 C


Assurance and Quality
Check Policy

1.3.7 Review EIA, EMP, EMoP 9/3/19 31/3/19 22 F


& Prepare EHS Policy

1.3.8 Prepare Formats for Site 31/3/19 10/4/19 10 F


Activity Records

Activity 1.4: Economic & Financial Analysis, Bid Assistance


1.4.1 Review, Revision of 10/4/19 20/4/19 10 C
Economic & Financial
Analysis

1.4.2 Preparation of STD 20/4/19 30/4/19 10 C

1.4.3 Tender Evaluation 13/5/19 20/5/19 7 C

1.4.4 Contractor Selection & 9/6/19 19/6/19 10 C


Award

Activity 1.5: Reporting in Design Phase


1.5.1 Inception Report (end of 9/2/19 15/2/19 6 F
1st month)

1.5.2 Preliminary Design Report 15/2/19 5/3/19 18 F


(end of 2nd week of 2nd
month)

1.5.3 Draft Final Design Report 1/3/19 15/4/19 45 F


(i/c Soil Investigation
Report) (end of 2nd
month)
1.5.4 Final Design Report (i/c 10/4/19 26/4/19 16 F
Cost Estimate Report)
Project Title: Consulting Services for Design review and Construction Supervision of “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied
work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)”
= Critical Task
Form 5A5: Work Schedule = Float Task

Month, Quarter,
2019 2020 2021
Duration

Year
Task Task Name Start Finish Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
(Days)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
1.5.5 EIA & SIA Report 9/6/19 19/6/19 10 F

1.5.6 BoQ Report 9/6/19 10/6/19 1 C

Activity 2: CONSTRUCTION SUPERVISION

Activity 2.1: Supervision Works


2.1.1 Review & Approve Work 2/5/19 31/7/19 90 C
Program, Quality
Management Plan,
Manpower & Equipment
Deployment Charter, EHS
Plans etc.

2.1.2 Review & Approve 2/5/19 30/8/19 120 C


Method Statements,
Material Source, Quality
Assurance Plan

2.1.3 Issuing Commencement 2/5/19 1/6/19 30 C


Order to the Contractor

2.1.4 Issuing Instructions, 1/6/19 18/10/21 870 C


Addl./Modified Drawing to
the Contractor

2.1.5 Verification of the 1/6/19 28/11/19 180 C


Contractor’s Surveys

2.1.6 Review & Approve setting 1/6/19 21/5/21 720 F


out of the Contractor’s
works

2.1.7 Assessment of the 2/5/19 18/10/21 900 F


Contractor’s Inputs

2.1.8 Material Testing, 1/7/19 20/6/21 720 C


maintaining Quality of
Material & Workmanship
Project Title: Consulting Services for Design review and Construction Supervision of “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied
work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)”
= Critical Task
Form 5A5: Work Schedule = Float Task

Month, Quarter,
2019 2020 2021
Duration

Year
Task Task Name Start Finish Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
(Days)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
2.1.9 Supervise Civil Works as 2/5/19 18/10/21 900 F
per Approved Design/
Drawing

2.1.10 Ensuring Health & Safety 30/8/19 13/10/21 775 C


on site as per EHS

2.1.11 Site Activities’ Records 2/5/19 18/10/21 900 F

2.1.12 Liaison with related 2/5/19 18/10/21 900 C


Services’ Authorities

2.1.13 Assistance and Direction to 2/5/19 18/10/21 900 F


the Contractor

2.1.14 Preparation of Variation 20/6/21 17/11/21 150 C


Order & Revised DPP

2.1.15 Prepare Mitigation & 20/6/21 17/11/21 150 F


Remedial Action Plan

2.1.16 Monitoring Physical & 2/5/19 18/10/21 900 F


Financial Progress

Activity 2.2: Completion & Taking Over


2.2.1 Inspection, arrangement & 21/4/21 18/9/21 150 F
Supervising Remedial
Works

2.2.2 Issuing Certification on 19/8/21 18/10/21 60 C


Completion and Taking
Over

2.2.3 Dispute Board Assistance 20/7/21 18/9/21 60 C

Activity 2.3: Guidance on O/M, Env. & Safety Consideration


2.3.1 Guidance on Operation, 3/12/19 2/1/20 30 F
Maintenance Plan
Project Title: Consulting Services for Design review and Construction Supervision of “Construction & Installation of demarcation pillar, Walkway, Bank Protection, Jetty with allied
work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)”
= Critical Task
Form 5A5: Work Schedule = Float Task

Month, Quarter,
2019 2020 2021
Duration

Year
Task Task Name Start Finish Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
(Days)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
2.3.2 Supervision & Monitoring 30/8/19 18/10/21 780 F
of EMP Implementation

Activity 2.4: Report in Construction Supervision Phase


2.4.1 Inception Report 28/12/19 28/12/19 0 F

2.4.2 1/6/19 1/6/19 0 F


Quarterly Progress Report

2.4.3 Progress Report as per 1/7/19 1/7/19 0 C


IMED requirements

2.4.4 Operation and 22/12/20 22/12/20 0 F


Maintenance Manual

2.4.5 Environmental Monitoring 31/7/19 31/7/19 0 F


Report

2.4.6 Construction Completion 19/8/21 24/8/21 5 C


Report

2.4.7 Service Completion Report 27/10/21 30/10/21 3 F


Appendix 02
Manning Schedule
APPENDIX-02

Project Title: Consulting Services for Design review and Construction Supervision of “Construction & Installation of demarcation pillar, Walkway, Bank Protection,
Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)”

Staffing Schedule Commencement Date: 10.01.2019

Project Period: 2019~2022


Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Task Name Design Stage: (6
Total Staff-Month Input
ID
Months) Construction Supervision Phase (Field): 30 Months
Number of Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Home Field Total
1 Team Leader 6 30 36

2 Structure Engineer 3 1 4

3 Material/ Quality Control Engineer 4 12 16

4 Land Record Specialist 1 1 2

5 Procurement Specialist 1 1 2

6 Resident Engineer/ Senior Engineer 6 30 36

7 Architect 3 1 4

8 Environment Safeguard Specialist 1 1 2

9 Electrical Engineer 1 0 1

10 Plumbing Engineer 1 0 1

11 Site Engineer 1 12 60 72

12 Site Engineer 2

13 Auto CAD Specialist 5 1 6

Total = 44 138 182


Appendix 03

Team Composition and Task


Assignments
APPENDIX-03
Project Title: Consulting Services for Design review and Construction Supervision of “Construction & Installation of demarcation pillar, Walkway, Bank Protection,
Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)”

Team Composition and Task Assignments

Name of Staff Firm/ Organization Areas of Expertise Position Assigned Task Assigned

Environment and
Design, Supervision,
Dr. Ahmedul Hassan Infrastructure Management Team Leader (TL) Overall responsibility in execution of service as per TOR, coordinate all professional inputs
Planning and Management
Solution (EIMS) Ltd.

Environment and Analysis & Design of River bank structure around the Dhaka Circular Waterways,
Structural Design and
Dr. Md. Monjur Hossain Infrastructure Management Structure Engineer (SE) coordinate with Architect & other members, assist Team Leader to complete the design
Analysis
Solution (EIMS) Ltd. works

Work under guidance of TL/RE, establish the work in laboratory, implement quality
Abdullah Al-Hossain Quality Control, Design, Material/ Quality Control
Inter Space assurance & quality control procedure, train & monitor work of Lab Technician & Site
Chowdhury Supervision Engineer (QCE)
Engineer, prepare checklist, approval format & records, control the quality of materials,
workmanship, completion of works

Design, Supervision, Land


Babul Akter DCon Design Studio Land Record Specialist Site invesitgation, Other survey works (Topographic & Hydrographic survey), Soil test
Suvey and Records

Procument as per PPR, Work under TL, prepare the bidding documents for works & goods for construction of
Md. Salem Inter Space Procurement Specialist (PS)
Contract Documentation walkway, RCC jetty with RCC steps/ stairs, bank protection, demarkation pillar, boundary
wall etc.

Design, Supervision,
Mohammad Rakibur Acts as Consultant's supervision team, administer the contractual work, supervise all works,
DCon Design Studio Coordination, Project Resident Engineer (RE)
Rahman quality assurance, work with Site Engineers and Material Engineer, monitor & control of
Management
site records, payments certificates, variation, progress of work and reporting etc.

Architectural Design, Work in close coordination with the TL & the team, prepare land development plan, Master
Abu Anas Faisal DCon Design Studio Architect
Supervision plan, concept/ preliminary Design, detailed Architectural Design

Dr. Miah M. EIA, Environment related Environment Safeguard Work under the guidance of TL & RE, Review & develop EIA/ EMP, support construction
DCon Design Studio
Hussainuzzaman Design Specialist (ES) supervision team in monitoring EMP, EMAPs implementation, specify for remedial action,
assist the project for coordinating with other necessary authorities, conduct training/
orientation to supervision team, project staff & Contractor's personnel on implementation of
ESH, EMAPs policy, monitor & prepare regular progress report related to implementation
of Environment requirement.
Project Title: Consulting Services for Design review and Construction Supervision of “Construction & Installation of demarcation pillar, Walkway, Bank Protection,
Jetty with allied work on Evicted Foreshore Land of the River Buriganga, Turag, Balu and Sitalakhya (2nd Phase)”

Team Composition and Task Assignments

Name of Staff Firm/ Organization Areas of Expertise Position Assigned Task Assigned

Md. Tarique Saifullah DCon Design Studio Electrical Designer Electrical Engineer Responsible for Electrical design preparation

Mohammad Sayedur Supervision, Plumbing


DCon Design Studio Plumbing Engineer Responsible for Plumbing design preparation
Rahman Advisor

Work under the guidance of RE, responsible for day to day field supervision works, qualilty
Md. Liakat Ali DCon Design Studio Construction Supervision Site Engineer 1 (SEng1)
assurance & control, site records, checking payment certificates, preapring variations,
preparing progress monitoring and reporting etc. Assist QCE, ES, SO, EE, SE & Architect
for day to day supervision, monitor & control the quality, environment, social & other
Rezoyan Mahabub DCon Design Studio Construction Supervision Site Engineer 2 (SEng2) works associated with the construction etc.

Architectural and Structural


Sanaul Haque DCon Design Studio Auto CAD Specialist Prepare detailed drawing in 2D & 3D for Architectural & Structural design works on survey
Detailing
activities, assist concerned experts in preparing reports & other drawings etc.