Documente Academic
Documente Profesional
Documente Cultură
SWIMMER
STROKE DAWSON JOEY PACEY JEN JACK
PORAC 2 3 5 1 250
MAYANTOC 6 2 8 4 450
BALANGA 4 7 9 6 380
TAYUG 13 9 15 11 550
1630
DEMAND 360 240 380 450
1430
1 1
PORAC 2 3 5 1 250
2 2 2 2 4
MAYANTOC 6 2 8 4 450
4 2 2 2 3
BALANGA 4 7 9 6 380
9 2 2 2 4
TAYUG + 13 + 9 + 15 250
11 550
+ 240 210 +
+ 240 210 +
DEMAND 360
360 + 240 380
20 + 450 1630
+ 150 200
+
2 1 3 3
2 1 3 3
COLUM
DIFFERENCE 2 5 1 2
2 1 2
1 2
Z =250*1+240*2+210*8+360*4+20*9+150*15+200*11+200*0
Z=8480
M+N-1=8
U1=-10 2 3 5 1
U2=-7 6 2 8 4
U3=-6 4 7 9 6
U4=0 13 9 15 11
Areas
Commercials
1 2 3 4
0 0 0 0 0
1 4 6 5 3
2 7 8 9 7
3 9 10 11 12
4 12 11 10 14
5 15 12 9 16
f3(S3,X3)=P3(X3)+f4(S3-X3)
n=3 S3/X3 f3*S3 X3*
0 1 2 3 4 5
0 0 0 0
1 3 5 5 1
2 7 8 9 9 2
3 12 12 12 11 12 1,2,3
4 14 17 16 14 10 17 1
5 16 19 21 18 13 9 21 2
f2(S2,X2)=P2(X2)+f3(S2-X2)
n=2 S2/X2 f2*S2 X2*
0 1 2 3 4 5
0 0 0 0
1 5 6 6 1
2 9 11 8 11 1
3 12 15 13 10 15 1
4 17 18 17 15 11 18 1
5 21 23 78 19 16 12 78 1
f1(S1,X1)=P1(X1)+f2(S1-X1)
n=1 S1/X1 f1*S1 X1*
0 1 2 3 4 5
5 78 22 22 20 18 15 78 0
NO. OF
AREA COMMERCIALS
1= 0 0
2= 1 6
3= 1 5
4= 23 12
total= 23
A construction company has four projects in progress. According to the current allocation of manpower,
equipment, and materials, the four projects can be completed in 15, 20 ,18 and 25 weeks . Management
wants to reduce the completion times and has decided to allocate an additional $35000 to all four
projects. The new completion times as functions of the additional funds allocated to each projects are
given in the table below. How should the $35,000 be allocated among the projects to achieved the
largest total reduction in completion time? Assume that the additional funds can be allocated only on
blocks of $5000.
f3(S3,X3)=P3(X3)+f4(S3-X3)
n=3 S3/X3 f3*S3 X3*
0 5 10 15 20 25 30 35
0 43 43 0
5 39 40 39 0
10 36 36 37 36 0/5
15 34 33 33 35 33 5/10
20 32 31 30 31 34 30 10
25 30 29 28 28 30 33 28 10/15
30 29 27 26 26 27 29 32 26 10/15
35 28 26 24 24 25 26 28 31 24 10/15
f2(S2,X2)=P2(X2)+f3(S2-X2)
n=2 S2/X2 f2*S2 X2*
0 5 10 15 20 25 30 35
0 63 63 0
5 59 59 59 0/5
10 56 55 56 55 5
15 53 52 52 54 52 5/10
20 50 49 49 50 52 49 5/10
25 48 46 46 47 48 51 46 5/10
30 46 44 43 44 45 47 50 43 10
35 44 42 41 41 42 44 46 50 41 10/15
f1(S1,X1)=P1(X1)+f2(S1-X1)
n=1 S1/X1 f1*S1 X1*
0 5 10 15 20 25 30 35
35 56 55 56 57 59 61 64 67 55 5
Allocation of
funds
Proj. 1 = 5 12
Proj. 2 = 10 13
Proj. 3 = 10 12
Proj. 4 = 10 18
total= 55
Swimmer
Stroke Dawson Joey Pacey Jen Jack
Backstroke 3.9 0 0 3.2 1.6
Breastroke 9.4 0 8.2 0.7 7.8
Butterfly 3.9 0 9.5 1 4.2
Freestyle 1.9 0 2.3 1.2 3.8
Dummy 0 0.9 0 0 0
Swimmer
Stroke Dawson Joey Pacey Jen Jack
Backstroke 3.9 0 0 3.2 1.6
Breastroke 9.4 0 8.2 0.7 7.8
Butterfly 3.9 0 9.5 1 4.2
Freestyle 1.9 0 2.3 1.2 3.8
Dummy 0 0.9 0 0 0
Swimmer
Stroke Dawson Joey Pacey Jen Jack
Backstroke 3.9 0.7 0 3.2 1.6
Breastroke 8.7 0 7.5 0 7.1
Butterfly 3.2 0 8.8 0.3 3.5
Freestyle 1.2 0 1.6 0.5 3.1
Dummy 0 1.6 0 0 0
Swimmer
Stroke Dawson Joey Pacey Jen Jack
Backstroke 3.9 0.7 0 3.2 1.6
Breastroke 8.7 0 7.5 0 7.1
Butterfly 3.2 0 8.8 0.3 3.5
Freestyle 1.2 0 1.6 0.5 3.1
Dummy 0 1.6 0 0 0
Swimmer
Stroke Dawson Joey Pacey Jen Jack
Backstroke 3.9 1.9 0 4.4 1.6
Breastroke 7.5 0.3 6.3 0 5.9
Butterfly 2 0 7.6 0 2.3
Freestyle 0 0 0.4 0.2 1.9
Dummy 0 2.8 0 1.2 0
Swimmer
Stroke Dawson Joey Pacey Jen Jack
Backstroke 3.9 1.9 0 4.4 1.6
Breastroke 7.5 0.3 6.3 0 5.9
Butterfly 2 0 7.6 0 2.3
Freestyle 0 0 0.4 0.2 1.9
Dummy 0 2.8 0 1.2 0
Electricity 20 units
Water heating 10 units
Space heating 30 units
The size of the roof limits the solar heater to 30 units, but there is no limit to the electricity
and natural gas available. Electricity needs can be met only by purchasing electricity (at a
cost of P50 per unit). Both other energy needs can be met by any source or combination of
sources. The unit costs are as follows:
Demand 20 10 30 70
M-50 30 10 0
30 10 0
Col. Diff. 30 10 0
30 10
20 40
U1=0 + +
50 90 80 0
10 30
U2=0 +
+ M 60 50 0
10 20
U3=-10 + +
M 30 40 0
50 10 50
30 10 40
A owner of a chain of three grocery stores has purchased five crates of fresh
strawberries. The estimated probability distribution of potential sales of the
strawberries before spoilage differs among the four stores. Thefore , the owner wants
to know how to allocate five crates to the four stores to maximize expected profit.
For administrative reasons, the owner does not wish to split crates between stores,
However, he is willing to distribute no crates to any of his stores
The following table gives the estimated profit at each store when it is allocated
various number of crates
Store
Crates
1 2 3 4
0 0 0 0 0
1 3 6 8 2
2 11 12 10 9
3 16 15 13 14
4 18 19 18 18
5 23 22 20 23
f3(S3,X3)=P3(X3)+f4(S3-X3)
n=3 S3/X3 f3*S3 X3*
0 1 2 3 4 5
0 0 0 0
1 2 8 8 1
2 9 10 10 10 1,2
3 14 17 12 13 17 1
4 18 22 19 15 18 22 1
5 23 26 24 22 20 20 26 1
f2(S2,X2)=P2(X2)+f3(S2-X2)
n=2 S2/X2 f2*S2 X2*
0 1 2 3 4 5
0 0 0 0
1 8 6 8 0
2 10 14 12 14 1
3 17 16 20 15 20 2
4 22 23 22 23 19 23 1,3
5 26 28 29 25 27 22 29 2
f1(S1,X1)=P1(X1)+f2(S1-X1)
n=1 S1/X1 f1*S1 X1*
0 1 2 3 4 5
5 29 26 31 30 26 23 31 2
Store Crates
1= 2 11
2= 2 12
3= 1 8
4= 0 0
total= 31
A purchasing agent must buy for his company, a special alloy in a market that trades only once a week and
the weekly prices are independent. Each week, there is a 20% chance that the alloy will cost PhP 100,000,
50% chance that it will cost PhP 110,000, and 30% that it will cost PhP 120,000. The agent knows that in
order to meet the company's production schedule, the alloy must be bought within the next month (4
trading weeks). Find the policy that the agent must adopt in purchasing the alloy.
Optimal:
If Price is 10 P
X1 If Price is 11 NP
If Price is 12 NP
If Price is 10 P
X2 If Price is 11 NP
If Price is 12 NP
If Price is 10 P
X3 If Price is 11 P
If Price is 12 NP
If Price is 10 P
X4 If Price is 11 P
If Price is 12 P