Sunteți pe pagina 1din 4

Technical Briefing plant performance

Solar O&M in the Middle East:


technical challenges and solutions

Operations and maintenance | From sandstorms to extreme heat, solar installations in the Middle East
face some unique operational and technical challenges. Experts from Jordan-based developer and
O&M specialist MASE describe some of the innovative solutions emerging to keep plants running in
the harshest conditions

T
he Middle East region has over facing unique technical and operational Extremely soiled solar PV capacity, corresponding to
the decade experienced an challenges not seen in other regions PV panels in approximately 5% of the country’s total
Jordan. Dust
unprecedented growth in solar such as Europe and the United States power generation. While traditionally
is one of the
energy, with some countries targeting where solar PV markets are generally region’s biggest Jordan has relied on 3.5GW of diesel- and
a triple-digit megawatt penetration of more established. Local O&M firms such challenges gas-fired conventional power plants for
solar capacity. Developers, contractors, as MASE with acute knowledge of the energy generation, plans are underway to
lenders and consultants now consider operational particulars are pioneering add a further 450MW of solar PV capacity
the Middle East region as one of the solutions to overcome these challenges over the next two years, boosting the
most promising solar energy markets. and are harvesting valid and reliable data total solar PV penetration in the overall
Pioneering countries such as Jordan, UAE in the process. This feedback is proving mix to over 10%. The Jordanian grid is
and Morocco have already interconnect- essential to stakeholders in the develop- managed by the National Electricity
ed over 500MW of solar capacity onto ment of a bespoke technical blueprint Power Company (NEPCO) and is intercon-
their electricity grids. to cater for the Middle East region’s nected to neighbouring Egypt and Syria
However, whilst solar energy sees growing demand for solar energy. with plans to connect to Iraq and Saudi
rapid penetration in the Middle East Arabia. This article contains data and
and more facilities interconnect to Background analysis gathered by MASE, a regional
the region’s grids, solar plant opera- Over the past four years, Jordan has operations and maintenance firm with
tors and asset management firms are interconnected over 200MW of utility over 80MW solar assets under care.

www.pv-tech.org | December 2017 | 67


plant performance Technical Briefing

As local and international solar O&M to decide when it is best to clean. As


firms measure up to manage utility sandstorms often appear haphaz-
solar PV plants currently operational ardly, site operators in Jordan refrain
in Jordan and elsewhere in the Middle from washing solar panels in the days
East region, they are having to deal immediately following a sandstorm in
with unique technical and opera- order to avoid adverse further escala-
tional challenges and innovate bespoke tion of soiling.
solutions to overcome them. Oftentimes, As mentioned earlier, whilst soiling
harsh weather conditions and unstable may not pose a significant operational
grid behaviour adversely impact the challenge elsewhere, it is a main concern
performance of solar PV plants by a daily for local operators in the Middle East.
factor of up to 40%. Also, soiling and Figure 1. Impact of soiling on daily energy production MASE’s experience is summarised as
high temperatures are proving to be follows:
more significant operational factors than • On average, module washing in
originally anticipated. intervals not exceeding 30 days will
maintain soiling losses to below 2%.
The impact of soiling on plant Longer intervals may result in signifi-
generation cant impacts on performance by up to
More than 80% of the Middle East region 40%;
is desert and receives fewer than 25 • Tracking sandstorm behaviour is
centimetres of rainfall a year. This trans- essential and must be evaluated
lates to a particular technical challenge by site operators when scheduling
for site operators who in many cases washing sequences to avoid adverse
are expected to stand behind perfor- impacts;
mance guarantees often benchmarked • Dry cleaning is not recommended,
against less harsh foreign topographical unless coupled with advanced clean-
conditions. Whilst soiling is a common Figure 2. A solar In the case above, the performance ing robots, which are generally yet to
concern for solar PV operators around PV plant in the benefits are unmistakable and the plant prove their effectiveness in the Middle
midst of a severe
the world, it poses a significant opera- is currently washed on average once a East.
sandstorm in
tional concern in the Middle East region, Jordan month during the summer season.
especially given that the majority of In addition to soiling, haphazard Power limitation and equipment
solar pants are constructed in remote sandstorm behaviour is another signifi- design
desert locations, by virtue of the higher cant weather anomaly common to Whereas soiling is mostly an operator-
levels of irradiation in such locations. the region and one that site operators managed concern, equipment manufac-
In some extreme cases, soiling losses must closely monitor. With its desert turers are responsible for thoroughly
of up to 30% have been recorded when conditions, the Middle East region is evaluating how their products perform
solar panels are left unwashed over prone to harsh sandstorms that often when operating in harsh Middle Eastern
relatively short periods of time (less than last for days and may reappear at weather conditions. The case for
60 consecutive days). The following data random intervals. This poses a particu- region-tailored equipment may require
was collected from a solar plant located lar challenge to site operators, who will commercial evaluation, but PV module
in Azraq, Jordan, a desert city to the need to actively analyse area-specific and inverter manufacturers need to
north east of the country. weather forecasts and track sandstorm consider that while their products may
As Figure 1 demonstrates, the severe behaviour. This may be an alien task to be suitable for one region they may not
soiling recorded not only impacts the operators in other parts of the world be for others.
overall production curve, but also but is extremely relevant to site opera- Unsuitable inverter design and
flattens the peak point during which tors in the Middle East. To manage the inadequate heat management have
the plant is expected to generate at its Figure 3. An impact of sandstorms on performance, been flagged as two of the main issues
event of Inverter
full capacity. In the case demonstrated local O&M operators use multiple site curtailing the performance of solar
shutdown due
in Figure 1, the plant was left unwashed to high tempera- reference cell data gathered from the plants in the Middle East. Inverter
for two consecutive months during the ture site coupled with weather forecasts stations, which are typically designed to
summer season (August and Septem-
ber) and was fully washed in October
using water and specialised mechanical
machinery.
Even though soiling can be managed
by increasing the frequency at which
solar panels are washed, site operators
and plant owners must evaluate the
economic cost benefit of each additional
wash given the scarcity of suitable water
sources in most countries in the region.

68 | December 2017 | www.pv-tech.org


plant performance Technical Briefing

plant’s SCADA shown in Figure 4.


For this particular plant, the recorded
losses of power due to inadequate
temperature tolerances add up to
460kWh per day or 2% of the plant’s
daily power, a significant concern when
it is a daily occurrence.
To overcome this issue, MASE
site operators installed separate air
conditioning units which feed off the
inverter’s auxiliary power supply and
Total Energy Lost per Day: 462.3 kWh  Figure 4. Two subsequent events are only triggered during times of
of inverter shutdown due to high peak heat as recorded by the plant’s
Period 1 Period 2 temperature
weather stations. While this solution
Time Power (kW) Time Power (kW)
has eliminated losses due to inverter
 Figure 5. Inverter operation data downtime for the time being, it is
14:25 718.5
15:45 693.8 and curtailment analysis understandably temporary and not
14:30 0
15:50 0
ideal. A permanent solution requires
14:35 0
xxx 15:55 0 proper inverter design that takes into
14:40 0
16:00 0 account the Middle East’s harsh condi-
14:45 0
16:05 0 tions and excessive high temperatures
14:50 0
16:10 0 during summer periods. Some inverter
14:55 700.4
16:15 661.7 manufacturers have taken steps to that
Total 20 minutes Total 20 minutes end and now offer inverter stations with
Downtime Downtime more powerful cooling systems and
Energy Lost 236.4 Energy Lost 225.9 also outdoor solutions that are meant
(kWh) (kWh)  Figure 6. Inverter operation when
to eliminate excessive heat resulting
properly cooled and ventilated
from the containerised enclosure. The
benefits of these bespoke solutions
include better performance, lower O&M
costs and higher plant availability. When
properly designed to withstand the
region’s specific weather conditions, the
inverter would otherwise operate as
demonstrated by the trend illustrated
in Figure 6.
In addition to the inverter stations,
ancillary equipment such as array boxes
and string combiner boxes also suffer
withstand predictable weather condi- to tolerate temperature levels slightly from excessive heat and dust build-up
tions of Europe, perform poorly in the beyond those limits. The power trend as a result of poor design. Typically, array
Middle East. Consequentially, site opera- in Figure 3 corresponds to a standard boxes and ancillary containers ventilate
tors have had to cope by implement- inverter station with an internal temper- through standard mesh filtration as
ing intuitive but temporary solutions ature tolerance of 65 degrees Celsius, shown in Figure 7 on the following page.
to overcome cooling and ventilation after which the inverter shuts down to This has been found to be ineffective
complications. protect itself and its ancillary equipment in harsh desert conditions. Oftentimes,
Data has shown that inadequate from overheating. significant amounts of pulsed sands
internal cooling results in daily plant The inverter station to which the have been recorded, causing the follow-
shutdowns of up to 15 minutes per day graph corresponds is of the enclosed ing:
during the summer season. For develop- type and utilises air flow cooling, which • Array box overheating, thus damag-
ers and plant owners, this translates to may be adequate in some regions but ing string monitoring sensors and
a bearing on their revenue stream and has proven to be impaired when faced burning fuses;
may on occasion hamper their ability to with Jordan’s hot summer climate. The • Dust accumulation, requiring more
meet financial and contractual obliga- graph demonstrates that once the frequent cleaning;
tions. For operators, inverter downtime internal cabin temperature reaches 65 • Degrading of IP protection features.
will directly impact their performance degrees Celsius, the inverter shuts down To solve this significant problem, MASE
indicators and decrease plant avail- for up to 15 minutes until its internal has worked with array box suppliers
ability. equipment cools down. On some on a more potent filtration system that
Inverter stations typically operate occasions, the inverter stations shuts is aimed at avoiding the accumulation
within a set range of internal tempera- itself down more than once a day as of pulsed sand in and around the array
ture parameters and are also designed demonstrated by the excerpt from the boxes. The solution, which is shown in

70 | December 2017 | www.pv-tech.org


Technical Briefing plant performance

Grid instability Authors


Data recently analysed by MASE has shown
that the Jordanian grid is considerably Tareq Khalifeh is director of
operations at MASE, a utili-
unstable, with frequency fluctuations
ty-scale solar energy devel-
recorded on a daily basis. This has been oper, operator and asset
found to adversely impact the daily perfor- manager based in Jordan
mance of solar PV plants as the Jordanian (www.mase-energy.com). He has over
grid code currently applied to renewable seven years’ experience in originating,
energy generating units requires compli- developing, operating and managing
ance with certain active power control utility PV plants across the Middle East
region. Tareq is an engineer, holds a mas-
covenants as shown in Figure 8.
ter’s degree in energy trade and finance
Figure 7. Standard versus enhanced array box filtration As shown in this figure, renewable and has a professional background in
energy generating units (whether solar or management consulting, utilities, project
wind) are required to gradually reduce their finance and solar asset management.
active power, while in operation, in cases In September 2016, the Middle East
of grid frequency exceeding 50.2Hz and Solar Industries Association (MESIA) and
disconnect from the grid in cases of grid Intersolar Middle East awarded Tareq
the highest-category Solar Pioneer gold
frequency exceeding 51.5Hz.
award in recognition of his achievements
Compliance with these grid requirements in advancing solar across the Middle East
under Jordan’s current grid conditions has region.
resulted in power limitations of up to 15%
on a daily basis, the reason being Jordan’s
unstable grid frequency as demonstrate by Ady Almadanat has over
the trend in Figure 9. The grid frequency three years’ experience
in the areas of solar plant
data shown in Figure 9 is recorded by a solar
operations, maintenance
PV plant’s SCADA over two days of normal and management. He is
Figure 8. Active power control requirements – Jordanian Grid
Code operation. currently responsible for operating solar
Site operators have little to no control PV assets of over 15MW in cumulative
over the grid frequency. On the other hand, capacity and manages an array of tasks
grid management is the exclusive responsi- including preventive, corrective and con-
bility of the grid operator, the entity which ditional maintenance as well as analysis
and reporting. Ady has a university
also determines the grid code and operating
degree in renewable energy engineer-
requirements. ing and is a principal member of MASE’s
The recommendations arising out of the O&M team.
observations summarised in this section are:
• When assessing the technical feasibil-
ity of introducing renewable energy Omar Baker is experienced
generating units into their network, in the design, engineering
and construction of solar
Figure 9. Recorded grid frequency grid operators need to understand the
PV plants with a focus on
coherent operational characteristics of distributed and utility solar.
these generating units and their poten- He operates and maintains a portfolio
the images shown in Figure 7, is perma- tial impact on the behaviour of the grid; of over 400 distributed solar PV plants
nent and has proven to be effective in • Project developers and operators must across Jordan and manages their peri-
protecting the delicate contents of the actively evaluate the relevant grid codes odical maintenance, troubleshooting,
array boxes. and regulations as part of their overall reporting and analysis tasks. Omar has a
university degree in electrical engineer-
In conclusion, the following recom- technical due diligence and engage in
ing and is a principal member of MASE’s
mendations form the outcome of these a discussion with grid operators on the O&M team.
technical concerns: susceptibility of operational parameters
• Inverter manufacturers and ancillary and regulations;
equipment suppliers must account • As part of their overarching approach Haya Shahatit is involved
for extreme weather conditions and towards renewable energy infiltration, in the origination, imple-
topography of the Middle East when regulators and grid owners must develop mentation and operations
of MASE’s diverse portfolio
designing the equipment; long-term plans to ensure the grid’s
of retail and utility solar PV
• Inverter and balance of system suppli- technical sustainability by implementing plants under management. She holds a
ers should work on enhancing filtra- supplementary projects such as energy degree in electrical power and energy
tion components to protect equip- storage aimed at stabilising and upgrad- engineering and has extensive experi-
ment from severe sandstorms and the ing the grid.  ence in project management, technical
accumulation of pulsed sand; analysis and reporting. She is an active
• Inverter behaviour must be improved member of MASE’s O&M team.
On p.72 Fraunhofer CSP researchers describe how to
to optimise performance and behav-
determine soiling losses on PV modules in desert regions
iour during periods of excessive heat.

www.pv-tech.org | December 2017 | 71

S-ar putea să vă placă și