No SO Number Order Expired Date Equipment Area

1 4510110659 WIF.AI2.3001.05 29-Mar-18 PSV BELIDA


2 4510110659 WIF.AI2.3001.05 29-Mar-18 PSV BELIDA
3 4510110659 WIF.AI2.3001.05 29-Mar-18 PSV BELIDA
4 4510110659 WIF.AI2.3001.05 18-Mar-18 PSV BELIDA
5 4510110659 WIF.AI2.3001.05 20-Mar-18 PSV BELIDA
6 4510110659 WIF.AI2.3001.05 20-Mar-18 PSV BELIDA
7 4510110659 WIF.AI2.3001.05 8-Dec-18 PSV BELIDA
8 4510110659 WIF.AI2.3001.05 8-Dec-18 PSV BELIDA
9 4510110659 WIF.AI2.3001.05 29-Nov-18 PSV BELIDA
10 4510110659 WIF.AI2.3001.05 29-Nov-18 PSV BELIDA
11 4510110659 WIF.AI2.3001.05 14-Mar-18 PSV BELIDA
12 4510110659 WIF.AI2.3001.05 1-Apr-18 PSV BELIDA
13 4510110659 WIF.AI2.3001.05 31-Mar-18 PSV BELIDA

No SO Number Order Expired Date Equipment Area


1 4510110659 WIF.AI2.2001.03 22-Sep-18 PSV KERISI
2 4510110659 WIF.AI2.2001.03 11-Oct-18 PSV KERISI

No SO Number Order Expired Date Equipment Area


1 4510110659 WIF.AI2.2001.03 24-Apr-18 PV KERISI
2 4510110659 WIF.AI2.2001.03 24-Apr-18 PV KERISI
3 4510110659 WIF.AI2.2001.03 24-Apr-18 PV KERISI
TOTAL

No SO Number Order Expired Date Equipment Area


1 4510110659 WIF.AI2.2001.01 20-Nov-18 PV BELANAK
2 4510110659 WIF.AI2.2001.01 20-Nov-18 PV BELANAK
3 4510110659 WIF.AI2.2001.01 20-Nov-18 PV BELANAK
4 4510110659 WIF.AI2.2001.01 20-Nov-18 PV BELANAK
5 4510110659 WIF.AI2.2001.01 20-Nov-18 PV BELANAK
6 4510110659 WIF.AI2.2001.01 20-Nov-18 PV BELANAK
7 4510110659 WIF.AI2.2001.01 20-Nov-18 PV BELANAK

No SO Number Order Expired Date Equipment Area


1 4510110659 WIF.AI2.3001.06 24-Apr-18 PV HANGTUAH
TOTAL

No SO Number Order Expired Date Equipment Area


1 4510110659 WIF.AI2.3001.06 3-Jun-18 ELECTRICALHANGTUAH
TOTAL
Functional Location Description of functional location Rate
ID-F-BA-DA-20-2PSV2316 VALVE,PRESSURE SAFETY OF PBA2230A 2,065,908.00
ID-F-BA-DA-20-2PSV2317 VALVE,PRESSURE SAFETY OF PBA2230B 2,065,908.00
ID-F-BA-DA-20-2PSV2318 VALVE,PRESSURE SAFETY OF PBA2230C 2,065,908.00
ID-F-BA-DA-21-PSV2208 VALVE,PRESSURE SAFETY OF KPT2260 2,065,908.00
ID-F-BA-DA-22-PSV1001 VALVE,PRESSURE SAFETY OF 22MBF001 2,065,908.00
ID-F-BA-DA-22-PSV1002 VALVE,PRESSURE SAFETY OF 22MBF001 2,065,908.00
ID-F-BA-FS-30-00098SV VALVE,PRESSURE SAFETY OF KPT2201 2,065,908.00
ID-F-BA-FS-30-00096SV VALVE,PRESSURE SAFETY OF KPT6410 2,065,908.00
ID-F-BA-LG-45-8PSV4807A VALVE,PRESS.SAFETY OF MBD8481 2,065,908.00
ID-F-BA-LG-45-8PSV4807B VALVE,PRESS.SAFETY OF MBD8481 2,065,908.00
ID-F-BA-LG-60-8PSV7001A VALVE,PRESSURE SAFETY OF HBG8700 2,065,908.00
ID-F-BA-WB-20-20PSV1002A VALVE,PRESS.SAFETY OF 20MBD4140 2,065,908.00
ID-F-BA-WB-20-20PSV1002B VALVE,PRESS.SAFETY OF 20MBD4140 2,065,908.00
26,856,804.00

Functional Location Description of functional location Rate


ID-F-KI-CP-23-23PSV0271 VALVE,PRESSURE SAFETY OF 23MAJ050 2,065,908.00
ID-F-KI-CP-23-23PSV0204A VALVE,PRESS.SAFETY OF 2ND STAGE COMPR. 2,065,908.00
4,131,816.00

Functional Location Description of functional location Rate


ID-F-KI-CP-20-20VZZ050B FAN,GAS SEPARATOR PROD.COOLER "B" 2,661,843.00
ID-F-KI-CP-23-23HAL251A COOLER,EXPORT COMPRESSOR DISCHARGE "A" 2,661,843.00
ID-F-KI-CP-23-23HAL251B FAN,EXPORT COMPR.DISCHARGE COOLER "B" 2,661,843.00
TOTAL 7,985,529.00

Functional Location Description of functional location Rate


ID-F-BK-FP-61-61MAJ017A FILTER,SEA WTR.FINE "A" 2,661,843.00
ID-F-BK-FP-61-61MAJ017B FILTER,SEA WTR.FINE "B" 2,661,843.00
ID-F-BK-FP-20-20MBD002 SEPARATOR,HP PRODUCTION 2,661,843.00
ID-F-BK-FP-61-61MAJ016B FILTER,SEAWATER COARSE "B" 2,661,843.00
ID-F-BK-FP-61-61MAJ016C FILTER,SEAWATER COARSE "C" 2,661,843.00
ID-F-BK-FP-61-61MAJ016D FILTER,SEAWATER COARSE "D" 2,661,843.00
ID-F-BK-WA-60-60MBF102 SCRUBBER,UTILITY GAS 2,661,843.00
18,632,901.00

Functional Location Description of functional location Rate


ID-F-HT-MU-22-22MAJ002 FILTER,BELANAK GAS 2,661,843.00
TOTAL 2,661,843.00

Functional Location Description of functional location Rate


ID-F-HT-MU-82-82EN001 SWITCHGEAR,20-201 LV METAL ENCLOSED 3,522,638.00
TOTAL 3,522,638.00
SUMMARY OF EQUIPMENT

Expired Date Equipment Qty. Total


(Month)

Oct-18 PSV 6
PL 8 17
SKKP 3

Nov-18 Crane 2
PL 2
PV 43 56
RE 5
SKKP 4

Dec-18 PSV 5
6
SKKP 1

Jan-19 RE 8
PL 1 16
PSV 7

Feb-19 PSV 2
4
CRANE 2

Mar-19 CRANE 1
PL 3
126
PV 116
RE 6

May-19 PSV 7
12
RE 5

Jun-19 PL 2
2

Jul-19 EL 31
31

Aug-19 EL 11
15
CRANE 4

Sep-19 SKKP 2
13
PSV 11

Oct-19 EL 3
PL 6 85
PSV 76

Nov-19 CRANE 2
51
51
PSV 49

Dec-19 PSV 24
CRANE 1
PL 8 70
PV 29
RE 8
63
Date Equipment Qty. Remarks
RE 8 have been issued
PLO 1 have been issued
PSV 4 have been issued
EL 13 have been issued
EL 16 have been issued