Documente Academic
Documente Profesional
Documente Cultură
27
Hermann Koch
Contents
27.1 Basics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 508
27.1.1 Basic Explanation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 508
27.1.2 Properties of the Insulating Gas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 509
27.1.3 Definition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 509
27.1.4 Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 510
27.2 Ratings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 515
27.2.1 GIL Electrical Parameters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 515
27.2.2 Directly Buried GIL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 516
27.2.3 Thermal Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 516
27.2.4 Short-Time Rating . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 517
27.2.5 Insulation Coordination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 518
27.2.6 Standard Values . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 519
27.2.7 Capacity of GIL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 521
27.3 Installation Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 523
27.3.1 Directly Buried GIL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 523
27.3.2 GIL in Structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 528
27.3.3 Automated Laying Processes of GIL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 535
27.4 Environmental Impact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 537
27.4.1 Environmental Life Cycle Assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 537
27.4.2 General Environmental Aspects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 538
27.4.3 Magnetic Fields . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 538
27.4.4 Environmental Aspects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 539
27.5 Long-Term Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 539
27.5.1 Feasibility Study of 420 kV GIL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 539
27.6 Example Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 540
27.6.1 PP9 Saudi Arabia . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 540
27.6.2 Limberg, Austria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 541
27.6.3 Kelsterbach GIL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 542
H. Koch (*)
Gas Insulated Technology, Power Transmission, Siemens, Erlangen, Germany
e-mail: hermann.koch@siemens.com
27.1 Basics
27.1.3 Definition
to provide electrical insulation. The conductors are held in position by solid support
insulators. The conductors of each phase may be located within separate enclosures
(single phase enclosed). Compensation for thermal expansion is provided, often by
sliding contacts in the conductor and, where the enclosure is free to move (i.e., in
tunnel or trough installations), by bellows as for long GIS bus bars. The GIL is
divided along its length into separate gas compartments. GIL dimensions are deter-
mined by dielectric, thermal, and mechanical considerations. Conductor and enclo-
sure diameters and thicknesses and gas composition and pressure may be varied
according to the application to provide an optimum solution. In many cases,
dielectric considerations will be predominant in determining dimensions, and the
required current rating will be achieved without difficulty. For more highly rated
circuits, thermal considerations may be predominant, and larger dimensions will be
chosen to maintain temperatures within acceptable limits.
• Technical:
• The overall losses are relatively low, because of large conductor cross sections.
• No significant dielectric losses.
• Ratings of 2000 MVA with a single circuit and directly buried without cooling.
• Low capacitance per unit length.
• Reactive compensation not needed even for longer lengths.
• Above ground, trough/tunnel, or directly buried installation is possible
• A GIL is immune to weather conditions: snow, ice, wind, and pollution.
• Environmental:
• No visual impact
• Low external power frequency electromagnetic fields
• No audible noise
• No risk of fire
• SF6 gas handling and management
• Economic:
• Cost of a GIL is greater than an equivalent overhead line.
• The comparative cost with cable depends on circuit ratings and installation
techniques.
All voltages for HV equipment are given as IEC Um, i.e., the highest voltage for
equipment. For GIS and GIL, the rated voltage Ur is equal to the highest voltage for
equipment, i.e., Ur=Um, according to IEC 60038 of TC 8 (IEC standard 2009).
Moreover, in this section the term ampacity is often used. Its genesis comes from
the two words ampere and capacity. It means the current carrying capacity or rated
normal current (Hillers and Koch 1998a; Alter et al. 2002).
27.1.4 Description
Gas insulated line (GIL) is the IEC acronym. Historical acronyms are GITL for gas
insulated transmission line and CGIC for compressed gas insulated cables.
27 Gas Insulated Lines (GIL) 511
GILs are the direct development of a SF6 insulated substation (or gas insulated
substation with acronym GIS), but differently from GIS, GIL does not have
switching or breaking functions.
In the past, GILs were called compressed gas insulated cables with acronym
CGIC. They were considered as “special cables” belonging to the family of insulated
cables. GIL is an electric transmission line, namely, it serves to transmit electric
active power (and on the time domain, electric energy) over a given distance.
Even if GIL could be used as a distribution line in LV and MV levels, its economic
burden confines and justifies its use only at HV levels as a transmission line.
It is well known that the isolated phase bus ducts have a structure similar to GILs
but are often used at MV levels for connecting generators to step-up transformers in
power plants. These MV isolated phase bus ducts are insulated with air under
atmospheric pressure and are manufactured, as abovementioned, with the same
general GIL structure but with larger diameters (since the air has a dielectric strength
which is one third of the most used gas, i.e., sulfur hexafluoride or SF6 under a given
pressure) and spacing.
There are two different kinds of GIL: single-phase (see Fig. 27.1) and the three-
phase design (see Fig. 27.2). The GIL configuration with three conductors in one
enclosure does not avoid phase-to-phase faults and significant forces between
conductors and, so far, has not been used in a practical application.
The GIL construction is composed of three tubular enclosures (made of high-
conductivity aluminum or aluminum-alloy) where each tubular phase conductor
(aluminum) is held in a centered position by epoxy resin insulators (see Fig. 27.3).
The GIS and GIL manufacturers have made continuous improvements over the
last 30 years to make the GIL virtually leak-free. The need for leak-tight GIL systems
is also driven by environmental concerns. Current standards (both IEEE and IEC)
400 – 550 mm
150 – 200 mm
5 – 10 mm
10 – 20 mm
1 2 3
4 5 6
800 – 1300 mm 800 – 1300 mm
Fig. 27.1 Indicative dimensions for a flat single-phase enclosed GIL (420–550 kV rated voltage).
Typical weight of one pipe without gas = 30 [kg/m] 60 [kg/m]. Typical diameters are
400–550 mm
512 H. Koch
6 – 8 mm
13 mm
Inner
Conductor
Outer
enclosure
require GIL systems to lose no more than 0.5% of their volume per year. Designs for
both welded and flange bolted GIL have improved to the point where meeting and
exceeding the required tightness standards is of no concern. In the case of welded
GIL, the gas tightness is even higher, e.g., the first welded GIL installation from
1976 is still in service with the first gas fill, exhibiting effective gas tightness without
any losses (Baer et al. 1976; Bär et al. 2002).
The space between phase conductor and enclosure is filled with an insulating gas
which must withstand the phase-to-earth voltage. This insulating gas can be pure SF6
under pressures of about 0.3–0.5 [MPa] or a SF6/N2 mixture (typical ratio of 10–20%
SF6 to 90–80% nitrogen) under higher pressures (up to 1.0 MPa): this mixture is
more environmentally friendly and less expensive.
27 Gas Insulated Lines (GIL) 513
In any case, the insulating gas contains sulfur hexafluoride (SF6), an inert,
nontoxic, non-flammable gas. More details on environmental impact of SF6 are
available in CIGRE Brochure 351 (clause 5.2). In some countries, the handling of
SF6 is regulated in IEC 62271-4 “Handling procedures for SF6” (IEC 62271-4
2013). The contribution to global warming of SF6 is small, and the use of SF6 is
regulated in several regional directives, e.g., EC 2003/87 European Directive.
The first generation of GIL was built from standard GIS components using pure
SF6 as insulating gas and straight enclosures. In the year 2000, a second generation
of GIL was introduced for managing longer distances and for reducing the environ-
mental impact of the equipment. It is made of gas mixture (like SF6/N2) and bending
radius of enclosures was introduced (typically 400 m) (Alter et al. 2002).
The optimal ratio to minimize the electric field between enclosure inner diameter and
conductor outer diameter should be 2.72. In practical applications, any ratio between 2.5
and 3 can be adopted since in this range the electric field increases only by 0.5%.
By observing one enclosure of a GIL, it resembles a gas transportation pipeline so
that, sometimes, GILs are mentioned as electric pipelines. The state of the art
indicates that, up to now, all the actual installations of GIL are short runs to provide
overhead line substitutions, getaways from hydroelectric, thermal, and nuclear
power plants: this seems to be an intrinsic contradiction with the technical features
of this electric transmission line that is suitable for long lengths and bulk power
transmission as it has been shown in CIGRE TB 351 (Cigré Technical Brochure
2008) (Figs. 27.4 and 27.5).
The most widely used application of GIL application is above ground inside
substations to connect overhead lines or transformers with GIS. Typical supports are
steel structures to hold the GIL above ground. When applied for long-distance
transmission, the connection to the overhead line is the first case of application
when the bushing for the link to the overhead line is connected to the GIL (Aucourt
et al. 1995; Koch 2000; Tanizawa et al. 1984).
The historical development of GILs is reported in Table. 27.1.
Enclosure
Phase conductor
Fig. 27.5 General overview of all the single-phase GIL units (courtesy Siemens). (A) straight unit,
(B) angle unit, (C) disconnecting unit, (D) compensation unit. (1) enclosure, (2) conductor, (3)
sliding contact, (4) nongas tight insulator for conductor fix point, (5) sliding post-type insulator, (6)
longitudinal thermal expansion compensator
27.2 Ratings
For single-phase type GIL with the enclosures solidly bonded at both ends, each
phase has series inductance and capacitance to earth. Coupling between phases is
negligible due to the screening effect of the enclosures.
The resistance (R) per unit length depends on the conductor and enclosure
dimensions and electrical resistivity, the skin and proximity effects, and
the conductor and enclosure temperatures. A method for calculating the resis-
tance is given in Cigré Technical Brochure 2008. The shunt conductance
(G) per unit length is not significant. Typical values for the electrical character-
istics of a 400 kV GIL with a continuous thermal rating of 2000 MVA are shown
in Table 27.2. Typical values for cables and overhead lines (OHL) having
comparable ratings are shown for comparison. A frequency of 50 Hz has been
assumed.
In preparing the above table, values have been sought for GIL, cables, and
overhead lines having a continuous thermal rating of approximately 2000 MVA.
Other geometries having equivalent continuous thermal ratings but different
electrical characteristics are possible; hence the table is intended for indication
only.
The overhead line characteristics correspond to a 420 kV line with 3 570 mm2
conductors per phase and two earth wires.
The values given for GIL correspond to a directly buried, single-phase GIL with
conductor diameter of 280 mm and enclosure inner diameter of 630 mm. The
enclosures are assumed to be solidly grounded. The depth of burial is 1050 mm
and axial spacing between phases 1300 mm. The soil conditions are an ambient
temperature of 15 C and a thermal resistivity of 1.2 K.m.W1. The continuous
thermal rating is determined by the maximum soil temperature, which is limited to
60 C.
Table 27.2 Technical data of 2000 MVA power transmission for GIL, OHL, and XLPE cable
GIL OHL XLPE cable (2 per phase)
Current rating (A) 3000 3000 3000
Transmissible power (MVA) 2078 2000 2000
Resistive losses at 3000 A (Wm1) 180 540 166
Dielectric losses (Wm1) –– 2.4 15.0
Total losses (Wm1) 180 542.4 181
AC resistance (μΩm1) 6.7 20 6.0
Inductance (nHm1) 162 892 189
Capacitance (pFm1) 68.6 13 426
Characteristic impedance (Ω) 48.6 263 21.0
Natural load (MW) 3292 608 7619
Surge impedance (Ω) 48.6 263 12.0
516 H. Koch
Much published work exists on the calculation of current ratings of (a) SF6 gas
insulated bus bar for in-air applications above ground and (b) conventional cables for
buried (laid direct) applications. However, prospective laid direct applications of
GIL may differ in the following respects:
The methods of calculation for both the continuous and short-time current ratings
are described in Annex A of Brochure 218 (Cigré Technical Brochure 2003), which
demonstrates the recommended calculation methods and sensitivity studies for direct
burial of horizontal, single-phase GIL sections. The GIL is insulated with either pure
SF6 gas or a mixture of N2 and SF6. A summary of the principles is given below. For
more details, see Cigré Technical Brochure 2003.
An idealized thermal model of the laid direct GIL circuit is shown in Fig. 27.6. This
model represents both continuous and short-time current ratings, although the thermal
circuits for the continuous and short-time ratings are different (Chakir-Koch 2001c).
Heat, Wc, is generated in the conductor by I2R conduction losses, where R is the
temperature-dependent ac resistance of the conductor. The heat is transferred
through the insulating gas to the metallic enclosure by the parallel mechanisms of
thermal radiation, Tr, and convection, Tc; these are highly dependent on the tem-
peratures of the conductor, c, and enclosure, e. Additional I2R heat, We, is generated
in the enclosure by circulating currents; these flow as a consequence of the magnetic
flux linkages with the conductor current, which link to the electrical circuit formed
by the three solidly bonded enclosures. The pressure-containing enclosures are of
large cross-sectional area and are usually fabricated from an aluminum alloy; hence
their electrical resistance is low, permitting the magnitude of the circulating current
27 Gas Insulated Lines (GIL) 517
Ground Surface
Oversheath
Surrounding ∅ 280
Enclosure L
Soil
Conductor
Gas Mixture
Conductor
S S
to approach that of the current in the primary conductors. As with the primary
conductors, the ac resistance is temperature dependent (Henningsen et al. 2000;
Chakir and Koch 2001a).
The same representative GIL dimensions were taken for the short-time rating. A
higher conductor short-time rating temperature limit of 95 C was taken, compared
to the 3000 A continuous rating conductor temperature of 71 C. Two examples were
calculated, in the first example, a zero starting current was taken. In a 12 h period, it
was possible to carry a current of 9840 A (328% of 3000 A full load); this
demonstrates the high thermal capacity of GIL. In the second example, the starting
current was taken as a steady-state load current of 2550 A (85% of 3000 A full load).
In a 12 h period, it was possible to carry a current of 7290 A (243% of 3000 A full
load). This illustrates that this particular design of GIL circuit could have taken the
additional full load current from a parallel faulted circuit for a useful period of 12 h
(i.e., 185% of full load), without reaching 95 C. The sensitivity study is recorded in
detail in Annex A of Brochure 218 (Cigré Technical Brochure 2003) and is summa-
rized as follows:
• The parameter that had the most effect on a 12 h rating period was K0, the gas
convection coefficient.
• The second most significant parameter was the soil thermal resistivity.
518 H. Koch
• The parameter that had the most effect on a 20 min rating period was the specific
heat of the conductor, and the second was K0, the gas convection coefficient. This
shows that the heating in this short period is nearly adiabatic.
It is recommended that, because the calculated short-time current ratings for GIL
are of such high magnitude:
The insulation coordination is a key issue for the reliability of components, and here
only the main aspects are summarized.
• Firstly, a utility must consider the GIL major failure rate (MFR) and its impact on
its own grid; in this respect, it is important to derive from Return of EXperience
(REX) for equipment of the same type (when possible) or similar type equipment
what the achievable MFR is with the present technology and insulation level
practice.
• Secondly, the insulation coordination deals not only with the overvoltage aspects
but should include also:
• The insulation characteristics of the GIL insulation
• The relations that link the dielectric type tests, routine tests, and on-site tests
with respect to the overvoltages in service and the self or not self-restoring
aspect of the GIL insulation
• The long-term withstand at service voltage taking into account the random
occurrence of insulation imperfections
(0.2–0.3 105 MF/year/meter of circuit per year). This results in a mean time
between failures (MTBF) of:
Table 27.5 Ampacity of GIL directly buried for 2000 MVA and 3000 MVA with maximum 60 C
soil temperature
insulating gases are used inside the aluminum pipe. Based on these design criteria,
no specific requirements for the tunnels and bridges are needed (Table 27.4).
The high ampacity of GIL is given by the high cross sections of GIL conductor and
enclosure pipes. The current rating needs to be calculated taking into account the
conductor and enclosure materials, the laying conditions in a tunnel, shaft, directly
buried or any other laying method. This calculation is required for each project if
conditions are not comparable (Chakir and Koch 2001b) (Tables 27.5 and 27.6).
Differently from insulated cables, there is not an international standard in order to
compute the ampacity of GIL. In IEC 62271-204 (International Standard IEC 2011),
there are only the allowable temperatures depending upon the installation type
(directly buried or tunnel).
522 H. Koch
Table 27.6 Ampacity of GIL tunnel laid for 2000 MVA and 3000 MVA with maximum 80 C
enclosure temperature if not touchable
Ampacity
Tunnel laid ϑg = 20 C
Diameter of At 0,8 MPa for gas
enclosure pipe Cross-sectional area of the mixtures and 6,5 MPa for
[mm] enclosure/conductor pipe SF6 Comments
[mm2] [A]
500 12,000/4300 3150 A 420 kV GIL at
Munich
500 16,000/5400 4000 A 420 kV
Nathpa Jhakri,
India
650 12,300/6600 4000 A 800 kV China
The temperature of the enclosure shall not exceed the maximum allowable temperature of
the anti-corrosion coating if applicable. For direct buried installation, the maximum temper-
ature of the enclosure shall be limited to minimise soil drying. A temperature in the 50–60 C
range is generally considered applicable.
For open air, tunnel and shaft installations, the maximum temperature of the enclosure
shall not exceed 80 C. Parts normally touched during operation not to exceed 70 C.
There are two ELECTRA papers and other documents which give details on this
computation:
1052 1052
Fig. 27.7 HV directly buried GIL equipped with an external protective PE coating
In the conditions shown in Fig. 27.7 and reported in Table 27.7, the ampacity
results equal to 2390 A. It can be easily ascertained that (leaving unchanged the
properties of soil – thermal resistivity and temperature) the ampacity increases if:
The installation of GIL can be of three different kinds: tunnel, outdoor surface
mounted, and directly buried.
The objectives of this section are to describe mechanical, corrosion, and installation
aspects of directly buried GIL. For the mechanical aspect, some simple methods for
524 H. Koch
the calculation and analysis of the stress on the enclosure are recommended,
disregarding the mechanical aspects of the internal components. Effects of short
circuit forces on the enclosure are excluded. The main aspects are the calculation of
required enclosure thickness, the vertical and horizontal stability, and the interaction
between the soil and the enclosure. For the corrosion aspects, two methods are
described, the coating and the cathodic polarization. Overground and tunnel instal-
lations are not dealt with because they are similar to GIS bus ducts which were first
installed more than 30 years ago (Koch 2012; Chakir and Koch 2002b).
Stresses
One of the main issues for gas insulated transmission lines is the mechanical
behavior in the soil during installation and operation. The GIL consists of three
single-phase encapsulated tubes which are directly buried in the ground. Each tube
consists of an outer aluminum alloy enclosure and an inner aluminum conductor. In
operation, thermal expansion and gas pressure generate the main forces acting on the
enclosure. Differential expansion between the inner and outer tubes is accommo-
dated by the use of sliding contacts already widely used in GIS. In addition, the
enclosure is anchored in the soil because of the friction which leads to high
mechanical loads. The enclosure is also subjected to load bearing, soil pressure,
27 Gas Insulated Lines (GIL) 525
and traffic loads. The GIL has to follow curvatures in vertical and horizontal
directions (minimum bending radius approximately 400 m), according to the terrain.
Stresses for abrupt changes (e.g., elbows) in direction are not dealt with in this study
(Henningsen et al. 2000).
The mechanical design needs to take into account all the effects applied on the
pipe listed below in general order of importance:
• Thermal expansion
• Friction between the soil and the enclosure due thermal effect
• Internal pressure
• Bending resulting from the vertical and horizontal curvatures
• Soil pressure
• Traffic loads
• Water pressure (if any)
• Seismic loads (if any)
the soil that will be crossed. Some soils can present a danger for the GIL because of
risk of corrosion and need at least deeper chemical analyses.
Compared to pipelines the GIL components must be handled with care because of
the components inside and the coating on the outside (Henningsen et al. 2000;
Chakir and Koch 2002b).
The routing needs to be optimized, which has a large impact on the cost.
27.3.2.1 Examples
Examples of existing GILs are split between special structures, made for the GIL,
and shared structures (GIL with rail or road) (Benato et al. 2007b).
GIL installations worldwide amount today to roughly 200 km of system length,
and the longest line length is 3.3 km with two three-phase systems in a tunnel. Much
longer runs are under study (Cigré Technical Brochure 2008).
Tables 27.8 and 27.9 show examples of characteristics of GIL installations in
structures.
= 58,108 m/Ωmm2
active corrosion protection. Also, the chemical composition of the shotcrete for the
primary tunnel lining should be specified to prevent corrosion effects. The sensitivity
of the GIL to vibration is low. Vibrations from sources around the GIL installation
may be damped by the support structure using dampers, if needed. If a GIL is laid on
27 Gas Insulated Lines (GIL) 531
a bridge where permanent swing from traffic and wind forces applies, the vibration
values need to be specified.
If the GIL is laid in a separate tunnel (pilot tunnel), then there is no vibrational
influence from the traffic tunnel. Tunnels with GIL systems in seismic active regions
have to reinforce the fixing points to avoid displacements of the pipes. In highly
active zones, where displacements of the tunnel itself cannot be excluded, flexible
tunnel cross and longitudinal sections may be installed. The electric and magnetic
fields in the vicinity of the GIL are negligible. Due to the solid grounding of the
enclosure, the electric field is practically zero, and due to the induced current in the
enclosure, the magnetic field in the surround of the GIL is low. There are no acoustic
noises coming from the GIL. The grounding of the GIL to limit touch voltage needs
to be planned with the structure. In the case of a tunnel, the GIL grounding should be
connected with the wire mesh. Special attention needs to be paid to the connecting
points at the ends and when other infrastructure is getting close, e.g., railway, gas
pipelines, and medium-voltage lines (Koch 2007–06).
Although GIL requires little maintenance, provision needs to be made for access
when repair work becomes necessary following an internal failure. The repair time
includes not only the direct repair work on a pipe but also the time for gas handling
(taking out the gas, storage, and refilling) and the high-voltage tests.
In the case of tunnel structures, the transport access from the tunnel entrance to
the working place inside the tunnel and return can significantly affect the total repair
time. To reduce time for transport and also for safety reasons, transport can be done
on rails.
Repair work requires access for gas handling equipment and gas storage con-
tainers. A replacement section of GIL will be installed and pressure and dielectric
tests will be performed. The safety issues associated with performing the pressure
test in the vicinity of shared services must be managed, and consideration must be
given to how the high-voltage test equipment will be connected. In order to return
the GIL to service within a short period, gas handling plant and spare components
must be available.
Existing tunnel owners always have a strong reluctance to add a GIL due to
concerns regarding space, responsibility, ownership, maintenance, safety, fire pro-
tection, cooling, and heat. Although GIL requires little maintenance, provision needs
to be made for access in the event that a repair following an internal fault becomes
necessary. The implications for any shared structure must be considered.
Safety distances around the GIL structure are not needed when the GIL is
sufficiently earthed; therefore it is also possible to work in the GIL structure without
restrictions. The GIL installed in a tunnel or on a bridge is usually only accessible by
trained experts (Koch 2012; Cigré Technical Brochure 2008; CIGRE Technical
Brochure 2015).
27.3.2.3 Tunnel
In its normal state, SF6 is nontoxic. However, in common with other gases, if
released in a confined space such as a tunnel, it can cause oxygen depletion and
the associated risk of suffocation. Control measures such as provision of forced
532 H. Koch
ventilation to ensure that the oxygen level remains sufficient in the event of a release
of gas should be considered.
It is often convenient to assemble the GIL at a shaft location, where more space is
available and welding fumes may more easily be extracted. The enclosure lengths
are welded at the shaft position, and the assembled GIL is advanced into the tunnel as
each new enclosure joint is completed. Since it is not possible to feed the assembled
GIL past a bend with low radius of curvature in this way, at such a bend the GIL must
be assembled at its final position.
The environment of GIL installation can bring water or water steam in contact
with the enclosure aluminum (or aluminum alloy) causing possible corrosion.
By virtue of the fact that the expected lifetime of a transmission line is rather long
(e.g., 30–40 years), the behavior of aluminum alloys exposed to environmental water
deserves very careful consideration (Koch 2007–06; Benato et al. 2005).
The scientific literature on chemical and biological behavior of aluminum prod-
ucts following exposure to environmental media is wide and comprehensive. The
literature agrees on this fact: the formation of oxide layers on aluminum and its
alloys have a protective function. Due to this protective layer, aluminum products are
not significantly corroded under environmental conditions (pH 4.5–8.5), unless
corrosion takes place through localized formation of elements caused by chemicals
and natural substances. The minimum space for long tunnels can be determined by
considering ventilation, humidity, temperature, management of any leaking of
non-flammable and nontoxic insulating gas, repair concept after internal fault,
tolerances of tunnel dimensioning (diameter, straight alignment, gradient), bending
radius (400 m), need for elbow elements in order to follow the route, power supply,
and transportation of spare parts, See examples in Figs. 27.8 and 27.9.
Inside service tunnels of long structures in certain distances, e.g., each 500 m or
1000 m widening, e.g., technical caverns, directional changes of the GIL are needed,
which may be achieved using elbow elements (Koch 2012; Cigré Technical Bro-
chure 2008).
Specific investigations of GIL applied to railway tunnels are given in Benato
et al. (2005).
2.80 m Ø 4.30 m
0.82 m Ø 4.30 m
Gas Insulated Lines (GIL)
7 10
1 4
0.3 m
0.82 m
0.3 m
0.82 m
8 11
2 5
2.28 m 1.48 m
2.51 m
0.82 m
0.82 m
2.25 m
9 12
3 6
0.70 m
Intermediate access
Inner diameter
of tunnel
∅.4,30 m
2.80 m
0.82 m
0.3 m
2.51 m
2.28 m
0.82 m
SERVICE
TROLLEY
0.70 m
structure and fixing points. To prove the long-term stability, a fatigue analysis is
required. Accessibility of the GIL should allow visual inspection and in case of a
repair the exchange of a section.
In normal service the GIL needs no frequent service or checks by operation
personnel. In service the structure and GIL will expand and contract, due to
temperature changes. Thermal expansion units of the GIL will take care of these
movements. There will be only a small impact by the friction of the movement of the
GIL that will affect the bridge. Safety regulations concerning the GIL will take care
that even in case of an electrical failure in the GIL there will be no critical impact on
the structure. The forces coming from the electromagnetic field during operation
(short circuit currents) are taken by the steel structure, and in case of an internal
electrical fault, the metallic enclosure prevents influences to the surrounding. To
prove the functioning of bridge and GIL thermal expansion, a fatigue analysis is
required.
27 Gas Insulated Lines (GIL) 535
Ambient conditions like wind and ice load, solar radiation, seismic conditions,
high humidity, and ambient temperature are service conditions as defined in IEC
62271-204 (International Standard IEC 2011) that are considered in the design of
GIL applications. The effects of these ambient conditions also need to be considered
as part of the design (Cigré Technical Brochure 2008).
The third generation of compact transmission lines based on gas insulated technol-
ogy is now being developed. There are two main goals behind this third-generation
design: improved assembly and laying of the pipe segments and robust and reliable
joint technology using new welding processes.
These improvements will further reduce the time for installing GIL which
accounts for almost 50% of the total cost. The mobile factory combines the auto-
mated assembly of GIL segments with the welding process. The mobile factory as
shown in Fig. 27.10 is equipped with a pipe magazine where on-site-prepared pipe
segments are stored and made ready for welding. There are two welding workplaces
which work alternately to generate a continuous production of GIL segments to be
pulled into the open trench or tunnel section.
The jointing technology of the mobile factory is supplemented by ultrasonic
quality control of the welds to ensure that only failure-free welds are installed.
eight GIL sections of up to 13 m length. On the bottom left-hand side of the mobile
factory, the welding section is located. In this area the orbital welding machine using
the friction steer welding process connects the conductor and enclosure pipes. With
two welding locations, the welding machine can make up to eight connections in one
working shift, which is equal to the number of prepared GIL sections stored in the
magazine.
On top of the welding section on the left-hand side of the mobile factory, the
control units, power generation, and room for employees are located. This means the
mobile factory does not require an external power supply enabling the use of the
mobile factory to lay GIL in remote areas.
When direct buried GIL laying is used the welded GIL, sections leave the mobile
factory at the left-hand end to be laid in the trench. In this condition, the mobile
factory can move with its own traction system for each new length of GIL, e.g., each
13 m. Another possible laying method when using longer open trenches, e.g.,
300–500 m, is that the GIL sections (e.g., 13 m long) are pulled into the trench,
and then the mobile factory will be moved for 300 or 500 m to the next laying
position.
The functional unit chosen for the assessment might be a unit length of GIL with a
given rated voltage and current.
The horizon of the study includes the life cycle phases which are considered, the
material production and energy generation scenarios that are assumed, the types of
environmental impact that are to be assessed, and the methodologies to be used.
The life cycle inventory (LCI) quantifies the relevant material and energy flows
into the system and emissions and waste flows out of it. In the case of GIL, the LCI
will include the materials used and the energy consumed in producing them,
emissions and waste generated during production and manufacture, energy losses
generated during the operational lifetime of the equipment, and energy losses and
emissions associated with decommissioning and disposal or recycling. The life
cycle impact assessment (LCIA) derives quantitative environmental impacts from
the LCI data.
The life cycle interpretation draws conclusions from the LCI and LCIA data.
A comparative assertion is a special type of LCA in which the environmental
impacts of two systems of equivalent performance are compared. The report
538 H. Koch
illustrates the basic principles of a comparative assertion for the case of SF6
emissions from systems using pure SF6 and a mixture of N2 and SF6.
Most of the materials used in GIL are easily recyclable at end of life.
• Visual impact
• Electromagnetic fields:
• Magnetic fields
• Electrostatic fields
• Depreciation of property/land values
• Restrictions on land use: buildings, air traffic, and land cultivation
• Audible noise
• Electromagnetic interference (radio interference voltage)
• Effects on forests and natural environment
• Risk of soil pollution
Where a GIL is of the single-phase enclosed design and the enclosures are solidly
bonded at each end (which will normally be the case), enclosure currents will
circulate tending to reduce the magnetic field external to the GIL. However, due to
the spatial disposition of the three phases, screening is not complete. Magnetic fields
have been calculated for typical overhead line, GIL, and cable systems. RMS values
of the magnetic flux density at 1 m above ground and at different distances from the
central axis are shown in Table 27.10. The values correspond to a transmitted power
of 2000 MW.
Where a GIL is of the single-phase enclosed design and the enclosures are bonded
in such a way that enclosure currents cannot circulate, e.g., where single point
bonding is used, eddy currents will flow in the enclosures, but these will provide
no effective magnetic screening. The magnetic field external to the GIL will there-
fore be higher than in the case where the enclosures are solidly bonded. It is thought
that such an arrangement will seldom be used.
The magnetic field external to the GIL may be calculated analytically using
Ampère’s Theorem and Biot and Savart’s Law. Alternatively, the magnetic field
can be calculated using a numerical method, such as the finite element method (Koch
2003; Koch and Connor 2003).
27 Gas Insulated Lines (GIL) 539
Table 27.10 Magnetic flux density for 400 kV lines and 3000 A
Distance from central axis (m)
B (μT) 0 10 20 30
Overhead line 42 36.5 21.0 10.8
GIL flat formation 5 0.25 0 0
XLPE cable 109 11 2.9 1.3
1 per phase
Flat formation
XLPE cable 13.2 0.74 0.19 0.08
2 per phase
Trefoil formation
The majority of the insulating gas is with 80% N2. This gas has no environmental
impact, as it is naturally available in the atmosphere. N2 is not toxic and
non-flammable. However, N2 can suffocate as it can reduce the oxygen content.
In addition to being a more economical solution, the use of a gas mixture
addresses environmental concerns, since SF6 has a global warming potential
(GWP) of 23,900 times that of carbon dioxide.
However, the absolute contribution by today’s amount of SF6 in the atmosphere
to global warming is 0.7%. The majority of SF6 in the atmosphere originates from
SF6 use outside of the electrical industry.
Most of such use has been banned (e.g., window insulation, tires, and shoes). The
welded enclosure structure ensures that a high level of gas tightness is maintained
throughout the life of the GIL. At the end of life, the gas mixture can be recovered,
recycled, and reused.
The use of N2/SF6 gas mixture is recommended for long-distance applications of
GIL. Most applications are in conjunction with GIS and use pure SF6 because of the
arc extinguishing capability of SF6.
A feasibility study began in 1994 and was completed in 1997. Studies have been
performed on dimensioning for insulation, thermal behavior, mechanical constraints,
and corrosion protection. Laboratory tests have been performed on dielectric perfor-
mance, short circuit performance, reliability studies, monitoring, and fault location
systems. All tests were successful. It was concluded that the required GIL technol-
ogies were accessible in the medium term (Henningsen et al. 2000; Koch 2000–10;
Miyazaki 2001).
540 H. Koch
In this section, some examples of installed GIL projects are given to show installa-
tion in air, in tunnel, and in direct buried (IEEE Guide for Application and User
Guide for Gas-Insulated Transmission Lines (GIL) 2012).
In a project at the PP9 Power Plant in Saudi Arabia, 420 kV GIL is used for connections
between transformers and a GIS substation (Koch 2012; Cigré Technical Brochure 2008,
2015). The connections consist of eight three-phase circuits, totalling 17 km of single-
phase circuit. The project was completed in four stages and was commissioned from May
1997 to March 2000. GIL was chosen as the only viable technical solution due to
restrictions imposed by the route and the very corrosive environment (due to plant
emissions and sandstorms). In addition, the GIL solution allows highly reliable transport
of high powers with low losses.
The GIL was installed above ground at heights between 7 and 9 m, to allow
passage for transformer transportation. The ambient temperature varies between
6 C and +55 C. The GIL is subject to winds of 120 km per hour with strong
gusts of up to 150 km per hour (Fig. 27.12).
27 Gas Insulated Lines (GIL) 541
Fig. 27.12 Views of the 420 kV PP9 GIL: erection and layout
3,2 m
0,3 m
3,4 m
5
Fig. 27.14 View into the tunnel slope of Limberg, Austria, 2010
directly buried GIL laying. In the middle of the photo, the on-site assembly tent is
shown which is placed on top of the laying trench. The GIL sections are assembled
and welded in the tent and then pulled into the trench (Koch 2012; Cigré Technical
Brochure 2008; CIGRE Technical Brochure 2015) (Fig. 27.15).
A view inside the assembly tent is given in Fig. 27.16. The straight units and angle
units are preassembled inside the tent before burial.
The straight units are welded on-site using the automated orbital welding process.
See Fig. 27.17.
The straight units were welded in the assembly tent and then pulled into the
trench. In Fig. 27.18, the trench with six single-phase GIL pipes for the two three-
phase systems is shown before the trench was closed.
The technical data of the directly buried GIL using N2/SF6 gas mixture is shown
in Table 27.14.
544 H. Koch
27.7.1 General
There are cases where GIL is a viable option in lieu of EHV overhead lines (OHL).
One application could be of GIL linking two EHV substations – “A” and “B” having
OHL entering into the substations from remote substations. However, there is no
27 Gas Insulated Lines (GIL) 545
Fig. 27.18 Six single-phase GIL pipes in the trench before backfilling
Table 27.14 Technical data of the directly buried GIL, Kelsterbach, Germany, 2010
Rated voltage Ur 420 kV
Rated current Ir 3000 A
Rated impulse withstand voltage UBIL 1425 kV
Rated short-time current Is 63 kA
Circuit length 2 circuits of 1 km
Insulating gas 80% N2/20% SF6
right of way for OHLs to interconnect the two substations to meet the network
configuration, or they are separated by a few kilometers of water (river or sea). GIL
buried below ground or inside a tunnel can be used. See Figs. 27.19 and 27.20.
Another possible application is shown in Fig. 27.21. OHL circuits are terminated
at an indoor EHV substation. There is no more space for landing additional OHL
circuits to the substation. In case circuit expansion is required, GIL/cables can be
used to interconnect the substation to the end tower of the new OHL circuits.
GIL/cables can be installed above ground, in tunnel, in troughs, or directly buried.
The third possible application is shown in Fig. 27.22 which explains the use of
GIL/cables to help migrate the OHL circuits and existing EHV switchgear boards
(to be replaced in stages) to new EHV switchgear boards in a new EHV substation at
some distance apart. Due to site and system constraints, e.g., in situ replacement of
switchgear not possible, diverting of existing OHL circuits not possible, outage
constraints, etc., the switchgear and circuit diversion must be carried out in stages,
and the existing switchgear boards and the new switchgear boards must be
interconnected to minimize the impact to the system security. GIL can be installed
above ground, in tunnel, or buried underground.
546 H. Koch
EHV Overhead
EHV Overhead
Lines
Lines
Fig. 27.19 GIL in lieu of overhead lines (due to no right of way) for linking two substations
OHLs OHLs
Sea
GIL/Cables in tunnel
Fig. 27.20 GIL for linking two substations separated apart a long distance by sea/river
OHLs OHLs
terminated to Terminated at
Indoor EHV Substation the substation end Tower
with no more space for
landing the overhead Air/SF6
line circuits GIL/Cables on/above ground Bushing
Fig. 27.21 GIL installed above ground/in tunnel/directly buried to link up the end tower of new
overhead lines with an existing substation having no more landing space for overhead line circuits
The above three cases are not exhaustive. The choice of the installation methods will
depend on technical, cost, and other related factors (CIGRE Technical Brochure 2015).
The GIL components are delivered to the preassembling site which is usually a
temporary facility close to the installation location or to the access point which may
be the entrance of a gallery or a tunnel. At the preassembling area, a temporary
workshop facility is erected where the individual pieces are put together to create
OHLs
27
1 2 3 4
(ii) OHLs 1 and 2 diverted to New EHV Substation via GIL/Cables above ground/ OHLs
underground 1 2 3 4
(i) Busbars of the two EHV Substations interconnected Existing EHV Substation
with GIL/Cables above ground and/or underground
Phase I New EHV New EHV
Development EHV Switchgear
Switchgear Switchgear Board B
Board A’ Board B’
OHLs
1 2 3 4
Fig. 27.22 GIL for EHV switchgear replacement/expansion under site/system constraints, e.g., in situ switchgear replacement not possible, relocation/addition
of overhead line towers not possible, long circuit outage not possible
547
548 H. Koch
components ready for the final assembly procedure. It is clear that one of the most
important requirements is to maintain the cleanliness inside the preassembling
workshop. The site of assembly of the GIL must also be equipped with the necessary
infrastructure such as offices, various buildings, power supply (not to forget welding
and gas treatment machines), water, and access for the site personnel and visitors.
Once the components have been completed, they are transported to the assembly
location. The latter is the place where the “continuous” tube is put together. This can
be done using flanges or welding. The latter is the more economical solution for
longer lengths; flanges are mostly used for frequently diverting routings or very short
installations. The progress of the installation is determined by the final assembly
procedure. A storage facility adjacent to the preassembling site is of advantage.
The testing is divided into two main steps: the ongoing quality assurance during
installation and the after-laying tests. The quality assurance during installation
covers among other things the ultrasonic inspection of each individual site weld
and the appropriate documentation in accordance with international and local pres-
sure vessel code requirements. The tests after burial are mainly the pressure test of
the entire system, the dielectric test, and the test of the conductor resistance. Details
of the site testing activities are prescribed in IEC 62271-204 (International Standard
IEC 2011). Due to the nature of the GIL installation works and mainly related to the
requirements of cleanliness, it is obvious that apart from the required health and
safety issues a couple of other prerequisites of the site need to be fulfilled before
installation can start. The most important of them is that the civil works in the
vicinity of the assembling area must be completed and permanent, unimpeded access
for the GIL installation crew provided (Koch 2012; Cigré Technical Brochure 2008;
CIGRE Technical Brochure 2015) (Figs. 27.23, 27.24, 27.25, 27.26, 27.27, and
27.28).
There are generally two options for the installation of GIL: welding of the pipes in
one location and pulling the continuously produced pipe or moving the welding
position along the route. The latter is a more complex option due to the fact that the
welding equipment and the equipment to maintain a clean welding place will need to
be moved. Up to now the assembly location usually remains in place until a certain
section of the GIL has been produced (Koch 2012; Cigré Technical Brochure 2008).
Fig. 27.23 Site logistics scheme for GIL installation in tunnel, above, and below ground
Each shipping section is tested before delivery from the factory to ensure the
standards of reliability. Routine testing includes high-voltage power frequency
electrical tests, partial discharge tests of each insulator and each shipping assembly,
and gas leakage tests on all shipping assemblies.
High-voltage power frequency electrical tests, partial discharge tests of each
insulator and each shipping assembly, and gas leakage tests on all shipping assem-
blies are done before shipping the section of bus bar for installation (Koch 2012;
Cigré Technical Brochur, 2008) (Fig. 27.29).
After the pre-testing is complete, GIL sections are ready to be shipped to the
installation site for final testing and commissioning (Fig. 27.30).
The utilization of flanged GIL sections makes the installation process simpler
on-site, and an expeditious installation program can be accomplished. It also does
not require any on-site assembly and testing area. Longer section lengths decrease
552 H. Koch
the number of connections required during installation and lower the risk of gas
leakage during operation (Koch 2012; Cigré Technical Brochure 2008) (Fig. 27.31).
Installations of GIL require gas handling facilities. To limit the gas volume necessary
to handle and process, the GIL is separated into gas compartments. The handling
instructions are defined in IEC 62271-4 gas handling standard (IEC 62271-4 2013).
It is necessary to organize sufficient space for the tanks of SF6 and N2. Specialized
machines are necessary to draw the vacuum in the tubes before filling, like treating
the gas (drying) and making mixture N2-SF6 before filling. The operation of filling
must be permanently supervised (Figs. 27.32 and 27.33).
The need to test the GIL on-site after burial imposes certain requirements on the GIL
and the structure in which it is installed. The guiding rule for high-voltage on-site
testing is not to exceed the maximum test current of about 20 A to limit the energy
charged to the system. In GIL, it is possible to use the accessibility to test sections of
GIL through the disconnection unit, which is used as an isolation point. One gas
compartment may have a maximum length of 1500 m. This also forms one high-
voltage test section which needs access for the test equipment. From there the tests
can be executed in two directions. Therefore, access to the GIL for high-voltage
testing in the tunnel from the main tunnel or from the outside is required at least
every 3000 m (Koch 2012; Cigré Technical Brochure 2008; Koch 2000; Chakir and
Koch 2001b; Koch 2000–10) (Figs. 27.34, 27.35, and 27.36).
27 Gas Insulated Lines (GIL) 555
Pressure tests are required by the EN standards for GIS and local requirements of
authorities. The EN standards on high-voltage equipment are written for
low-pressure compartments (typical up to 8 bars) and dry and inert gases (SF6 and
N2). The EN standards are the following (Koch 2012; Cigré Technical Brochure
2008) (Table 27.15):
556 H. Koch
Activities specific to GIL have been treated in depth in the Technical Brochure
218 (Cigré Technical Brochure 2003). Annex B of TB 218 reviews all the various
diagnostic methods to apply either during on-site test or for online monitoring in
service: physical sensors and signal processing to detect, locate, and identify the
occurring defects. Nowadays, two methods are mainly used to detect online the
presence of possible defects: UHF methods for new equipment provided with internal
UHF sensors and acoustic methods for other equipment. Up to now, however, the
assessment of the actual impact of the detected defects on the GIL insulation and thus
on the remaining life is indeed still a difficult matter (Okubo et al. 1998).
This matter is further addressed in Part H.
The grounding of GIL must be adapted to the different service conditions represented by
normal service, short circuit, and overvoltage conditions. The disposition of the GIL
(buried, in a tunnel, in a trench) and the possibility of having low-voltage equipment such
as gas density monitors, temperature sensors, or partial discharge monitoring systems
connected on the enclosure have to be considered when the grounding mesh is studied.
The design of the grounding system must provide all the safety regarding persons and
equipment in case of potential rise, touch voltage, and step voltage and must remain lower
than the limit values for permanent or short circuit conditions.
Optimization of the grounding system can be achieved through modeling. For
short lengths of GIL (less than 500 m), the GIS design rules are applicable. For
longer ones, the design must take into account the IEC standard 62271-204 (Inter-
national Standard IEC 2011).
In contrast to insulated cables, the grounding and bonding of the enclosure at
short spacing does not affect the thermal rating of GIL because of the good enclosure
conductivity. Thus, for safety reasons the enclosure grounding and bonding would
be done for directly buried GIL every 500 m to 1 km reducing the power frequency
touch voltage to safe limit values and the transient overvoltage between enclosure
and ground to ensure very low values which are not dangerous for people or for the
insulating layer over the aluminum alloy GIL enclosure.
For GIL in tunnel the enclosure grounding and bonding is repeated more fre-
quently and needs to be part of the tunnel earthing design.
27.9.3 Operation
gas in the tubes to be monitored permanently. They are equipped with a display for
visual control at the time of inspection, such as several levels of alarm for minimal
pressure in the case of leakage or gas loss. These alarms can be transmitted remotely
to the control system and/or to alert the personnel. The sensitivity of the monitors
and the determination of the alarm thresholds must be carefully studied according to
the volume of gas by compartment.
GIL can be equipped with one arc detector and locator system based on the
principle of a measurement of the difference in travel time of the wave between the
place where the arc occurs and the ends of the tubes equipped with reception
antennas; the precision is ensured by GPS synchronization.
Monitoring requirements and safety rules are very much related to the operator
and local authorities. The technical installations and the operation instructions are
not different from other high-voltage installations and very similar to GIS. Technol-
ogy is available on the market (Schoeffner et al.; Boettger and Koch 2005; Koch and
Kunze 2006).
27.9.4 Maintenance
GIL theoretically requires very little maintenance; however, the limited experience
feedback concerning this technology requires the owners to establish an appropriate
level of preventive maintenance. The following maintenance actions can be men-
tioned (Koch 2012; Cigré Technical Brochure 2008):
• Periodic inspection. The interval is to be fixed between weekly (at the beginning of
the operation) and monthly. This makes sure that there is nothing abnormal on the
level of GIL, but also on the whole of the installation and the end stations. In particular
the pressure in the tube (density monitors) should be visually inspected, as well as the
general state (water infiltration, cleanliness, etc.) to make sure these are working.
558 H. Koch
The principle of GIL is relatively simple and includes few peripheral devices; however
even though there are high-quality manufacture and assembly standards, defects or faults
are possible; therefore repairs to the installation may be required and appropriate
measures put in place to facilitate them (Cigré Technical Brochure 2008).
Consequently, various measures should be incorporated such as:
• To stock spare parts, for example, of the tubes, near to the installation or in the
gallery for an underground system
• To ensure permanent or emergency access for vehicles and machines
• To have quick access to cisterns or batteries of bottles to handle and treat large
quantities of gas
• To distribute electric power to supply various machines (welding, treatment of
gas, ventilation, light, etc.) all along the GIL
An example of a repair scheme which has been performed and proven is given in
Fig. 27.37. The duration of a potential repair is app. 2 weeks including preparation
and final testing.
27.10 Safety
The integrity of the metallic enclosure to internal arcs prevents external problems
such as fire (Koch 2012; Cigré Technical Brochure 2008).
Third-party accidents in the proximity of the GIL might be a danger for the GIL
and separation from vehicles is required.
There is no influence from radioactivity in the tunnel expected to the insulating
gas and the electrical stability of the GIL, as the metallic enclosure is shielding the
inside from the surrounding.
Oxygen measurements in the tunnel are recommended at low locations in the
tunnel to make sure that there is no risk to personnel (asphyxiation).
When the GIL gas compartment needs to be opened, care has to be taken to avoid
direct contact with possible decomposition product of the insulating gas. Therefore,
the operation manual instructions need to be followed.
The gas handling needs to be carried out in accordance with the IEC 62271-4 gas
handling standard (IEC 62271-4 2013).
Touch voltages and touch temperatures need to be limited to values below the
required values of the related IEC standards.
Tunnel inspections are recommended to coincide with possible impacts coming
from water, dust, or other environmental impact. Such sequences of inspections
could be in a yearly cycle.
Seismic requirements should be taken into account in earthquake-prone areas.
During HV testing and during pressure vessel testing at the installation and
commissioning process, precautions as used with high-voltage systems have to be
taken into account.
Safety assessments need to be made for each installation in tunnels or bridges.
The requirement will vary with the use of the structure. Part of the safety analysis is
the impact coming from failure in the GIL, e.g., internal arc, fire in the structure, and
accidents in the tunnel or on the bridge.
27.10.2 Fire
Precaution associated with the GIL is not needed, since only metal and
non-combustive materials are used. There is no additional fire risk coming from
the GIL.
560 H. Koch
of which depend on the particular project. GIL terminations are less expensive than
cable sealing ends.
To match the ratings of some overhead lines, it is sometimes necessary to use two
cables per phase, thus increasing the cost per unit length of the cable option. GIL has
a significantly higher rating than cable, and it may be possible to match the overhead
line rating with a single GIL per phase.
The design of a GIL must satisfy dielectric, thermal, and mechanical require-
ments. If the current rating for an application is low, it does not follow that GIL
dimensions may be reduced. GIL may therefore be less competitive than conven-
tional cables at lower ratings.
For those wishing to compare the costs of GIL with cable installations, reference
should be made to CIGRE TB 639 “Factors for Investment Decision GIL vs. Cable.”
References
Alter, J., Ammann, M., Boeck, W., Degen, W., Diessner, A., Koch, H., Renaud, F., Poehler, S.:
N2/SF6 gas-insulated line of a new GIL generation in service, CIGRÈ 21-204 (2002)
Aucourt, C., Boisseau, C., Feldmann, D.: Gas insulated cables: from the state of the art to feasibility
for 400 kV transmission lines. In: Proceedings of Jicable 95 Conference, Versailles, France,
133–138 (1995)
Baer, G.P., Diessner, A., Luxa, G.F.: 420 kV SF6-insulated tubular bus for the Wehr pumped-
storage plant- electric tests. IEEE Trans. Power App. Syst. PAS-95, 469–477 (1976)
Bär, G., Dürschner, R., Koch, H.: 25 Jahre Betriebserfahrung mit GIL. heutige Anwendungsmö-
glichkeiten. ETZ. 123(1–2), 46–50 (2002)
Benato, R., Napolitano, D.: Overall cost comparison between cable and overhead lines including
the costs for repair after random failures. IEEE Trans. Power Deliv. 27(3), 1213–1222, 2012.
https://doi.org/10.1109/TPWRD.2012.2191803
Benato, R., Carlini, E.M., Di Mario, C., Fellin, L., Paolucci, A., Turri, R.: Gas insulated transmis-
sion lines in railway galleries. IEEE Trans. Power Deliv. 20(2), 704–709 (2005)
Benato, R., Capra, D., Conti, R., Gatto, M., Lorenzoni, A., Marazzi, M., Paris, G., Sala, F.:
Methodologies to assess the interaction of network, environment and territory in planning
transmission lines. In: Proceedings of CIGRÉ 2006, Paper C2-208 (2006a)
Benato, R., Del Brenna, M., Di Mario, C., Lorenzoni, A., Zaccone, E.: A new procedure to compare
the social costs of EHVHV overhead lines and underground XLPE cables. In: Proceedings of
CIGRÉ, Paper B1-301, Sept (2006b)
Benato, R., Di Mario, C., Lorenzoni, A.: Lines versus cables: consider all factors. Trans. Distribu-
tion World. 59(11), 26–32 (2007a). ISSN 1087-0849
Benato, R., Di Mario, C., Koch, H.: High capability applications of long gas insulated lines in
structures. IEEE Trans. Power Deliv. 22(1), 619–626 (2007b). https://doi.org/10.1109/
TDC.2006.1668566
Boettger, L., Koch, H.: Operation and monitoring of GIS/GIL. IEEE PES General Meeting, San
Francisco (2005)
Chakir, A., Koch, H.: Thermal calculation of buried GIL and XLPE cable. IEEE Winter Power
Meeting, Columbus (2001a)
Chakir, A., Koch, H.: Long term test of buried GIL. CIGRE SC 15 Symposium, Dubai (2001b)
Chakir, A., Koch, H.: Transient thermal behaviour of GIL at variable loads. HSME J (2001c)
Chakir, A., Koch, H.: Corrosion protection of GIL. IEEE PES Summer Meeting, Chicago. (2002a)
Chakir, A., Koch, H.: Seismic calculation of directly buried GIL. IEEE PES T&D Conference, Asia
Pacific, Singapore (2002b)
27 Gas Insulated Lines (GIL) 563
Christophorou, L.G., Van Brunt, R.J.: SF6-N2 mixtures basic and HV insulation properties. IEEE
Trans. Dielectr. Electr. Insul. 2(5), 952–1003 (1995)
CIGRE TB 639: Factors for investment decision GIL vs. cables for AC transmission. Joint WG
B3/B1.27, 12/2015
Cigré Technical Brochure # 351: Application of long high capacity gas-insulated lines in structures,
Working Group B3/B1.09. ISBN: 978-2-85873-044-5 (2008)
Cigré Technical Brochure 218: “Gas insulated transmission lines (GIL)”, Joint working group
23/21/33.15, Feb (2003)
CIGRE Technical Brochure 639, JWG B3/B1-27: Factors for investment decision GIL vs. cables
for AC transmission (2015)
CIGRE WG 21.12: Calculation of the continuous rating single core compressed gas insulated cables
in still air with no solar radiation, Electra 100 (1985)
Cigre WG 21.12: Calculation of the continuous rating of three-core, rigid type, compressed gas
insulated cables in still air and buried, Electra 125 (1989)
CIGRE WG 23.10/TF 03: User guide for the application of gas-insulated switchgear (GIS) for rated
voltages of 72.5 kV and above. CIGRE Brochure 125 (1998)
CIGRÉ Working Group 23.02: Guide for SF6 gas mixtures. CIGRÉ Brochure 163 (2000)
Cousin, V., Koch, H.: From gas-insulated switchgear to cross country cables. Jicable Conference,
Versailles (1996–05)
Diarra, T.B., Béroual, A., Buret, F., Thuries, E., Guillen, M., Roussel, Ph.: N2-SF6 mixtures for
high voltage gas insulated lines. In: 10th International Symposium on HV Engineering, Mon-
treal (1997)
EN 50064: Wrought aluminium and aluminium alloy enclosures for gas-filled high-voltage
switchgear and controlgear (1989)
Eteiba, M., Rizk, F.A.M., Trinh, N.G., Vincent, C.: Influence of a conducting particle attached to an
epoxy resin spacer on the breakdown voltage of compressed gas insulation. Gaseous Discharge
II. Pergamon press, pp. 250–254 (1980)
Hauschild, W., Mosch, W.: Statistical techniques for high voltage engineering. IEE Power series
13, Peter Peregrinus, London. ISBN 0 86341 205 X (1992)
Henningsen, C., Kaul, G., Schuette, A., Plant, R., Koch, H.: Electrical and mechanical long-time
behaviour of gas- insulated transmission lines, CIGRÈ 21/23/33-03 Session, Paris (2000)
Hillers, T., Koch, H.: Gas insulated transmission lines for high power transmission over long
distances. In: Proceedings of EMDP 98, 3–5, Singapore, 613–617 (1998a)
Hillers, T., Koch, H.: GIL for high power transmission over long distances. EPRI. 44, 613–618
(1998b)
IEC 60287-3-1: Electric cables – calculations of the current rating – part 3.1: Sections on operation
conditions (1995)
IEC 62271-1: High-voltage switchgear and controlgear – part 1: common specifications (2007)
IEC 62271-4: High-voltage switchgear and controlgear – part 4: handling procedures for sulphur
hexafluoride (SF6) and its mixtures (2013)
IEC standard 60038: IEC standard voltages (2009)
IEC standard 60071-1: Insulation co-ordination part 1: definitions, principles and rules règles,
seventh edition (1993–12)
IEC standard 60071-2: Insulation co-ordination part 2: application guide, third edition, (1996–12)
IEEE Guide for Application and User Guide for Gas-Insulated Transmission Lines (GIL): Rated
72.5 kV and Above, IEEE PC38.122.4/DH, December 2012, 1, 48, (2013)
International Standard IEC 62271-204:2011 High-voltage switchgear and control gear – part 204:
Rigid gas-insulated transmission lines for rated voltage above 52 kV, Edition 1 (2011)
Koch, H.: Future aspects of GIL applications. CIGRE Colloquium Zurich (1999)
Koch, H.: Development long duration testing and first application of GIL. IEEE PES and ICC Fall
Meeting, October 30, 2000, St. Petersburg (2000)
Koch, H.: Long duration test of GIL. IEEE ICC Fall Meeting (2000–10)
Koch, H.: Environmental reasons for underground GIL. CIGRE Session, Paris (2002a)
564 H. Koch
Koch, H.: Future needs of high power interconnections solved with GIL. IEEE PES PowerCon,
Kunming (2002b)
Koch, H.: Magnetic fields of GIL – calculations and measurements. ISH Conference, Delft (2003)
Koch, H.: The use of traffic tunnels for electric power transmission. Power Grid Europe Conference
(2007–06)
Koch, H.: Gas-Insulated Transmission Lines. Wiley, Chichester (2012)
Koch, H., Connor, T.: General aspects of EMF in High voltage systems. In: ISH Conference, Delft
(2003)
Koch, H., Kunze, D.: Monitoring system of GIL. CEPSI, Mumbai (2006)
Miyazaki, A., Takinami, N., Kobayachi, S., Hama, H., Araki, T., Hata, H., Yamaguci, H.: Line
constant measurements and loading current test in long-distance 275 kV GIL. IEEE Trans.
Power Deliv. 16(2), 165–170 (2001)
Okubo, H., Yoshida, M., Takahashi, T., Hoshino, T., Hikita, M., Miyazaki, A.: Partial discharge
measurement in a long distance SF6 gas insulated transmission line (GIL). IEEE Trans. Power
Deliv. 13(3), 683–690 (1998)
Schoeffner, G., Boeck, W., Graf, R., Diessner, A.: ATTENUATION OF UHF-SIGNAL IN GIL.
Institute of High Voltage Engineering and Electric Power Transmission Technical University of
Munich, Germany (2001)
Tanizawa, K., Minaguchi, D., Honaga, Y.: Application of gas insulated transmission line in Japan.
CIGRE SC21-05 (1984)
Völcker, O., Koch, H.: Insulation co-ordination for GIL. IEEE Transactions, PE-102 PRD, 07/2000
Ward, S.A.: Influence of Conducting Particles on the Breakdown Voltages of SF6-N2 Mixture, vol.
11, pp. 23–27. ISH, London (1999)