Highlight on Risk
Alocation and
Pricing Scheme
1
Non Geothermal IPPs Having Signed Power Purchase Contract With PLN
Non Geothermal IPPs in Operation
1. Paiton I Coal Fired 2 x 615 MW
2. Paiton II Coal Fired Plant 2 x 610 MW
3. Cilacap Coal Fired Plant 2 x 300 MW
4. Sengkang Gas Fired Plant 1 x 135 MW
5. Palembang Timur Gas Fired Plant 1 x 150 MW
6. Pare-pare MFO Fired Plant 6 x 10 MW
2
Geothermal IPPs Having Signed Power Purchase Contract With PLN
3
HYDRO POWER PROJECT- IPP
1 HEPP PARLILITAN 4X2,50 Sumatera Utara PT MEGA POWER MANDIRI -In Construction
2 HEPP PAKAT 1 2X5,00 Sumatera Utara PT ENERGY MANDIRI -Preparation for Negotiation Process
3 MHPP 2X2,10 Sumatera Utara PT INPOLA MEKA ELEKTRINDO -Preparation for Negotiation Process
PARLUASAN
4 HPP LEBONG 4X3,00 Bengkulu PT MEGA POWER MANDIRI --Preparation for Negotiation Process
5 HPP TANGKA 2X4,40 Sulawesi Selatan PT SULAWESI MINI HIDRO POWER --Preparation for Negotiation Process
( Manipi)
6 MHPP RANTEBALLA 2X2,20 Sulawesi Selatan PT FAJAR FUTURA INDAH -Negotiation Process
7 HPP TELUN BERASAP 2X4,00 Jambi PT MABRUK SARANA INTERBUANA --Negotiation Process
8 MHPP MABUYA 3X1,00 Sulawesi Utara PT CIPTA DAYA NUSANTARA -Yearly PPA
-In Construction
4
SMALL SCALE HYDRO POWER PROJECTS
( Funded by ADB)
Location
Capacity
Project Status
(MW)
Province Load Center
5
Power Purchase Contract of Non Geothermal IPP [Hydro, Coal Fired,
Gas Fired]
Offtaker
PLN
Power Purchase
Agreement
(“PPA”)
EPC Contract
EPC Contract
Engineering,Procurement, O&M
Construction (“EPC”) Contactor
Contactor
6
Power Purchase Contract of Geothermal IPP [Hydro, Coal Fired, Gas Fired]
Offtaker
PLN
Energy Sales
Contract (“ESC”)
Joint Operation
Seller Contract (“JOC”)
EPC Contract
EPC Contract
Engineering,Procurement, O&M
Construction (“EPC”) Contactor
Contactor
7
Price Structure of IPP
Price for Non Geothermal IPP is consisted
by 2 main part:
- Fixed Payment: for recovery fixed cost such as debt services,
fixed O&M, equity return
- Variable Payments: fuels cost and variable O&M
- Fixed and Variable escalated according to CPI
8
Price Structure for Geothermal IPP
4.45 c/kWh
Escalation Factor
45 % Not Escalated
55 % escalated according to CPI
9
Example of Price structure
Coal Fired Power Plant
Comp Price Abb. Appendix G
(c$/kWh)
A 3.00 CCR 2,496,600 Rp/kw year
B 0.30 FOMRl 142,500 Rp/kw year
FOMRf 142.500,- Rp/kw year
C 1.61 152.95 Rp/kwh
2300 kcal/kWh
Fuel Price 35 US$/ton
HHV 5000 kcal/kg
11
Term of • 30 years contract duration for Coal Fired and Hydro IPP
Agreement • 20 Years contract for Gas Fired IPP
13
Start Up and •Seller shall not energize or back-feed 150kV power into the
Commissioning Plant without the prior written approval of PLN's
Representative and Seller shall notify PLN of the initial
energization at least thirty (30) Days prior to the proposed date
of energizing the 150 kV switchyards and back-feeding power
to the Plant.
Operation and •Seller shall also operate the Plant in accordance with the
Maintenance Operating Procedures and the Dispatch Instructions, subject to
the Technical Limits.
•The Parties shall establish an Operating Committee comprising
four (4) members, two (2) appointed by each of Seller and PLN.
•Seller shall provide to PLN a proposed schedule of Net
Dependable Capacity Test for each unit and all unit, not later
than sixty (60) Days prior to the Scheduled Commercial
Operation Date of first unit.
14
Sale & • Prior to the Commercial Operation Date, Seller shall make
Purchasing available to PLN and PLN shall purchase the Net Electrical
Output of the Plant from Seller.
• From and after the Commission Date of the first operating unit
until the Commercial Operation Date, Seller shall make
available to PLN, and PLN shall purchase from Seller the NDC
and NEO of such unit.
• In the event Seller shall be unable to conduct the NDC Test for
a Unit or Units because of any action or failure by PLN or any
Governmental of RI or an Event of Force Majeure affecting the
PLN Grid System or other PLN owned facilities for more than
six (6) hours continuously, then PLN shall compensate the
Seller the NDC equivalent to CC MW with Actual Availability
Factor (AFa) deemed to be 80% for each Unit.
• If such Unit thereafter when tested at less than CC MW, then
the amounts paid by PLN during the period of deemed
commissioning in excess of the amount that PLN would have
had to pay if the Plant, had been deemed commissioned at a
NDC as so commissioned shall be credited against future
payments.
15
Billing and • On initial of payment process, Seller submit the invoice (provisional
Payment invoice) for such billing period. The content of such invoice are :
(Exchange Rate) nominal NDC, NEO dan Emergency Output made available to PLN
based on metering reading.
• The amount of such invoice is divided into A, B, C and D
components for both Rp. and USD portion.
• In the event PLN disputes any portion of an Invoice, PLN may refer it
to an expert. No previously undisputed Invoice or payment may be
disputed more than twelve (12) months after the Payment Date of
such Invoice.
• Late payments by either Party shall bear interest at the Late Payment
Interest Rate from the date on which such payment was originally
due until the date that such payment was made.
Insurance Seller shall obtain and maintain insurance policies with respect to
power generating facilities of similar size, technology, location and
long term relation to the power purchaser, including general coverage
and workmen’s compensation. The Seller shall pay the premi amount.
16
Force Majeur • If an event of Force Majeure affects PLN’s ability to accept NDC
and NEO, and after fourteen (14) Days period, the Plant shall be
deemed dispatched to the extent that Seller would have been able
to deliver NEO in accordance with the terms and conditions of the
Agreement. For the occurrence of such Event of Force Majeure
PLN shall continue to be obligated to make payments for NDC of
such deemed dispatch.
• If an Event of Force Majeure shall have occurred that results in a
material delay in the completion of the Project or causes material
damage to the Plant, and such Event of Force Majeure is not
normally insured against in accordance with Good Utility Practice,
then both parties shall enter into good faith negotiations to obtain
funding to complete or repair the Plant.
Settlement of • If any dispute arise between the Parties, the Parties shall attempt,
Disputes for a period of thirty (30) Days after the receipt by one Party of a
notice from the other Party of the existence of the Dispute, to
settle such Dispute by mutual discussions between the Parties.
• If the Dispute cannot be settled within the 30-Day period provided
and the Parties so agree in writing, the Dispute shall be referred to
an expert for determination.
• In the event that no written agreement to refer the Dispute to an
expert is reached within thirty (30) Days between the Parties, the
Party who gives the notice of the existence of the Dispute have the
right to directly refer such Dispute to Badan Arbitrase Nasional.
PLN Purchase At any time after the Financing Date through the end of the Term,
Option PLN may exercise an option to purchase , PLN shall give Seller not
less than one hundred eighty (180) Days written notice. 17
Term of • 42 years contract for Geothermal IPP
Agreement • 30 years production period for each unit of Geothermal IPP
Basically most of the major the Terms and Condition of Non Geothermal
IPP contract is also addressed in Geothermal IPP contract but in more
simpler way.
18