PROJECT MANAGEMENT (MGMT727)

Assignment No. 1
Due Date: February 7, 2019 Marks: 20
Question:
Given following information, draw the project network (CPM) using AON method. Compute
the early, late, and slack times for all activities. Identify the project duration and critical
path(s).

Finish-to-Start Finish-to-Start Additional Lag


ID Duration Predecessor Lag Relationships Lag
A 4 None 0 None 0
B 8 None 0 None 0
C 9 A 4 Start-start C to D 4
Finish-finish C to F 9
D 10 B 0 None 0
E 20 B 0 Start-finish E to G 10
C 12
F 5 D 0 None 0
G 7 F 6 Start-start G to H 12
H 8 None 0 None 0
I 16 E 5 Finish-finish I to J 8
J 18 G, H 0 None 0

Instructions:
1. This is a practical assignment in which you have to draw a proper project network.
2. Draw project network (PERT/CPM) using „activity on node‟ method. (10 Marks)
3. Compute early, late and slack times for each activity. (6 Marks)
4. Identify critical activities/ path and the project duration. (4 Marks)
5. Use following legend to show an activity on node:
ES Activity EF
Start ID Finish
Slack Slack
LS Duration LF
where
ES: earliest start time LS: latest start time
EF: earliest finish time LF: latest finish time

6. For slack and project duration, first calculate earliest and latest times.
7. No theoretical definitions and explanations are required.
8. Consult Chapter 6 of Recommended Text Book for further guidance.
9. Show all necessary working and calculations in your assignment solution.
Important:
24 hours extra/ grace period after the due date are usually available to overcome
uploading difficulties. This extra time should only be used to meet the emergencies and
above mentioned due dates should always be treated as final to avoid any
inconvenience.

Deadline:
 Make sure to upload the solution file before the due date on VULMS.
 Any submission made via email after the due date will not be accepted.

Formatting Guidelines:
 Use the font style “Times New Roman” or “Arial” and font size “12”.
 It is advised to compose your document in MS-Word format.
 You may also compose your assignment in Open Office format.
 Use black and blue font colours only.

Referencing Guidelines:
 Use APA style for referencing and citation. For guidance search “APA reference
style” in Google and read various websites containing information for better
understanding or visit http://linguistics.byu.edu/faculty/henrichsenl/apa/APA01.html

Rules for Marking


Please note that your assignment will not be graded or graded as Zero (0), if:
 Any of the given instructions is not followed
 It is copied or plagiarized
 It is submitted after the due date.
 The file you uploaded does not open or is corrupt.
PROJECT MANAGEMENT (MGMT727)
Assignment No. 1
Solution:

Project duration = 78

Critical path: A – C – E – I – J

Lag 4
Lag 12
Lag 12

Lag 4 Lag 5 End


Start
Lag 10
Lag 9 Lag 8

Lag 6