• overall Atoll technical manual does not contain PRACH RSI planning
PRACH / RSI
scripts
1st order neighbour: relative weight assigned to 1st order neighbour relation violation
2nd order neighbour: relative weight assigned to 2nd order neighbour relation violation
weights pending on network configuration, density Distance: relative weight assigned to distance based relation violation
and topology
start audit
Number of required PRACH RSIs: required PRACH RSI as defined within the allocation cycle
Validity of … PRACH RSIs: required number is valid or not x
List of PRACH RSIs: allocated PRACH RSIs
Compliance … PRACH RSIs: number of allocated PRACH RSI matches required number or not x
whether a neighbour / second neighbour or common cell neighbour relations exists or not x and the related importance
Sites: 536
Neighbours: considered
Distribution
Allocation
Confidentiality Level - C2- Vodafone internal 30
Test Allocation
Allocation Results from different weights
• limitation to a user-defined range of RSI available with next release of Atoll 3.2.1
• group and domains required for border planned for Atoll 3.3.0
coordination
• RSI indicator to be listed separately can be done by custom field / Forsk can provide Macro if required
• add table field for restricted / unrestricted rejected by Forsk
scenario Forsk will disable defining not existing PRACH RSI length
Forsk will provide Macro to calculate cell range and number of
required PRACH RSI
• rename “PRACH RSI” table header also requested by other user, final Forsk decision open
• defining “Common Neighbours” ??? no need, will be fixed with next release