⑪ Install 2nd layer vertical frame of the Falling from height. Use safety belt in case of the height of the
scaffolding. floor exceed 2m or more.
⑫ Install bracings at both side. Falling from height. Use safety belt in case of the height of the
floor is 2m or more.
⑮ Install life line. Falling from height. Use life line of the lower layer of the
scaffolding during installation of life line of
the upper layer.
Tight the life line by each 5 spans.
⑯ Install the 3rd layer's vertical frames Falling from height. Hook the safety belt to the life line.
at each 5 spans.
⑰ Install life line. Falling from height. Use life line of the lower layer of the
scaffolding during installation of life line of
the upper layer.
⑱ Install entire vertical frame of 3rd layer. Falling from height. Proceed the work with changing hang safety
belt to the upper life line.
⑲ Install bracings at both side. Falling from height. Proceed the work with changing hang safety
⑳ Install platform. belt to the upper life line.
2
2 Hoist up materials with using pulley Struck by falling object. Do not enter the area where hoisting
installing pipe or bracket. materials.
Rope will be broken. Use tag line for hoisting materials to high
place.
Check the rope.
Use safety belt.
Receive the materials of vertical frame Falling from height. Use safety belt.
2
3
from 3rd layer and install it at each 5 Struck by falling object. Do not enter the area where hoisting
spans of the 4th layer. materials.
2
4 Relocate life line of the lower layer to Falling from height. Use safety belt.
the upper layer.
2
5
Repeat ⑱~ 24
2
6 Install 2 layers hand rail or vertical Falling from height. Use safety belt.
frames at the top layer of the
scaffolding.
Install end stopper.
2
7 Scaffolding tie.
Work procedure of scaffolding erection
5
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
④ Assemble vertical frame of the Collapsing of the scaffolding. Bracing have to be installed immediately once the
scaffolding with bracing one by one. vertical frame of the scaffolding will be erected in
order to prevent falling down of the vertical frame.
Perform the work by 2
persons.
6
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
⑤ Check and adjust the level of the It become difficult to install bracing
scaffolding with using horizontal and platform without maintaining the
measurement equipment. level of the scaffolding.
No Entry
except persons
concerned.
⑥ Install bottom pipe to the scaffolding Install the bottom pipe to the both side of the
in order to maintain alignment of the scaffolding.
scaffolding.
7
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Workpipe
sequence (Expected accident) (Counter measures )
Install bottom to the scaffolding Install the bottom pipe to the both side of the
in order to maintain alignment of the scaffolding.
scaffolding.
No Entry
except persons
concerned.
8
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
No Entry
except persons
concerned.
⑨ Install staircase.
9
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
No Entry
except persons
concerned.
No Entry
except persons
concerned.
10
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
Install 2nd layer vertical frame of the Use safety belt in case of the height of the floor
⑪ Falling from height.
scaffolding. exceed 2m or more.
No Entry
except persons
concerned.
11
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
No Entry
except persons
concerned.
No Entry
except persons
concertned.
12
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
No Entry
except persons
concertned.
Use life line of the lower layer of the
⑮ Install life line. Falling from height. scaffolding during installation of life line of the
upper layer.
Tight the life line by each 5 spans.
No Entry
except persons
concertned.
13
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
No Entry
except
persons
concertned.
14
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
No Entry
except
persons
concertned.
Install entire vertical frame of 3rd Proceed the work with changing hang safety
⑱ Falling from height.
layer. belt to the upper life line.
No Entry
except persons
concertned.
15
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
No Entry
except persons
concertned.
2
1
Install staircase.
No Entry
except persons
concertned.
16
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
2 Hoist up materials with using pulley
2 Struck by falling object. Do not enter the area where hoisting materials.
installing pipe or bracket.
Use tag line for hoisting materials to high
Install pipe temporalily in stead of Rope will be broken.
place.
bracing in order to ease hoisting Falling from height. Check the rope.
materials. Use safety belt.
No Entry
except persons
concertned.
2
3 Receive the materials of vertical
frame from 3rd layer and install it at Falling from height. Use safety belt.
each 5 spans of the 4th layer.
Struck by falling object. Do not enter the area where hoisting materials.
17
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
No Entry
except persons
concertned.
No Entry
except persons
concertned.
2
5
Repeat ⑱~ 24
18
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
19
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
No Entry
except persons
concertned.
2
7
Scaffolding tie.
20
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
21
Approved by Confirmed by Produced by