Work procedure of scaffolding erection

Identification of the dangerous and Identification of measures to be taken for


Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
① Grading and compaction of the ground The scaffolding likely to sink Sufficient compaction after the grading.
where scaffolding will be erected. inequitably in case of uneven level of
ground a insufficient compaction.

Falling down of the compaction Operate compaction machine with 2


machine due to the operation mistake persons at the front and the rear.
or injury of leg.
( The compaction machine showing below
can be operated by one person.)
② Arrangement of duck board. The scaffolding likely to sink
inequitably in case of cave-in by heavy
rain.

(Duck board is not required in case of


the scaffolding stands on flat concrete
surface.)
③ Arrangement of jack base. It is difficult to erect scaffolding due to
impossible of the level adjustment
without jack base.

④ Assemble vertical frame of the Collapsing of the scaffolding.


Bracing have to be installed immediately
scaffolding with bracing one by one.
once the vertical frame of the scaffolding
will be erected in order to prevent falling
down of the vertical frame. Perform the
work by 2 persons.

Take measure of entry prohibition of


excluding parties concerned.
⑤ Check and adjust the level of the It become difficult to install bracing
scaffolding with using horizontal and platform without maintaining the
measurement equipment. level of the scaffolding.
⑥ Install bottom pipe to the scaffolding Install the bottom pipe to the both side of
in order to maintain alignment of the the scaffolding.
scaffolding.

⑦ Fix the jack base to the duck board


with nails to prevent the slipping.
(The number of the nail to be 2 or more.)

⑧ Install platform. 2 numbers of platforms to be installed in


case of the width of the scaffolding is
1,200mm or more.
⑨ Install staircase.
⑩ Arrange materials of the 2nd layer.

⑪ Install 2nd layer vertical frame of the Falling from height. Use safety belt in case of the height of the
scaffolding. floor exceed 2m or more.

⑫ Install bracings at both side. Falling from height. Use safety belt in case of the height of the
floor is 2m or more.

Identification of the dangerous and Identification of measures to be taken for


Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
⑬ Install platform. 2 numbers of platforms to be installed in
case of the width of the scaffolding is
1,200mm or more.
⑭ Install staircase and handrail.

⑮ Install life line. Falling from height. Use life line of the lower layer of the
scaffolding during installation of life line of
the upper layer.
Tight the life line by each 5 spans.
⑯ Install the 3rd layer's vertical frames Falling from height. Hook the safety belt to the life line.
at each 5 spans.

⑰ Install life line. Falling from height. Use life line of the lower layer of the
scaffolding during installation of life line of
the upper layer.
⑱ Install entire vertical frame of 3rd layer. Falling from height. Proceed the work with changing hang safety
belt to the upper life line.

⑲ Install bracings at both side. Falling from height. Proceed the work with changing hang safety
⑳ Install platform. belt to the upper life line.

2 numbers of platforms to be installed in


case of the width of the scaffolding is
1,200mm or more.
2
1
Install staircase.

2
2 Hoist up materials with using pulley Struck by falling object. Do not enter the area where hoisting
installing pipe or bracket. materials.
Rope will be broken. Use tag line for hoisting materials to high
place.
Check the rope.
Use safety belt.

Receive the materials of vertical frame Falling from height. Use safety belt.
2
3
from 3rd layer and install it at each 5 Struck by falling object. Do not enter the area where hoisting
spans of the 4th layer. materials.
2
4 Relocate life line of the lower layer to Falling from height. Use safety belt.
the upper layer.

2
5
Repeat ⑱~  24

2
6 Install 2 layers hand rail or vertical Falling from height. Use safety belt.
frames at the top layer of the
scaffolding.
Install end stopper.

2
7 Scaffolding tie.
Work procedure of scaffolding erection

Identification of the dangerous and Identification of measures to be taken for


Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
① Grading and compaction of the The scaffolding likely to sink Sufficient compaction after the grading.
ground where scaffolding will be inequitably in case of uneven level of
erected. ground a d insufficient compaction.

Operate compaction machine with 2 persons at


Falling down of the compaction the front and the rear.
machine due to the operation mistake
or injury of leg. ( The compaction machine showing below can
be operated by one person.)

② Arrangement of duck board. The scaffolding likely to sink inequitably


in case of cave-in by heavy rain.

(Duck board is not required in case of


the scaffolding stands on flat
concrete surface.)

5
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

③ Arrangement of jack base. It is difficult to erect scaffolding due


to impossible of the level adjustment
without jack base.

④ Assemble vertical frame of the Collapsing of the scaffolding. Bracing have to be installed immediately once the
scaffolding with bracing one by one. vertical frame of the scaffolding will be erected in
order to prevent falling down of the vertical frame.
Perform the work by 2
persons.

Take measure of entry prohibition of excluding


parties concerned.

6
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

⑤ Check and adjust the level of the It become difficult to install bracing
scaffolding with using horizontal and platform without maintaining the
measurement equipment. level of the scaffolding.

No Entry
except persons
concerned.

⑥ Install bottom pipe to the scaffolding Install the bottom pipe to the both side of the
in order to maintain alignment of the scaffolding.
scaffolding.
7
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Workpipe
sequence (Expected accident) (Counter measures )
Install bottom to the scaffolding Install the bottom pipe to the both side of the
in order to maintain alignment of the scaffolding.
scaffolding.

No Entry
except persons
concerned.

⑦ Fix the jack base to the duck board


with nails to prevent the slipping.
(The number of the nail to be 2 or more.)

8
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

⑧ Install platform. 2 numbers of platforms to be installed in case


of the width of the scaffolding is 1,200mm or
more.

No Entry
except persons
concerned.

⑨ Install staircase.

9
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

No Entry
except persons
concerned.

⑩ Arrange materials of the 2nd layer.

No Entry
except persons
concerned.

10
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

Install 2nd layer vertical frame of the Use safety belt in case of the height of the floor
⑪ Falling from height.
scaffolding. exceed 2m or more.

No Entry
except persons
concerned.

Use safety belt in case of the height of the floor


⑫ Install bracings at both side. Falling from height.
is 2m or more.

11
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

No Entry
except persons
concerned.

2 numbers of platforms to be installed in case


⑬ Install platform. of the width of the scaffolding is 1,200mm or
more.

No Entry
except persons
concertned.

⑭ Install staircase and handrail.

12
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

No Entry
except persons
concertned.
Use life line of the lower layer of the
⑮ Install life line. Falling from height. scaffolding during installation of life line of the
upper layer.
Tight the life line by each 5 spans.

No Entry
except persons
concertned.

Install the 3rd layer's vertical frames


⑯ Falling from height. Hook the safety belt to the life line.
at each 5 spans.

13
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

No Entry
except
persons
concertned.

Use life line of the lower layer of the


⑰ Install life line. Falling from height. scaffolding during installation of life line of the
upper layer.

14
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

No Entry
except
persons
concertned.

Install entire vertical frame of 3rd Proceed the work with changing hang safety
⑱ Falling from height.
layer. belt to the upper life line.

No Entry
except persons
concertned.

Proceed the work with changing hang safety


⑲ Install bracings at both side. Falling from height.
belt to the upper life line.
2 numbers of platforms to be installed in case
⑳ Install platform. of the width of the scaffolding is 1,200mm or
more.

15
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

No Entry
except persons
concertned.

2
1
Install staircase.

No Entry
except persons
concertned.

16
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )
2 Hoist up materials with using pulley
2 Struck by falling object. Do not enter the area where hoisting materials.
installing pipe or bracket.
Use tag line for hoisting materials to high
Install pipe temporalily in stead of Rope will be broken.
place.
bracing in order to ease hoisting Falling from height. Check the rope.
materials. Use safety belt.

No Entry
except persons
concertned.

2
3 Receive the materials of vertical
frame from 3rd layer and install it at Falling from height. Use safety belt.
each 5 spans of the 4th layer.
Struck by falling object. Do not enter the area where hoisting materials.

17
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

No Entry
except persons
concertned.

2 Relocate life line of the lower layer


4 Falling from height. Use safety belt.
to the upper layer.

No Entry
except persons
concertned.

2
5
Repeat ⑱~ 24

18
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

Install 2 layers hand rail or vertical


2 frames at the top layer of the Falling from height. Use safety belt.
6
scaffolding.
Install end stopper.

19
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

No Entry
except persons
concertned.

2
7
Scaffolding tie.

Propsal for scaffolding tie ①

20
Identification of the dangerous and Identification of measures to be taken for
Work schedule
harmful factors. removal and minimization of the risks.
Work sequence (Expected accident) (Counter measures )

Propsal for scaffolding tie ②

21
Approved by Confirmed by Produced by

NFC NFC NFC NFC


YASUHIRO NAKAYAMA YAMASHITA KAWAKAMI

19/Dec/08 19/Dec/08 19/Dec/08 19/Dec/08

S-ar putea să vă placă și