MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 2 / 37
TABLE OF CONTENT
1. SCOPE .................................................................................................................................... 6
APPENDIX 5 - WORK STEP AND WEIGHT FACTORS FOR CONSTRUCTION WORKS ............................................... 23
1. SCOPE
This procedure describes the basis and method to be used for calculating the progress of
Engineering, Procurement, Construction, Commissioning, and Overall progress for PT PANCA
AMARA UTAMA (hereinafter referred to as OWNER) that will be prepared by PT Rekayasa
Industri (hereinafter referred as CONTRACTOR) during all Engineering, Procurement,
Construction, and Commissioning activities of Banggai Ammonia Plant Project (hereinafter
referred to as BAP PROJECT).
This procedure is not meant to circumvent or override any provisions of Contract. In-case of
any conflict between this procedure document and contract, provisions of contract shall prevail
over this document.
This procedure will be the basis for calculation of physical monthly progress.
- Construction 33%
Commissioning (Wtg) 5%
3.3 Weight Factors and Weight Value of Engineering Progress
There are two kinds of weight factors:
a. Weight factors for engineering work steps (Appendix 1) to summarize progress for each
work steps into progress for each document.
b. Weight factors for each work discipline for engineering (Appendix 2) to summarize
progress for each work discipline into total engineering function progress and then to
summarize progress for each phase into total engineering progress.
3.4 Weight Factors of Procurement Progress
There are two kinds of weight factors:
a. Weight factors for procurement work steps (Appendix 3) to summarize progress for each
procurement work step into progress for each procurement discipline/package.
b. Discipline Weight factors for each category (Appendix 4) to summarize progress based
on each Equipment/Material cost for each procurement discipline/package into total
procurement category and then to summarize progress for each of procurement category
into total procurement services progress.
3.5 Construction Progress
There are three kinds of weight factors:
a. Weight factors for construction work step (Appendix 5) to summarize progress for each
work step into the progress for each work item.
b. Weight factors for each work category will be developed based on cost.
c. Weight factors for each work discipline (Appendix 6) to summarize progress for each work
discipline into total Construction progress.
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 11 / 37
4. PROGRESS CALCULATION
4.1 Engineering Progress Calculation
Discipline / Functional schedules with assigned weightages based onMan-hours will be
finalised prior to progress measurement. The progress will be calculated as shown below :
4.1.1 Progress Percentage of Each Document
Pd = ∑ pd.wd
Where:
Pd = progress percentage of each document
pd = actual progress percentages for work steps of document
wd = weight factors for work steps of each document (refer to Appendix
1)
4.1.2 Progress Percentage of Each Work Discipline
The progress percentage of each work discipline is calculated by:
Pe = ∑ Pd.Wd
Where:
Pe = progress percentage of each work discipline for engineering
Pd = progress percentage of each document
Wd = weight factor for each document
4.1.3 Total Progress Percentage for Engineering
PE = ∑ Pe.wpe
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 12 / 37
Where :
PE = progress percentage of engineering
Pe = progress percentage of each work discipline for engineering
wpe = weight factors for each discipline (refer to Appendix 3)
4.2 Procurement Progress Calculation
Discipline / Functional schedules with assigned weightages based on cost will be finalised
prior to progress measurement.
Procurement to be sub-divided into :
- Ordering
- Manufacturing & Delivery
The progress will be calculated as shown below.
4.2.1 Progress Percentage of each procurement equipment/Item for
Ordering/Manufacturing
Ppo/m = ∑ ppo/m.wpo/m
Where:
Ppo/m = progress percentage of each procurement equipment/item for
ordering/manufacturing
Ppo/m = progress percentages of work steps of each procurement
equipment/item for ordering/manufacturing
Wpo/m = weight factors for work steps of each procurement equipment/item
for ordering/manufacturing (refer to Appendix 2)
4.2.2 Progress Percentage of Each Procurement Discipline for Ordering/Manufacturing
Ppdo/m = ∑Ppo/m.Wpdo/m
Where:
Ppdo/m = progress percentage of each procurement discipline, i.e. civil
materials, mechanical equipment/materials, piping materials, etc. for
ordering/manufacturing
Ppo/m = progress percentage of each procurement equipment/item for
ordering/manufacturing
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 13 / 37
PPo/m = ∑Ppdo/m.Wpeo/m
Where:
PP o/m = progress total procurement for ordering/manufacturing
Ppdo/m = progress percentage of each procurement discipline for
ordering/manufacturing
Wpeo/m = weight factor of each procurement discipline (refer to Appendix 4)
for ordering/manufacturing
4.2.4 Progress Percentage of Procurement
PP = PPo.Wpo +∑PPm.Wpm
Where:
PP = progress total procurement
PPo = progress total procurement for ordering
PPm = progress total procurement for manufacturing
Wpo = weight factor for ordering
Wpm = weight factor for manufacturing
Note : o for ordering; m for manufacturing
4.3 Construction Progress Calculation
Discipline / Functional schedules with assigned weightages based on cost will be finalised
prior to progress measurement. Construction will be sub-divided into :
- Sub contracting
- Construction works
The progress will be calculated as shown below.
4.3.1 Progress Percentage of Each Subcontracting/Construction Work Item (Px)
The progress percentage for Subcontracting/ Construction work items is calculated
by:
Pxs/c = ∑ pxs/c.wxs/c
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 14 / 37
Where :
Pxs/c = progress percentage of each construction work item for
subcontracting/construction work
pxs/c = progress percentages of each work step of each work item for
subcontracting/construction work
wxs/c = weight factors for each work step for subcontracting/construction
work (refer to Appendix 5)
4.3.2 Progress Percentage of Each Subcontracting/Construction Work Category (Pxt)
The progress percentage of each Subcontracting/Construction work category is
calculated by:
Pxts/c = ∑Pxs/c.nxs/c
Where:
Pxts/c = progress percentage of each construction category for
subcontracting/construction work
Pxs/c = progress percentage of each construction work item for
subcontracting/construction work
nxs/c = weight factor for each work item for subcontracting/construction work
4.3.3 Progress Percentage of Each Subcontracting/Construction Work Discipline (Pc)
The progress percentage of each Subcontracting/Construction work discipline is
calculated by:
Pcs/c = ∑ Pxts/c.Wds/c
Where:
Pcs/c = progress percentage of each construction work discipline for
subcontracting/ construction work
Pxts/c = progress percentage of each construction category for
subcontracting/ construction work
Wds/c = weight factors for each work category for subcontracting/
construction work (refer to Appendix 6)
4.3.4 Total Percentage of Subcontracting/Construction Work Progress (PCs/c)
The total percentage of subcontracting/construction progress is calculated by:
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 15 / 37
PCs/c = ∑ Pcs/c.Wks/c
Where:
PCs/c = progress total of subcontracting/construction work
Pc = progress percentage of each subcontracting/construction work
discipline
Wk = weight factors per each work discipline for
subcontracting/construction work (refer to Appendix 6)
4.3.5 Total Percentage of Construction (PC)
The total percentage of construction progress is calculated by:
PC = PCs.Wks+ PCc.Wkc
Where:
PC = progress total of construction
PCs = progress total of construction for subcontracting
PCc = progress total of construction for construction work
Wks = weight factors for subcontracting
Wkc = weight factors for construction work
PT = PTA.Wta + PTU.Wtu
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 17 / 37
Where:
5. PROGRESS REPORT
5.1 Progress Summary
5.1.1 Progress Table
As an aid in planning and control, progress curves will be developed to monitor
progress.
The progress of the work is summarized in tabular format. It shall include plan and
actual progress achieved for the month.
5.1.2 Overall PROJECT Progress
The “S” curves will have the following elements:
• Schedule Curve
• Actual Progress
The "S" curves will be derived utilizing the weight values agreed with OWNER. The
"S" curves will include profiles for the entire duration. The curves will be updated
periodically to display actual versus planned progress, as well as projected trend for
the remaining period. These will be issued as a part of the Monthly Progress Report.
5.2 Progress Reporting
CONTRACTOR shall prepare and issue the Monthly Progress Report in accordance to the
agreed cut-off and issuance date with OWNER. The contents and format of this report shall
be provided to OWNER as per agreed reporting procedure.
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 18 / 37
(wd)
1. Issue For Approval/Review (1) Drafting Completed 30%
(2) Issued to owner 30%
(3) OWNER’s comment Incorporated 25%
(4) Owner Approved (Code A) 15%
100%
(wd)
2. Issue For Information (1) Drafting Completed 35%
(2) Issued to owner 65%
100%
Note : if in any case, a work step does not have any evidence that it was already done, but
Contractor have the evidences for its successor, so then it would be deemed done too.
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 20 / 37
(wpe)
(wp)
For Bulk materials work steps for Ordering and Manufacturing will be same as above and as
applicable however dispatch/FOB and receipt at site will be measured progressively as per
quantity of material dispatched / received out of total scope.
Note : if in any case, a work step does not have any evidence that it was already done, but
Contractor have the evidences for its successor, so then it would be deemed done too.
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 22 / 37
(Wpe)
1. Amonia
Civil /Structural 5%
Mechanical 60%
Piping 15%
Electrical 7%
Instrument 11%
Miscellaneous 2%
100%
2. Utility
Civil /Structural 4%
Mechanical 60%
Piping 15%
Electrical 10%
Instrument 9%
Miscellaneous 2%
100%
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 23 / 37
1. Subcontracting
WORK STEP WEIGHT
FACTOR
Subcontracting (1) Issue RFQ 20%
(2) Issue TBE 30%
(2) Contract Signed 50%
100%
2. Construction
Weighted value for each construction work items under each work packages for construction will
be assigned based on contract value or cost with respet to the total work packages contract value
or cost. The progress of each work item will be calculated as per work step shown below. Work
step progress percentage will be calculated based on quantity completed out of scope quantity.
The general work step for construction work items are as follows for reference:
1. CIVIL WORKS
General Civil/Jetty
Piling Subarea Load Test 10% nos
Piling 90% nos
Sewer Subarea Excavation 20% m3
Sand Filling 10% m3
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 24 / 37
Backfilling &
20% m3
compaction
Drainage Subarea Excavation 20% m3
Rebar 15% kg
Formwork 15% m2
Backfilling 10% m3
Miscellaneous Civil Work Subarea Excavation 10% m3
Rebar 15% kg
Formwork 15% m2
Backfilling 10% m3
Install Temp. Sheet
Sea Water Intake 20% lot
pile
Rebar 15% kg
Formwork 15% m2
Backfilling 10% m3
Plumbing, AC &
25% nos
Electrical
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 26 / 37
2. STRUCTURAL WORKS
Steel Structure Erection Str. no. Preparation 5% lot
Erection 50% kg
Grouting 5% lot
Grating/Checkers
15% kg
Plate
Stair/Ladder 15% kg
Fire Proofed 10% M3
3. MECHANICAL WORKS (wx)
Static Equipment
Vessel, HE, Drum, Stack Eqp no Preparation 10% lot
Grouting 5% lot
Test and inspection 10% lot
4. RIGGING WORKS
Equipment
Heavy Lifting Eqp no 10% lot
Mobilization
preparation 10% lot
Installation 45% ea
Alignment &
10% lot
Grouting
Platform a.
15% kg
Equipment
5. PIPING WORKS
Underground Piping Underground Excavation 10% m3
Installation 15% dia-in
Welding 15% dia-in
Wrapping and
20% m'
coating
6. ELECTRICAL WORKS
Fixing base plate
15% lot
/preparation
Equipment
Power Distribution Subs. no. 40% set
Installation
Cable Wiring 30% point
Test 15% ea
Power &Control Wiring Subarea Conduit 10% set
Cable Tray 25% m'
Push Button/LCS 10% set
Cable Wiring 20% m'
Termination 25% point
Test 10% point
Pole/Fixture
Plant Lighting Subarea 35% m'
Installation
Wiring and
50% set
connection
Test 15% set
Electrode
Grounding Subarea 20% nos
Installation
Ground Wiring 30% m'
Termination 35% point
Test 15% point
Cathodic Subarea Equipment 45% set
Wiring 40% point
Test 15% point
Equipment
Communication System Subarea 35% set
Installation
Wiring and
40% point
Connection
Test 25% point
Building Electrical Subarea Conduit Piping 30% m'
Wiring and
35% point
Connection
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 30 / 37
7. INSTRUMENT WORKS
Equipment
Control Building Subarea 30% ea
Installation
Tubing 35% ea
Air Supply Piping &Tubing Subarea Air Supply Piping 40% m'
8. PAINTING WORKS
Painting for Equipment Eqp.no. Preparation 10% lot
Intermediate coat 30% m2
Finish Coat 60% m2
Painting for Piping Subarea Preparation 10% m2
Primer & Second
40% m2
Coat
Scaffolding 10%
Weatherproofing 35% m2
Cold Insulation
Cold Insulation for Equipment Eqp.no. Scaffolding 10% m2
Insulation 45% m2
Weatherproofing 35% m2
Weatherproofing 50% m2
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 32 / 37
10. PRECOMMISSIONING
Loop Check and Sequence System/Su Loop Test / Sequence Test 50% ea
Test bsystem
Function test 50% ea
Note : if in any case, a work step does not have any evidence that it was already done, but
Contractor have the evidences for its successor, so then it would be deemed done too.
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 33 / 37
(Wk)
AMMONIA UTILITY
5. Buildings 0% 14%
6. Mechanical/Equipment 21% 5%
8. Electrical 5% 5%
9. Instrument 7% 3%
11. Pre-commissioning 5% 1%
-------- ---------
100% 100%
PHYSICAL PROGRESS
MEASUREMENT PROCEDURE
Doc no : BAP-00-80-PE-0103-R
BANGGAI AMMONIA
Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 34 / 37
The progress for commissioning activities will be measured system wise as follows:
A. Ammonia
System
Weight Factor
Description
(%)
B. UOA
Weight
System
Description Factor
(%)
APPENDIX 8 - SUMMARY
Civil 4%
Mechanical 60%
Piping 15%
Electrical 10%
Instrument 9%
Miscellaneous 2%
Total 100%
Infrastructure/enabling work 8%
Marine Work 14%
Tankage Work 14%
Civil/Structural Work 19%
Buildings 14%
Mechanical 5%
Construction 44%
Piping 14%
Electrical 5%
Instrument 3%
Painting & Insulation 3%
Pre-commissioning 1%
Total 100%
Commissioning 2%
Total 100%
Total 100%