PROCEDURE
Doc no : BAP-00-80-PE-0203-R
BANGGAI AMMONIA Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 2 / 12
1 Nov 11, 2015 CONSTRUCTION” or “FOR RECORD” and/or as the case may
be.”
- Revision on Appendix 1: “Issued For Construction” changed
into “Stamped For Construction”
- Revision on Appendix 2: Revise the table, especially on Non
P&ID and additional statements on explanation.
2 Jan 30, 2018 As Final
REVIEW AND APPROVAL
PROCEDURE
Doc no : BAP-00-80-PE-0203-R
BANGGAI AMMONIA Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 3 / 12
TABLE OF CONTENT
1. GENERAL SCOPE
This document describes the procedure for the review and approval of the documents by PT
PANCA AMARA UTAMA (hereinafter referred to as OWNER) submitted by PT. Rekayasa
Industri (hereinafter referred to as CONTRACTOR) during all Engineering, Procurement,
Construction and Commissioning activities of BANGGAI AMONIA PLANT PROJECT
(hereinafter referred to as PROJECT).
This procedure is not meant to circumvent or override any provisions of contracts. In case of
any conflict between this procedure document and contract, provisions of contract shall prevail
over this document.
2. REFERENCE
The following procedure shall be referred to many documents below :
Reference Title
BAP-00-80-PE-1201-R Document Preparation Procedure
BAP-00-80-PE-1203-R Document Numbering Procedure
BAP-00-80-PE-1204-R Correspondence and Communication Procedure
3. DEFINITION
The following terms used in this procedure shall have the meaning as denoted below:
1. Approval
It means OWNER’s formal acceptance or authorization of project documents to ensure
that CONTRACTOR has in conformance to Project Contract requirements or to require
modification to the Project Contract requirements under change order provision in
accordance with the Contract to allow CONTRACTOR to proceed with the relevant work.
2. Review
It means OWNER’s review of certain documents, which do not require OWNER’s approval
before CONTRACTOR proceeds with the work, where OWNER’s comment is made based
on its experience and intimate knowledge of site conditions would be of value to
CONTRACTOR, or where it is desirable by OWNER to modify certain requirements of the
Project Contract, provided that those comments are given within the appropriate period,
CONTRACTOR will then incorporate such comments in accordance the Contract.
REVIEW AND APPROVAL
PROCEDURE
Doc no : BAP-00-80-PE-0203-R
BANGGAI AMMONIA Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 5 / 12
3. Information
It means OWNER’s information of certain documents other than documents subject for
Approval or Review which do not require OWNER’s approval or review before construction
proceeds with the work.
4. Approved
It means CONTRACTOR received formal notification from OWNER that the submitted
documents/drawings (either revised reflecting OWNER’s comments/other inputs agreed
by both parties or without any revision), have been duly reviewed and approved by
OWNER without any further comment.
5. Reviewed
It means CONTRACTOR received formal notification from OWNER that the submitted
documents/drawings (either revised reflecting OWNER’s comments/other inputs agreed
by both parties or without any revision), have been duly reviewed by OWNER without any
further comment.
6. Construction
It means OWNER approved the original documents/drawings and thereafter,
CONTRACTOR may issue it either for fabrication or construction.
7. Record/As Final
It means OWNER approved the original documents/drawings and thereafter,
CONTRACTOR may issue it for record.
Notwithstanding to the above, any approval or comments by OWNER will not relieve
CONTRACTOR of any of its responsibilities under the Project Contract.
remaining comments with OWNER to resolve any issue incurred. After incorporating above
comment, document will be issued in next revision number with information in control sheet
as “Revised as per OWNER comment/other occurrence including the date/place”.
If document already approved by OWNER and/or there were no further comment from
OWNER, such document will be stamped by CONTRACTOR with “FOR CONSTRUCTION”
or “FOR RECORD” and/or as the case may be.
Any approvals or comments by owner shall not relieve CONTRACTOR of any its
responsibilities under the contract. Drawing larger than folder size sent to OWNER shall be
folded to folder size for easy filling. Drawing sizes shall follow CONTRACTOR’s standard.
Documents which are bulky or complex shall be released for approval in stages as completed,
rather than all at once after completion of the last one. This also allow OWNER reasonable
chance to review and comment without being swamped by so many items released
simultaneously as to make timely approval impossible.
Any errors discovered/comments agreed in drawings or other document shall be corrected
expeditiously irrespective of whether document has previously approved by OWNER.
All documents requiring OWNER review and approval shall not be submitted until
CONTRACTOR thorough review is made.
Flowchart for document reviewing procedure is shown on Block Diagram – A & B as shown
in Appendix -1 of this procedure.
CONTRACTOR will circulate list of documents “deemed approved” every fortnight on a
mandatory basis.
6. INDICATION
All documents submitted to OWNER shall be delivered with a transmittal which indicates “For
Approval”, “For Review”, “For Information”, “For Record” or “For Construction”. This
information also may be indicated on the first page of each document.
The style of stamps is as follows:
REVIEW AND APPROVAL
PROCEDURE
Doc no : BAP-00-80-PE-0203-R
BANGGAI AMMONIA Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 9 / 12
FOR RECORD
OWNER’s comments on the Project documents submitted by CONTRACTOR will be classified
into the following 4 (four) status:
Status “A”: Approved, CONTRACTOR or vendor to proceed to next step without revision on
the next document issue.
Status “B”: Approved with minor comments (Approved with notes), CONTRACTOR or vendor
may proceed to next step if all comments are incorporated in the next document issue.
Status “C”: Not Approved, CONTRACTOR or vendor shall revise incorporating the agreed
comments and resubmit the revised document for approval with explanation.
The style of stamps is as follows:
c. Revision – 2 and so on = Re-Issued for the purposes of any change, revision, and/or
modification made on the preceding issued documents.
9. CHANGE OF SCOPE
Any approval by OWNER of any document with lead to change in PROJECT scope or design
as specified in CONTRACT shall need approval of at least OWNER's Project Director or any
other Director of OWNER. Without such approval from OWNER's PD or Director, Contractor
can implement such change only at its own cost and risk, and cannot claim additional cost
and extension of time.
REVIEW AND APPROVAL
PROCEDURE
Doc no : BAP-00-80-PE-0203-R
BANGGAI AMMONIA Project No : 15-1802
PLANT PROJECT Rev. No.: 2 Page 11 / 12
BY CONTRACTOR
DOCUMENT REVISED &
REISSUED
BY CONTRACTOR REVIEWED
BY OWNER
Need to be revised
OWNER COMMENT/REPLY
BY CONTRACTOR
DOCUMENT REVISED &
BY CONTRACTOR
REVIEWED
BY OWNER
Approved with
MEETING AND DISCUSSION DOCUMENT REVISED
OWNER Comments minor comment
CONTRACTOR & OWNER COMMENT/ REPLY
BY CONTRACTOR
OWNER
Approved
APPROVED DOCUMENT /
Yes No
STAMPED “FOR
Revision Required
CONSTRUCTION”
BY CONTRACTOR
APPENDIX 2 - Summary
Explanation:
For approval document (IFA for non P&ID, AFP for P&ID), after OWNER give approval with code A
to the document, CONTRACTOR will submit it again with revision status as shown on the table above.
For non P&ID, if document is needed for construction, CONTRACTOR will stamp on the document
with “FOR CONSTRUCTION” stamp. But if it is not, revision status directly change into Record or As
Final. Documents with “FOR CONSTRUCTION” stamp, will be distributed to site and uploaded to
EDOCS.