New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
New Assiut B
Barrage and Hydropower Plant 1900 02-May-12 A 02-Aug-18 A 02-Aug-18 A, New Assiut B

GENERAL 1900 02-May-12 02-Aug-18 A 02-Aug-18 A, GENERAL


A
MILESTONES 1900 02-May-12 02-Aug-18 A 02-Aug-18 A, MILESTONE
A
General 2203 02-May-12 14-May-18 A 14-May-18 A, General
230 Contract Commencement Lot 1 - Civil Works 0 A
02-May-12 AC.Lot 1 Contract Commencement Lot 1 - Civil Works, 02-May-12 A
A
231 Completion of Works 0 14-May-18 A AC.Lot 1 Completion of Works,
MILESTONE LOT 1
MILESTONES 1663 01-Oct-12 A 28-Mar-18 A 28-Mar-18 A, MILESTONES LOT 1
234 MS 1-01: Subm. of Loading-/ Foundation-/ Arrangemen 0 01-Oct-12 A AC.Lot 1 MS 1-01: Subm. of Loading-/ Foundation-/ Arrangement. / Layout Drawings, 01-Oct-12 A
235 MS 1-02: Starting of NL Concrete Works (Revised) 0 01-Oct-13 A AC.Lot 1 MS 1-02: Starting of NL Concrete Works (Revised), 01-Oct-13 A
233 MS 1-00: Completing of Housing Compound 0 01-Jan-14 A AC.Lot 1 MS 1-00: Completing of Housing Compound,
236 MS 1-03: PH-Unit 1, Step 1 Concrete Works complete 0 03-Dec-14 A AC.Lot 1 MS 1-03: PH-Unit 1, Step 1 Concrete Works complete,
238 MS 1-05: PH-Unit 1, Step 2 Concrete Works complete 0 03-Jul-15 A AC.Lot 1 MS 1-05: PH-Unit 1, Step 2 Concrete Works complete,
237 MS 1-04: SLW- Abutment & Standard Pier Axis 06 Firs 0 16-Jul-15 A AC.Lot 1 MS 1-04: SLW- Abutment & Standard Pier Axis 06 First Stage Concrete Works complete (Revised New Sequence),
240 MS 1-07: Main Gantry Crane Traffic Way passable 0 21-Feb-16 AC.Lot 1 MS 1-07: Main Gantry Crane Traffic Way passable, 21-Feb-16 A
A
239 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete 0 25-May-16 A AC.Lot 1 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete,
242 MS 1-09: All structures ready for impounding 0 13-Jun-16 A AC.Lot 1 MS 1-09: All structures ready for impounding, 13-Jun-16 A
241 MS 1-08: PH Units 1 & 2, u/s Trans. Zone 2nd Stage C 0 08-Aug-16 A AC.Lot 1 MS 1-08: PH Units 1 & 2, u/s Trans. Zone 2nd Stage Concrete complete (El 45.15),
244 MS 1-11: PH Units 3 & 4, u/s Trans. Zone 2nd Stage C 0 01-Sep-16 A AC.Lot 1 MS 1-11: PH Units 3 & 4, u/s Trans. Zone 2nd Stage Concrete complete,
245 MS 1-12: Switchyard Foundation Works complete 0 12-Jan-17 A AC.Lot 1 MS 1-12: Switchyard Foundation Works complete,
243 MS 1-10 (1): Navigation Locks operational (revised ac 0 23-Nov-17 A AC.Lot 1 MS 1-10 (1): Navigation Locks operational (revised acc. T
A2570 TOC for the whole of works 0 28-Mar-18 A AC.Lot 1 TOC for the whole of works,
MILESTONE LOT 2
MILESTONES 1662 01-Oct-12 A 26-Mar-18 A 26-Mar-18 A, MILESTONES LOT 2
247 MS 2-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Dr 0 01-Oct-12 A AC.Lot 2 MS 2-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Draw.
248 MS 2-02: Ready for Impounding 0 13-Jun-16 A AC.Lot 2 MS 2-02: Ready for Impounding
250 MS 2-03 : Navigation Locks operational (requested by 0 23-Nov-17 A AC.Lot 2 MS 2-03 : Navigation Locks operational (requested by RG
A2580 TOC for the whole of works 0 26-Mar-18 A AC.Lot 2 TOC for the whole of works
MILESTONE LOT 3
MILESTONES 1772 01-Oct-12 A 02-Aug-18 A 02-Aug-18 A, MILESTONE
252 MS 3-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Dr 0 01-Oct-12 A AC.Lot 3 MS 3-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Draw.
253 MS 3-02: Unit 1&2 Draft Tube Erec. ready for Step 2 C 0 30-Jan-15 A AC.Lot 3 MS 3-02: Unit 1&2 Draft Tube Erec. ready for Step 2 Concr. Works
254 MS 3-03: Unit 3&4 Draft Tube Erec. ready for Step 2 C 0 01-Apr-15 A AC.Lot 3 MS 3-03: Unit 3&4 Draft Tube Erec. ready for Step 2 Concr. Works
255 MS 3-04: Unit 1&2 Stayring Inst. ready for 2nd Stage C 0 30-Jan-16 A AC.Lot 3 MS 3-04: Unit 1&2 Stayring Inst. ready for 2nd Stage Concrete
256 MS 3-05: Unit 3&4 Stayring Inst. ready for 2nd Stage C 0 01-May-16 AC.Lot 3 MS 3-05: Unit 3&4 Stayring Inst. ready for 2nd Stage Concrete
A
257 MS 3-06: Ready for Impounding 0 31-May-16 AC.Lot 3 MS 3-06: Ready for Impounding
A
A2600 TOC for the whole of works 0 02-Aug-18 A AC.Lot 3 TOC for the whole of works
MS 3-07: Operational Acceptance Certificate 80 24-Mar-18 12-Jun-18 A 12-Jun-18 A, MS 3-07: Operation
260 MS 3-07.2: Turbine & Generator and common equipme 0 A
24-Mar-18 AC.Lot 3 MS 3-07.2: Turbine & Generator and comm
A
261 MS 3-07.3: Turbine & Generator and common equipme 0 02-Apr-18 A AC.Lot 3 MS 3-07.3: Turbine & Generator and comm
262 MS 3-07.4: Turbine & Generator and common equipme 0 18-Apr-18 A AC.Lot 3 MS 3-07.4: Turbine & Generator and com
259 MS 3-07.1: Turbine & Generator and common equipme 0 12-Jun-18 A AC.Lot 3 MS 3-07.1: Turbine & Generator a
MILESTONE LOT 4
MILESTONES 1773 01-Oct-12 A 02-Aug-18 A 02-Aug-18 A, MILESTONE
264 MS 4-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Dr 0 01-Oct-12 A AC.Lot 4 MS 4-01: Subm. of Loading-/ Found.-/ Arr.-/ Layout Draw.
265 MS 4-02: Ready for Impounding 0 31-May-16 AC.Lot 4 MS 4-02: Ready for Impounding
A
268 MS 4-04: Ready for Testing/ Commissioning and Trial 0 19-Nov-17 AC.Lot 4 MS 4-04: Ready for Testing/ Commissioning and Trial Oper
A
267 MS 4-03 : Navigation Locks operational (requested by 0 23-Nov-17 A AC.Lot 4 MS 4-03 : Navigation Locks operational (requested by RG
A2590 TOC for the whole of works 0 02-Aug-18 A AC.Lot 4 TOC for the whole of works
TAREGT DATES
DAT 1639 01-Oct-12 A 28-Feb-18 A 28-Feb-18 A, TAREGT DATES
TARGET DA
DATES LOT 1 1403 15-Jul-13 A 28-Feb-18 A 28-Feb-18 A, TARGET DATES LOT 1
DIAPHRAGM WALLS & CUT-OFF WALLS
DIAPHRA 0 15-Jul-13 A 15-Jul-13 A 15-Jul-13 A, DIAPHRAGM WALLS & CUT-OFF WALLS
5 TD 101:Start to Trenching for Permanent COW 0 15-Jul-13 A AC.Lot 1 TD 101:Start to Trenching for Permanent COW, 15-Jul-13 A
NAVIGAT
NAVIGATION LOCK 1019 01-Jun-14 A 09-Oct-17 A 09-Oct-17 A, NAVIGATION LOCK
7 TD 102:u/s Head ready for fixed Parts installation 0 01-Jun-14 A AC.Lot 1 TD 102:u/s Head ready for fixed Parts installation, 01-Jun-14 A
8 TD 104: d/s Head ready for fixed Parts installation 0 17-Jul-14 A AC.Lot 1 TD 104: d/s Head ready for fixed Parts installation, 17-Jul-14 A
10 TD 109: Approach Area su/s completed 0 27-Apr-17 A AC.Lot 1 TD 109: Approach Area su/s completed,
11 TD 110: Removal of Old Barrage Parts complete (rev 0 09-Oct-17 A AC.Lot 1 TD 110: Removal of Old Barrage Parts complete (revised acc.
SLUICEW
SLUICEWAY 792 14-Apr-14 A 03-Dec-16 A 03-Dec-16 A, SLUICEWAY
ABUTMENT PIER, AXIS 1
ABUT 0 16-Apr-15 A 16-Apr-15 A 16-Apr-15 A, ABUTMENT PIER, AXIS 1
46 TD 213: Main Gantry Crane Extension Beams Comple 0 16-Apr-15 A AC.Lot 1 TD 213: Main Gantry Crane Extension Beams Complete,
SLUIC
SLUICEWAY, AXES 1-6 558 14-Apr-14 A 21-Feb-16 A 21-Feb-16 A, SLUICEWAY, AXES 1-6
65 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erectio 0 14-Apr-14 A AC.Lot 1 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erection, 14-Apr-14 A
60 TD 201:Start SLW-Axes 01-06 Concrete Works 0 03-Aug-14 AC.Lot 1 TD 201:Start SLW-Axes 01-06 Concrete Works, 03-Aug-14 A
A
61 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erectio 0 18-Dec-14 AC.Lot 1 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erection, 18-Dec-14 A
A
64 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erectio 0 30-Dec-14 AC.Lot 1 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erection, 30-Dec-14 A
A
62 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erectio 0 07-Feb-15 AC.Lot 1 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erection, 07-Feb-15 A
A
66 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erectio 0 24-Mar-15 AC.Lot 1 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erection, 24-Mar-15 A
A
63 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erectio 0 21-Feb-16 AC.Lot 1 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erection, 21-Feb-16 A
A
ABUT
ABUTMENT PIER, AXIS 16 0 21-Feb-16 21-Feb-16 A 21-Feb-16 A, ABUTMENT PIER, AXIS 16
44 TD 270: Auxiliary Building concrete Works complete 0 21-Feb-16 A AC.Lot 1 TD 270: Auxiliary Building concrete Works complete,
SLUIC
SLUICEWAY, AXES 13-16 225 17-Sep-14 16-Jun-15 A 16-Jun-15 A, SLUICEWAY, AXES 13-16
48 TD 202:Start SLW-Axes 13-16 Concrete Works 0 17-Sep-14 AC.Lot 1 TD 202:Start SLW-Axes 13-16 Concrete Works, 17-Sep-14 A
A
49 TD 204: Pier 9, Axis 15, Access Lot 2, Trunnion Erecti 0 15-Mar-15 AC.Lot 1 TD 204: Pier 9, Axis 15, Access Lot 2, Trunnion Erection, 15-Mar-15 A
A
52 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 1 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erection, 15-Mar-15 A
A
50 TD 206: Pier 8, Axis 14, Access Lot 2, Trunnion Erecti 0 17-May-15 AC.Lot 1 TD 206: Pier 8, Axis 14, Access Lot 2, Trunnion Erection, 17-May-15 A
A
51 TD 209: Pier 7, Axis 13, Access Lot 2, Trunnion Erecti 0 16-Jun-15 A AC.Lot 1 TD 209: Pier 7, Axis 13, Access Lot 2, Trunnion Erection, 16-Jun-15 A
BAY 1,
1 AXES 1-2 199 29-Mar-15 28-Nov-15 A 28-Nov-15 A, BAY 1, AXES 1-2
A
Milestone Lot 1 Lot 2 Page 1 of 19
Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
20 TD 217: Bay 1, Axes 1-2, Access Lot 2, fixed Parts Ins 0 29-Mar-15 AC.Lot 1 TD 217: Bay 1, Axes 1-2, Access Lot 2, fixed Parts Installation, 29-Mar-15 A
A
18 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (r 0 03-Sep-15 AC.Lot 1 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (revised Sequence), 03-Sep-15 A
A
19 TD 233: Bay 1, 2nd Stage Concrete Works complete 0 28-Nov-15 AC.Lot 1 TD 233: Bay 1, 2nd Stage Concrete Works complete, 28-Nov-15 A
A
BAY 2,
2 AXES 2-3 126 03-May-15 03-Oct-15 A 03-Oct-15 A, BAY 2, AXES 2-3
14 TD 221: Bay 2, Axes 2-3, Access Lot 2, fixed Parts Ins 0 03-May-15 AC.Lot 1 TD 221: Bay 2, Axes 2-3, Access Lot 2, fixed Parts Installation, 03-May-15 A
A
15 TD 242: Bay 2, 2nd Stage Concrete Works complete ( 0 13-May-15 AC.Lot 1 TD 242: Bay 2, 2nd Stage Concrete Works complete (revised Sequence), 13-May-15 A
A
16 TD 251: Bay 2, Start of SLW Gantry Crane u/s Beam ( 0 03-Oct-15 A AC.Lot 1 TD 251: Bay 2, Start of SLW Gantry Crane u/s Beam (revised Sequence), 03-Oct-15 A
BAY 3,
3 AXES 3-4 158 02-Nov-15 10-May-16 A 10-May-16 A, BAY 3, AXES 3-4
23 TD 257: Bay 3, Start of SLW Gantry Crane u/s Beam 0 A
02-Nov-15 AC.Lot 1 TD 257: Bay 3, Start of SLW Gantry Crane u/s Beam, 02-Nov-15 A
A
24 TD 250: Bay 3,2nd Stage Concrete Works complete 0 18-Apr-16 A AC.Lot 1 TD 250: Bay 3,2nd Stage Concrete Works complete,
22 TD 226: Bay 3, Axes 3-4, Access Lot 2, fixed Parts Ins 0 10-May-16 AC.Lot 1 TD 226: Bay 3, Axes 3-4, Access Lot 2, fixed Parts Installation, 10-May-16 A
A
BAY 4,
4 AXES 4-5 179 25-Apr-16 A 03-Dec-16 A 03-Dec-16 A, BAY 4, AXES 4-5
57 TD 256: Bay4, 2nd Stage Concrete Works complete 0 25-Apr-16 A AC.Lot 1 TD 256: Bay4, 2nd Stage Concrete Works complete,
55 TD 235: Bay 4, Axes 4-5, Access Lot 2, fixed Parts Ins 0 06-Jun-16 A AC.Lot 1 TD 235: Bay 4, Axes 4-5, Access Lot 2, fixed Parts Installation, 06-Jun-16 A
56 TD 262: Bay 4, Start of SLW Gantry Crane u/s Beam ( 0 03-Dec-16 AC.Lot 1 TD 262: Bay 4, Start of SLW Gantry Crane u/s Beam (revised Sequence), 03-Dec-16 A
A
BAY 5,
5 AXES 5-6 468 08-May-15 28-Nov-16 A 28-Nov-16 A, BAY 5, AXES 5-6
33 TD 261: Bay 5 , 2nd Stage Concrete Works complete 0 08-May-15 A AC.Lot 1 TD 261: Bay 5 , 2nd Stage Concrete Works complete,
30 TD 245: Bay 5, Axes 5-6, Access Lot 2, fixed Parts Ins 0 02-Sep-15 AC.Lot 1 TD 245: Bay 5, Axes 5-6, Access Lot 2, fixed Parts Installation, 02-Sep-15 A
A
31 TD 266: Bay 5, Start of SLW Gantry Crane u/s Beam ( 0 03-Jan-16 A AC.Lot 1 TD 266: Bay 5, Start of SLW Gantry Crane u/s Beam (revised Sequence), 03-Jan-16 A
32 TD 269: Bays 1-5, Gantry Crane Beams ready for Rail 0 28-Nov-16 AC.Lot 1 TD 269: Bays 1-5, Gantry Crane Beams ready for Rail Installation (revised Sequence), 28-Nov-16 A
A
BAY 6,
6 AXES 13-14 388 21-May-15 02-Sep-16 A 02-Sep-16 A, BAY 6, AXES 13-14
40 TD 237:Bay6, 2nd Stage Concrete Works complete 0 21-May-15 A AC.Lot 1 TD 237:Bay6, 2nd Stage Concrete Works complete,
39 TD 248 : Bay6, Start of SLW Gantry Crane u/s Beam 0 17-Oct-15 A AC.Lot 1 TD 248 : Bay6, Start of SLW Gantry Crane u/s Beam, 17-Oct-15 A
42 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 21-Feb-16 AC.Lot 1 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation, 21-Feb-16 A
A
41 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts 0 02-Sep-16 AC.Lot 1 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts Installation, 02-Sep-16 A
A
BAY 7,
7 AXES 14-15 104 12-May-15 13-Sep-15 A 13-Sep-15 A, BAY 7, AXES 14-15
26 TD 228: Bay7,2nd Stage Concrete Works complete 0 A 12-May-15 A AC.Lot 1 TD 228: Bay7,2nd Stage Concrete Works complete,
28 TD 215: Bay 7, Axes 14-15, Access Lot 2, fixed Parts 0 02-Aug-15 AC.Lot 1 TD 215: Bay 7, Axes 14-15, Access Lot 2, fixed Parts Installation, 02-Aug-15 A
A
27 TD 239:Bay7,Start of SLW Gantry Cran/S Beam 0 13-Sep-15 AC.Lot 1 TD 239:Bay7,Start of SLW Gantry Cran/S Beam, 13-Sep-15 A
A
BAY 8,
8 AXES 15-16 139 11-May-15 28-Oct-15 A 28-Oct-15 A, BAY 8, AXES 15-16
36 TD 222: Bay 8, 2nd Stage Concrete Works complete 0 A 11-May-15 A AC.Lot 1 TD 222: Bay 8, 2nd Stage Concrete Works complete,
35 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts 0 01-Jun-15 A AC.Lot 1 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts Installation, 01-Jun-15 A
37 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam 0 28-Oct-15 A AC.Lot 1 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam, 28-Oct-15 A
POWERH
POWERHOUSE 631 23-Jul-14 A 28-Aug-16 A 28-Aug-16 A, POWERHOUSE
Unit-1 576 23-Jul-14 A 21-Jun-16 A 21-Jun-16 A, Unit-1
69 TD 301: Start U1 First Stage Concrete Works 0 23-Jul-14 A AC.Lot 1 TD 301: Start U1 First Stage Concrete Works, 23-Jul-14 A
70 TD 315: U1, Step 2a (Inlet Part u/s Axis B) Concrete W 0 12-Sep-15 A AC.Lot 1 TD 315: U1, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
72 TD 329: Start U1 u/s Transition Zone Concrete Works 0 02-Feb-16 AC.Lot 1 TD 329: Start U1 u/s Transition Zone Concrete Works up to EL. 42.10, 02-Feb-16 A
A
A11 TD 324: U1, Step 3 (Draft Tube d/s Axis C) Concrete 0 05-Mar-16 A AC.Lot 1 TD 324: U1, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
73 TD 346: U1 u/s Transition Zone Concrete Works up to 0 21-Jun-16 A AC.Lot 1 TD 346: U1 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
Unit-2 596 04-Aug-14 26-Jul-16 A 26-Jul-16 A, Unit-2
A11 TD 302: Start U2 First Stage Concrete Works 0 04-Aug-14 AC.Lot 1 TD 302: Start U2 First Stage Concrete Works, 04-Aug-14 A
A
A11 TD 306: U2, Step 1 (Draft Tube Steel Liner Foundation 0 18-Dec-14 AC.Lot 1 TD 306: U2, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed, 18-Dec-14 A
A
A11 TD 313: U2, Step 2 (Central Part Axes B-C) Concrete 0 19-Aug-15 A AC.Lot 1 TD 313: U2, Step 2 (Central Part Axes B-C) Concrete Works completed,
A11 TD 316: U2, Step 2a (Inlet Part u/s Axis B) Concrete W 0 11-Oct-15 A AC.Lot 1 TD 316: U2, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
A12 TD 344: Start U2 u/s Transition Zone Concrete Works 0 01-Feb-16 AC.Lot 1 TD 344: Start U2 u/s Transition Zone Concrete Works up to EL. 42.10, 01-Feb-16 A
A
A12 TD 352: U2 u/s Transition Zone Concrete Works up to 0 17-Jul-16 A AC.Lot 1 TD 352: U2 u/s Transition Zone Concrete Works up to EL. 42.10 completed ( revised ),
A11 TD 326: U2, Step 3 (Draft Tube d/s Axis C) Concrete 0 26-Jul-16 A AC.Lot 1 TD 326: U2, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
Unit-3 598 25-Aug-14 17-Aug-16 A 17-Aug-16 A, Unit-3
A12 TD 303: Start U3 First Stage Concrete Works 0 25-Aug-14 AC.Lot 1 TD 303: Start U3 First Stage Concrete Works, 25-Aug-14 A
A
A12 TD 308: U3, Step 1 (Draft Tube Steel Liner Foundation 0 29-Jan-15 A AC.Lot 1 TD 308: U3, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed,
A12 TD 331: U3, Step 2a (Inlet Part u/s Axis B) Concrete W 0 13-Dec-15 A AC.Lot 1 TD 331: U3, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
A12 TD 317: U3, Step 2 (Central Part Axes B-C) Concrete 0 10-Jan-16 A AC.Lot 1 TD 317: U3, Step 2 (Central Part Axes B-C) Concrete Works completed,
A12 TD 349: Start U3 u/s Transition Zone Concrete Works 0 12-Apr-16 A AC.Lot 1 TD 349: Start U3 u/s Transition Zone Concrete Works up to EL. 42.10, 12-Apr-16 A
A12 TD 341: U3, Step 3 (Draft Tube d/s Axis C) Concrete 0 25-May-16 A AC.Lot 1 TD 341: U3, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
A12 TD 355: U3 u/s Transition Zone Concrete Works up to 0 17-Aug-16 A AC.Lot 1 TD 355: U3 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
Unit-4 599 02-Sep-14 28-Aug-16 A 28-Aug-16 A, Unit-4
A12 TD 304: Start U4 First Stage Concrete Works 0 02-Sep-14 AC.Lot 1 TD 304: Start U4 First Stage Concrete Works, 02-Sep-14 A
A
A13 TD 310: U4, Step 1 (Draft Tube Steel Liner Foundation 0 13-Sep-15 A AC.Lot 1 TD 310: U4, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed,
A13 TD 332: U4, Step 2a (Inlet Part u/s Axis B) Concrete W 0 31-Jan-16 A AC.Lot 1 TD 332: U4, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
A13 TD 320: U4, Step 2 (Central Part Axes B-C) Concrete 0 11-Feb-16 A AC.Lot 1 TD 320: U4, Step 2 (Central Part Axes B-C) Concrete Works completed,
A13 TD 354: Start U4 u/s Transition Zone Concrete Works 0 01-May-16 AC.Lot 1 TD 354: Start U4 u/s Transition Zone Concrete Works up to EL. 42.10, 01-May-16 A
A
A13 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete 0 25-May-16 A AC.Lot 1 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete,
A13 TD 359: U4 u/s Transition Zone Concrete Works up to 0 28-Aug-16 A AC.Lot 1 TD 359: U4 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
GANT
GANTRY CRANES, TRASH R.C.& JIP CRANE 0 24-Jun-15 A 24-Jun-15 A 24-Jun-15 A, GANTRY CRANES, TRASH R.C.& JIP CRANE
98 TD 312: Crane Runway Axes 6-8 ready for Rail Installa 0 24-Jun-15 A AC.Lot 1 TD 312: Crane Runway Axes 6-8 ready for Rail Installation, 24-Jun-15 A
PUBLIC B
BRIDGE AND PUBLIC ROAD 628 13-Feb-16 28-Feb-18 A 28-Feb-18 A, PUBLIC BRIDGE AND PUBLIC R
59 TD 264: Public road Bridge Axes 01-06 complete (revi 0 A 13-Feb-16 A AC.Lot 1 TD 264: Public road Bridge Axes 01-06 complete (revised Sequence),
53 TD 271: Public road Bridge Axes13-16 complete (revis 0 02-Apr-16 A AC.Lot 1 TD 271: Public road Bridge Axes13-16 complete (revised Sequence),
9 TD 107 : Public road Bridge from Right Bridge Abutme 0 17-Sep-16 A AC.Lot 1 TD 107 : Public road Bridge from Right Bridge Abutment to Axis 16 complete,
A1390 Connection between Temp. Road and Existing East R 0 21-Jul-17 A AC.Lot 1 Connection between Temp. Road and Existing East Road to be completed
A1400 Connection between Permanent Road and Existing ro 0 28-Feb-18 AC.Lot 1 Connection between Permanent Road and Ex
A
TARGET DA
DATES LOT 2 1210 01-Oct-12 A 15-Oct-16 A 15-Oct-16 A, TARGET DATES LOT 2
Design a
and Fabrication 0 01-Oct-12 A 01-Oct-12 A 01-Oct-12 A, Design and Fabrication

Milestone Lot 1 Lot 2 Page 2 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
137 TD 001: Lot 2, 1st stage concrete embedded parts av 0 01-Oct-12 A AC.Lot 2 TD 001: Lot 2, 1st stage concrete embedded parts available at Site
SLUICEW
SLUICEWAY 318 15-Dec-14 03-Jan-16 A 03-Jan-16 A, SLUICEWAY
General
Gener 77 15-Mar-15 16-Jun-15 A 16-Jun-15 A, General
A14 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erec 0 15-Mar-15A AC.Lot 2 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erection
A
A14 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 2 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erection
A
A14 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erec 0 17-May-15 AC.Lot 2 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erection
A
A14 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erec 0 16-Jun-15 A AC.Lot 2 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erection
SLUIC
SLUICEWAY, AXES 1-6 100 15-Dec-14 15-Apr-15 A 15-Apr-15 A, SLUICEWAY, AXES 1-6
A14 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erectio 0 15-Dec-14 AC.Lot 2 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erection (revised Sequence)
A
A14 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erectio 0 15-Dec-14 AC.Lot 2 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erection (revised Sequence)
A
A14 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erectio 0 14-Jan-15 A AC.Lot 2 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erection (revised Sequence)
A14 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erectio 0 15-Feb-15 AC.Lot 2 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erection (revised Sequence)
A
A14 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erectio 0 15-Mar-15 AC.Lot 2 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erection (revised Sequence)
A
A15 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erectio 0 15-Apr-15 A AC.Lot 2 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erection (revised Sequence)
SLUIC
SLUICEWAY, AXES 13-16 77 15-Mar-15 16-Jun-15 A 16-Jun-15 A, SLUICEWAY, AXES 13-16
A18 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erec 0 15-Mar-15A AC.Lot 2 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erection
A
A18 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 2 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erection
A
A18 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erec 0 17-May-15 AC.Lot 2 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erection
A
A19 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erec 0 16-Jun-15 A AC.Lot 2 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erection
Bay 1, AXES 1-2 154 01-Mar-15 02-Sep-15 A 02-Sep-15 A, Bay 1, AXES 1-2
A15 TD 217: Bay 1, Access Lot 2, fixed Parts Installation (r 0 01-Mar-15 AC.Lot 2 TD 217: Bay 1, Access Lot 2, fixed Parts Installation (revised Sequence)
A
A15 TD 229: Bay 1, Axes 1-2, fixed Parts Installation Comp 0 16-Apr-15 A AC.Lot 2 TD 229: Bay 1, Axes 1-2, fixed Parts Installation Complete (revised Sequence)
A15 TD 234: Bay 1, Start of Radial Gate Erection (revised S 0 16-May-15 AC.Lot 2 TD 234: Bay 1, Start of Radial Gate Erection (revised Sequence)
A
A15 TD 241: Bay 1, Radial Gate Erection Complete (revise 0 16-Jun-15 A AC.Lot 2 TD 241: Bay 1, Radial Gate Erection Complete (revised Sequence)
A15 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (r 0 02-Sep-15 AC.Lot 2 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (revised Sequence)
A
Bay 2, AXES 2-3 91 30-Mar-15 19-Jul-15 A 19-Jul-15 A, Bay 2, AXES 2-3
A15 TD 221: Bay 2, Access Lot 2, fixed Parts Installation (r 0 30-Mar-15A AC.Lot 2 TD 221: Bay 2, Access Lot 2, fixed Parts Installation (revised Sequence)
A
A15 TD 238: Bay 2, Axes 2-3, fixed Parts Installation Comp 0 16-May-15 AC.Lot 2 TD 238: Bay 2, Axes 2-3, fixed Parts Installation Complete (revised Sequence)
A
A15 TD 244: Bay 2, Start of Radial Gate Erection (revised S 0 16-Jun-15 A AC.Lot 2 TD 244: Bay 2, Start of Radial Gate Erection (revised Sequence)
A15 TD 249: Bay 2, Radial Gate Erection Complete (revise 0 19-Jul-15 A AC.Lot 2 TD 249: Bay 2, Radial Gate Erection Complete (revised Sequence)
Bay 3, AXES 3-4 89 02-May-15 16-Aug-15 A 16-Aug-15 A, Bay 3, AXES 3-4
A16 TD 226: Bay 3, Access Lot 2, fixed Parts Installation 0 02-May-15 AC.Lot 2 TD 226: Bay 3, Access Lot 2, fixed Parts Installation
A
A16 TD 247: Bay 3, Axes 3-4, fixed Parts Installation Comp 0 16-Jun-15 A AC.Lot 2 TD 247: Bay 3, Axes 3-4, fixed Parts Installation Complete
A16 TD 252: Bay 3, Start of Radial Gate Erection 0 16-Jul-15 A AC.Lot 2 TD 252: Bay 3, Start of Radial Gate Erection
A16 TD 255: Bay 3, Radial Gate Erection Complete 0 16-Aug-15 AC.Lot 2 TD 255: Bay 3, Radial Gate Erection Complete
A
Bay 4, AXES 4-5 91 31-May-15 16-Sep-15 A 16-Sep-15 A, Bay 4, AXES 4-5
A16 TD 235: Bay 4, Access Lot 2, fixed Parts Installation (r 0 31-May-15 AC.Lot 2 TD 235: Bay 4, Access Lot 2, fixed Parts Installation (revised Sequence)
A
A16 TD 254: Bay 4, Axes 4-5, fixed Parts Installation Comp 0 15-Jul-15 A AC.Lot 2 TD 254: Bay 4, Axes 4-5, fixed Parts Installation Complete (revised Sequence)
A16 TD 258: Bay 4, Start of Radial Gate Erection (revised S 0 16-Aug-15 AC.Lot 2 TD 258: Bay 4, Start of Radial Gate Erection (revised Sequence)
A
A16 TD 260: Bay 4, Radial Gate Erection Complete (revise 0 16-Sep-15 AC.Lot 2 TD 260: Bay 4, Radial Gate Erection Complete (revised Sequence)
A
Bay 5, AXES 5-6 90 29-Jun-15 A 20-Oct-15 A 20-Oct-15 A, Bay 5, AXES 5-6
A16 TD 245: Bay 5, Access Lot 2, fixed Parts Installation (r 0 29-Jun-15 A AC.Lot 2 TD 245: Bay 5, Access Lot 2, fixed Parts Installation (revised Sequence)
A16 TD 259: Bay 5, Axes 5-6, fixed Parts Installation Comp 0 15-Aug-15 AC.Lot 2 TD 259: Bay 5, Axes 5-6, fixed Parts Installation Complete (revised Sequence)
A
A17 TD 263: Bay 5, Start of Radial Gate Erection (revised S 0 15-Sep-15 AC.Lot 2 TD 263: Bay 5, Start of Radial Gate Erection (revised Sequence)
A
A17 TD 265: Bay 5, Radial Gate Erection Complete (revise 0 20-Oct-15 A AC.Lot 2 TD 265: Bay 5, Radial Gate Erection Complete (revised Sequence)
bay 6, AXES 13-14 101 02-Sep-15 03-Jan-16 A 03-Jan-16 A, bay 6, AXES 13-14
A17 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts 0 02-Sep-15 AC.Lot 2 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts Installation
A
A17 TD 232: Bay 6, Axes 13-14, fixed Parts Installation Co 0 09-Oct-15 A AC.Lot 2 TD 232: Bay 6, Axes 13-14, fixed Parts Installation Complete
A17 TD 240: Bay 6, Start of Radial Gate Erection 0 20-Nov-15 A AC.Lot 2 TD 240: Bay 6, Start of Radial Gate Erection
A17 TD 246: Bay 6, Radial Gate Erection Complete 0 24-Dec-15 A AC.Lot 2 TD 246: Bay 6, Radial Gate Erection Complete
A17 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 03-Jan-16 A AC.Lot 2 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation
Bay 7, AXES 14-15 103 24-Jul-15 A 26-Nov-15 A 26-Nov-15 A, Bay 7, AXES 14-15
A17 TD 215: Bay 7, Axes 15-16, Access Lot 2, fixed Parts 0 24-Jul-15 A AC.Lot 2 TD 215: Bay 7, Axes 15-16, Access Lot 2, fixed Parts Installation
A17 TD 231: Bay 7, Start of Radial Gate Erection 0 03-Sep-15 AC.Lot 2 TD 231: Bay 7, Start of Radial Gate Erection
A
A18 TD 239: Bay 7, Start of SLW Gantry Crane u/s Beam 0 13-Sep-15 AC.Lot 2 TD 239: Bay 7, Start of SLW Gantry Crane u/s Beam
A
A17 TD 225: Bay 7, Axes 14-15, fixed Parts Installation Co 0 17-Sep-15 A AC.Lot 2 TD 225: Bay 7, Axes 14-15, fixed Parts Installation Complete
A18 TD 236: Bay 7, Radial Gate Erection Complete 0 26-Nov-15 A AC.Lot 2 TD 236: Bay 7, Radial Gate Erection Complete
bay 8, AXES 15-16 94 01-Jun-15 A 21-Sep-15 A 21-Sep-15 A, bay 8, AXES 15-16
A18 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts 0 01-Jun-15 A AC.Lot 2 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts Installation
A18 TD 220: Bay 8, Axes 15-16, fixed Parts Installation Co 0 14-Jul-15 A AC.Lot 2 TD 220: Bay 8, Axes 15-16, fixed Parts Installation Complete
A18 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam 0 18-Jul-15 A AC.Lot 2 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam
A18 TD 223: Bay 8, Start of Radial Gate Erection 0 16-Aug-15 AC.Lot 2 TD 223: Bay 8, Start of Radial Gate Erection
A
A18 TD 227: Bay 8, Radial Gate Erection Complete 0 21-Sep-15 AC.Lot 2 TD 227: Bay 8, Radial Gate Erection Complete
A
GANT
GANTRY CRANES 191 17-May-15 03-Jan-16 A 03-Jan-16 A, GANTRY CRANES
A19 TD 207: Lot 2, Start of SLW-W Gantry Crane No. 01 E 0 17-May-15A AC.Lot 2 TD 207: Lot 2, Start of SLW-W Gantry Crane No. 01 Erection (on Abutment Pier Axis 01 & Extension Beams)
A
A19 TD 212: Lot 2, SLW-W Gantry Crane No. 01 Erection 0 30-Jul-15 A AC.Lot 2 TD 212: Lot 2, SLW-W Gantry Crane No. 01 Erection complete
A19 TD 269: Bays1-5, Gantry Crane Beams ready for Rail 0 01-Nov-15 AC.Lot 2 TD 269: Bays1-5, Gantry Crane Beams ready for Rail Installation
A
A19 TD 214: Start of SLW-E Gantry Crane No. 2 Erection 0 29-Nov-15 AC.Lot 2 TD 214: Start of SLW-E Gantry Crane No. 2 Erection
A
A19 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 03-Jan-16 A AC.Lot 2 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation
POWERH
POWERHOUSE 358 03-Aug-15 15-Oct-16 A 15-Oct-16 A, POWERHOUSE
Unit-1 27 03-Aug-15 03-Sep-15 A 03-Sep-15 A, Unit-1
199 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part 0 A
03-Aug-15 AC.Lot 2 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part Installation
A
198 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Ins 0 03-Sep-15 AC.Lot 2 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Installation
A
Unit-2 172 15-Mar-16 15-Oct-16 A 15-Oct-16 A, Unit-2
A

Milestone Lot 1 Lot 2 Page 3 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
207 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Ins 0 15-Mar-16 AC.Lot 2 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Installation
A
208 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part 0 15-Oct-16 A AC.Lot 2 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part Installation
Unit-3 46 31-Jan-16 A 24-Mar-16 A 24-Mar-16 A, Unit-3
202 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 2 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part Installation
201 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Ins 0 24-Mar-16 AC.Lot 2 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Installation
A
Unit-4 26 16-Jan-16 A 16-Feb-16 A 16-Feb-16 A, Unit-4
204 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Ins 0 16-Jan-16 A AC.Lot 2 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Installation
205 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part 0 16-Feb-16 AC.Lot 2 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part Installation
A
NAVIGAT
NAVIGATION LOCK 213 02-Jun-14 A 15-Feb-15 A 15-Feb-15 A, NAVIGATION LOCK
A1960 TD 103: Lot 2, Start of u/s Head fixed Part Installation 0 02-Jun-14 A AC.Lot 2 TD 103: Lot 2, Start of u/s Head fixed Part Installation
A1970 TD 105: Lot 2, Start of d/s Head fixed Part Installation 0 18-Jul-14 A AC.Lot 2 TD 105: Lot 2, Start of d/s Head fixed Part Installation
A1980 TD106: Start of NL Gantry Cranes Erection 0 15-Feb-15 AC.Lot 2 TD106: Start of NL Gantry Cranes Erection
A
TARGET DA
DATES LOT 3 1434 01-Oct-12 A 04-Jul-17 A 04-Jul-17 A, TARGET DATES LOT 3
Design a
and Fabrication 0 01-Oct-12 A 01-Oct-12 A 01-Oct-12 A, Design and Fabrication
101 TD 002: Lot 3, 1st stage concrete embedded parts av 0 01-Oct-12 A AC.Lot 3 TD 002: Lot 3, 1st stage concrete embedded parts available at Site
POWERH
POWERHOUSE 783 03-Dec-14 04-Jul-17 A 04-Jul-17 A, POWERHOUSE
Unit-1 636 03-Dec-14 13-Jan-17 A 13-Jan-17 A, Unit-1
A19 TD 305: Start DT Steel Liner U1 erection 0 A
03-Dec-14 AC.Lot 3 TD 305: Start DT Steel Liner U1 erection
A
A20 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Ins 0 02-Sep-15 AC.Lot 3 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Installation
A
104 TD 321: PH Main Gantry Crane operational 0 03-Oct-15 A AC.Lot 3 TD 321: PH Main Gantry Crane operational
A20 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part 0 03-Dec-15 AC.Lot 3 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part Installation
A
A20 TD 323: Stayring and Pier Nose U1 installation in pit ( r 0 15-Dec-15 AC.Lot 3 TD 323: Stayring and Pier Nose U1 installation in pit ( revised )
A
A20 TD 325: Stayring & Pier Nose U1 Installation in the pit 0 14-Jan-16 A AC.Lot 3 TD 325: Stayring & Pier Nose U1 Installation in the pit ready for concrete
108 TD 314: Start of PH Main Gantry Crane Erection (Inter 0 22-Jun-16 A AC.Lot 3 TD 314: Start of PH Main Gantry Crane Erection (Intermediate Pier/Unit1)
A20 TD 357: Start Turbine and Generator Erection U1 0 21-Jul-16 A AC.Lot 3 TD 357: Start Turbine and Generator Erection U1
A20 TD 347: Generator hatch cover installation 0 13-Jan-17 A AC.Lot 3 TD 347: Generator hatch cover installation
Unit-2 770 18-Dec-14 04-Jul-17 A 04-Jul-17 A, Unit-2
A20 TD 307: Start DT Steel Liner U2 erection 0 18-Dec-14A AC.Lot 3 TD 307: Start DT Steel Liner U2 erection
A
A21 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Ins 0 02-Sep-15 AC.Lot 3 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Installation
A
A20 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part 0 03-Dec-15 AC.Lot 3 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part Installation
A
A20 TD 335: Stayring and Pier Nose U2 installation in pit ( r 0 31-Dec-15 AC.Lot 3 TD 335: Stayring and Pier Nose U2 installation in pit ( revised )
A
A21 TD 358: Start Turbine and Generator Erection U2 0 08-Aug-16 AC.Lot 3 TD 358: Start Turbine and Generator Erection U2
A
A21 TD 353: Generator hatch cover installation 0 04-Jul-17 A AC.Lot 3 TD 353: Generator hatch cover installation
Unit-3 672 31-Jan-15 A 21-Apr-17 A 21-Apr-17 A, Unit-3
A21 TD 309: Start DT Steel Liner U3 erection 0 31-Jan-15 A AC.Lot 3 TD 309: Start DT Steel Liner U3 erection
A21 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Ins 0 02-Nov-15 AC.Lot 3 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Installation
A
A21 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 3 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part Installation
A21 TD 345: Stayring and Pier Nose U3 installation in pit ( r 0 10-Feb-16 AC.Lot 3 TD 345: Stayring and Pier Nose U3 installation in pit ( revised )
A
A21 TD 348: Stayring & Pier Nose U3 Installation in the pit 0 10-Mar-16 AC.Lot 3 TD 348: Stayring & Pier Nose U3 Installation in the pit ready for concrete
A
A21 TD 361: Start Turbine and Generator Erection U3 0 04-Sep-16 AC.Lot 3 TD 361: Start Turbine and Generator Erection U3
A
A21 TD 356: Generator hatch cover installation 0 21-Apr-17 A AC.Lot 3 TD 356: Generator hatch cover installation
Unit-4 608 10-Jan-15 A 17-Jan-17 A 17-Jan-17 A, Unit-4
A22 TD 311: Start DT Steel Liner U4 erection 0 10-Jan-15 A AC.Lot 3 TD 311: Start DT Steel Liner U4 erection
A22 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Ins 0 02-Nov-15 AC.Lot 3 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Installation
A
A22 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 3 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part Installation
A22 TD 351: Stayring and Pier Nose U4 installation in pit 0 27-Mar-16 AC.Lot 3 TD 351: Stayring and Pier Nose U4 installation in pit
A
A22 TD 362: Start Turbine and Generator Erection U4 0 26-Sep-16 AC.Lot 3 TD 362: Start Turbine and Generator Erection U4
A
A22 TD 360: Generator hatch cover installation 0 17-Jan-17 A AC.Lot 3 TD 360: Generator hatch cover installation
TARGET DA
DATES LOT 4 947 03-Sep-13 31-Oct-16 A 31-Oct-16 A, TARGET DATES LOT 4
Design a
and Fabrication 0 03-Sep-13 03-Sep-13 A 03-Sep-13 A, Design and Fabrication
215 TD 003: Lot 4, grounding system parts available at Site 0 03-Sep-13A AC.Lot 4 TD 003: Lot 4, grounding system parts available at Site
A
SLUICEW
SLUICEWAY 33 29-Jan-16 A 08-Mar-16 A 08-Mar-16 A, SLUICEWAY
A2390 TD 267: SLW, Axes 13-16, Access Lot 4, Cable Tray I 0 29-Jan-16 A AC.Lot 4 TD 267: SLW, Axes 13-16, Access Lot 4, Cable Tray Installation
A2400 TD 268 lot 4: SLW, Axes 1-6, Access Lot 4, Cable Tra 0 08-Mar-16 AC.Lot 4 TD 268 lot 4: SLW, Axes 1-6, Access Lot 4, Cable Tray Installation
A
POWERH
POWERHOUSE 0 03-Jan-16 A 03-Jan-16 A 03-Jan-16 A, POWERHOUSE
A2350 TD 337: U1 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 337: U1 ready for cable tray installation
A2360 TD 338: U2 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 338: U2 ready for cable tray installation
A2370 TD 339: U3 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 339: U3 ready for cable tray installation
A2380 TD 340: U4 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 340: U4 ready for cable tray installation
NAVIGAT
NAVIGATION LOCK 0 31-Oct-16 A 31-Oct-16 A 31-Oct-16 A, NAVIGATION LOCK
1193 TD 108: Lot 4, Start of Cable Tray Installation 0 31-Oct-16 A AC.Lot 4 TD 108: Lot 4, Start of Cable Tray Installation

CONSTRUCTION
CONSTRUC 1900 02-May-12 02-Aug-18 A 02-Aug-18 A, CONSTRUC
A
SITE INSTALLATION
INSTALL 1790 02-May-12 28-Mar-18 A 28-Mar-18 A, SITE INSTALLATION
A
SITE INSTA
INSTALLATION AREA Lot 1 1790 02-May-12 28-Mar-18 A 28-Mar-18 A, SITE INSTALLATION AREA L
280 Design - Procurement 65 02-May-12 16-Jul-12 A AC.Lot 1 Design - Procurement
A
281 Clearing, Grubbing & Site Stripping - Site Installation Ar 21 02-May-12 26-May-12 A AC.Lot 1 Clearing, Grubbing & Site Stripping - Site Installation Area
A
282 Contract Stockpile has been prevented to accessed to 0 22-May-12 AC.Lot 1 Contract Stockpile has been prevented to accessed to on 22/5/12, 22-May-12 A
A
283 100 cm Top Soil Removal - Site installation area 38 27-May-12 09-Jul-12 A AC.Lot 1 100 cm Top Soil Removal - Site installation area
A
284 Opening of quarries 100 04-Jun-12 A 01-Oct-12 A AC.Lot 1 Opening of quarries
285 Quay construction 88 01-Jul-12 A 15-Oct-12 A AC.Lot 1 Quay construction
288 Geotextile Installation and Sub-Base Crushed Stone w 68 09-Jul-12 A 30-Sep-12 A AC.Lot 1 Geotextile Installation and Sub-Base Crushed Stone where pertinent
286 Water supply and sewage treatment 68 10-Jul-12 A 30-Sep-12 A AC.Lot 1 Water supply and sewage treatment
287 Site communications 55 22-Jul-12 A 26-Sep-12 A AC.Lot 1 Site communications
291 Materials laboratory 32 24-Jul-12 A 02-Sep-12 A AC.Lot 1 Materials laboratory

Milestone Lot 1 Lot 2 Page 4 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
289 Installation of Fences 225 02-Aug-12 04-May-13 A AC.Lot 1 Installation of Fences
A
293 Offices for employer/ employers representatives 46 05-Aug-12 30-Sep-12 A AC.Lot 1 Offices for employer/ employers representatives
A
294 Offices for Contractor 46 05-Aug-12 30-Sep-12 A AC.Lot 1 Offices for Contractor
A
290 NAB-JV Camp. 55 14-Aug-12 21-Oct-12 A AC.Lot 1 NAB-JV Camp.
A
292 Site Installation zone temporary roads 45 22-Aug-12 15-Oct-12 A AC.Lot 1 Site Installation zone temporary roads
A
295 Steel Reinforcement Yard 60 14-Feb-13 27-Apr-13 A AC.Lot 1 Steel Reinforcement Yard
A
296 Concrete production facilities installation 99 02-Mar-13 30-Jun-13 A AC.Lot 1 Concrete production facilities installation
A
297 Complete Main Works for Site Installation Lot 1 0 31-Jul-13 A AC.Lot 1 Complete Main Works for Site Installation Lot 1, 31-Jul-13 A
298 Demobilization/ Restoration of site 114 15-Nov-17 28-Mar-18 A AC.Lot 1 Demobilization/ Restoration of site
A
Earth Works 1784 09-May-12 28-Mar-18 A 28-Mar-18 A, Earth Works
A
TEMPORAR WORKS
TEMPORARY 1355 30-Jul-12 A 31-Jan-17 A 31-Jan-17 A, TEMPORARY WORKS
TEMPORARY RING DAM CONSTRUCTION
TEMPOR 1179 30-Jul-12 A 30-Jun-16 A 30-Jun-16 A, TEMPORARY RING DAM CONSTRUCTION
STOCKPILE AREA ON RIGHT BANK
STOCK 186 30-Jul-12 A 12-Mar-13 A 12-Mar-13 A, STOCKPILE AREA ON RIGHT BANK
319 S&G and sand fill till base level guide wall 70 30-Jul-12 A 22-Oct-12 A AC.Lot 1 S&G and sand fill till base level guide wall
320 Guide wall incl. fill till top of wall 51 19-Sep-12 21-Nov-12 A AC.Lot 1 Guide wall incl. fill till top of wall
A
321 Slurry wall 70 06-Dec-12 27-Feb-13 A AC.Lot 1 Slurry wall
A
322 Preparation top layer 66 24-Dec-12 12-Mar-13 A AC.Lot 1 Preparation top layer
A
UPSTR
UPSTREAM 112 23-Oct-12 A 07-Mar-13 A 07-Mar-13 A, UPSTREAM
324 S&G fill till base level guide wall 60 23-Oct-12 A 03-Jan-13 A AC.Lot 1 S&G fill till base level guide wall
325 Guide wall incl. sand fill till top of wall 60 26-Nov-12 05-Feb-13 A AC.Lot 1 Guide wall incl. sand fill till top of wall
A
326 Slurry wall 77 02-Dec-12 03-Mar-13 A AC.Lot 1 Slurry wall
A
327 Preparation top layer 66 19-Dec-12 07-Mar-13 A AC.Lot 1 Preparation top layer
A
DOWN
DOWNSTREAM 93 18-Nov-12 07-Mar-13 A 07-Mar-13 A, DOWNSTREAM
329 S&G fill till base level guide wall 53 18-Nov-12A 19-Jan-13 A AC.Lot 1 S&G fill till base level guide wall
A
330 Guide wall incl. sand fill till top of wall 58 04-Dec-12 11-Feb-13 A AC.Lot 1 Guide wall incl. sand fill till top of wall
A
331 Slurry wall 65 16-Dec-12 03-Mar-13 A AC.Lot 1 Slurry wall
A
332 Preparation top layer 51 06-Jan-13 A 07-Mar-13 A AC.Lot 1 Preparation top layer
PUMP
PUMPING AND DEWATERING 1040 16-Jan-13 A 30-Jun-16 A 30-Jun-16 A, PUMPING AND DEWATERING
335 Deep Wells installation (inside pit) 160 16-Jan-13 A 28-Jul-13 A AC.Lot 1 Deep Wells installation (inside pit)
334 Surface dewatering unit installation + test 69 06-Feb-13 28-Apr-13 A AC.Lot 1 Surface dewatering unit installation + test
A
336 Pumping test 23 29-Apr-13 A 28-May-13 A AC.Lot 1 Pumping test
337 Pumping out and Dewatering of Pit 929 29-Apr-13 A 31-May-16 A AC.Lot 1 Pumping out and Dewatering of Pit
338 Impounding 25 01-Jun-16 A 30-Jun-16 A AC.Lot 1 Impounding
TEMPOR
TEMPORARY RING DAM REMOVAL 186 19-Jun-16 A 31-Jan-17 A 31-Jan-17 A, TEMPORARY RING DAM REMOVAL
340 Ring Dam removal 186 19-Jun-16 A 31-Jan-17 A AC.Lot 1 Ring Dam removal
GEOTECHN
GEOTECHNICAL INVESTIGATIONS 108 24-May-12 30-Sep-12 A 30-Sep-12 A, GEOTECHNICAL INVESTIGATIONS
General 108 24-May-12 30-Sep-12 A 30-Sep-12 A, General
272 Drilling Two Wells for Pumping & 12 Piezometers 30 24-May-12 27-Jun-12 A AC.Lot 1 Drilling Two Wells for Pumping & 12 Piezometers
A
273 Mobilization of Geotechnical Tests 30 05-Jun-12 A 09-Jul-12 A AC.Lot 1 Mobilization of Geotechnical Tests
274 Long Term Pumping Test from Two Wells 25 28-Jun-12 A 28-Jul-12 A AC.Lot 1 Long Term Pumping Test from Two Wells
275 Site Tests ( On Shore / Off Shore ) 60 10-Jul-12 A 20-Sep-12 A AC.Lot 1 Site Tests ( On Shore / Off Shore )
276 Laboratory Tests 56 16-Jul-12 A 22-Sep-12 A AC.Lot 1 Laboratory Tests
277 Geotechnical Reports 56 25-Jul-12 A 30-Sep-12 A AC.Lot 1 Geotechnical Reports
EXCAVATIO WORKS AND TEMPORARY RIVER PROTECTION
EXCAVATION 1313 09-May-12 20-Sep-16 A 20-Sep-16 A, EXCAVATION WORKS AND TEMPORARY RIVER PROTECTION
TOP SOIL REMOVAL 145 09-May-12A 31-Oct-12 A 31-Oct-12 A, TOP SOIL REMOVAL
343 Clearing, grubbing and stripping, Bani Murr Island-Firs 14 09-May-12A 24-May-12 A AC.Lot 1 Clearing, grubbing and stripping, Bani Murr Island-First Stage
A
344 Topsoil Removal to Stockpile, Bani Murr Island-First S 12 12-May-12 24-May-12 A AC.Lot 1 Topsoil Removal to Stockpile, Bani Murr Island-First Stage
A
345 Clearing, grubbing and stripping, Bani Murr Island-Sec 12 01-Sep-12 13-Sep-12 A AC.Lot 1 Clearing, grubbing and stripping, Bani Murr Island-Second Stage
A
346 Topsoil Removal to Stockpile, Bani Murr Island-Secon 38 15-Sep-12 31-Oct-12 A AC.Lot 1 Topsoil Removal to Stockpile, Bani Murr Island-Second Stage
A
EXCAVAT
EXCAVATION UNDERWATER 126 29-Sep-12 28-Feb-13 A 28-Feb-13 A, EXCAVATION UNDERWATER
348 Connection Channel - First Phase (to el. 43) 32 A
29-Sep-12 07-Nov-12 A AC.Lot 1 Connection Channel - First Phase (to el. 43)
A
350 Inside Construction Pit (to el. 39) 56 20-Oct-12 A 26-Dec-12 A AC.Lot 1 Inside Construction Pit (to el. 39)
349 Riverbed - u/s 83 22-Nov-12 28-Feb-13 A AC.Lot 1 Riverbed - u/s
A
351 Connection Channel - Second Phase (to el. 39) 26 05-Jan-13 A 05-Feb-13 A AC.Lot 1 Connection Channel - Second Phase (to el. 39)
BACKFIL
BACKFILLING 75 19-Jun-16 A 20-Sep-16 A 20-Sep-16 A, BACKFILLING
353 Closure of connection channel 75 19-Jun-16 A 20-Sep-16 A AC.Lot 1 Closure of connection channel
RIP RAP - RIVER PROTECTION 164 15-Jan-13 A 31-Jul-13 A 31-Jul-13 A, RIP RAP - RIVER PROTECTION
355 RBP in connection channel / u/s / central part 102 15-Jan-13 A 19-May-13 A AC.Lot 1 RBP in connection channel / u/s / central part
356 RBP d/s old barrage 82 22-Apr-13 A 31-Jul-13 A AC.Lot 1 RBP d/s old barrage
EXCAVAT
EXCAVATION IN THE DRY 642 11-May-13 25-Jun-15 A 25-Jun-15 A, EXCAVATION IN THE DRY
358 Construction Pit, Bulk Exc. Step 1 (to El. 40.00m-DW) 61 11-May-13 20-Jul-13 A AC.Lot 1 Construction Pit, Bulk Exc. Step 1 (to El. 40.00m-DW)
A
359 Construction Pit, Bulk Exc. Step 2 (to El. 42.00/38.00m 120 27-Jun-13 A 21-Nov-13 A AC.Lot 1 Construction Pit, Bulk Exc. Step 2 (to El. 42.00/38.00m-pit) + inside piers
360 Construction Pit, Bulk Exc. Step 3 (to El. 36.70m-NL) 70 27-Jun-13 A 18-Sep-13 A AC.Lot 1 Construction Pit, Bulk Exc. Step 3 (to El. 36.70m-NL)
363 Grounding System Primary Grid By Lot 4 (Earth works 250 28-Jul-13 A 28-May-14 A AC.Lot 1 Grounding System Primary Grid By Lot 4 (Earth works by Lot 1)
361 Construction Pit, Bulk Exc. Step 4 (to El. 21.40/33.00m 93 20-Jan-14 A 12-May-14 A AC.Lot 1 Construction Pit, Bulk Exc. Step 4 (to El. 21.40/33.00m-PH&SLW)
362 Construction Pit, Bulk Exc. ( EL42.00:38.00m) & below 190 11-Nov-14 25-Jun-15 A AC.Lot 1 Construction Pit, Bulk Exc. ( EL42.00:38.00m) & below 38.00/Final Rip Rap
A
DIAPHRAGM WALLS & CUT-OFF WALLS 1155 15-Jul-13 A 15-May-17 A 15-May-17 A, DIAPHRAGM WALLS & CUT-OFF WALLS
General 1155 15-Jul-13 A 15-May-17 A 15-May-17 A, General
366 TD 101: Start of Trenching for Permanent COW (Revi 0 15-Jul-13 A AC.Lot 1 TD 101: Start of Trenching for Permanent COW (Revised), 15-Jul-13 A
367 Cut-off Wall, Construction Phase 1 51 15-Jul-13 A 14-Sep-13 A AC.Lot 1 Cut-off Wall, Construction Phase 1
368 PH Diaphragm Wall t=0.8m, Axis 12 42 01-Oct-13 A 24-Nov-13 A AC.Lot 1 PH Diaphragm Wall t=0.8m, Axis 12
370 PH Diaphragm Wall t=0.8m, Axis 6 42 01-Oct-13 A 24-Nov-13 A AC.Lot 1 PH Diaphragm Wall t=0.8m, Axis 6
369 SLW Diaphragm Wall t=0.8m, Axis 16 20 25-Nov-13 17-Dec-13 A AC.Lot 1 SLW Diaphragm Wall t=0.8m, Axis 16
A
371 SLW Diaphragm Wall t=0.8m, Axis 1 21 09-Dec-13 01-Jan-14 A AC.Lot 1 SLW Diaphragm Wall t=0.8m, Axis 1
A

Milestone Lot 1 Lot 2 Page 5 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
372 Cut-off Wall, Construction Phase 2, Right Bank 24 01-Dec-16 30-Dec-16 A AC.Lot 1 Cut-off Wall, Construction Phase 2, Right Bank
A
373 Cut-off Wall, Construction Phase 3a, Left Bank (acc. t 3 28-Dec-16 01-Jan-17 A AC.Lot 1 Cut-off Wall, Construction Phase 3a, Left Bank (acc. to alternative 2)
A
374 Cut-off Wall, Construction Phase 3b, Left Bank (acc. t 115 01-Jan-17 A 15-May-17 A AC.Lot 1 Cut-off Wall, Construction Phase 3b, Left Bank (acc. to alternative 2)
CLOSURE DAM
D 951 15-Feb-15 28-Mar-18 A 28-Mar-18 A, CLOSURE DAM
Piezometers installation
Piezome 457 10-Oct-16 A 28-Mar-18 A 28-Mar-18 A, Piezometers installation
377 Piezometers installation 457 10-Oct-16 A 28-Mar-18 A AC.Lot 1 Piezometers installation
CLOSUR DAM INSIDE CONSTRUCTION PIT
CLOSURE 62 15-Feb-15 30-Apr-15 A 30-Apr-15 A, CLOSURE DAM INSIDE CONSTRUCTION PIT
379 Rock fill Dam Part Inside Construction Pit Axis 1 62 15-Feb-15A 30-Apr-15 A AC.Lot 1 Rock fill Dam Part Inside Construction Pit Axis 1
A
380 Class B Fill Dam Part Inside Construction Pit Axis 1 61 15-Feb-15 29-Apr-15 A AC.Lot 1 Class B Fill Dam Part Inside Construction Pit Axis 1
A
CLOSUR DAM OUTSIDE CONSTRUCTION PIT
CLOSURE 546 19-Jun-16 A 28-Mar-18 A 28-Mar-18 A, CLOSURE DAM OUTSIDE C
382 Class U/B Fill Dam Part Outside Construction Pit Upst 76 19-Jun-16 A 21-Sep-16 A AC.Lot 1 Class U/B Fill Dam Part Outside Construction Pit Upstream Dyke
384 Class U/B Fill Dam Part Outside Construction Pit Dow 206 27-Jul-16 A 31-Mar-17 A AC.Lot 1 Class U/B Fill Dam Part Outside Construction Pit Downstream Dyke (1st part) (acc. To
383 Rock fill Dam Part Outside Construction Pit 443 22-Aug-16 28-Jan-18 A AC.Lot 1 Rock fill Dam Part Outside Construction Pit
A
385 Class U/B Fill Dam Part Outside Construction Pit Dow 315 26-Mar-17 28-Mar-18 A AC.Lot 1 Class U/B Fill Dam Part Outside Construct
A
387 Class U/B Fill Dam Part Outside Construction Pit (2nd 267 24-Apr-17 A 01-Mar-18 A AC.Lot 1 Class U/B Fill Dam Part Outside Construction
386 Class U/B Fill Dam Part Outside Construction Pit (1st 80 01-Oct-17 A 02-Jan-18 A AC.Lot 1 Class U/B Fill Dam Part Outside Construction Pit (1st
BACKFILLI
BACKFILLING EMBANKMENT 477 27-Apr-14 A 26-Nov-15 A 26-Nov-15 A, BACKFILLING EMBANKMENT
General 477 27-Apr-14 A 26-Nov-15 A 26-Nov-15 A, General
392 NL, U/S + D/S Approach Areas, Right Bank Slope 477 27-Apr-14 A 26-Nov-15 A AC.Lot 1 NL, U/S + D/S Approach Areas, Right Bank Slope
391 NL, d/s Head, Axes 20/O-S 173 06-Aug-14 02-Mar-15 A AC.Lot 1 NL, d/s Head, Axes 20/O-S
A
390 NL, Guide Walls, Axes 16-17/F-S 119 18-Jan-15 A 09-Jun-15 A AC.Lot 1 NL, Guide Walls, Axes 16-17/F-S
394 Piezometers installation 70 27-Apr-15 A 19-Jul-15 A AC.Lot 1 Piezometers installation
393 PRB Ramp, Right Bank 35 11-Aug-15 20-Sep-15 A AC.Lot 1 PRB Ramp, Right Bank
A
FINAL RIP R
RAP 865 30-May-15 28-Mar-18 A 28-Mar-18 A, FINAL RIP RAP
RIVERBED UNDERNEATH RING DAM
RIVERBE 125 20-Jul-16 AA 19-Dec-16 A 19-Dec-16 A, RIVERBED UNDERNEATH RING DAM
397 Riverbed underneath ring dam 125 20-Jul-16 A 19-Dec-16 A AC.Lot 1 Riverbed underneath ring dam
Rip Rap - SLW + PH 865 30-May-15 28-Mar-18 A 28-Mar-18 A, Rip Rap - SLW + PH
RIP RAP
RA (SLW + PH) INSIDE PIT 330 30-May-15A 30-Jun-16 A 30-Jun-16 A, RIP RAP (SLW + PH) INSIDE PIT
400 u/s area, PH + SLW 300 30-May-15 26-May-16 A AC.Lot 1 u/s area, PH + SLW
A
401 d/s area, PH + SLW 300 04-Jul-15 A 30-Jun-16 A AC.Lot 1 d/s area, PH + SLW
RIP RAP
RA (SLW + PH) OUTSIDE PIT 535 02-Jul-16 A 28-Mar-18 A 28-Mar-18 A, RIP RAP (SLW + PH) OUTS
404 d/s right canal, PH + SLW + BMI reshaping 277 02-Jul-16 A 31-May-17 A AC.Lot 1 d/s right canal, PH + SLW + BMI reshaping
405 d/s left canal, PH + SLW + BMI reshaping 535 02-Jul-16 A 28-Mar-18 A AC.Lot 1 d/s left canal, PH + SLW + BMI reshaping
403 u/s area, PH + SLW 323 20-Jul-16 A 09-Aug-17 A AC.Lot 1 u/s area, PH + SLW
Rip Rap - NL 611 24-Jun-15 A 30-Jun-17 A 30-Jun-17 A, Rip Rap - NL
RIP RAP
RA (NL) INSIDE PIT 611 24-Jun-15 A 30-Jun-17 A 30-Jun-17 A, RIP RAP (NL) INSIDE PIT
408 u/s area, NL 272 24-Jun-15 A 20-May-16 A AC.Lot 1 u/s area, NL
409 d/s area, NL 278 24-Jun-15 A 28-May-16 A AC.Lot 1 d/s area, NL
410 TD 109: Approach Areas u/s completed 0 30-Jun-17 A AC.Lot 1 TD 109: Approach Areas u/s completed, 30-Jun-17 A
RIP RAP
RA (NL) OUTSIDE PIT 250 02-Jul-16 A 30-Apr-17 A 30-Apr-17 A, RIP RAP (NL) OUTSIDE PIT
413 d/s area, NL 250 02-Jul-16 A 30-Apr-17 A AC.Lot 1 d/s area, NL
412 u/s area, NL 50 20-Jul-16 A 20-Sep-16 A AC.Lot 1 u/s area, NL
Rip Rap - Closure Dam 381 15-Sep-15 25-Dec-16 A 25-Dec-16 A, Rip Rap - Closure Dam
RIP RA
RAP (CD) INSIDE PIT 113 15-Sep-15 02-Feb-16 A 02-Feb-16 A, RIP RAP (CD) INSIDE PIT
416 Riverbed Protection Closure Dam inside pit, u/s + d/s 113 15-Sep-15 02-Feb-16 A AC.Lot 1 Riverbed Protection Closure Dam inside pit, u/s + d/s
A
RIP RA
RAP (CD) OUTSIDE PIT 77 24-Sep-16 25-Dec-16 A 25-Dec-16 A, RIP RAP (CD) OUTSIDE PIT
418 Riverbed Protection Closure Dam outside pit, u/s + d/s 77 24-Sep-16A 25-Dec-16 A AC.Lot 1 Riverbed Protection Closure Dam outside pit, u/s + d/s
A
Sub Project 982 02-May-12 06-Aug-15 A 06-Aug-15 A, Sub Project
A
HOUSING F
FOR EMPLOYER/EMP. REPRES. (2 Bldgs.) 502 02-May-12 01-Jan-14 A 01-Jan-14 A, HOUSING FOR EMPLOYER/EMP. REPRES. (2 Bldgs.)
GENERAL 502 02-May-12A 01-Jan-14 A 01-Jan-14 A, GENERAL
301 Construction Permit 37 02-May-12A 13-Jun-12 A AC.Lot 1 Construction Permit
A
302 Approval of Construction Permit 0 14-Jun-12 A AC.Lot 1 Approval of Construction Permit, 14-Jun-12 A
303 Installations + Excavation 25 17-Jun-12 A 15-Jul-12 A AC.Lot 1 Installations + Excavation
304 R.C. Columns & Walls 250 11-Jul-12 A 13-May-13 A AC.Lot 1 R.C. Columns & Walls
305 R.C. Slabs & Beams 250 24-Jul-12 A 25-May-13 A AC.Lot 1 R.C. Slabs & Beams
306 Block Works 240 11-Sep-12 29-Jun-13 A AC.Lot 1 Block Works
A
307 Plastering 201 25-Nov-12 24-Jul-13 A AC.Lot 1 Plastering
A
310 Internal Electro-Mechanical Works 220 25-Nov-12 17-Aug-13 A AC.Lot 1 Internal Electro-Mechanical Works
A
308 Flooring Works 136 06-Jun-13 A 19-Nov-13 A AC.Lot 1 Flooring Works
309 Other Finishing Activities 163 06-Jun-13 A 21-Dec-13 A AC.Lot 1 Other Finishing Activities
313 Exterior E.M. Services 85 30-Jun-13 A 09-Oct-13 A AC.Lot 1 Exterior E.M. Services
311 Installation of Elevators 33 13-Nov-13 21-Dec-13 A AC.Lot 1 Installation of Elevators
A
314 Internal Furnishing 29 27-Nov-13 30-Dec-13 A AC.Lot 1 Internal Furnishing
A
312 Testing and Commissioning 12 18-Dec-13 31-Dec-13 A AC.Lot 1 Testing and Commissioning
A
315 Complete Works of Employer Housing 0 01-Jan-14 A AC.Lot 1 Complete Works of Employer Housing, 01-Jan-14 A
HEAD REGULATOR
REGU 406 01-Apr-14 A 06-Aug-15 A 06-Aug-15 A, HEAD REGULATOR
General 406 01-Apr-14 A 06-Aug-15 A 06-Aug-15 A, General
1281 Start of Works 0 01-Apr-14 A AC.Lot 1 Start of Works, 01-Apr-14 A
1282 Preparation works/ Mobilization 55 25-May-14 31-Jul-14 A AC.Lot 1 Preparation works/ Mobilization
A
1286 Piezometers 25 06-Aug-14 03-Sep-14 A AC.Lot 1 Piezometers
A
1284 Control Building and Radio Mast Foundation incl. Cable 181 23-Sep-14 01-May-15 A AC.Lot 1 Control Building and Radio Mast Foundation incl. Cable Trench
A
1285 Drilling and grouting of piers U/s Piers 124 01-Dec-14 30-Apr-15 A AC.Lot 1 Drilling and grouting of piers U/s Piers
A
1283 Install HPU and Electrical Cabinets incl. cabling in Con 7 15-Dec-14 22-Dec-14 A AC.Lot 4 Install HPU and Electrical Cabinets incl. cabling in Control Building
A
1287 End of Works 0 06-Aug-15 AC.Lot 1 End of Works, 06-Aug-15 A
A
Phase A (Left Side) 182 02-Aug-14 08-Mar-15 A 08-Mar-15 A, Phase A (Left Side)

Milestone Lot 1 Lot 2 Page 6 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
Down
Downstream Concrete Works 182 02-Aug-14 08-Mar-15 A 08-Mar-15 A, Downstream Concrete Works
1295 Temporary separation wall D/S 79 A 05-Nov-14 A
02-Aug-14 AC.Lot 1 Temporary separation wall D/S
A
1290 Sheet Piling 13 01-Sep-14 15-Sep-14 A AC.Lot 1 Sheet Piling
A
1292 Removal of Stone Pitching in Area of New Weir 8 16-Sep-14 24-Sep-14 A AC.Lot 1 Removal of Stone Pitching in Area of New Weir
A
1291 Drilling and grouting of piers D/s Phase A 20 24-Sep-14 20-Oct-14 A AC.Lot 1 Drilling and grouting of piers D/s Phase A
A
1293 Concrete works for Side Wall Extension 125 11-Oct-14 A 08-Mar-15 A AC.Lot 1 Concrete works for Side Wall Extension
1294 New Weir 36 25-Nov-14 06-Jan-15 A AC.Lot 1 New Weir
A
1296 Bed Protection below Weir 23 15-Dec-14 12-Jan-15 A AC.Lot 1 Bed Protection below Weir
A
1297 Slab over old one 69 15-Dec-14 08-Mar-15 A AC.Lot 1 Slab over old one
A
Rehab
Rehabilitation of Head regulator 85 19-Nov-14 01-Mar-15 A 01-Mar-15 A, Rehabilitation of Head regulator
1299 Works on gates 1-5 by Lot 1 85 19-Nov-14A 01-Mar-15 A AC.Lot 1 Works on gates 1-5 by Lot 1
A
1301 Works + Commissioning by other Lots 85 19-Nov-14 28-Feb-15 A AC.Lot 2 Works + Commissioning by other Lots
A
1300 Cladding on old piers 28 03-Dec-14 04-Jan-15 A AC.Lot 1 Cladding on old piers
A
Phase B (Right Side) 93 14-Feb-15 04-Jun-15 A 04-Jun-15 A, Phase B (Right Side)
Downstream Concrete Works
Down 90 14-Feb-15 01-Jun-15 A 01-Jun-15 A, Downstream Concrete Works
1304 Sheet Piling 15 A 02-Mar-15 A
14-Feb-15 AC.Lot 1 Sheet Piling
A
1306 Removal of Stone Pitching in Area of New Weir 6 03-Mar-15 09-Mar-15 A AC.Lot 1 Removal of Stone Pitching in Area of New Weir
A
1307 Concrete works for Side Wall Extension 45 15-Mar-15 09-May-15 A AC.Lot 1 Concrete works for Side Wall Extension
A
1305 Drilling and grouting of piers D/s Phase B 20 18-Mar-15 09-Apr-15 A AC.Lot 1 Drilling and grouting of piers D/s Phase B
A
1308 New Weir 15 15-Apr-15 A 03-May-15 A AC.Lot 1 New Weir
1309 Bed Protection below Weir 12 04-May-15 17-May-15 A AC.Lot 1 Bed Protection below Weir
A
1310 Slab over old one 25 04-May-15 01-Jun-15 A AC.Lot 1 Slab over old one
A
Rehab
Rehabilitation of Head regulator 74 08-Mar-15 04-Jun-15 A 04-Jun-15 A, Rehabilitation of Head regulator
1312 Works on gates 6-9 by Lot 1 62 A 21-May-15 A
08-Mar-15 AC.Lot 1 Works on gates 6-9 by Lot 1
A
1314 Works + Commissioning by other Lots 71 11-Mar-15 04-Jun-15 A AC.Lot 2 Works + Commissioning by other Lots
A
1313 Cladding on old piers 22 19-Mar-15 15-Apr-15 A AC.Lot 1 Cladding on old piers
A
POWERHOUSE AND INTERMEDIATE PIERS
POWERHOU 1391 11-Jan-14 A 02-Aug-18 A 02-Aug-18 A, POWERHOU
INTERMEDI
INTERMEDIATE PIER, AXES 6-7 629 06-Mar-14 05-Apr-16 A 05-Apr-16 A, INTERMEDIATE PIER, AXES 6-7
422 d/s Part - slab 50 06-Mar-14 07-May-14 A AC.Lot 1 d/s Part - slab
A
421 Central part - slab 22 22-Mar-14 16-Apr-14 A AC.Lot 1 Central part - slab
A
423 Central Part - Superstructure 612 26-Mar-14 05-Apr-16 A AC.Lot 1 Central Part - Superstructure
A
424 d/s Part - Superstructure 399 15-May-14 08-Sep-15 A AC.Lot 1 d/s Part - Superstructure
A
INTERMEDI
INTERMEDIATE PIER, AXES 12-13 897 11-Jan-14 A 04-Jan-17 A 04-Jan-17 A, INTERMEDIATE PIER, AXES 12-13
427 d/s Part - slab 28 11-Jan-14 A 14-Feb-14 A AC.Lot 1 d/s Part - slab
426 Central part - slab 38 14-Feb-14 31-Mar-14 A AC.Lot 1 Central part - slab
A
428 Central Part - Superstructure 869 15-Feb-14 04-Jan-17 A AC.Lot 1 Central Part - Superstructure
A
429 d/s Part - Superstructure 784 05-Apr-14 A 14-Nov-16 A AC.Lot 1 d/s Part - Superstructure
PH-UNIT 1-2,
1-2 AXES 7-9 957 03-Jun-14 A 31-Jul-17 A 31-Jul-17 A, PH-UNIT 1-2, AXES 7-9
UNIT (1) 817 03-Jun-14 A 18-Feb-17 A 18-Feb-17 A, UNIT (1)
U1 Lot
Lo 1 / Concrete Works 486 23-Jul-14 A 05-Mar-16 A 05-Mar-16 A, U1 Lot 1 / Concrete Works
433 TD 301: Start U1 First Stage Concrete Works 0 23-Jul-14 A AC.Lot 1 TD 301: Start U1 First Stage Concrete Works, 23-Jul-14 A
438 U1, Step 1-a (DT Steel Liner Foundation Axis C:B ) 101 23-Jul-14 A 25-Nov-14 A AC.Lot 1 U1, Step 1-a (DT Steel Liner Foundation Axis C:B )
439 U1, Step 1-b ( U/S Axis B: A) 62 17-Sep-14 01-Dec-14 A AC.Lot 1 U1, Step 1-b ( U/S Axis B: A)
A
440 MS 1-03: PH-Unit 1, Step 1 Concrete Works complete 0 01-Dec-14 A AC.Lot 1 MS 1-03: PH-Unit 1, Step 1 Concrete Works complete,
445 U1, Step 2 (Central Part Axes B-C) 164 07-Dec-14 22-Jun-15 A AC.Lot 1 U1, Step 2 (Central Part Axes B-C)
A
444 U1, Step 2a (Inlet Part u/s Axis B) 160 23-Feb-15 03-Sep-15 A AC.Lot 1 U1, Step 2a (Inlet Part u/s Axis B)
A
447 U1, Step 3 (Draft Tube Part d/s Axis C) 296 11-Mar-15 05-Mar-16 A AC.Lot 1 U1, Step 3 (Draft Tube Part d/s Axis C)
A
446 MS 1-05: PH-Unit 1, Step 2 Concrete Works complete 0 22-Jun-15 A AC.Lot 1 MS 1-05: PH-Unit 1, Step 2 Concrete Works complete,
448 TD 315: U1, Step 2a (Inlet Part u/s Axis B) Concrete W 0 02-Sep-15 A AC.Lot 1 TD 315: U1, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
451 TD 324: U1, Step 3 (Draft Tube d/s Axis C) Concrete 0 05-Mar-16 A AC.Lot 1 TD 324: U1, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
U1, Draft
Dr Tube installation 452 03-Jun-14 A 03-Dec-15 A 03-Dec-15 A, U1, Draft Tube installation
455 Installation of Dewatering Pipes in Step 1- Raft 25 03-Jun-14 A 01-Jul-14 A AC.Lot 3 Installation of Dewatering Pipes in Step 1- Raft
453 Installation of embedded parts Phase 1/ Step 1 25 20-Jul-14 A 20-Aug-14 A AC.Lot 3 Installation of embedded parts Phase 1/ Step 1
454 TD 305: Start DT Steel Liner U1 erection 0 03-Dec-14 AC.Lot 3 TD 305: Start DT Steel Liner U1 erection
A
458 DT installation 35 03-Dec-14 13-Jan-15 A AC.Lot 3 DT installation
A
449 U1, Second Stage(Concrete for DT) 61 16-Jan-15 A 30-Mar-15 A AC.Lot 1 U1, Second Stage(Concrete for DT)
456 Draft Tube Sandblasting and painting 22 24-Feb-15 21-Mar-15 A AC.Lot 3 Draft Tube Sandblasting and painting
A
457 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part 0 03-Dec-15 AC.Lot 3 TD 327: Lot 2, U1 Draft Tube Area, Start of fixed Part Installation
A
U1, Stayring
St installation 449 18-Aug-14 11-Feb-16 A 11-Feb-16 A, U1, Stayring installation
460 Installation of embedded parts Phase 1/ Step 1 12 18-Aug-14 31-Aug-14 A AC.Lot 3 Installation of embedded parts Phase 1/ Step 1
A
462 TD 323: Stayring and Pier Nose U1 installation in pit ( r 0 15-Dec-15 AC.Lot 3 TD 323: Stayring and Pier Nose U1 installation in pit ( revised )
A
463 Stayring installation in pit 25 15-Dec-15 13-Jan-16 A AC.Lot 3 Stayring installation in pit
A
461 TD 325: Stayring & Pier Nose U1 Installation in the pit 0 14-Jan-16 A AC.Lot 3 TD 325: Stayring & Pier Nose U1 Installation in the pit ready for concrete
464 Installation of embedded parts for horizontal adjustmen 12 30-Jan-16 A 11-Feb-16 A AC.Lot 3 Installation of embedded parts for horizontal adjustment of generator
U1, Turbine
Tu & Generator Main Installation 316 01-Feb-16 18-Feb-17 A 18-Feb-17 A, U1, Turbine & Generator Main Installation
436 TD 329: Start U1 u/s Transition Zone Concrete Works 0 01-Feb-16A AC.Lot 1 TD 329: Start U1 u/s Transition Zone Concrete Works up to EL. 42.10, 01-Feb-16 A
A
435 U1, Second Stage Concrete Works U1, EL 27.20 to 4 113 02-Feb-16 16-Jun-16 A AC.Lot 1 U1, Second Stage Concrete Works U1, EL 27.20 to 42.10, Axes B-C
A
437 TD 346: U1 u/s Transition Zone Concrete Works up to 0 16-Jun-16 A AC.Lot 1 TD 346: U1 u/s Transition Zone Concrete Works up to EL. 42.10 completed, 16-Jun-16 A
442 U1, Second Stage(Concrete for Hatch Cover) 5 26-Jun-16 A 02-Jul-16 A AC.Lot 1 U1, Second Stage(Concrete for Hatch Cover)
469 TD 357: Start Turbine and Generator Erection U1 0 21-Jul-16 A AC.Lot 3 TD 357: Start Turbine and Generator Erection U1
470 Installation Distributor anchoring, distributor & discharg 71 21-Jul-16 A 19-Oct-16 A AC.Lot 3 Installation Distributor anchoring, distributor & discharge ring
443 U1, Second stage Concrete for anchoring (Turbine & 15 20-Oct-16 A 07-Nov-16 A AC.Lot 1 U1, Second stage Concrete for anchoring (Turbine & Generator Main Installation)
471 Main installation: turbine + generator incl. Piping & aux 86 08-Nov-16 18-Feb-17 A AC.Lot 3 Main installation: turbine + generator incl. Piping & auxiliaries
A
466 TD 347: Generator hatch cover installation 0 13-Jan-17 A AC.Lot 3 TD 347: Generator hatch cover installation

Milestone Lot 1 Lot 2 Page 7 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
467 Generator hatch cover installation 1 13-Jan-17 A 15-Jan-17 A AC.Lot 3 Generator hatch cover installation
468 Sandblasting and painting hatch cover 0 15-Jan-17 A 15-Jan-17 A AC.Lot 3 Sandblasting and painting hatch cover
U1, Trash
Tra Rack installation 456 21-Oct-14 A 21-Apr-16 A 21-Apr-16 A, U1, Trash Rack installation
474 Installation of embedded parts - 1st stage 25 21-Oct-14 A 18-Nov-14 A AC.Lot 3 Installation of embedded parts - 1st stage
475 Installation of embedded parts - 2nd stage 50 02-Feb-15 01-Apr-15 A AC.Lot 3 Installation of embedded parts - 2nd stage
A
476 Installation of fish beams u1 & u2 50 02-Aug-15 01-Oct-15 A AC.Lot 3 Installation of fish beams u1 & u2
A
473 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Ins 0 02-Sep-15 AC.Lot 3 TD 318: Lot 2 & 3, U1 Inlet Area, Start of fixed Part Installation
A
441 U1, Second Stage(Concrete for Fish Beam) 27 09-Nov-15 10-Dec-15 A AC.Lot 1 U1, Second Stage(Concrete for Fish Beam)
A
477 TR installation 118 03-Dec-15 21-Apr-16 A AC.Lot 3 TR installation
A
U1, Stop
St log U/S 223 03-Sep-15 01-Jun-16 A 01-Jun-16 A, U1, Stop log U/S
479 Installation of embedded parts - 1st stage 7 A 12-Sep-15 A
03-Sep-15 AC.Lot 2 Installation of embedded parts - 1st stage
A
480 Installation of embedded parts - 2nd stage (sill beam + 87 12-Sep-15 28-Dec-15 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
450 U1, Second Stage(Concrete for U/S Stop Log) 74 29-Dec-15 27-Mar-16 A AC.Lot 1 U1, Second Stage(Concrete for U/S Stop Log)
A
481 Stop log U/S installation 54 27-Mar-16 01-Jun-16 A AC.Lot 2 Stop log U/S installation
A
U1, Stop
St log D/S (DS Draft Tube Bulkheads ) 236 03-Aug-15 16-May-16 A 16-May-16 A, U1, Stop log D/S (DS Draft Tube Bulkheads )
483 Installation of embedded parts - 1st stage 164 03-Aug-15 18-Feb-16 A AC.Lot 2 Installation of embedded parts - 1st stage
A
484 Installation of embedded parts - 2nd stage (sill beam + 40 18-Feb-16 05-Apr-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
434 U1, Second Stage(Concrete for D/S Stop Log) 20 05-Apr-16 A 30-Apr-16 A AC.Lot 1 U1, Second Stage(Concrete for D/S Stop Log)
485 Stop log D/S installation 8 07-May-16 16-May-16 A AC.Lot 2 Stop log D/S installation
A
UNIT (2) 907 04-Aug-14 31-Jul-17 A 31-Jul-17 A, UNIT (2)
U2 Lot
Lo 1 / Concrete Works 596 A 26-Jul-16 A
04-Aug-14 26-Jul-16 A, U2 Lot 1 / Concrete Works
489 TD 302: Start U2 First Stage Concrete Works 0 04-Aug-14 AC.Lot 1 TD 302: Start U2 First Stage Concrete Works, 04-Aug-14 A
A
488 U2, Step 1-a (DT Steel Liner Foundation Axis C:B ) 112 05-Aug-14 17-Dec-14 A AC.Lot 1 U2, Step 1-a (DT Steel Liner Foundation Axis C:B )
A
490 U2, Step 1-b ( U/S Axis B: A) 60 08-Oct-14 A 16-Dec-14 A AC.Lot 1 U2, Step 1-b ( U/S Axis B: A)
495 TD 306: U2, Step 1 (Draft Tube Steel Liner Foundation 0 18-Dec-14 AC.Lot 1 TD 306: U2, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed, 18-Dec-14 A
A
491 U2, Step 2 (Central Part Axes B-C) 200 21-Dec-14 19-Aug-15 A AC.Lot 1 U2, Step 2 (Central Part Axes B-C)
A
504 U2, Step 2a (Inlet Part u/s Axis B) 167 18-Mar-15 11-Oct-15 A AC.Lot 1 U2, Step 2a (Inlet Part u/s Axis B)
A
505 U2, Step 3 (Draft Tube Part d/s Axis C) 308 14-Jul-15 A 25-Jul-16 A AC.Lot 1 U2, Step 3 (Draft Tube Part d/s Axis C)
502 TD 313: U2, Step 2 (Central Part Axes B-C) Concrete 0 19-Aug-15 A AC.Lot 1 TD 313: U2, Step 2 (Central Part Axes B-C) Concrete Works completed,
503 TD 316: U2, Step 2a (Inlet Part u/s Axis B) Concrete W 0 11-Oct-15 A AC.Lot 1 TD 316: U2, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
506 TD 326: U2, Step 3 (Draft Tube d/s Axis C) Concrete 0 26-Jul-16 A AC.Lot 1 TD 326: U2, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
U2, Draft
Dr Tube installation 392 16-Aug-14 03-Dec-15 A 03-Dec-15 A, U2, Draft Tube installation
508 Installation of embedded parts 25 16-Aug-14A 13-Sep-14 A AC.Lot 3 Installation of embedded parts
A
509 TD 307: Start DT Steel Liner U2 erection 0 18-Dec-14 AC.Lot 3 TD 307: Start DT Steel Liner U2 erection
A
513 DT installation 35 18-Dec-14 29-Jan-15 A AC.Lot 3 DT installation
A
492 U2, Second Stage(Concrete for DT) 65 21-Jan-15 A 08-Apr-15 A AC.Lot 1 U2, Second Stage(Concrete for DT)
511 MS 3-02: Unit 1&2 Draft Tube Erec. ready for Step 2 C 0 30-Jan-15 A AC.Lot 3 MS 3-02: Unit 1&2 Draft Tube Erec. ready for Step 2 Concr. Works
510 Draft Tube Sandblasting and painting 22 11-Mar-15 05-Apr-15 A AC.Lot 3 Draft Tube Sandblasting and painting
A
512 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part 0 03-Dec-15 AC.Lot 3 TD 328: Lot 2, U2 Draft Tube Area, Start of fixed Part Installation
A
U2, Stayring
St installation 468 10-Aug-14 25-Feb-16 A 25-Feb-16 A, U2, Stayring installation
515 Installation of embedded parts 12 A
10-Aug-14 23-Aug-14 A AC.Lot 3 Installation of embedded parts
A
516 TD 335: Stayring and Pier Nose U2 installation in pit ( r 0 31-Dec-15 AC.Lot 3 TD 335: Stayring and Pier Nose U2 installation in pit ( revised )
A
517 Stayring installation in pit 25 31-Dec-15 31-Jan-16 A AC.Lot 3 Stayring installation in pit
A
518 Installation of embedded parts for horizontal adjustmen 12 13-Feb-16 25-Feb-16 A AC.Lot 3 Installation of embedded parts for horizontal adjustment of generator
A
U2, Turbine
Tu & Generator Main Installation 456 01-Feb-16 31-Jul-17 A 31-Jul-17 A, U2, Turbine & Generator Main Installation
500 TD 344: Start U2 u/s Transition Zone Concrete Works 0 A
01-Feb-16 AC.Lot 1 TD 344: Start U2 u/s Transition Zone Concrete Works up to EL. 42.10, 01-Feb-16 A
A
498 U2, Second Stage Concrete Works U2, EL 27.20 to 42 137 02-Feb-16 17-Jul-16 A AC.Lot 1 U2, Second Stage Concrete Works U2, EL 27.20 to 42.10, Axes B-C
A
501 TD 352: U2 u/s Transition Zone Concrete Works up to 0 17-Jul-16 A AC.Lot 1 TD 352: U2 u/s Transition Zone Concrete Works up to EL. 42.10 completed ( revised ),
496 U2, Second Stage(Concrete for Hatch Cover) 5 18-Jul-16 A 25-Jul-16 A AC.Lot 1 U2, Second Stage(Concrete for Hatch Cover)
521 TD 358: Start Turbine and Generator Erection U2 0 08-Aug-16 AC.Lot 3 TD 358: Start Turbine and Generator Erection U2
A
523 Installation Distributor anchoring, distributor & discharg 8 17-Aug-16 27-Aug-16 A AC.Lot 3 Installation Distributor anchoring, distributor & discharge ring
A
497 U2, Second stage Concrete for anchoring (Turbine & 63 28-Aug-16 15-Nov-16 A AC.Lot 1 U2, Second stage Concrete for anchoring (Turbine & Generator Main Installation)
A
525 Main installation: turbine + generator incl. Piping & aux 219 16-Nov-16 31-Jul-17 A AC.Lot 3 Main installation: turbine + generator incl. Piping & auxiliaries
A
520 TD 353: Generator hatch cover installation 0 04-Jul-17 A AC.Lot 3 TD 353: Generator hatch cover installation
522 Generator hatch cover installation 1 04-Jul-17 A 05-Jul-17 A AC.Lot 3 Generator hatch cover installation
524 Sandblasting and painting hatch cover 12 05-Jul-17 A 19-Jul-17 A AC.Lot 3 Sandblasting and painting hatch cover
U2, Trash
Tra Rack installation 339 17-Dec-14 01-Feb-16 A 01-Feb-16 A, U2, Trash Rack installation
528 Installation of embedded parts - 1st stage 25 17-Dec-14 15-Jan-15 A AC.Lot 3 Installation of embedded parts - 1st stage
A
529 Installation of embedded parts - 2nd stage 50 30-May-15 28-Jul-15 A AC.Lot 3 Installation of embedded parts - 2nd stage
A
530 Installation of fish beams 50 29-Jul-15 A 28-Sep-15 A AC.Lot 3 Installation of fish beams
527 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Ins 0 02-Sep-15 AC.Lot 3 TD 319: Lot 2 & 3, U2 Inlet Area, Start of fixed Part Installation
A
494 U2, Second Stage(Concrete for Fish Beam) 28 08-Nov-15 10-Dec-15 A AC.Lot 1 U2, Second Stage(Concrete for Fish Beam)
A
531 TR installation 43 12-Dec-15 01-Feb-16 A AC.Lot 3 TR installation
A
U2, Stop
St log U/S 165 15-Oct-15 A 28-Apr-16 A 28-Apr-16 A, U2, Stop log U/S
533 Installation of embedded parts - 1st stage 11 15-Oct-15 A 28-Oct-15 A AC.Lot 2 Installation of embedded parts - 1st stage
534 Installation of embedded parts - 2nd stage (sill beam + 65 29-Oct-15 A 14-Jan-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
493 U2, Second Stage(Concrete for U/S Stop Log) 76 15-Jan-16 A 14-Apr-16 A AC.Lot 1 U2, Second Stage(Concrete for U/S Stop Log)
535 Stop log U/S installation 11 14-Apr-16 A 28-Apr-16 A AC.Lot 2 Stop log U/S installation
U2, Stop
St log D/S (DS Draft Tube Bulkheads ) 62 15-Mar-16 30-May-16 A 30-May-16 A, U2, Stop log D/S (DS Draft Tube Bulkheads )
537 Installation of embedded parts - 1st stage 18 15-Mar-16 05-Apr-16 A AC.Lot 2 Installation of embedded parts - 1st stage
A
538 Installation of embedded parts - 2nd stage (sill beam + 7 06-Apr-16 A 14-Apr-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
499 U2, Second Stage(Concrete for D/S Stop Log) 22 15-Apr-16 A 15-May-16 A AC.Lot 1 U2, Second Stage(Concrete for D/S Stop Log)
539 Stop log D/S installation 8 21-May-16 30-May-16 A AC.Lot 2 Stop log D/S installation
A
MIDDLE PIER
PIE 1183 11-May-14 28-Mar-18 A 28-Mar-18 A, MIDDLE PIER
A

Milestone Lot 1 Lot 2 Page 8 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
Lot 1 ( C
Concrete & Elevators ) 1183 11-May-14 28-Mar-18 A 28-Mar-18 A, Lot 1 ( Concrete & Elevators
542 Middle Pier 646 11-May-14A 29-Jun-16 A AC.Lot 1 Middle Pier
A
543 Elevator - installation & testing 471 21-Sep-16 28-Mar-18 A AC.Lot 1 Elevator - installation & testing
A
Fixed pa
parts installation 336 25-May-14 02-Jul-15 A 02-Jul-15 A, Fixed parts installation
545 Embedded pipes installation in raft 12 25-May-14A 07-Jun-14 A AC.Lot 1 Embedded pipes installation in raft
A
546 Drainage pit cover / Dewatering pit cover installation 25 04-Jun-15 A 02-Jul-15 A AC.Lot 1 Drainage pit cover / Dewatering pit cover installation
PH-UNIT 3-4,
3-4 AXES 10-12 1011 25-Aug-14 20-Dec-17 A 20-Dec-17 A, PH-UNIT 3-4, AXES 10-12
UNIT (3) 983 25-Aug-14A 18-Nov-17 A 18-Nov-17 A, UNIT (3)
U3 Lot
Lo 1 / Concrete Works 528 25-Aug-14A 25-May-16 A 25-May-16 A, U3 Lot 1 / Concrete Works
568 TD 303: Start U3 First Stage Concrete Works 0 25-Aug-14 AC.Lot 1 TD 303: Start U3 First Stage Concrete Works, 25-Aug-14 A
A
550 U3, Step 1-a (DT Steel Liner Foundation Axis C:B ) 48 26-Aug-14 23-Oct-14 A AC.Lot 1 U3, Step 1-a (DT Steel Liner Foundation Axis C:B )
A
552 U2, Step 1-b ( U/S Axis B: A) 60 19-Nov-14 29-Jan-15 A AC.Lot 1 U2, Step 1-b ( U/S Axis B: A)
A
551 U3, Step 2 (Central Part Axes B-C) 297 14-Jan-15 A 10-Jan-16 A AC.Lot 1 U3, Step 2 (Central Part Axes B-C)
553 TD 308: U3, Step 1 (Draft Tube Steel Liner Foundation 0 29-Jan-15 A AC.Lot 1 TD 308: U3, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed,
554 U3, Step 2a (Inlet Part u/s Axis B) 229 09-Mar-15 13-Dec-15 A AC.Lot 1 U3, Step 2a (Inlet Part u/s Axis B)
A
555 U3, Step 3 (Draft Tube Part d/s Axis C) 226 24-Aug-15 25-May-16 A AC.Lot 1 U3, Step 3 (Draft Tube Part d/s Axis C)
A
563 TD 331: U3, Step 2a (Inlet Part u/s Axis B) Concrete W 0 13-Dec-15 A AC.Lot 1 TD 331: U3, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
562 TD 317: U3, Step 2 (Central Part Axes B-C) Concrete 0 10-Jan-16 A AC.Lot 1 TD 317: U3, Step 2 (Central Part Axes B-C) Concrete Works completed,
567 TD 341: U3, Step 3 (Draft Tube d/s Axis C) Concrete 0 25-May-16 A AC.Lot 1 TD 341: U3, Step 3 (Draft Tube d/s Axis C) Concrete Works completed,
U3, Draft
Dr Tube installation 421 07-Sep-14 31-Jan-16 A 31-Jan-16 A, U3, Draft Tube installation
570 Installation of embedded parts 25 07-Sep-14A 08-Oct-14 A AC.Lot 3 Installation of embedded parts
A
571 TD 309: Start DT Steel Liner U3 erection 0 31-Jan-15 A AC.Lot 3 TD 309: Start DT Steel Liner U3 erection
574 DT installation 35 31-Jan-15 A 11-Mar-15 A AC.Lot 3 DT installation
572 Draft Tube Sandblasting and painting 22 23-Apr-15 A 19-May-15 A AC.Lot 3 Draft Tube Sandblasting and painting
556 U3, Second Stage(Concrete for DT) 67 25-May-15 13-Aug-15 A AC.Lot 1 U3, Second Stage(Concrete for DT)
A
573 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 3 TD 342: Lot 2, U3 Draft Tube Area, Start of fixed Part Installation
U3, Stayring
St installation 472 01-Sep-14 23-Mar-16 A 23-Mar-16 A, U3, Stayring installation
576 Installation of embedded parts 12 01-Sep-14 14-Sep-14 A AC.Lot 3 Installation of embedded parts
A
579 TD 345: Stayring and Pier Nose U3 installation in pit ( r 0 10-Feb-16 AC.Lot 3 TD 345: Stayring and Pier Nose U3 installation in pit ( revised )
A
580 Stayring installation in pit 25 10-Feb-16 09-Mar-16 A AC.Lot 3 Stayring installation in pit
A
577 Installation of embedded parts for horizontal adjustmen 12 10-Mar-16 23-Mar-16 A AC.Lot 3 Installation of embedded parts for horizontal adjustment of generator
A
578 TD 348: Stayring & Pier Nose U3 Installation in the pit 0 10-Mar-16 AC.Lot 3 TD 348: Stayring & Pier Nose U3 Installation in the pit ready for concrete
A
U3, Turbine
Tu & Generator Main Installation 489 12-Apr-16 A 18-Nov-17 A 18-Nov-17 A, U3, Turbine & Generator Main Installation
565 TD 349: Start U3 u/s Transition Zone Concrete Works 0 12-Apr-16 A AC.Lot 1 TD 349: Start U3 u/s Transition Zone Concrete Works up to EL. 42.10, 12-Apr-16 A
564 U3, Second Stage Concrete Works U3, EL 27.20 to 42 102 13-Apr-16 A 17-Aug-16 A AC.Lot 1 U3, Second Stage Concrete Works U3, EL 27.20 to 42.10, Axes B-C
566 TD 355: U3 u/s Transition Zone Concrete Works up to 0 17-Aug-16 A AC.Lot 1 TD 355: U3 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
560 U3, Second Stage(Concrete for Hatch Cover) 4 18-Aug-16 23-Aug-16 A AC.Lot 1 U3, Second Stage(Concrete for Hatch Cover)
A
583 TD 361: Start Turbine and Generator Erection U3 0 04-Sep-16 AC.Lot 3 TD 361: Start Turbine and Generator Erection U3
A
582 Installation Distributor anchoring, distributor & discharg 63 05-Sep-16 23-Nov-16 A AC.Lot 3 Installation Distributor anchoring, distributor & discharge ring
A
561 U3, Second stage Concrete for anchoring (Turbine & 19 24-Nov-16 17-Dec-16 A AC.Lot 1 U3, Second stage Concrete for anchoring (Turbine & Generator Main Installation)
A
587 Main installation: turbine + generator incl. Piping & aux 286 18-Dec-16 18-Nov-17 A AC.Lot 3 Main installation: turbine + generator incl. Piping & auxiliarie
A
585 Generator hatch cover installation 0 21-Apr-17 A 22-Apr-17 A AC.Lot 3 Generator hatch cover installation
586 TD 356: Generator hatch cover installation 0 21-Apr-17 A AC.Lot 3 TD 356: Generator hatch cover installation
584 Sandblasting and painting hatch cover 5 24-Apr-17 A 30-Apr-17 A AC.Lot 3 Sandblasting and painting hatch cover
U3, Trash
Tra Rack installation 353 31-Jan-15 A 30-Mar-16 A 30-Mar-16 A, U3, Trash Rack installation
590 Installation of embedded parts - 1st stage 25 31-Jan-15 A 28-Feb-15 A AC.Lot 3 Installation of embedded parts - 1st stage
591 Installation of embedded parts - 2nd stage 50 29-Jul-15 A 28-Sep-15 A AC.Lot 3 Installation of embedded parts - 2nd stage
592 Installation of fish beams 50 29-Sep-15 28-Nov-15 A AC.Lot 3 Installation of fish beams
A
589 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Ins 0 02-Nov-15 AC.Lot 3 TD 333: Lot 2 & 3, U3 Inlet Area, Start of fixed Part Installation
A
558 U3, Second Stage(Concrete for Fish Beam) 17 07-Feb-16 27-Feb-16 A AC.Lot 1 U3, Second Stage(Concrete for Fish Beam)
A
593 TR installation 27 29-Feb-16 30-Mar-16 A AC.Lot 3 TR installation
A
U3, Stop
St log U/S 98 31-Jan-16 A 28-May-16 A 28-May-16 A, U3, Stop log U/S
595 Installation of embedded parts - 1st stage 12 31-Jan-16 A 14-Feb-16 A AC.Lot 2 Installation of embedded parts - 1st stage
596 Installation of embedded parts - 2nd stage (sill beam + 31 15-Feb-16 22-Mar-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
557 U3, Second Stage(Concrete for U/S Stop Log) 38 26-Mar-16 12-May-16 A AC.Lot 1 U3, Second Stage(Concrete for U/S Stop Log)
A
597 Stop log U/S installation 12 13-May-16 28-May-16 A AC.Lot 2 Stop log U/S installation
A
U3, Stop
St log D/S (DS Draft Tube Bulkheads ) 57 24-Mar-16 02-Jun-16 A 02-Jun-16 A, U3, Stop log D/S (DS Draft Tube Bulkheads )
599 Installation of embedded parts - 1st stage 13 A 09-Apr-16 A
24-Mar-16 AC.Lot 2 Installation of embedded parts - 1st stage
A
600 Installation of embedded parts - 2nd stage (sill beam + 21 10-Apr-16 A 08-May-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
559 U3, Second Stage(Concrete for D/S Stop Log) 16 27-Apr-16 A 18-May-16 A AC.Lot 1 U3, Second Stage(Concrete for D/S Stop Log)
601 Stop log D/S installation 13 18-May-16 02-Jun-16 A AC.Lot 2 Stop log D/S installation
A
UNIT (4) 1004 02-Sep-14 20-Dec-17 A 20-Dec-17 A, UNIT (4)
U4 Lot
Lo 1 / Concrete Works 559 02-Sep-14A 10-Jul-16 A 10-Jul-16 A, U4 Lot 1 / Concrete Works
604 TD 304: Start U4 First Stage Concrete Works 0 02-Sep-14A AC.Lot 1 TD 304: Start U4 First Stage Concrete Works, 02-Sep-14 A
A
605 U4, Step 1-a (DT Steel Liner Foundation Axis C:B ) 63 02-Sep-14 17-Nov-14 A AC.Lot 1 U4, Step 1-a (DT Steel Liner Foundation Axis C:B )
A
607 U2, Step 1-b ( U/S Axis B: A) 47 04-Dec-14 31-Jan-15 A AC.Lot 1 U2, Step 1-b ( U/S Axis B: A)
A
606 U4, Step 2 (Central Part Axes B-C) 324 14-Jan-15 A 11-Feb-16 A AC.Lot 1 U4, Step 2 (Central Part Axes B-C)
610 U4, Step 3 (Draft Tube Part d/s Axis C) 132 09-Aug-15 16-Jan-16 A AC.Lot 1 U4, Step 3 (Draft Tube Part d/s Axis C)
A
609 U4, Step 2a (Inlet Part u/s Axis B) 121 02-Sep-15 30-Jan-16 A AC.Lot 1 U4, Step 2a (Inlet Part u/s Axis B)
A
623 d/s Separation Bored Pile Wall 170 17-Dec-15 10-Jul-16 A AC.Lot 1 d/s Separation Bored Pile Wall
A
617 TD 332: U4, Step 2a (Inlet Part u/s Axis B) Concrete W 0 31-Jan-16 A AC.Lot 1 TD 332: U4, Step 2a (Inlet Part u/s Axis B) Concrete Works completed,
613 TD 320: U4, Step 2 (Central Part Axes B-C) Concrete 0 11-Feb-16 A AC.Lot 1 TD 320: U4, Step 2 (Central Part Axes B-C) Concrete Works completed,
611 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete 0 25-May-16 A AC.Lot 1 MS 1-06: PH-Unit 4, Step 3 Concrete Works complete,
U4, Draft
Dr Tube installation 380 28-Oct-14 A 31-Jan-16 A 31-Jan-16 A, U4, Draft Tube installation

Milestone Lot 1 Lot 2 Page 9 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
625 Installation of embedded parts 25 28-Oct-14 A 25-Nov-14 A AC.Lot 3 Installation of embedded parts
626 TD 311: Start DT Steel Liner U4 erection 0 10-Jan-15 A AC.Lot 3 TD 311: Start DT Steel Liner U4 erection
630 DT installation 44 10-Jan-15 A 03-Mar-15 A AC.Lot 3 DT installation
629 MS 3-03: Unit 3&4 Draft Tube Erec. ready for Step 2 C 0 03-Mar-15 AC.Lot 3 MS 3-03: Unit 3&4 Draft Tube Erec. ready for Step 2 Concr. Works
A
618 U4, Second Stage(Concrete for DT) 160 04-Mar-15 13-Sep-15 A AC.Lot 1 U4, Second Stage(Concrete for DT)
A
608 TD 310: U4, Step 1 (Draft Tube Steel Liner Foundation 0 13-Sep-15 A AC.Lot 1 TD 310: U4, Step 1 (Draft Tube Steel Liner Foundation) Concrete Works completed,
628 Draft Tube Sandblasting and painting 35 14-Sep-15 30-Oct-15 A AC.Lot 3 Draft Tube Sandblasting and painting
A
627 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part 0 31-Jan-16 A AC.Lot 3 TD 343: Lot 2, U4 Draft Tube Area, Start of fixed Part Installation
U4, Stayring
St installation 476 20-Oct-14 A 16-May-16 A 16-May-16 A, U4, Stayring installation
632 Installation of embedded parts 12 20-Oct-14 A 02-Nov-14 A AC.Lot 3 Installation of embedded parts
633 TD 351: Stayring and Pier Nose U4 installation in pit 0 27-Mar-16 AC.Lot 3 TD 351: Stayring and Pier Nose U4 installation in pit
A
635 Stayring installation in pit 25 31-Mar-16 30-Apr-16 A AC.Lot 3 Stayring installation in pit
A
634 Installation of embedded parts for horizontal adjustmen 12 03-May-16 16-May-16 A AC.Lot 3 Installation of embedded parts for horizontal adjustment of generator
A
U4, Turbine
Tu & Generator Main Installation 502 01-May-16 20-Dec-17 A 20-Dec-17 A, U4, Turbine & Generator Main Installation
615 TD 354: Start U4 u/s Transition Zone Concrete Works 0 A
01-May-16 AC.Lot 1 TD 354: Start U4 u/s Transition Zone Concrete Works up to EL. 42.10, 01-May-16 A
A
614 U4, Second Stage Concrete Works U4, EL 27.20 to 42 96 02-May-16 27-Aug-16 A AC.Lot 1 U4, Second Stage Concrete Works U4, EL 27.20 to 42.10, Axes B-C
A
616 TD 359: U4 u/s Transition Zone Concrete Works up to 0 28-Aug-16 A AC.Lot 1 TD 359: U4 u/s Transition Zone Concrete Works up to EL. 42.10 completed,
622 U4, Second Stage(Concrete for Hatch Cover) 6 28-Aug-16 04-Sep-16 A AC.Lot 1 U4, Second Stage(Concrete for Hatch Cover)
A
637 TD 362: Start Turbine and Generator Erection U4 0 26-Sep-16 AC.Lot 3 TD 362: Start Turbine and Generator Erection U4
A
638 Installation Distributor anchoring, distributor & discharg 46 26-Sep-16 20-Nov-16 A AC.Lot 3 Installation Distributor anchoring, distributor & discharge ring
A
612 U4, Second stage Concrete for anchoring (Turbine & 15 21-Nov-16 08-Dec-16 A AC.Lot 1 U4, Second stage Concrete for anchoring (Turbine & Generator Main Installation)
A
642 Main installation: turbine + generator incl. Piping & aux 321 09-Dec-16 20-Dec-17 A AC.Lot 3 Main installation: turbine + generator incl. Piping & auxil
A
641 TD 360: Generator hatch cover installation 0 17-Jan-17 A AC.Lot 3 TD 360: Generator hatch cover installation
640 Generator hatch cover installation 12 17-Jul-17 A 31-Jul-17 A AC.Lot 3 Generator hatch cover installation
639 Sandblasting and painting hatch cover 12 04-Oct-17 A 18-Oct-17 A AC.Lot 3 Sandblasting and painting hatch cover
U4, Trash
Tra Rack installation 347 15-Feb-15 08-Apr-16 A 08-Apr-16 A, U4, Trash Rack installation
645 Installation of embedded parts - 1st stage 25 15-Feb-15 15-Mar-15 A AC.Lot 3 Installation of embedded parts - 1st stage
A
646 Installation of embedded parts - 2nd stage 50 30-Jul-15 A 29-Sep-15 A AC.Lot 3 Installation of embedded parts - 2nd stage
647 Installation of fish beams 50 30-Sep-15 29-Nov-15 A AC.Lot 3 Installation of fish beams
A
644 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Ins 0 02-Nov-15 AC.Lot 3 TD 334: Lot 2 & 3, U4 Inlet Area, Start of fixed Part Installation
A
620 U4, Second Stage(Concrete for Fish Beam) 17 07-Feb-16 27-Feb-16 A AC.Lot 1 U4, Second Stage(Concrete for Fish Beam)
A
648 TR installation 35 28-Feb-16 08-Apr-16 A AC.Lot 3 TR installation
A
U4, Stop
St log U/S 116 16-Jan-16 A 04-Jun-16 A 04-Jun-16 A, U4, Stop log U/S
650 Installation of embedded parts - 1st stage 12 16-Jan-16 A 31-Jan-16 A AC.Lot 2 Installation of embedded parts - 1st stage
651 Installation of embedded parts - 2nd stage (sill beam + 60 01-Feb-16 11-Apr-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
619 U4, Second Stage(Concrete for U/S Stop Log) 29 12-Apr-16 A 19-May-16 A AC.Lot 1 U4, Second Stage(Concrete for U/S Stop Log)
652 Stop log U/S installation 13 19-May-16 04-Jun-16 A AC.Lot 2 Stop log U/S installation
A
U4, Stop
St log D/S (DS Draft Tube Bulkheads ) 83 16-Feb-16 26-May-16 A 26-May-16 A, U4, Stop log D/S (DS Draft Tube Bulkheads )
654 Installation of embedded parts - 1st stage 10 16-Feb-16 28-Feb-16 A AC.Lot 2 Installation of embedded parts - 1st stage
A
655 Installation of embedded parts - 2nd stage (sill beam + 41 29-Feb-16 17-Apr-16 A AC.Lot 2 Installation of embedded parts - 2nd stage (sill beam + side guides)
A
621 U4, Second Stage(Concrete for D/S Stop Log) 17 18-Apr-16 A 11-May-16 A AC.Lot 1 U4, Second Stage(Concrete for D/S Stop Log)
656 Stop log D/S installation 13 11-May-16 26-May-16 A AC.Lot 2 Stop log D/S installation
A
FINISHING W
WORKS 512 01-Aug-16 28-Mar-18 A 28-Mar-18 A, FINISHING WORKS
658 Finishing works 512 A 28-Mar-18 A
01-Aug-16 AC.Lot 1 Finishing works
A
GANTRY CR
CRANES, TRASH R.C.& JIP CRANE 853 16-Apr-15 A 31-Jan-18 A 31-Jan-18 A, GANTRY CRANES, TRASH R.C.& J
PH Main Gantry Crane 407 16-Apr-15 A 22-Aug-16 A 22-Aug-16 A, PH Main Gantry Crane
665 PH Main Gantry Crane Rail on Pier 01 - Extension Bea 105 16-Apr-15 A 20-Aug-15 A AC.Lot 3 PH Main Gantry Crane Rail on Pier 01 - Extension Beam
663 TD 321: PH Main Gantry Crane operational 0 02-May-15 AC.Lot 3 TD 321: PH Main Gantry Crane operational
A
667 PH Main Gantry Crane Pre-assembly 24 07-May-15 04-Jun-15 A AC.Lot 3 PH Main Gantry Crane Pre-assembly
A
661 TD 312: Crane Runway Axes 6-8 ready for Rail Installa 0 04-Jul-15 A AC.Lot 3 TD 312: Crane Runway Axes 6-8 ready for Rail Installation
664 TD 314: Start of PH Main Gantry Crane Erection (Inter 0 20-Aug-15 AC.Lot 3 TD 314: Start of PH Main Gantry Crane Erection (Intermediate Pier/Unit1)
A
A2270 Commissioning and Load-Test 5 20-Sep-15 29-Sep-15 A AC.Lot 3 Commissioning and Load-Test
A
662 PH Main Gantry Crane Installation in unloading Area/ E 27 30-Nov-15 31-Dec-15 A AC.Lot 3 PH Main Gantry Crane Installation in unloading Area/ Extension Beams axis 1
A
666 Pouring fort PH Main G. Crane 24 07-May-16 04-Jun-16 A AC.Lot 1 Pouring fort PH Main G. Crane
A
A2280 Final Acceptance Test 0 22-Aug-16 A AC.Lot 3 Final Acceptance Test
Jib Crane 343 30-Jun-15 A 21-Aug-16 A 21-Aug-16 A, Jib Crane
669 Embedded plates fort Jib crane ( Pier axis 16 ) 22 30-Jun-15 A 28-Jul-15 A AC.Lot 3 Embedded plates fort Jib crane ( Pier axis 16 )
670 Concreteting fort Jib crane ( Pier axis 16 ) 27 28-Jul-15 A 29-Aug-15 A AC.Lot 1 Concreteting fort Jib crane ( Pier axis 16 )
671 Installation of Jib crane ( Pier axis 16 ) 2 29-Aug-15 31-Aug-15 A AC.Lot 3 Installation of Jib crane ( Pier axis 16 )
A
A2290 Commissioning and Load-Test 7 11-Aug-16 20-Aug-16 A AC.Lot 3 Commissioning and Load-Test
A
A2300 Final Acceptance Test 0 21-Aug-16 A
DT Gantry
Gantr Crane 561 21-Feb-16 20-Dec-17 A 20-Dec-17 A, DT Gantry Crane
674 Concreteting for DT Gantry Crane 561 A 20-Dec-17 A
21-Feb-16 AC.Lot 1 Concreteting for DT Gantry Crane
A
675 DT Gantry Crane Erection 25 01-Mar-16 29-Mar-16 A AC.Lot 3 DT Gantry Crane Erection
A
673 DT Gantry Crane Rail Installation 46 02-Mar-16 25-Apr-16 A AC.Lot 3 DT Gantry Crane Rail Installation
A
A2310 Commissioning and Load-Test 9 25-Apr-16 A 09-May-16 A AC.Lot 3 Commissioning and Load-Test
A2320 Final Acceptance Test 0 10-May-16 A AC.Lot 3 Final Acceptance Test
PWH / Bridge
Br Crane 254 10-Apr-17 A 31-Jan-18 A 31-Jan-18 A, PWH / Bridge Crane
677 PWH / Bridge Crane Rail Installation 218 10-Apr-17 A 20-Dec-17 A AC.Lot 3 PWH / Bridge Crane Rail Installation
678 Concreteting fort PWH / Bridge Crane 209 30-Apr-17 A 30-Dec-17 A AC.Lot 1 Concreteting fort PWH / Bridge Crane
679 PWH / Bridge Crane Erection 198 13-Jun-17 A 30-Jan-18 A AC.Lot 3 PWH / Bridge Crane Erection
A2330 Commissioning and Load-Test 9 20-Jan-18 A 30-Jan-18 A AC.Lot 3 Commissioning and Load-Test
A2340 Final Acceptance Test 0 31-Jan-18 A AC.Lot 3 Final Acceptance Test
PH Trash Rack Cleaning Machine TRCM 225 21-Oct-15 A 17-Jul-16 A 17-Jul-16 A, PH Trash Rack Cleaning Machine TRCM

Milestone Lot 1 Lot 2 Page 10 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
681 PWH Trash Conveyor Rail Installation 25 21-Oct-15 A 18-Nov-15 A AC.Lot 3 PWH Trash Conveyor Rail Installation
682 Concreteting fort TRCM 25 04-Nov-15 02-Dec-15 A AC.Lot 1 Concreteting fort TRCM
A
683 PWH Trash Rack Cleaning Machine (2x) Installation 50 18-May-16 17-Jul-16 A AC.Lot 3 PWH Trash Rack Cleaning Machine (2x) Installation
A
ELECTRICA WORKS
ELECTRICAL 517 03-Jan-16 A 13-Sep-17 A 13-Sep-17 A, ELECTRICAL WORKS
685 TD 337: U1 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 337: U1 ready for cable tray installation
686 TD 338: U2 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 338: U2 ready for cable tray installation
687 TD 339: U3 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 339: U3 ready for cable tray installation
688 TD 340: U4 ready for cable tray installation 0 03-Jan-16 A AC.Lot 4 TD 340: U4 ready for cable tray installation
689 Cable Tray installation at level 42.75 and below 244 04-Jan-16 A 30-Oct-16 A AC.Lot 4 Cable Tray installation at level 42.75 and below
690 Installation of cables 494 01-Feb-16 13-Sep-17 A AC.Lot 4 Installation of cables
A
691 U1 - Installation of electrical equipment at level 45.15 a 401 01-Mar-16 26-Jun-17 A AC.Lot 4 U1 - Installation of electrical equipment at level 45.15 and below
A
692 U2 - Installation of electrical equipment at level 45.15 a 395 01-Apr-16 A 20-Jul-17 A AC.Lot 4 U2 - Installation of electrical equipment at level 45.15 and below
693 U3 - Installation of electrical equipment at level 45.15 a 392 01-May-16 14-Aug-17 A AC.Lot 4 U3 - Installation of electrical equipment at level 45.15 and below
A
694 U4 - Installation of electrical equipment at level 45.15 a 393 01-Jun-16 A 13-Sep-17 A AC.Lot 4 U4 - Installation of electrical equipment at level 45.15 and below
TESTING / C
COMMISSIONING & TRIAL OPERATION 471 31-Jan-17 A 02-Aug-18 A 02-Aug-18 A, TESTING / C
Unit 1 471 31-Jan-17 A 02-Aug-18 A 02-Aug-18 A, Unit 1
1321 U1 Tests Lot3 & Lot 4 228 31-Jan-17 A 24-Oct-17 A AC.Lot 3 U1 Tests Lot3 & Lot 4
1317 U1 DT Gate, Intake Stoplogs Commissioning 62 07-Nov-17 18-Jan-18 A AC.Lot 2 U1 DT Gate, Intake Stoplogs Commissioning
A
1322 U1 Commissioning Lot3 & Lot 4 0 14-May-18 14-May-18 A AC.Lot 3 U1 Commissioning Lot3 & Lot 4
A
1323 U1 Trial Operation Lot3 & Lot 4 44 12-Jun-18 A 02-Aug-18 A AC.Lot 3 U1 Trial Operation Lot3 & L
A2560 Effective Date TOC,TURBINE, GENERATOR UNIT 1, 0 02-Aug-18 A AC.Lot 3 Effective Date TOC,TURB
Unit 2 285 01-Jun-17 A 30-Apr-18 A 30-Apr-18 A, Unit 2
1324 U2 Tests Lot3 & Lot 4 138 01-Jun-17 A 09-Nov-17 A AC.Lot 3 U2 Tests Lot3 & Lot 4
1325 U2 Commissioning Lot3 & Lot 4 114 09-Nov-17 22-Mar-18 A AC.Lot 3 U2 Commissioning Lot3 & Lot 4
A
1318 U2 DT Gate, Intake Stoplogs Commissioning 52 13-Nov-17 13-Jan-18 A AC.Lot 2 U2 DT Gate, Intake Stoplogs Commissioning
A
1326 U2 Trial Operation Lot3 & Lot 4 32 24-Mar-18 30-Apr-18 A AC.Lot 3 U2 Trial Operation Lot3 & Lot 4
A
A2530 Effective Date TOC,TURBINE, GENERATOR UNIT 2, 0 30-Apr-18 A AC.Lot 3 Effective Date TOC,TURBINE, GENER
Unit 3 324 23-May-17 05-Jun-18 A 05-Jun-18 A, Unit 3
1327 U3 Tests Lot3 & Lot 4 167 23-May-17A 04-Dec-17 A AC.Lot 3 U3 Tests Lot3 & Lot 4
A
1319 U3 DT Gate, Intake Stoplogs Commissioning 35 16-Dec-17 25-Jan-18 A AC.Lot 2 U3 DT Gate, Intake Stoplogs Commissioning
A
1328 U3 Commissioning Lot3 & Lot 4 58 28-Jan-18 A 05-Apr-18 A AC.Lot 3 U3 Commissioning Lot3 & Lot 4
1329 U3 Trial Operation Lot3 & Lot 4 55 02-Apr-18 A 05-Jun-18 A AC.Lot 3 U3 Trial Operation Lot3 & Lot 4
A2540 Effective Date TOC,TURBINE, GENERATOR UNIT 3, 0 05-Jun-18 A AC.Lot 3 Effective Date TOC,TURBINE, GE
Unit 4 327 28-May-17 13-Jun-18 A 13-Jun-18 A, Unit 4
1330 U4 Tests Lot3 & Lot 4 237 28-May-17 28-Feb-18 A AC.Lot 3 U4 Tests Lot3 & Lot 4
A
1320 U4 DT Gate, Intake Stoplogs Commissioning 17 06-Feb-18 26-Feb-18 A AC.Lot 2 U4 DT Gate, Intake Stoplogs Commissioning
A
1331 U4 Commissioning Lot3 & Lot 4 42 28-Feb-18 18-Apr-18 A AC.Lot 3 U4 Commissioning Lot3 & Lot 4
A
1332 U4 Trial Operation Lot3 & Lot 4 48 18-Apr-18 A 13-Jun-18 A AC.Lot 3 U4 Trial Operation Lot3 & Lot 4
A2550 Effective Date TOC,TURBINE, GENERATOR UNIT 4, 0 13-Jun-18 A AC.Lot 3 Effective Date TOC,TURBINE, G
SLUICEWAY A
AND ABUTMENT PIERS 1214 01-Apr-14 A 28-Mar-18 A 28-Mar-18 A, SLUICEWAY AND ABUTMEN
ABUTMENT PIER, AXIS 16 657 08-Apr-14 A 13-Jun-16 A 13-Jun-16 A, ABUTMENT PIER, AXIS 16
699 d/s Part - Slab 7 08-Apr-14 A 15-Apr-14 A AC.Lot 1 d/s Part - Slab
697 Central part - slab 58 15-Apr-14 A 25-Jun-14 A AC.Lot 1 Central part - slab
698 Central Part - Superstructure 312 01-Jul-14 A 13-Jul-15 A AC.Lot 1 Central Part - Superstructure
700 d/s Part - Superstructure 450 16-Dec-14 13-Jun-16 A AC.Lot 1 d/s Part - Superstructure
A
701 Main Gantry Crane Extension Beam Axis 16 8 01-Nov-15 10-Nov-15 A AC.Lot 1 Main Gantry Crane Extension Beam Axis 16
A
702 Auxiliary Building 65 05-Dec-15 21-Feb-16 A AC.Lot 1 Auxiliary Building
A
703 electrical works incl. commissioning 123 02-Jan-16 A 29-May-16 A AC.Lot 4 electrical works incl. commissioning
704 TD 270: Auxiliary Building concrete Works complete 0 31-Jan-16 A AC.Lot 1 TD 270: Auxiliary Building concrete Works complete,
ABUTMENT PIER, AXIS 1 628 01-Apr-14 A 03-May-16 A 03-May-16 A, ABUTMENT PIER, AXIS 1
708 d/s Part - Slab 12 01-Apr-14 A 15-Apr-14 A AC.Lot 1 d/s Part - Slab
706 Central part - slab 49 15-Apr-14 A 15-Jun-14 A AC.Lot 1 Central part - slab
707 Central Part - Superstructure 497 16-Apr-14 A 12-Dec-15 A AC.Lot 1 Central Part - Superstructure
709 US & DS Part - Superstructure 606 29-Apr-14 A 03-May-16 A AC.Lot 1 US & DS Part - Superstructure
710 Main Gantry Crane Extension Beam Axis 1 17 25-Mar-15 16-Apr-15 A AC.Lot 1 Main Gantry Crane Extension Beam Axis 1
A
711 TD 213: Main Gantry Crane Extension Beams Comple 0 18-Apr-15 A AC.Lot 1 TD 213: Main Gantry Crane Extension Beams Complete,
SLUICEWAY AXES 13-16
SLUICEWAY, 512 18-Sep-14 31-May-16 A 31-May-16 A, SLUICEWAY, AXES 13-16
GENERAL 512 18-Sep-14 31-May-16 A 31-May-16 A, GENERAL
Lot 1 / Concrete Works 512 18-Sep-14 31-May-16 A 31-May-16 A, Lot 1 / Concrete Works
722 TD 202: Start SLW - Axes 13-16 Concrete Works 0 A
18-Sep-14 AC.Lot 1 TD 202: Start SLW - Axes 13-16 Concrete Works, 18-Sep-14 A
A
716 Standard Pier 09, Axis 15 First Phase (Trun. Area On 146 20-Sep-14 15-Mar-15 A AC.Lot 1 Standard Pier 09, Axis 15 First Phase (Trun. Area On Hold)
A
723 Standard Pier 10, Axis 16 First Phase (Trun. Area On 131 10-Oct-14 A 15-Mar-15 A AC.Lot 1 Standard Pier 10, Axis 16 First Phase (Trun. Area On Hold)
718 Standard Pier 08, Axis 14 First Phase (Trun. Area On 139 24-Nov-14 11-May-15 A AC.Lot 1 Standard Pier 08, Axis 14 First Phase (Trun. Area On Hold)
A
715 Standard Pier 10, Axis 16 Second Phase 123 17-Mar-15 13-Aug-15 A AC.Lot 1 Standard Pier 10, Axis 16 Second Phase
A
721 Standard Pier 07, Axis 13 First Phase (Trun. Area On 51 07-Apr-15 A 09-Jun-15 A AC.Lot 1 Standard Pier 07, Axis 13 First Phase (Trun. Area On Hold)
717 Standard Pier 09, Axis 15 Second Phase 26 16-Apr-15 A 17-May-15 A AC.Lot 1 Standard Pier 09, Axis 15 Second Phase
720 Standard Pier 08, Axis 14 Second Phase 72 15-May-15 10-Aug-15 A AC.Lot 1 Standard Pier 08, Axis 14 Second Phase
A
719 Standard Pier 07, Axis 13 Second Phase 160 12-Jun-15 A 24-Dec-15 A AC.Lot 1 Standard Pier 07, Axis 13 Second Phase
725 Downstream Slab / between axes ( 16:13 ) 98 03-Feb-16 31-May-16 A AC.Lot 1 Downstream Slab / between axes ( 16:13 )
A
Lot 2 //Fixed parts installation 265 14-Mar-15 31-Jan-16 A 31-Jan-16 A, Lot 2 /Fixed parts installation
731 Trunnion installation Pier 10 69 14-Mar-15 06-Jun-15 A AC.Lot 2 Trunnion installation Pier 10
A
732 Trunnion installation Pier 09 20 14-Mar-15 06-Apr-15 A AC.Lot 2 Trunnion installation Pier 09
A
727 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 2 TD 203: Pier 10, Axis 16, Access Lot 2, Trunnion Erection
A
729 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erec 0 15-Mar-15 AC.Lot 2 TD 204: Pier 09, Axis 15, Access Lot 2, Trunnion Erection
A

Milestone Lot 1 Lot 2 Page 11 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
734 Trunnion installation Pier 08 26 14-May-15 14-Jun-15 A AC.Lot 2 Trunnion installation Pier 08
A
733 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erec 0 17-May-15 AC.Lot 2 TD 206: Pier 08, Axis 14, Access Lot 2, Trunnion Erection
A
728 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erec 0 16-Jun-15 A AC.Lot 2 TD 209: Pier 07, Axis 13, Access Lot 2, Trunnion Erection
735 Cylinder Support installation Pier 09 38 15-Dec-15 31-Jan-16 A AC.Lot 2 Cylinder Support installation Pier 09
A
736 Cylinder Support installation Pier 08 27 28-Dec-15 31-Jan-16 A AC.Lot 2 Cylinder Support installation Pier 08
A
730 Cylinder Support installation Pier 07 17 10-Jan-16 A 31-Jan-16 A AC.Lot 2 Cylinder Support installation Pier 07
737 Trunnion installation Pier 07 17 10-Jan-16 A 31-Jan-16 A AC.Lot 2 Trunnion installation Pier 07
738 Cylinder Support installation Pier 10 17 10-Jan-16 A 31-Jan-16 A AC.Lot 2 Cylinder Support installation Pier 10
BAY 8, AX
AXES 15-16 298 01-Jun-15 A 28-May-16 A 28-May-16 A, BAY 8, AXES 15-16
Stop LLogs ( D/s & U/s ) 124 29-Dec-15 28-May-16 A 28-May-16 A, Stop Logs ( D/s & U/s )
745 Sill beam installation (for stop log D/S) 90 29-Dec-15A 14-Apr-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
742 Sill beam installation (for stop log U/S) 12 13-Jan-16 A 27-Jan-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
744 Side guides installation (for stop log D/S) 79 13-Jan-16 A 15-Apr-16 A AC.Lot 2 Side guides installation (for stop log D/S)
741 Side guides installation (for stop log U/S) 25 28-Jan-16 A 25-Feb-16 A AC.Lot 2 Side guides installation (for stop log U/S)
749 2nd Stage Concrete, Bay 8 for US/Stop Logs 46 27-Feb-16 20-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 8 for US/Stop Logs
A
750 2nd Stage Concrete, Bay 8 for D/S Stop Logs 18 15-Apr-16 A 10-May-16 A AC.Lot 1 2nd Stage Concrete, Bay 8 for D/S Stop Logs
751 TD 222: Bay 8, 2nd Stage Concrete Works complete 0 11-May-16 AC.Lot 1 TD 222: Bay 8, 2nd Stage Concrete Works complete, 11-May-16 A
A
743 Stop log U/S installation 11 15-May-16 28-May-16 A AC.Lot 2 Stop log U/S installation
A
746 Stop log D/S installation 11 15-May-16 28-May-16 A AC.Lot 2 Stop log D/S installation
A
Radial Gate 94 01-Jun-15 A 21-Sep-15 A 21-Sep-15 A, Radial Gate
754 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts 0 01-Jun-15 A AC.Lot 2 TD 210: Bay 8, Axes 15-16, Access Lot 2, fixed Parts Installation
759 Side guides installation (for radial gate) 32 07-Jun-15 A 14-Jul-15 A AC.Lot 2 Side guides installation (for radial gate)
760 Sill beam installation (for radial gate) 12 30-Jun-15 A 14-Jul-15 A AC.Lot 2 Sill beam installation (for radial gate)
761 TD 220: Bay 8, Axes 15-16, fixed Parts Installation Co 0 14-Jul-15 A AC.Lot 2 TD 220: Bay 8, Axes 15-16, fixed Parts Installation Complete
752 2nd Stage Concrete, Bay 8 for Radial Gate Installation 26 15-Jul-15 A 17-Aug-15 A AC.Lot 1 2nd Stage Concrete, Bay 8 for Radial Gate Installation
755 Pre erection of radial gate in storage yard, Bay 8 23 15-Jul-15 A 13-Aug-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 8
756 TD 223: Bay 8, Start of Radial Gate Erection 0 16-Aug-15 AC.Lot 2 TD 223: Bay 8, Start of Radial Gate Erection
A
757 Radial gate erection, Bay 8 24 17-Aug-15 14-Sep-15 A AC.Lot 2 Radial gate erection, Bay 8
A
758 TD 227: Bay 8, Radial Gate Erection Complete 0 21-Sep-15 AC.Lot 2 TD 227: Bay 8, Radial Gate Erection Complete
A
Beams for gantry crane & Service bridge 158 22-Jun-15 A 31-Dec-15 A 31-Dec-15 A, Beams for gantry crane & Service bridge
766 Service Bridge, Bay 8 12 22-Jun-15 A 06-Jul-15 A AC.Lot 1 Service Bridge, Bay 8
763 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam 0 18-Jul-15 A AC.Lot 2 TD 230: Bay 8, Start of SLW Gantry Crane u/s Beam
765 u/s Gantry Crane Beam, Bay 8 11 27-Jul-15 A 09-Aug-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 8
764 d/s Gantry Crane Beam, Bay 8 & Precast Trash Conve 11 23-Aug-15 05-Sep-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 8 & Precast Trash Conveyor channel
A
768 Installation of precast elements U/S G.Crane 4 22-Oct-15 A 27-Oct-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
769 Installation of precast elements D/S ( Service Bridge & 7 28-Oct-15 A 05-Nov-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
767 Gantry crane rails installation 36 07-Nov-15 19-Dec-15 A AC.Lot 2 Gantry crane rails installation
A
748 2nd Stage Concrete, Bay 8 for G. Crane Rails 11 19-Dec-15 31-Dec-15 A AC.Lot 1 2nd Stage Concrete, Bay 8 for G. Crane Rails
A
Electri
Electrical works 158 06-Sep-15 16-Mar-16 A 16-Mar-16 A, Electrical works
771 Hydraulic SLW radial gate, Bay 8 135 06-Sep-15 18-Feb-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 8
A
772 Electrical SLW radial gate, Bay 8 158 06-Sep-15 16-Mar-16 A AC.Lot 4 Electrical SLW radial gate, Bay 8
A
BAY 7, AX
AXES 14-15 253 24-Jul-15 A 26-May-16 A 26-May-16 A, BAY 7, AXES 14-15
Stop LLogs ( D/s & U/s ) 110 14-Jan-16 A 26-May-16 A 26-May-16 A, Stop Logs ( D/s & U/s )
775 Side guides installation (for stop log U/S) 42 14-Jan-16 A 05-Mar-16 A AC.Lot 2 Side guides installation (for stop log U/S)
776 Sill beam installation (for stop log U/S) 42 14-Jan-16 A 05-Mar-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
778 Side guides installation (for stop log D/S) 30 05-Feb-16 10-Mar-16 A AC.Lot 2 Side guides installation (for stop log D/S)
A
779 Sill beam installation (for stop log D/S) 48 10-Feb-16 06-Apr-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
784 2nd Stage Concrete, Bay 7 for US/Stop Logs 49 23-Feb-16 20-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 7 for US/Stop Logs
A
785 2nd Stage Concrete, Bay 7 for DS/Stop Logs 18 15-Apr-16 A 10-May-16 A AC.Lot 1 2nd Stage Concrete, Bay 7 for DS/Stop Logs
782 TD 228: Bay 7, 2nd Stage Concrete Works complete 0 11-May-16 A AC.Lot 1 TD 228: Bay 7, 2nd Stage Concrete Works complete,
780 Stop log D/S installation 11 14-May-16 26-May-16 A AC.Lot 2 Stop log D/S installation
A
777 Stop log U/S installation 9 16-May-16 26-May-16 A AC.Lot 2 Stop log U/S installation
A
Radial Gate 103 24-Jul-15 A 26-Nov-15 A 26-Nov-15 A, Radial Gate
788 TD 215: Bay 7, Axes 15-16, Access Lot 2, fixed Parts 0 24-Jul-15 A AC.Lot 2 TD 215: Bay 7, Axes 15-16, Access Lot 2, fixed Parts Installation
791 Side guides installation (for radial gate) 17 25-Jul-15 A 13-Aug-15 A AC.Lot 2 Side guides installation (for radial gate)
792 Sill beam installation (for radial gate) 17 25-Jul-15 A 13-Aug-15 A AC.Lot 2 Sill beam installation (for radial gate)
786 2nd Stage Concrete, Bay 7 for Radial Gate Installation 2 15-Aug-15 17-Aug-15 A AC.Lot 1 2nd Stage Concrete, Bay 7 for Radial Gate Installation
A
789 Pre erection of radial gate in storage yard, Bay 7 37 03-Sep-15 21-Oct-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 7
A
790 TD 231: Bay 7, Start of Radial Gate Erection 0 03-Sep-15 AC.Lot 2 TD 231: Bay 7, Start of Radial Gate Erection
A
795 Radial gate erection, Bay 7 67 03-Sep-15 26-Nov-15 A AC.Lot 2 Radial gate erection, Bay 7
A
793 TD 225: Bay 7, Axes 14-15, fixed Parts Installation Co 0 17-Sep-15 A AC.Lot 2 TD 225: Bay 7, Axes 14-15, fixed Parts Installation Complete
794 TD 236: Bay 7, Radial Gate Erection Complete 0 26-Nov-15 A AC.Lot 2 TD 236: Bay 7, Radial Gate Erection Complete
Beams for gantry crane & Service bridge 206 08-Aug-15 12-Apr-16 A 12-Apr-16 A, Beams for gantry crane & Service bridge
801 Service Bridge, Bay 7 24 08-Aug-15 05-Sep-15 A AC.Lot 1 Service Bridge, Bay 7
A
797 TD 239: Bay 7, Start of SLW Gantry Crane u/s Beam 0 13-Sep-15 AC.Lot 2 TD 239: Bay 7, Start of SLW Gantry Crane u/s Beam
A
798 d/s Gantry Crane Beam Bay 7 & Precast Trash Conve 10 18-Sep-15 05-Oct-15 A AC.Lot 1 d/s Gantry Crane Beam Bay 7 & Precast Trash Conveyor channel
A
799 u/s Gantry Crane Beam, Bay 7 10 18-Sep-15 05-Oct-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 7
A
802 Installation of precast elements U/S G.Crane 4 08-Dec-15 13-Dec-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
803 Installation of precast elements D/S ( Service Bridge & 12 17-Dec-15 31-Dec-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
A
800 Gantry crane rails installation 37 17-Feb-16 31-Mar-16 A AC.Lot 2 Gantry crane rails installation
A
783 2nd Stage Concrete, Bay 7 for G. Crane Rails 41 24-Feb-16 12-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 7 for G. Crane Rails
A
Electri
Electrical works 59 10-Jan-16 A 20-Mar-16 A 20-Mar-16 A, Electrical works
805 Hydraulic SLW radial gate, Bay 7 36 10-Jan-16 A 22-Feb-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 7
806 Electrical SLW radial gate, Bay 7 59 10-Jan-16 A 20-Mar-16 A AC.Lot 4 Electrical SLW radial gate, Bay 7

Milestone Lot 1 Lot 2 Page 12 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:45

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
BAY 6, AX
AXES 13-14 295 06-Jun-15 A 29-May-16 A 29-May-16 A, BAY 6, AXES 13-14
Stop LLogs ( D/s & U/s ) 103 25-Jan-16 A 29-May-16 A 29-May-16 A, Stop Logs ( D/s & U/s )
809 Side guides installation (for stop log U/S) 38 25-Jan-16 A 10-Mar-16 A AC.Lot 2 Side guides installation (for stop log U/S)
810 Sill beam installation (for stop log U/S) 38 25-Jan-16 A 10-Mar-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
812 Side guides installation (for stop log D/S) 46 25-Feb-16 19-Apr-16 A AC.Lot 2 Side guides installation (for stop log D/S)
A
813 Sill beam installation (for stop log D/S) 46 25-Feb-16 19-Apr-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
817 2nd Stage Concrete, Bay 6 US/for Stop Logs 38 13-Mar-16 27-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 6 US/for Stop Logs
A
818 2nd Stage Concrete, Bay 6 for DS/Stop Logs 22 21-Apr-16 A 21-May-16 A AC.Lot 1 2nd Stage Concrete, Bay 6 for DS/Stop Logs
811 Stop log U/S installation 11 16-May-16 29-May-16 A AC.Lot 2 Stop log U/S installation
A
814 Stop log D/S installation 11 16-May-16 29-May-16 A AC.Lot 2 Stop log D/S installation
A
819 TD 237: Bay 6, 2nd Stage Concrete Works complete 0 21-May-16 A AC.Lot 1 TD 237: Bay 6, 2nd Stage Concrete Works complete,
Radial Gate 93 02-Sep-15 24-Dec-15 A 24-Dec-15 A, Radial Gate
822 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts 0 A
02-Sep-15 AC.Lot 2 TD 218: Bay 6, Axes 13-14, Access Lot 2, fixed Parts Installation
A
827 Side guides installation (for radial gate) 26 02-Sep-15 08-Oct-15 A AC.Lot 2 Side guides installation (for radial gate)
A
828 Sill beam installation (for radial gate) 26 02-Sep-15 08-Oct-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
820 2nd Stage Concrete, Bay 6 for Radial Gate Installation 17 09-Oct-15 A 29-Oct-15 A AC.Lot 1 2nd Stage Concrete, Bay 6 for Radial Gate Installation
829 TD 232: Bay 6, Axes 13-14, fixed Parts Installation Co 0 09-Oct-15 A AC.Lot 2 TD 232: Bay 6, Axes 13-14, fixed Parts Installation Complete
824 Pre erection of radial gate in storage yard, Bay 6 24 21-Oct-15 A 18-Nov-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 6
825 Radial gate erection, Bay 6 24 29-Oct-15 A 26-Nov-15 A AC.Lot 2 Radial gate erection, Bay 6
823 TD 240: Bay 6, Start of Radial Gate Erection 0 20-Nov-15 A AC.Lot 2 TD 240: Bay 6, Start of Radial Gate Erection
826 TD 246: Bay 6, Radial Gate Erection Complete 0 24-Dec-15 A AC.Lot 2 TD 246: Bay 6, Radial Gate Erection Complete
Beams for gantry crane & Service bridge 268 06-Jun-15 A 24-Apr-16 A 24-Apr-16 A, Beams for gantry crane & Service bridge
831 TD 248: Bay 6, Start of SLW Gantry Crane u/s Beam 0 06-Jun-15 A AC.Lot 1 TD 248: Bay 6, Start of SLW Gantry Crane u/s Beam, 06-Jun-15 A
833 u/s Gantry Crane Beam, Bay 6 13 08-Oct-15 A 24-Oct-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 6
834 Service Bridge, Bay 6 25 15-Nov-15 14-Dec-15 A AC.Lot 1 Service Bridge, Bay 6
A
836 Installation of precast elements U/S G.Crane 5 10-Dec-15 16-Dec-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
832 d/s Gantry Crane Beam, Bay 6 & Precast Trash Conve 7 15-Dec-15 23-Dec-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 6 & Precast Trash Conveyor channel
A
837 Installation of precast elements D/S ( Service Bridge & 11 02-Jan-16 A 16-Jan-16 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
835 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 03-Jan-16 A AC.Lot 2 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation
838 Gantry crane rails installation 50 17-Feb-16 16-Apr-16 A AC.Lot 2 Gantry crane rails installation
A
816 2nd Stage Concrete, Bay 6 for G. Crane Rails 5 18-Apr-16 A 24-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 6 for G. Crane Rails
Electri
Electrical works 77 29-Jan-16 A 30-Apr-16 A 30-Apr-16 A, Electrical works
841 TD 267: SLW, Axes 13-16, Access Lot 4, Cable Tray I 0 29-Jan-16 A AC.Lot 4 TD 267: SLW, Axes 13-16, Access Lot 4, Cable Tray Installation
840 Hydraulic SLW radial gate, Bay 6 36 30-Jan-16 A 12-Mar-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 6
842 Electrical SLW radial gate, Bay 6 76 31-Jan-16 A 30-Apr-16 A AC.Lot 4 Electrical SLW radial gate, Bay 6
SLUICEWAY AXES 1-6
SLUICEWAY, 543 01-Aug-14 18-May-16 A 18-May-16 A, SLUICEWAY, AXES 1-6
GENERAL 543 01-Aug-14 18-May-16 A 18-May-16 A, GENERAL
Lot 1 / Concrete Works 543 01-Aug-14 18-May-16 A 18-May-16 A, Lot 1 / Concrete Works
846 TD 201: Start SLW - Axes 01-06 Concrete Works 0 A
01-Aug-14 AC.Lot 1 TD 201: Start SLW - Axes 01-06 Concrete Works, 01-Aug-14 A
A
852 Standard Pier 1, Axis 1 First Phase (Trun. Area On Ho 113 02-Aug-14 15-Dec-14 A AC.Lot 1 Standard Pier 1, Axis 1 First Phase (Trun. Area On Hold)
A
854 Standard Pier 2, Axis 2 First Phase (Trun. Area On Ho 84 20-Sep-14 30-Dec-14 A AC.Lot 1 Standard Pier 2, Axis 2 First Phase (Trun. Area On Hold)
A
858 Standard Pier 3, Axis 3 First Phase (Trun. Area On Ho 96 15-Oct-14 A 07-Feb-15 A AC.Lot 1 Standard Pier 3, Axis 3 First Phase (Trun. Area On Hold)
856 Standard Pier 4, Axis 4 First Phase (Trun. Area On Ho 124 16-Oct-14 A 11-Mar-15 A AC.Lot 1 Standard Pier 4, Axis 4 First Phase (Trun. Area On Hold)
853 Standard Pier 1, Axis 1 Second Phase 86 16-Dec-14 29-Mar-15 A AC.Lot 1 Standard Pier 1, Axis 1 Second Phase
A
857 Standard Pier 2, Axis 2 Second Phase 73 31-Dec-14 29-Mar-15 A AC.Lot 1 Standard Pier 2, Axis 2 Second Phase
A
862 Standard Pier 5, Axis 5 First Phase (Trun. Area On Ho 43 10-Jan-15 A 02-Mar-15 A AC.Lot 1 Standard Pier 5, Axis 5 First Phase (Trun. Area On Hold)
860 Standard Pier 6, Axis 6 First Phase (Trun. Area On Ho 51 15-Jan-15 A 17-Mar-15 A AC.Lot 1 Standard Pier 6, Axis 6 First Phase (Trun. Area On Hold)
855 Standard Pier 3, Axis 3 Second Phase 128 08-Feb-15 11-Jul-15 A AC.Lot 1 Standard Pier 3, Axis 3 Second Phase
A
861 Standard Pier 4, Axis 4 Second Phase 145 23-Feb-15 17-Aug-15 A AC.Lot 1 Standard Pier 4, Axis 4 Second Phase
A
859 Standard Pier 5, Axis 5 Second Phase 171 03-Mar-15 28-Sep-15 A AC.Lot 1 Standard Pier 5, Axis 5 Second Phase
A
847 Standard Pier 6, Axis 6 Second Phase 215 18-Mar-15 06-Dec-15 A AC.Lot 1 Standard Pier 6, Axis 6 Second Phase
A
849 MS 1-04: SLW- Abutment & Standard Pier Axis 06 Firs 0 16-Jul-15 A AC.Lot 1 MS 1-04: SLW- Abutment & Standard Pier Axis 06 First Stage Concrete Works complete (Revised New Sequence),
848 Downstream Slab / First phase between axes ( 1:3 ) 105 14-Dec-15 17-Apr-16 A AC.Lot 1 Downstream Slab / First phase between axes ( 1:3 )
A
851 Downstream Slab / Second phase between axes ( 4:6 90 01-Feb-16 18-May-16 A AC.Lot 1 Downstream Slab / Second phase between axes ( 4:6 )
A
Lot 2 //Fixed parts installation 301 15-Dec-14 15-Dec-15 A 15-Dec-15 A, Lot 2 /Fixed parts installation
864 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erectio 0 15-Dec-14 AC.Lot 2 TD 205: Pier 1, Axis 1, Access Lot 2, Trunnion Erection (revised Sequence)
A
870 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erectio 0 15-Dec-14 AC.Lot 2 TD 208: Pier 2, Axis 2, Access Lot 2, Trunnion Erection (revised Sequence)
A
869 Trunnion installation Pier 1 18 18-Dec-14 10-Jan-15 A AC.Lot 2 Trunnion installation Pier 1
A
871 Trunnion installation Pier 2 43 30-Dec-14 21-Feb-15 A AC.Lot 2 Trunnion installation Pier 2
A
872 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erectio 0 14-Jan-15 A AC.Lot 2 TD 211: Pier 3, Axis 3, Access Lot 2, Trunnion Erection (revised Sequence)
873 Trunnion installation Pier 3 21 07-Feb-15 03-Mar-15 A AC.Lot 2 Trunnion installation Pier 3
A
874 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erectio 0 15-Feb-15 AC.Lot 2 TD 216: Pier 4, Axis 4, Access Lot 2, Trunnion Erection (revised Sequence)
A
867 Trunnion installation Pier 4 52 21-Feb-15 26-Apr-15 A AC.Lot 2 Trunnion installation Pier 4
A
868 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erectio 0 15-Mar-15 AC.Lot 2 TD 219: Pier 5, Axis 5, Access Lot 2, Trunnion Erection (revised Sequence)
A
877 Trunnion installation Pier 5 43 24-Mar-15 17-May-15 A AC.Lot 2 Trunnion installation Pier 5
A
880 Trunnion installation Pier 6 27 14-Apr-15 A 17-May-15 A AC.Lot 2 Trunnion installation Pier 6
878 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erectio 0 15-Apr-15 A AC.Lot 2 TD 224: Pier 6, Axis 6, Access Lot 2, Trunnion Erection (revised Sequence)
875 Cylinder Support installation Pier 1 101 01-Jun-15 A 04-Oct-15 A AC.Lot 2 Cylinder Support installation Pier 1
865 Cylinder Support installation Pier 2 133 13-Jun-15 A 23-Nov-15 A AC.Lot 2 Cylinder Support installation Pier 2
866 Cylinder Support installation Pier 3 84 12-Aug-15 24-Nov-15 A AC.Lot 2 Cylinder Support installation Pier 3
A
876 Cylinder Support installation Pier 4 52 19-Sep-15 24-Nov-15 A AC.Lot 2 Cylinder Support installation Pier 4
A
879 Cylinder Support installation Pier 5 43 04-Oct-15 A 24-Nov-15 A AC.Lot 2 Cylinder Support installation Pier 5
881 Cylinder Support installation Pier 6 13 30-Nov-15 15-Dec-15 A AC.Lot 2 Cylinder Support installation Pier 6
A
BAY 1, AX
AXES 1-2 353 01-Mar-15 02-May-16 A 02-May-16 A, BAY 1, AXES 1-2
A
Milestone Lot 1 Lot 2 Page 13 of 19
Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
Stop L
Logs ( D/s & U/s ) 201 31-Aug-15 02-May-16 A 02-May-16 A, Stop Logs ( D/s & U/s )
884 Sill beam installation (for stop log D/S) 24 A
31-Aug-15 01-Oct-15 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
885 Side guides installation (for stop log D/S) 24 31-Aug-15 01-Oct-15 A AC.Lot 2 Side guides installation (for stop log D/S)
A
886 Sill beam installation (for stop log U/S) 32 20-Sep-15 02-Nov-15 A AC.Lot 2 Sill beam installation (for stop log U/S)
A
887 Side guides installation (for stop log U/S) 32 20-Sep-15 02-Nov-15 A AC.Lot 2 Side guides installation (for stop log U/S)
A
895 2nd Stage Concrete Bay 1 for DS/Stop Logs 41 01-Oct-15 A 21-Nov-15 A AC.Lot 1 2nd Stage Concrete Bay 1 for DS/Stop Logs
893 2nd Stage Concrete Bay 1 for US/Stop Logs 20 03-Nov-15 26-Nov-15 A AC.Lot 1 2nd Stage Concrete Bay 1 for US/Stop Logs
A
891 TD 233: Bay 1, 2nd Stage Concrete Works complete ( 0 26-Nov-15 A AC.Lot 1 TD 233: Bay 1, 2nd Stage Concrete Works complete (revised Sequence),
888 Stop log U/S installation 12 16-Apr-16 A 02-May-16 A AC.Lot 2 Stop log U/S installation
889 Stop log D/S installation 12 16-Apr-16 A 02-May-16 A AC.Lot 2 Stop log D/S installation
Radial Gate 95 01-Mar-15 23-Jun-15 A 23-Jun-15 A, Radial Gate
897 TD 217: Bay 1, Access Lot 2, fixed Parts Installation (r 0 01-Mar-15 AC.Lot 2 TD 217: Bay 1, Access Lot 2, fixed Parts Installation (revised Sequence)
A
898 Side guides installation (for radial gate) 31 29-Mar-15 07-May-15 A AC.Lot 2 Side guides installation (for radial gate)
A
899 Sill beam installation (for radial gate) 31 29-Mar-15 07-May-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
900 TD 229: Bay 1, Axes 1-2, fixed Parts Installation Comp 0 16-Apr-15 A AC.Lot 2 TD 229: Bay 1, Axes 1-2, fixed Parts Installation Complete (revised Sequence)
892 2nd Stage Concrete Bay 1 for Radial Gate Installation 15 08-May-15 26-May-15 A AC.Lot 1 2nd Stage Concrete Bay 1 for Radial Gate Installation
A
902 TD 234: Bay 1, Start of Radial Gate Erection (revised S 0 16-May-15 AC.Lot 2 TD 234: Bay 1, Start of Radial Gate Erection (revised Sequence)
A
901 Pre erection of radial gate in storage yard, Bay 1 24 26-May-15 23-Jun-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 1
A
903 Radial gate erection, Bay 1 24 26-May-15 23-Jun-15 A AC.Lot 2 Radial gate erection, Bay 1
A
904 TD 241: Bay 1, Radial Gate Erection Complete (revise 0 16-Jun-15 A AC.Lot 2 TD 241: Bay 1, Radial Gate Erection Complete (revised Sequence)
Beams for gantry crane & Service bridge 206 09-Mar-15 16-Nov-15 A 16-Nov-15 A, Beams for gantry crane & Service bridge
909 Service Bridge, Bay 1 18 09-Mar-15 30-Mar-15 A AC.Lot 1 Service Bridge, Bay 1
A
908 U/S Gantry Crane Beam, Bay 1 10 16-Mar-15 28-Mar-15 A AC.Lot 1 U/S Gantry Crane Beam, Bay 1
A
907 D/S Gantry Crane Beam, Bay 1 8 07-Apr-15 A 19-Apr-15 A AC.Lot 1 D/S Gantry Crane Beam, Bay 1
910 Installation of precast elements D/S ( Service Bridge & 8 17-Jun-15 A 27-Jun-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
911 Installation of precast elements U/S G.Crane 6 15-Aug-15 22-Aug-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
906 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (r 0 02-Sep-15 AC.Lot 2 TD 243: Bay 1 Start of SLW Gantry Crane u/s Beam (revised Sequence)
A
912 Gantry crane rails installation 23 03-Sep-15 05-Oct-15 A AC.Lot 2 Gantry crane rails installation
A
894 2nd Stage Concrete Bay 1 for G. Crane Rails 5 10-Nov-15 16-Nov-15 A AC.Lot 1 2nd Stage Concrete Bay 1 for G. Crane Rails
A
Electri
Electrical works 162 01-Jul-15 A 16-Jan-16 A 16-Jan-16 A, Electrical works
915 Electrical SLW radial gate, Bay 1 35 01-Jul-15 A 13-Aug-15 A AC.Lot 4 Electrical SLW radial gate, Bay 1
914 Hydraulic SLW radial gate, Bay 1 86 05-Oct-15 A 16-Jan-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 1
BAY 2, AX
AXES 2-3 333 29-Mar-15 08-May-16 A 08-May-16 A, BAY 2, AXES 2-3
Stop LLogs ( D/s & U/s ) 180 03-Oct-15 A 08-May-16 A 08-May-16 A, Stop Logs ( D/s & U/s )
918 Side guides installation (for stop log U/S) 180 03-Oct-15 A 08-May-16 A AC.Lot 2 Side guides installation (for stop log U/S)
919 Sill beam installation (for stop log U/S) 30 03-Oct-15 A 09-Nov-15 A AC.Lot 2 Sill beam installation (for stop log U/S)
928 2nd Stage Concrete Bay 2 for US/Stop Logs 17 10-Nov-15 30-Nov-15 A AC.Lot 1 2nd Stage Concrete Bay 2 for US/Stop Logs
A
921 Side guides installation (for stop log D/S) 56 12-Nov-15 18-Jan-16 A AC.Lot 2 Side guides installation (for stop log D/S)
A
922 Sill beam installation (for stop log D/S) 56 12-Nov-15 18-Jan-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
927 2nd Stage Concrete Bay 2 for DS/Stop Logs 37 19-Jan-16 A 03-Mar-16 A AC.Lot 1 2nd Stage Concrete Bay 2 for DS/Stop Logs
929 TD 242: Bay 2, 2nd Stage Concrete Works complete ( 0 03-Mar-16 A AC.Lot 1 TD 242: Bay 2, 2nd Stage Concrete Works complete (revised Sequence),
920 Stop log U/S installation 11 21-Apr-16 A 08-May-16 A AC.Lot 2 Stop log U/S installation
923 Stop log D/S installation 11 21-Apr-16 A 08-May-16 A AC.Lot 2 Stop log D/S installation
Radial Gate 91 30-Mar-15 19-Jul-15 A 19-Jul-15 A, Radial Gate
931 TD 221: Bay 2, Access Lot 2, fixed Parts Installation (r 0 30-Mar-15 AC.Lot 2 TD 221: Bay 2, Access Lot 2, fixed Parts Installation (revised Sequence)
A
933 Sill beam installation (for radial gate) 28 02-May-15 03-Jun-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
932 Side guides installation (for radial gate) 50 03-May-15 30-Jun-15 A AC.Lot 2 Side guides installation (for radial gate)
A
935 Pre erection of radial gate in storage yard, Bay 2 51 04-May-15 02-Jul-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 2
A
934 TD 238: Bay 2, Axes 2-3, fixed Parts Installation Comp 0 16-May-15 AC.Lot 2 TD 238: Bay 2, Axes 2-3, fixed Parts Installation Complete (revised Sequence)
A
925 2nd Stage Concrete, Bay 2 for Radial Gate Installation 13 04-Jun-15 A 20-Jun-15 A AC.Lot 1 2nd Stage Concrete, Bay 2 for Radial Gate Installation
936 TD 244: Bay 2, Start of Radial Gate Erection (revised S 0 16-Jun-15 A AC.Lot 2 TD 244: Bay 2, Start of Radial Gate Erection (revised Sequence)
937 Radial gate erection, Bay 2 24 20-Jun-15 A 19-Jul-15 A AC.Lot 2 Radial gate erection, Bay 2
938 TD 249: Bay 2, Radial Gate Erection Complete (revise 0 19-Jul-15 A AC.Lot 2 TD 249: Bay 2, Radial Gate Erection Complete (revised Sequence)
Beams for gantry crane & Service bridge 194 29-Mar-15 22-Nov-15 A 22-Nov-15 A, Beams for gantry crane & Service bridge
940 TD 251: Bay 2, Start of SLW Gantry Crane u/s Beam ( 0 29-Mar-15 AC.Lot 1 TD 251: Bay 2, Start of SLW Gantry Crane u/s Beam (revised Sequence), 29-Mar-15 A
A
942 u/s Gantry Crane Beam, Bay 2 43 30-Mar-15 23-May-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 2
A
943 Service Bridge, Bay 2 12 03-Apr-15 A 20-Apr-15 A AC.Lot 1 Service Bridge, Bay 2
941 d/s Gantry Crane Beam, Bay 2 15 22-Apr-15 A 11-May-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 2
945 Installation of precast elements D/S ( Service Bridge & 5 23-Jul-15 A 30-Jul-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
944 Installation of precast elements U/S G.Crane 4 22-Aug-15 26-Aug-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
946 Gantry crane rails installation 38 17-Sep-15 07-Nov-15 A AC.Lot 2 Gantry crane rails installation
A
926 2nd Stage Concrete, Bay 2 for G. Crane Rails 10 10-Nov-15 22-Nov-15 A AC.Lot 1 2nd Stage Concrete, Bay 2 for G. Crane Rails
A
Electri
Electrical works 59 25-Oct-15 A 02-Jan-16 A 02-Jan-16 A, Electrical works
948 Hydraulic SLW radial gate, Bay 2 59 25-Oct-15 A 02-Jan-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 2
949 Electrical SLW radial gate, Bay 2 45 25-Oct-15 A 16-Dec-15 A AC.Lot 4 Electrical SLW radial gate, Bay 2
BAY 3, AX
AXES 3-4 305 02-May-15 05-May-16 A 05-May-16 A, BAY 3, AXES 3-4
Stop LLogs ( D/s & U/s ) 166 19-Oct-15 A 05-May-16 A 05-May-16 A, Stop Logs ( D/s & U/s )
952 Side guides installation (for stop log U/S) 37 19-Oct-15 A 01-Dec-15 A AC.Lot 2 Side guides installation (for stop log U/S)
953 Sill beam installation (for stop log U/S) 37 19-Oct-15 A 01-Dec-15 A AC.Lot 2 Sill beam installation (for stop log U/S)
962 2nd Stage Concrete Bay 3 for US/Stop Logs 45 21-Nov-15 13-Jan-16 A AC.Lot 1 2nd Stage Concrete Bay 3 for US/Stop Logs
A
956 Sill beam installation (for stop log D/S) 90 03-Dec-15 20-Mar-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
955 Side guides installation (for stop log D/S) 82 13-Dec-15 20-Mar-16 A AC.Lot 2 Side guides installation (for stop log D/S)
A
961 2nd Stage Concrete, Bay 3 for DS/Stop Logs 44 26-Feb-16 18-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 3 for DS/Stop Logs
A
963 TD 250: Bay 3, 2nd Stage Concrete Works complete 0 18-Apr-16 A AC.Lot 1 TD 250: Bay 3, 2nd Stage Concrete Works complete,

Milestone Lot 1 Lot 2 Page 14 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
954 Stop log U/S installation 11 19-Apr-16 A 05-May-16 A AC.Lot 2 Stop log U/S installation
957 Stop log D/S installation 11 19-Apr-16 A 05-May-16 A AC.Lot 2 Stop log D/S installation
Radial Gate 89 02-May-15 16-Aug-15 A 16-Aug-15 A, Radial Gate
965 TD 226: Bay 3, Access Lot 2, fixed Parts Installation 0 02-May-15 AC.Lot 2 TD 226: Bay 3, Access Lot 2, fixed Parts Installation
A
966 Side guides installation (for radial gate) 28 10-May-15 11-Jun-15 A AC.Lot 2 Side guides installation (for radial gate)
A
967 Sill beam installation (for radial gate) 28 10-May-15 11-Jun-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
959 2nd Stage Concrete, Bay 3 for Radial Gate Installation 23 12-Jun-15 A 09-Jul-15 A AC.Lot 1 2nd Stage Concrete, Bay 3 for Radial Gate Installation
968 TD 247: Bay 3, Axes 3-4, fixed Parts Installation Comp 0 16-Jun-15 A AC.Lot 2 TD 247: Bay 3, Axes 3-4, fixed Parts Installation Complete
970 Pre erection of radial gate in storage yard, Bay 3 25 16-Jun-15 A 14-Jul-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 3
972 Radial gate erection, Bay 3 22 09-Jul-15 A 06-Aug-15 A AC.Lot 2 Radial gate erection, Bay 3
971 TD 252: Bay 3, Start of Radial Gate Erection 0 16-Jul-15 A AC.Lot 2 TD 252: Bay 3, Start of Radial Gate Erection
969 TD 255: Bay 3, Radial Gate Erection Complete 0 16-Aug-15 AC.Lot 2 TD 255: Bay 3, Radial Gate Erection Complete
A
Beams for gantry crane & Service bridge 138 05-Jun-15 A 22-Nov-15 A 22-Nov-15 A, Beams for gantry crane & Service bridge
977 Fabrication of Service Bridge, Bay 3 14 05-Jun-15 A 22-Jun-15 A AC.Lot 1 Fabrication of Service Bridge, Bay 3
976 u/s Gantry Crane Beam, Bay 3 6 12-Jul-15 A 20-Jul-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 3
979 Installation of precast elements U/S G.Crane 11 25-Aug-15 07-Sep-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
980 Installation of precast elements D/S ( Service Bridge & 5 01-Oct-15 A 10-Oct-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
975 d/s Gantry Crane Beam, Bay 3 7 07-Oct-15 A 15-Oct-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 3
974 TD 257: Bay 3, Start of SLW Gantry Crane u/s Beam 0 02-Nov-15 AC.Lot 1 TD 257: Bay 3, Start of SLW Gantry Crane u/s Beam, 02-Nov-15 A
A
978 Gantry crane rails installation 4 07-Nov-15 11-Nov-15 A AC.Lot 2 Gantry crane rails installation
A
960 2nd Stage Concrete, Bay 3 for G. Crane Rails 8 12-Nov-15 22-Nov-15 A AC.Lot 1 2nd Stage Concrete, Bay 3 for G. Crane Rails
A
Electri
Electrical works 137 02-Aug-15 16-Jan-16 A 16-Jan-16 A, Electrical works
982 Hydraulic SLW radial gate, Bay 3 114 02-Aug-15 19-Dec-15 A AC.Lot 4 Hydraulic SLW radial gate, Bay 3
A
983 Electrical SLW radial gate, Bay 3 59 07-Nov-15 16-Jan-16 A AC.Lot 4 Electrical SLW radial gate, Bay 3
A
BAY 4, AX
AXES 4-5 291 31-May-15 18-May-16 A 18-May-16 A, BAY 4, AXES 4-5
Stop LLogs ( D/s & U/s ) 169 28-Oct-15 AA 18-May-16 A 18-May-16 A, Stop Logs ( D/s & U/s )
987 Sill beam installation (for stop log U/S) 83 28-Oct-15 A 04-Feb-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
986 Side guides installation (for stop log U/S) 72 04-Jan-16 A 30-Mar-16 A AC.Lot 2 Side guides installation (for stop log U/S)
989 Side guides installation (for stop log D/S) 72 04-Jan-16 A 30-Mar-16 A AC.Lot 2 Side guides installation (for stop log D/S)
990 Sill beam installation (for stop log D/S) 72 04-Jan-16 A 30-Mar-16 A AC.Lot 2 Sill beam installation (for stop log D/S)
993 2nd Stage Concrete, Bay 4 for US/Stop Logs 32 05-Feb-16 14-Mar-16 A AC.Lot 1 2nd Stage Concrete, Bay 4 for US/Stop Logs
A
988 Stop log U/S installation 83 06-Feb-16 16-May-16 A AC.Lot 2 Stop log U/S installation
A
995 TD 256: Bay 4, 2nd Stage Concrete Works complete ( 0 20-Feb-16 AC.Lot 1 TD 256: Bay 4, 2nd Stage Concrete Works complete (revised Sequence), 20-Feb-16 A
A
994 2nd Stage Concrete, Bay 4 for D/S Stop Logs 20 01-Apr-16 A 25-Apr-16 A AC.Lot 1 2nd Stage Concrete, Bay 4 for D/S Stop Logs
991 Stop log D/S installation 11 05-May-16 18-May-16 A AC.Lot 2 Stop log D/S installation
A
Radial Gate 91 31-May-15 16-Sep-15 A 16-Sep-15 A, Radial Gate
999 TD 235: Bay 4, Access Lot 2, fixed Parts Installation (r 0 31-May-15 AC.Lot 2 TD 235: Bay 4, Access Lot 2, fixed Parts Installation (revised Sequence)
A
1003 Side guides installation (for radial gate) 26 06-Jun-15 A 06-Jul-15 A AC.Lot 2 Side guides installation (for radial gate)
1004 Sill beam installation (for radial gate) 26 06-Jun-15 A 06-Jul-15 A AC.Lot 2 Sill beam installation (for radial gate)
996 2nd Stage Concrete, Bay 4 for Radial Gate Installation 25 05-Jul-15 A 05-Aug-15 A AC.Lot 1 2nd Stage Concrete, Bay 4 for Radial Gate Installation
1001 Pre erection of radial gate in storage yard, Bay 4 25 15-Jul-15 A 15-Aug-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 4
1005 TD 254: Bay 4, Axes 4-5, fixed Parts Installation Comp 0 15-Jul-15 A AC.Lot 2 TD 254: Bay 4, Axes 4-5, fixed Parts Installation Complete (revised Sequence)
1006 Radial gate erection, Bay 4 24 06-Aug-15 03-Sep-15 A AC.Lot 2 Radial gate erection, Bay 4
A
1002 TD 258: Bay 4, Start of Radial Gate Erection (revised S 0 16-Aug-15 AC.Lot 2 TD 258: Bay 4, Start of Radial Gate Erection (revised Sequence)
A
1000 TD 260: Bay 4, Radial Gate Erection Complete (revise 0 16-Sep-15 AC.Lot 2 TD 260: Bay 4, Radial Gate Erection Complete (revised Sequence)
A
Beams for gantry crane & Service bridge 112 22-Jul-15 A 07-Dec-15 A 07-Dec-15 A, Beams for gantry crane & Service bridge
1010 u/s Gantry Crane Beam, Bay 4 9 22-Jul-15 A 03-Aug-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 4
1012 Installation of precast elements U/S G.Crane 3 09-Sep-15 13-Sep-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
1011 Service Bridge, Bay 4 12 12-Sep-15 29-Sep-15 A AC.Lot 1 Service Bridge, Bay 4
A
1009 d/s Gantry Crane Beam, Bay 4 7 07-Oct-15 A 15-Oct-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 4
1013 Installation of precast elements D/S ( Service Bridge & 9 08-Nov-15 18-Nov-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
A
1014 Gantry crane rails installation 8 23-Nov-15 02-Dec-15 A AC.Lot 2 Gantry crane rails installation
A
997 2nd Stage Concrete, Bay 4 for G. Crane Rails 3 03-Dec-15 07-Dec-15 A AC.Lot 1 2nd Stage Concrete, Bay 4 for G. Crane Rails
A
1008 TD 262: Bay 4, Start of SLW Gantry Crane u/s Beam ( 0 05-Dec-15 AC.Lot 1 TD 262: Bay 4, Start of SLW Gantry Crane u/s Beam (revised Sequence), 05-Dec-15 A
A
Electri
Electrical works 59 05-Dec-15 14-Feb-16 A 14-Feb-16 A, Electrical works
1016 Hydraulic SLW radial gate, Bay 4 36 05-Dec-15A 17-Jan-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 4
A
1017 Electrical SLW radial gate, Bay 4 59 05-Dec-15 14-Feb-16 A AC.Lot 4 Electrical SLW radial gate, Bay 4
A
BAY 5, AX
AXES 5-6 387 04-Feb-15 18-May-16 A 18-May-16 A, BAY 5, AXES 5-6
Stop LLogs ( D/s & U/s ) 387 04-Feb-15A 18-May-16 A 18-May-16 A, Stop Logs ( D/s & U/s )
1029 Side guides installation (for stop log D/S) 55 04-Feb-15 09-Apr-15 A AC.Lot 2 Side guides installation (for stop log D/S)
A
1030 Sill beam installation (for stop log D/S) 55 04-Feb-15 09-Apr-15 A AC.Lot 2 Sill beam installation (for stop log D/S)
A
1026 Side guides installation (for stop log U/S) 24 23-Jan-16 A 21-Feb-16 A AC.Lot 2 Side guides installation (for stop log U/S)
1027 Sill beam installation (for stop log U/S) 24 23-Jan-16 A 21-Feb-16 A AC.Lot 2 Sill beam installation (for stop log U/S)
1022 2nd Stage Concrete, Bay 5 for US/Stop Logs 46 05-Feb-16 30-Mar-16 A AC.Lot 1 2nd Stage Concrete, Bay 5 for US/Stop Logs
A
1023 2nd Stage Concrete, Bay 5 for DS/Stop Logs 62 22-Feb-16 08-May-16 A AC.Lot 1 2nd Stage Concrete, Bay 5 for DS/Stop Logs
A
1028 Stop log U/S installation 11 05-May-16 18-May-16 A AC.Lot 2 Stop log U/S installation
A
1031 Stop log D/S installation 11 05-May-16 18-May-16 A AC.Lot 2 Stop log D/S installation
A
1024 TD 261: Bay 5, 2nd Stage Concrete Works complete ( 0 10-May-16 A AC.Lot 1 TD 261: Bay 5, 2nd Stage Concrete Works complete (revised Sequence),
Radial Gate 109 29-Jun-15 A 11-Nov-15 A 11-Nov-15 A, Radial Gate
1033 TD 245: Bay 5, Access Lot 2, fixed Parts Installation (r 0 29-Jun-15 A AC.Lot 2 TD 245: Bay 5, Access Lot 2, fixed Parts Installation (revised Sequence)
1038 TD 259: Bay 5, Axes 5-6, fixed Parts Installation Comp 0 15-Aug-15 AC.Lot 2 TD 259: Bay 5, Axes 5-6, fixed Parts Installation Complete (revised Sequence)
A
1036 Side guides installation (for radial gate) 15 02-Sep-15 20-Sep-15 A AC.Lot 2 Side guides installation (for radial gate)
A
1037 Sill beam installation (for radial gate) 15 02-Sep-15 20-Sep-15 A AC.Lot 2 Sill beam installation (for radial gate)
A
1035 TD 263: Bay 5, Start of Radial Gate Erection (revised S 0 15-Sep-15 AC.Lot 2 TD 263: Bay 5, Start of Radial Gate Erection (revised Sequence)
A

Milestone Lot 1 Lot 2 Page 15 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
1020 2nd Stage Concrete, Bay 5 for Radial Gate Installation 14 21-Sep-15 13-Oct-15 A AC.Lot 1 2nd Stage Concrete, Bay 5 for Radial Gate Installation
A
1034 Pre erection of radial gate in storage yard, Bay 5 24 21-Sep-15 25-Oct-15 A AC.Lot 2 Pre erection of radial gate in storage yard, Bay 5
A
1039 Radial gate erection, Bay 5 24 14-Oct-15 A 11-Nov-15 A AC.Lot 2 Radial gate erection, Bay 5
1040 TD 265: Bay 5, Radial Gate Erection Complete (revise 0 20-Oct-15 A AC.Lot 2 TD 265: Bay 5, Radial Gate Erection Complete (revised Sequence)
Beams for gantry crane & Service bridge 116 16-Aug-15 04-Jan-16 A 04-Jan-16 A, Beams for gantry crane & Service bridge
1045 u/s Gantry Crane Beam, Bay 5 11 A
16-Aug-15 28-Aug-15 A AC.Lot 1 u/s Gantry Crane Beam, Bay 5
A
1047 Service Bridge, Bay 5 10 13-Oct-15 A 25-Oct-15 A AC.Lot 1 Service Bridge, Bay 5
1044 d/s Gantry Crane Beam, Bay 5 6 25-Oct-15 A 01-Nov-15 A AC.Lot 1 d/s Gantry Crane Beam, Bay 5
1048 Installation of precast elements U/S G.Crane 5 01-Nov-15 07-Nov-15 A AC.Lot 1 Installation of precast elements U/S G.Crane
A
1042 TD 269: Bays 1-5, Gantry Crane Beams ready for Rail 0 02-Nov-15 AC.Lot 1 TD 269: Bays 1-5, Gantry Crane Beams ready for Rail Installation (revised Sequence), 02-Nov-15 A
A
1049 Installation of precast elements D/S ( Service Bridge & 7 19-Nov-15 28-Nov-15 A AC.Lot 1 Installation of precast elements D/S ( Service Bridge & D/S G.Crane )
A
1046 Gantry crane rails installation 11 28-Nov-15 10-Dec-15 A AC.Lot 2 Gantry crane rails installation
A
1021 2nd Stage Concrete, Bay 5 for G. Crane Rails 4 10-Dec-15 14-Dec-15 A AC.Lot 1 2nd Stage Concrete, Bay 5 for G. Crane Rails
A
1043 TD 266: Bay 5, Start of SLW Gantry Crane u/s Beam ( 0 04-Jan-16 A AC.Lot 1 TD 266: Bay 5, Start of SLW Gantry Crane u/s Beam (revised Sequence), 04-Jan-16 A
Electri
Electrical works 59 28-Dec-15 08-Mar-16 A 08-Mar-16 A, Electrical works
1051 Hydraulic SLW radial gate, Bay 5 36 28-Dec-15A 10-Feb-16 A AC.Lot 4 Hydraulic SLW radial gate, Bay 5
A
1053 Electrical SLW radial gate, Bay 5 59 28-Dec-15 08-Mar-16 A AC.Lot 4 Electrical SLW radial gate, Bay 5
A
1052 TD 268 lot 4: SLW, Axes 1-6, Access Lot 4, Cable Tra 0 08-Mar-16 AC.Lot 4 TD 268 lot 4: SLW, Axes 1-6, Access Lot 4, Cable Tray Installation
A
FINISHING W
WORKS 83 29-Dec-15 05-Apr-16 A 05-Apr-16 A, FINISHING WORKS
1055 Finishing works 83 29-Dec-15A 05-Apr-16 A AC.Lot 1 Finishing works
A
GANTRY CR
CRANES 197 17-May-15 10-Jan-16 A 10-Jan-16 A, GANTRY CRANES
1059 TD 207: Lot 2, Start of SLW-W Gantry Crane No. 01 E 0 17-May-15A AC.Lot 2 TD 207: Lot 2, Start of SLW-W Gantry Crane No. 01 Erection (on Abutment Pier Axis 01 & Extension Beams)
A
1058 SLW-W Gantry Crane Rail Installation 25 18-May-15 15-Jun-15 A AC.Lot 2 SLW-W Gantry Crane Rail Installation
A
1060 SLW-W Gantry Crane Pre-assembly & Erection 25 16-Jun-15 A 14-Jul-15 A AC.Lot 2 SLW-W Gantry Crane Pre-assembly & Erection
1061 SLW-W Gantry Crane Testing 10 15-Jul-15 A 28-Jul-15 A AC.Lot 2 SLW-W Gantry Crane Testing
1062 TD 212: Lot 2, SLW-W Gantry Crane No. 01 Erection 0 30-Jul-15 A AC.Lot 2 TD 212: Lot 2, SLW-W Gantry Crane No. 01 Erection complete
1057 TD 269: Bays1-5, Gantry Crane Beams ready for Rail 0 01-Nov-15 AC.Lot 2 TD 269: Bays1-5, Gantry Crane Beams ready for Rail Installation
A
1063 SLW-E Gantry Crane Rail Installation 25 01-Nov-15 29-Nov-15 A AC.Lot 2 SLW-E Gantry Crane Rail Installation
A
1067 TD 214: Start of SLW-E Gantry Crane No. 2 Erection 0 29-Nov-15 AC.Lot 2 TD 214: Start of SLW-E Gantry Crane No. 2 Erection
A
1065 SLW-E Gantry Crane Pre-assembly & Erection 25 30-Nov-15 28-Dec-15 A AC.Lot 2 SLW-E Gantry Crane Pre-assembly & Erection
A
1066 SLW-E Gantry Crane Testing 10 29-Dec-15 10-Jan-16 A AC.Lot 2 SLW-E Gantry Crane Testing
A
1064 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rai 0 03-Jan-16 A AC.Lot 2 TD 253: Bays 6-8 Gantry Crane Beams Ready for Rail Installation
Test & Commissioning
Com 412 01-Dec-16 28-Mar-18 A 28-Mar-18 A, Test & Commissioning
Dry Test 220 01-Dec-16 16-Aug-17 A 16-Aug-17 A, Dry Test
A2410 LV Common Equipment 220 01-Dec-16 16-Aug-17 A AC.Lot 4 LV Common Equipment
A
A2420 Sluiceway Common Control Board [+50CXA11] 7 28-Feb-17 08-Mar-17 A AC.Lot 4 Sluiceway Common Control Board [+50CXA11]
A
Wet Test 83 21-Dec-17 28-Mar-18 A 28-Mar-18 A, Wet Test
A2430 Wet Test 83 21-Dec-17 28-Mar-18 A AC.Lot 2 Wet Test
A
NAVIGATION LOCK, GUIDE WALLS AND SEPARATION PIERS 1278 04-Sep-13 23-Nov-17 A 23-Nov-17 A, NAVIGATION LOCK, GUIDE WALLS AND S
A
NAVIGATION LOCK 1278 04-Sep-13 23-Nov-17 A 23-Nov-17 A, NAVIGATION LOCK
Upstream head 504 04-Sep-13 11-May-15 A 11-May-15 A, Upstream head
1071 Plain Concrete Under Raft Foundation of u/s Head, Ax 40 04-Sep-13A 24-Oct-13 A AC.Lot 1 Plain Concrete Under Raft Foundation of u/s Head, Axes 17-20/F-J
A
1072 Raft Foundation of u/s Head, Axes 17-20/F-J 95 10-Nov-13 04-Mar-14 A AC.Lot 1 Raft Foundation of u/s Head, Axes 17-20/F-J
A
1074 Superstructure of u/s Head, Axes 17-20/F-J 357 04-Mar-14 11-May-15 A AC.Lot 1 Superstructure of u/s Head, Axes 17-20/F-J
A
1073 TD 103: Lot 2, Start of u/s Head fixed Part Installation 0 02-Jun-14 A AC.Lot 2 TD 103: Lot 2, Start of u/s Head fixed Part Installation
1075 TD 102: u/s Head ready for fixed Parts installation 0 02-Jun-14 A AC.Lot 1 TD 102: u/s Head ready for fixed Parts installation, 02-Jun-14 A
Fixed pa
parts installation U/S 888 02-Jun-14 A 10-May-17 A 10-May-17 A, Fixed parts installation U/S
Culvert Gates and Bulkheads
Culver 299 02-Jun-14 A 30-May-15 A 30-May-15 A, Culvert Gates and Bulkheads
1081 guiding rails G-J / 20 93 02-Jun-14 A 22-Sep-14 A AC.Lot 2 guiding rails G-J / 20
1078 guiding rails G-J / 17 87 12-Jul-14 A 28-Oct-14 A AC.Lot 2 guiding rails G-J / 17
1080 guiding rails G-J / 19 101 23-Jul-14 A 25-Nov-14 A AC.Lot 2 guiding rails G-J / 19
1079 guiding rails G-J / 18 72 11-Sep-14 08-Dec-14 A AC.Lot 2 guiding rails G-J / 18
A
1082 2nd stage concrete (civil contractor) 145 11-Nov-14 05-May-15 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1083 Culvert gate and Bulkhead Lock 1 17 09-May-15 28-May-15 A AC.Lot 2 Culvert gate and Bulkhead Lock 1
A
1084 Culvert gate and Bulkhead Lock 2 18 09-May-15 30-May-15 A AC.Lot 2 Culvert gate and Bulkhead Lock 2
A
Stoplo between axes H & J
Stoplogs 353 08-Nov-14 09-Jan-16 A 09-Jan-16 A, Stoplogs between axes H & J
1088 guiding rails Lock 2 150 08-Nov-14A 07-May-15 A AC.Lot 2 guiding rails Lock 2
A
1089 2nd stage concrete (civil contractor) 174 09-May-15 06-Dec-15 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1086 guiding rails Lock 1 46 04-Jun-15 A 30-Jul-15 A AC.Lot 2 guiding rails Lock 1
1087 2nd stage concrete (civil contractor) 27 05-Oct-15 A 07-Nov-15 A AC.Lot 1 2nd stage concrete (civil contractor)
1091 Stop log Lock 2 13 07-Dec-15 22-Dec-15 A AC.Lot 2 Stop log Lock 2
A
1090 Stop log Lock 1 13 23-Dec-15 09-Jan-16 A AC.Lot 2 Stop log Lock 1
A
Sector Gates 521 11-Mar-15 05-Dec-16 A 05-Dec-16 A, Sector Gates
1095 emb. Parts + gate frames Lock 2 216 A
11-Mar-15 30-Nov-15 A AC.Lot 2 emb. Parts + gate frames Lock 2
A
1099 trunnion Lock 2 186 19-May-15 30-Dec-15 A AC.Lot 2 trunnion Lock 2
A
1093 emb. Parts + gate frames Lock 1 46 14-Nov-15 06-Jan-16 A AC.Lot 2 emb. Parts + gate frames Lock 1
A
1096 2nd stage concrete (civil contractor) 107 24-Nov-15 30-Mar-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1097 trunnion Lock 1 97 25-Nov-15 20-Mar-16 A AC.Lot 2 trunnion Lock 1
A
1100 2nd stage concrete (civil contractor) 285 23-Dec-15 05-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1094 2nd stage concrete (civil contractor) 23 09-Jan-16 A 06-Feb-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1103 Sector Gate Lock 2 97 18-Jan-16 A 15-May-16 A AC.Lot 2 Sector Gate Lock 2
1098 2nd stage concrete (civil contractor) 19 08-Mar-16 30-Mar-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1101 Sector Gate Lock 1 37 30-Mar-16 16-May-16 A AC.Lot 2 Sector Gate Lock 1
A
1104 Hydraulic Lock 2 24 30-Apr-16 A 30-May-16 A AC.Lot 2 Hydraulic Lock 2

Milestone Lot 1 Lot 2 Page 16 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
1102 Hydraulic Lock 1 24 03-May-16 31-May-16 A AC.Lot 2 Hydraulic Lock 1
A
Stoplo between axes G & H
Stoplogs 413 30-Jan-15 A 13-Jun-16 A 13-Jun-16 A, Stoplogs between axes G & H
1108 guiding rails Lock 2 53 30-Jan-15 A 02-Apr-15 A AC.Lot 2 guiding rails Lock 2
1109 2nd stage concrete (civil contractor) 189 04-Apr-15 A 22-Nov-15 A AC.Lot 1 2nd stage concrete (civil contractor)
1106 guiding rails Lock 1 48 19-Nov-15 16-Jan-16 A AC.Lot 2 guiding rails Lock 1
A
1111 Stop log Lock 2 168 23-Nov-15 12-Jun-16 A AC.Lot 2 Stop log Lock 2
A
1107 2nd stage concrete (civil contractor) 30 17-Jan-16 A 22-Feb-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1110 Stop log Lock 1 92 23-Feb-16 13-Jun-16 A AC.Lot 2 Stop log Lock 1
A
Arrest Cable Systems
Arrester 340 26-Mar-16 10-May-17 A 10-May-17 A, Arrester Cable Systems
NL1 338 A 10-May-17 A
28-Mar-16 10-May-17 A, NL1
1 Arrester cable system incl. hoists Lock 1 163 A 17-Oct-16 A
28-Mar-16 AC.Lot 2 Arrester cable system incl. hoists Lock 1
A
1 embedded parts Lock 1 56 16-Apr-16 A 23-Jun-16 A AC.Lot 2 embedded parts Lock 1
1 2nd stage concrete (civil contractor) 35 17-Oct-16 A 27-Nov-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1 deflection sheet without rail 26 27-Nov-16 28-Dec-16 A AC.Lot 2 deflection sheet without rail
A
1 2nd stage concrete (Deflection Sheet) 18 29-Dec-16 19-Jan-17 A AC.Lot 1 2nd stage concrete (Deflection Sheet)
A
1 motor console and double chain wheels,vertical rails o 68 20-Jan-17 A 10-Apr-17 A AC.Lot 2 motor console and double chain wheels,vertical rails on deflection sheets,Lower chain
1 hydraulic & flushing devices Lock 1 26 10-Apr-17 A 10-May-17 A AC.Lot 2 hydraulic & flushing devices Lock 1
NL2 340 26-Mar-16 10-May-17 A 10-May-17 A, NL2
1 embedded parts Lock 2 74 26-Mar-16 23-Jun-16 A AC.Lot 2 embedded parts Lock 2
A
1 Arrester cable system incl. hoists Lock 2 174 28-Mar-16 30-Oct-16 A AC.Lot 2 Arrester cable system incl. hoists Lock 2
A
1 deflection sheet without rail 24 03-Oct-16 A 01-Nov-16 A AC.Lot 2 deflection sheet without rail
1 2nd stage concrete (civil contractor) 31 30-Oct-16 A 05-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1 2nd stage concrete (Deflection Sheet) 75 01-Nov-16 29-Jan-17 A AC.Lot 1 2nd stage concrete (Deflection Sheet)
A
1 motor console and double chain wheels,vertical rails o 74 29-Jan-17 A 24-Apr-17 A AC.Lot 2 motor console and double chain wheels,vertical rails on deflection sheets,Lower cha
1 hydraulic & flushing devices Lock 2 14 24-Apr-17 A 10-May-17 A AC.Lot 2 hydraulic & flushing devices Lock 2
Middle Part
P 641 12-Dec-13 30-Jan-16 A 30-Jan-16 A, Middle Part
1122 Plain Concrete Under Raft Foundation of Middle Part, A 35 12-Dec-13 23-Jan-14 A AC.Lot 1 Plain Concrete Under Raft Foundation of Middle Part, Axes 17-20/J-O
A
1123 Raft Foundation of Middle Part, Axes 17-20/J-O 109 01-May-14 10-Sep-14 A AC.Lot 1 Raft Foundation of Middle Part, Axes 17-20/J-O
A
1124 Superstructure of Middle Part, Axes 17-20/J-O 411 17-Sep-14 30-Jan-16 A AC.Lot 1 Superstructure of Middle Part, Axes 17-20/J-O
A
Downstr
Downstream head 568 26-Oct-13 A 12-Sep-15 A 12-Sep-15 A, Downstream head
1126 Plain Concrete Under Raft Foundation of d/s Head, Ax 40 26-Oct-13 A 11-Dec-13 A AC.Lot 1 Plain Concrete Under Raft Foundation of d/s Head, Axes 17-20/O-S
1127 Raft Foundation of d/s Head, Axes 17-20/O-S 108 12-Dec-13 23-Apr-14 A AC.Lot 1 Raft Foundation of d/s Head, Axes 17-20/O-S
A
1128 Superstructure of u/s Head, Axes 17-20/O-S 444 24-Mar-14 12-Sep-15 A AC.Lot 1 Superstructure of u/s Head, Axes 17-20/O-S
A
1130 TD 104: d/s Head ready for fixed Parts installation 0 18-Jul-14 A AC.Lot 1 TD 104: d/s Head ready for fixed Parts installation, 18-Jul-14 A
1129 TD 105: Lot 2, Start of d/s Head fixed Part Installation 0 18-Jul-14 A AC.Lot 2 TD 105: Lot 2, Start of d/s Head fixed Part Installation
Fixed pa
parts installation D/S 837 02-Sep-14 08-Jun-17 A 08-Jun-17 A, Fixed parts installation D/S
Culvert Gates and Bulkheads
Culver 632 02-Sep-14A 11-Oct-16 A 11-Oct-16 A, Culvert Gates and Bulkheads
1136 guiding rails O-Q / 20 94 02-Sep-14A 24-Dec-14 A AC.Lot 2 guiding rails O-Q / 20
A
1134 guiding rails O-Q / 18 125 10-Dec-14 11-May-15 A AC.Lot 2 guiding rails O-Q / 18
A
1135 guiding rails O-Q / 19 91 01-Jan-15 A 22-Apr-15 A AC.Lot 2 guiding rails O-Q / 19
1133 guiding rails O-Q / 17 122 12-Mar-15 08-Aug-15 A AC.Lot 2 guiding rails O-Q / 17
A
1137 2nd stage concrete (civil contractor) 133 23-Aug-15 02-Feb-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1138 Culvert gate and Bulkhead Lock 1 254 09-Nov-15 10-Sep-16 A AC.Lot 2 Culvert gate and Bulkhead Lock 1
A
1139 Culvert gate and Bulkhead Lock 2 142 16-Apr-16 A 11-Oct-16 A AC.Lot 2 Culvert gate and Bulkhead Lock 2
Stoplo between axes P & O
Stoplogs 225 12-Dec-15 08-Sep-16 A 08-Sep-16 A, Stoplogs between axes P & O
1141 guiding rails Lock 1 119 12-Dec-15 04-May-16 A AC.Lot 2 guiding rails Lock 1
A
1143 guiding rails Lock 2 84 12-Dec-15 21-Mar-16 A AC.Lot 2 guiding rails Lock 2
A
1142 2nd stage concrete (civil contractor) 37 22-Mar-16 08-May-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1144 2nd stage concrete (civil contractor) 91 05-May-16 23-Aug-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1146 Stop log Lock 2 13 09-May-16 24-May-16 A AC.Lot 2 Stop log Lock 2
A
1145 Stop log Lock 1 13 24-Aug-16 08-Sep-16 A AC.Lot 2 Stop log Lock 1
A
Mitre Gates
G 370 01-Dec-15 21-Feb-17 A 21-Feb-17 A, Mitre Gates
1148 emb. Parts + gate frames Lock 1 60 01-Dec-15 11-Feb-16 A AC.Lot 2 emb. Parts + gate frames Lock 1
A
1150 emb. Parts + gate frames Lock 2 66 12-Dec-15 29-Feb-16 A AC.Lot 2 emb. Parts + gate frames Lock 2
A
1149 2nd stage concrete (civil contractor) 20 13-Feb-16 07-Mar-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1151 2nd stage concrete (civil contractor) 22 01-Mar-16 27-Mar-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1154 Mitre Gate Lock 1 114 08-Mar-16 26-Jul-16 A AC.Lot 2 Mitre Gate Lock 1
A
1158 Mitre Gate Lock 2 139 28-Mar-16 17-Sep-16 A AC.Lot 2 Mitre Gate Lock 2
A
1152 Collar Bearing / Servomotor / Sill Beam Lock 1 24 27-Jul-16 A 24-Aug-16 A AC.Lot 2 Collar Bearing / Servomotor / Sill Beam Lock 1
1159 2nd stage concrete (civil contractor) 49 25-Aug-16 27-Oct-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1153 Collar Bearing / Servomotor / Sill Beam Lock 2 36 02-Sep-16 20-Oct-16 A AC.Lot 2 Collar Bearing / Servomotor / Sill Beam Lock 2
A
1156 Mechanical final works 49 15-Oct-16 A 11-Dec-16 A AC.Lot 2 Mechanical final works
1155 2nd stage concrete (civil contractor) 49 22-Oct-16 A 18-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
1160 Mechanical final works 49 05-Dec-16 01-Feb-17 A AC.Lot 2 Mechanical final works
A
1157 Hydraulic Lock 1 52 08-Dec-16 08-Feb-17 A AC.Lot 2 Hydraulic Lock 1
A
1161 Hydraulic Lock 2 16 02-Feb-17 21-Feb-17 A AC.Lot 2 Hydraulic Lock 2
A
Stoplo between axes O & Q
Stoplogs 225 12-Dec-15 08-Sep-16 A 08-Sep-16 A, Stoplogs between axes O & Q
1163 guiding rails Lock 1 84 12-Dec-15 21-Mar-16 A AC.Lot 2 guiding rails Lock 1
A
1164 2nd stage concrete (civil contractor) 37 22-Mar-16 08-May-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1165 guiding rails Lock 2 15 13-Apr-16 A 04-May-16 A AC.Lot 2 guiding rails Lock 2
1166 2nd stage concrete (civil contractor) 91 05-May-16 23-Aug-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A
1168 Stop log Lock 2 19 21-May-16 12-Jun-16 A AC.Lot 2 Stop log Lock 2
A
1167 Stop log Lock 1 13 24-Aug-16 08-Sep-16 A AC.Lot 2 Stop log Lock 1
A
Arrester Cable Systems
Arrest 347 16-Apr-16 A 08-Jun-17 A 08-Jun-17 A, Arrester Cable Systems

Milestone Lot 1 Lot 2 Page 17 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
NL1 347 16-Apr-16 A 08-Jun-17 A 08-Jun-17 A, NL1
A Arrester cable system incl. hoists Lock 1 214 16-Apr-16 A 04-Jan-17 A AC.Lot 2 Arrester cable system incl. hoists Lock 1
A embedded parts Lock 1 13 18-Jul-16 A 03-Aug-16 A AC.Lot 2 embedded parts Lock 1
A 2nd stage concrete (civil contractor) 57 17-Oct-16 A 22-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A deflection sheet without rail 22 27-Nov-16 22-Dec-16 A AC.Lot 2 deflection sheet without rail
A
A 2nd stage concrete (Deflection Sheet) 27 22-Dec-16 24-Jan-17 A AC.Lot 1 2nd stage concrete (Deflection Sheet)
A
A motor console and double chain wheels,vertical rails o 92 24-Jan-17 A 11-May-17 A AC.Lot 2 motor console and double chain wheels,vertical rails on deflection sheets,Lower ch
A hydraulic & flushing devices Lock 1 24 11-May-17 08-Jun-17 A AC.Lot 2 hydraulic & flushing devices Lock 1
A
NL2 314 26-Apr-16 A 10-May-17 A 10-May-17 A, NL2
A embedded parts Lock 2 67 26-Apr-16 A 18-Jul-16 A AC.Lot 2 embedded parts Lock 2
A Arrester cable system incl. hoists Lock 2 126 29-Apr-16 A 04-Oct-16 A AC.Lot 2 Arrester cable system incl. hoists Lock 2
A 2nd stage concrete (civil contractor) 52 04-Oct-16 A 05-Dec-16 A AC.Lot 1 2nd stage concrete (civil contractor)
A deflection sheet without rail 75 04-Oct-16 A 02-Jan-17 A AC.Lot 2 deflection sheet without rail
A 2nd stage concrete (Deflection Sheet) 26 02-Jan-17 A 01-Feb-17 A AC.Lot 1 2nd stage concrete (Deflection Sheet)
A motor console and double chain wheels,vertical rails o 71 01-Feb-17 24-Apr-17 A AC.Lot 2 motor console and double chain wheels,vertical rails on deflection sheets,Lower cha
A
A hydraulic & flushing devices Lock 2 14 24-Apr-17 A 10-May-17 A AC.Lot 2 hydraulic & flushing devices Lock 2
Gantry cranes
cr 532 15-Feb-15 23-Nov-16 A 23-Nov-16 A, Gantry cranes
NL 1 GGantry Crane 197 26-Mar-16A 23-Nov-16 A 23-Nov-16 A, NL 1 Gantry Crane
1180 gantry crane rails 78 26-Mar-16 28-Jun-16 A AC.Lot 2 gantry crane rails
A
1181 2nd stage concrete gantry crane rails (civil contractor) 49 12-Jun-16 A 11-Aug-16 A AC.Lot 1 2nd stage concrete gantry crane rails (civil contractor)
1182 pre assembly gantry crane 11 30-Jul-16 A 11-Aug-16 A AC.Lot 2 pre assembly gantry crane
1183 installation gantry crane 12 13-Aug-16 26-Aug-16 A AC.Lot 2 installation gantry crane
A
1184 testing gantry crane 5 17-Nov-16 23-Nov-16 A AC.Lot 2 testing gantry crane
A
NL 2 G
Gantry Crane 532 15-Feb-15 23-Nov-16 A 23-Nov-16 A, NL 2 Gantry Crane
1187 TD106: Start of NL Gantry Cranes Erection 0 A
15-Feb-15 AC.Lot 2 TD106: Start of NL Gantry Cranes Erection
A
1186 gantry crane rails 448 16-Mar-15 10-Sep-16 A AC.Lot 2 gantry crane rails
A
1188 2nd stage concrete gantry crane rails (civil contractor) 148 24-Apr-16 A 26-Oct-16 A AC.Lot 1 2nd stage concrete gantry crane rails (civil contractor)
1189 pre assembly gantry crane 49 24-Aug-16 26-Oct-16 A AC.Lot 2 pre assembly gantry crane
A
1190 installation gantry crane 11 27-Oct-16 A 09-Nov-16 A AC.Lot 2 installation gantry crane
1191 testing gantry crane 5 17-Nov-16 23-Nov-16 A AC.Lot 2 testing gantry crane
A
Electrica works
Electrical 332 31-Oct-16 A 23-Nov-17 A 23-Nov-17 A, Electrical works
1195 Ship arrester NL1 & NL2 174 31-Oct-16 A 23-May-17 A AC.Lot 4 Ship arrester NL1 & NL2
1196 Mitre gate / Sector gate NL1 & NL2 248 31-Oct-16 A 17-Aug-17 A AC.Lot 4 Mitre gate / Sector gate NL1 & NL2
1194 Culvert gate NL1 & NL2 268 15-Jan-17 A 23-Nov-17 A AC.Lot 4 Culvert gate NL1 & NL2
U/S GUIDE W
WALL, AXES 16-17/P-F 342 15-Feb-15 03-Apr-16 A 03-Apr-16 A, U/S GUIDE WALL, AXES 16-17/P-F
1198 Guide Wall, Axes 16-17/F-H 155 15-Feb-15A 20-Aug-15 A AC.Lot 1 Guide Wall, Axes 16-17/F-H
A
1199 Guide Wall, Axes 16-17/M-H 335 23-Feb-15 03-Apr-16 A AC.Lot 1 Guide Wall, Axes 16-17/M-H
A
1200 Guide Wall, Axes 16-17/P-M 130 05-May-15 12-Oct-15 A AC.Lot 1 Guide Wall, Axes 16-17/P-M
A
D/S GUIDE W
WALL, AXES 17 251 05-Jun-15 A 04-Apr-16 A 04-Apr-16 A, D/S GUIDE WALL, AXES 17
1202 Guide Wall, Part 1, Axes 17/S 98 05-Jun-15 A 05-Oct-15 A AC.Lot 1 Guide Wall, Part 1, Axes 17/S
1203 Guide Wall, Middle Part 121 16-Jun-15 A 11-Nov-15 A AC.Lot 1 Guide Wall, Middle Part
1204 Guide Wall, Part 3 187 22-Aug-15 04-Apr-16 A AC.Lot 1 Guide Wall, Part 3
A
U/S APPROACH
APPROA AREA, SEPARATION PIER 525 01-Sep-15 28-May-17 A 28-May-17 A, U/S APPROACH AREA, SEPARATION PIER
1207 Contiguous Bored Pile Walls 107 01-Sep-15 11-Jan-16 A AC.Lot 1 Contiguous Bored Pile Walls
A
1206 Fill Separation Dyke 44 08-Sep-15 04-Nov-15 A AC.Lot 1 Fill Separation Dyke
A
1210 Fender walls + mooring structures 422 05-Jan-16 A 28-May-17 A AC.Lot 1 Fender walls + mooring structures
1208 Separation Pier Concrete Superstructure 338 15-Mar-16 27-Apr-17 A AC.Lot 1 Separation Pier Concrete Superstructure
A
1209 Removal Separation Dyke 11 29-Apr-17 A 11-May-17 A AC.Lot 1 Removal Separation Dyke
REMOVAL OF
O OLD BARRAGE PARTS 320 10-Oct-16 A 19-Oct-17 A 19-Oct-17 A, REMOVAL OF OLD BARRAGE PARTS
1213 Removal of Bridge and Arches 320 10-Oct-16 A 19-Oct-17 A AC.Lot 1 Removal of Bridge and Arches
1212 Strengthening of adjacent Vent 163 20-Oct-16 A 30-Apr-17 A AC.Lot 1 Strengthening of adjacent Vent
1214 TD 110 (1): Removal of Old Barrage Parts complete (s 0 19-Oct-17 A AC.Lot 1 TD 110 (1): Removal of Old Barrage Parts complete (suggestio
FINISHING W
WORKS 234 19-Apr-16 A 31-Jan-17 A 31-Jan-17 A, FINISHING WORKS
1216 Finishing works 234 19-Apr-16 A 31-Jan-17 A AC.Lot 1 Finishing works
Test & Commissioning
Com 173 06-May-17 23-Nov-17 A 23-Nov-17 A, Test & Commissioning
Dry Test 130 06-May-17A 04-Oct-17 A 04-Oct-17 A, Dry Test
A2450 US Culvert Gate , Sector Gate & Ship Arrester 113 06-May-17 14-Sep-17 A AC.Lot 2 US Culvert Gate , Sector Gate & Ship Arrester
A
A2460 DS Culvert Gate , Sector Gate & Ship Arrester 113 06-May-17 14-Sep-17 A AC.Lot 2 DS Culvert Gate , Sector Gate & Ship Arrester
A
A2440 Gantry Crane -NL#1 & NL #2 82 01-Jul-17 A 04-Oct-17 A AC.Lot 2 Gantry Crane -NL#1 & NL #2
Wet TesT 46 01-Oct-17 A 23-Nov-17 A 23-Nov-17 A, Wet TesT
A2470 Wet Test NL 1 & 2 46 01-Oct-17 A 23-Nov-17 A AC.Lot 2 Wet Test NL 1 & 2
PUBLIC BRIDGE
BRID AND PUBLIC ROAD 1069 24-Sep-14 28-Mar-18 A 28-Mar-18 A, PUBLIC BRIDGE AND PUBL
A
General 1069 24-Sep-14 28-Mar-18 A 28-Mar-18 A, General
1219 PRB Beams, Axes 18-19 317 A
24-Sep-14 15-Oct-15 A AC.Lot 1 PRB Beams, Axes 18-19
A
1223 PRB Abutment / Piers (Axis 20-Right Bank) 75 07-Oct-14 A 01-Jan-15 A AC.Lot 1 PRB Abutment / Piers (Axis 20-Right Bank)
1220 PRB Beams, Axes 17-18 295 23-Oct-14 A 15-Oct-15 A AC.Lot 1 PRB Beams, Axes 17-18
1221 PRB Beams, Axes 19-20 273 18-Nov-14 15-Oct-15 A AC.Lot 1 PRB Beams, Axes 19-20
A
1225 PRB Beams, Axes 17-16 256 14-Dec-14 21-Oct-15 A AC.Lot 1 PRB Beams, Axes 17-16
A
1224 PRB Beams, Axes 20 ( E. Side) 242 03-Jan-15 A 25-Oct-15 A AC.Lot 1 PRB Beams, Axes 20 ( E. Side)
1226 PRB Beams, Axes 16-17 234 10-Jan-15 A 21-Oct-15 A AC.Lot 1 PRB Beams, Axes 16-17
1236 Bridge Beams, SW Bay 1 218 05-Feb-15 28-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 1
A
1222 PRB Pier between Abut Pier 16 and N.L D/S 25 03-Mar-15 31-Mar-15 A AC.Lot 1 PRB Pier between Abut Pier 16 and N.L D/S
A
1235 Bridge Beams, SW Bay 2 196 03-Mar-15 28-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 2
A
1234 Bridge Beams, SW Bay 3 172 29-Mar-15 26-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 3
A

Milestone Lot 1 Lot 2 Page 18 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work
New Assiut Barrage and Hydropower Plant Schedule Impletation Programme 12-Oct-18 13:46

Activity ID Activity Name Actual Actual Start Actual Finish The 2012 2013 2014 2015 2016 2017 2018 2019
Duration Contractor
M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul A S O N D J F M
1233 Bridge Beams, SW Bay 4 148 27-Apr-15 A 24-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 4
1232 Bridge Beams, SW Bay 5 129 23-May-15 27-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 5
A
1228 Bridge Beams, SW Bay 8 105 17-Jun-15 A 25-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 8
1229 Bridge Beams, SW Bay 7 85 13-Jul-15 A 27-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 7
1230 Bridge Beams, SW Bay 6 72 27-Jul-15 A 24-Oct-15 A AC.Lot 1 Bridge Beams, SW Bay 6
1231 TD 264: Public road Bridge Axes 01-06 complete 0 19-Dec-15 AC.Lot 1 TD 264: Public road Bridge Axes 01-06 complete, 19-Dec-15 A
A
1239 Public Road Works 396 02-Apr-16 A 21-Jul-17 A AC.Lot 1 Public Road Works
1237 TD 271: Public road Bridge Axes 13-16 complete 0 02-Apr-16 A AC.Lot 1 TD 271: Public road Bridge Axes 13-16 complete, 02-Apr-16 A
1240 Temporary Road Works Right and Left Bank (acc. to a 253 27-Sep-16 21-Jul-17 A AC.Lot 1 Temporary Road Works Right and Left Bank (acc. to alternative 2)
A
1227 TD 107: Public road Bridge from Right Bridge Abutmen 0 21-Jul-17 A AC.Lot 1 TD 107: Public road Bridge from Right Bridge Abutment to Axis 16 comple
1238 Connection between Temp. Road and Existing East R 0 21-Jul-17 A AC.Lot 1 Connection between Temp. Road and Existing East Road to be completed
1242 Permanent Road Works at Service Area Right and Le 214 21-Jul-17 A 28-Mar-18 A AC.Lot 1 Permanent Road Works at Service Area R
1241 Connection between Permanent Road and Existing ro 0 28-Feb-18 AC.Lot 1 Connection between Permanent Road and Ex
A
ADMINISTRATION BUILDING
ADMINISTRA 721 22-Nov-15 28-Mar-18 A 28-Mar-18 A, ADMINISTRATION BUILDIN
A
General 721 22-Nov-15 28-Mar-18 A 28-Mar-18 A, General
1245 Civil Works 489 22-Nov-15 30-Jun-17 A AC.Lot 1 Civil Works
A
1247 Electrical works 521 20-Jul-16 A 28-Mar-18 A AC.Lot 4 Electrical works
1246 Finishing and Installation Works 496 20-Aug-16 28-Mar-18 A AC.Lot 1 Finishing and Installation Works
A
1249 Finishing of Control Room & Ready to Install Other Lot 389 20-Aug-16 23-Nov-17 A AC.Lot 4 Finishing of Control Room & Ready to Install Other Lots Eq
A
A2480 11KV MV Equipment 38 14-Oct-17 A 27-Nov-17 A AC.Lot 4 11KV MV Equipment
A2490 Protection System 104 19-Oct-17 A 18-Feb-18 A AC.Lot 4 Protection System
A2510 Fire Fighting System 21 20-Jan-18 A 13-Feb-18 A AC.Lot 4 Fire Fighting System
1248 Elevator - installation & testing 57 21-Jan-18 A 28-Mar-18 A AC.Lot 1 Elevator - installation & testing
A2500 Fire detection system 15 27-Jan-18 A 13-Feb-18 A AC.Lot 4 Fire detection system
SWITCHYARD 417 29-Oct-16 A 28-Feb-18 A 28-Feb-18 A, SWITCHYARD
General 417 29-Oct-16 A 28-Feb-18 A 28-Feb-18 A, General
1252 Primary Earthing 25 29-Oct-16 A 26-Nov-16 A AC.Lot 4 Primary Earthing
1253 Foundation Works 37 29-Nov-16 12-Jan-17 A AC.Lot 1 Foundation Works
A
1255 SWY Erection Works 92 12-Jan-17 A 30-Apr-17 A AC.Lot 4 SWY Erection Works
1254 Control Building, Fence, Cable Trenches 186 13-Jan-17 A 19-Aug-17 A AC.Lot 1 Control Building, Fence, Cable Trenches
1256 Control Building Equipment , Cable Trenches 318 22-Feb-17 28-Feb-18 A AC.Lot 4 Control Building Equipment , Cable Trenches
A
A2520 Lighting system 33 08-Jan-18 A 15-Feb-18 A AC.Lot 4 Lighting system
ANCILLARY BUILDINGS
B 396 20-Dec-16 28-Mar-18 A 28-Mar-18 A, ANCILLARY BUILDINGS
A
RIGHT BANK
BAN BUILDINGS 344 20-Feb-17 28-Mar-18 A 28-Mar-18 A, RIGHT BANK BUILDINGS
1261 Mosque 344 20-Feb-17 28-Mar-18 A AC.Lot 1 Mosque
A
1260 Auxiliary transformer and fire fighting tank building 138 20-Sep-17 28-Feb-18 A AC.Lot 1 Auxiliary transformer and fire fighting tank build
A
1263 Electrical works 137 21-Sep-17 28-Feb-18 A AC.Lot 4 Electrical works
A
1259 Guard houses and towers 60 20-Dec-17 28-Feb-18 A AC.Lot 1 Guard houses and towers
A
1262 Sewage treatment plant building 59 20-Dec-17 27-Feb-18 A AC.Lot 1 Sewage treatment plant building
A
LEFT BANK BUILDINGS 371 20-Dec-16 27-Feb-18 A 27-Feb-18 A, LEFT BANK BUILDINGS
1267 Pump house 222 20-Dec-16A 06-Sep-17 A AC.Lot 1 Pump house
A
1268 Electrical works 232 01-Jun-17 A 27-Feb-18 A AC.Lot 4 Electrical works
1266 Guard houses and towers 50 30-Nov-17 27-Jan-18 A AC.Lot 1 Guard houses and towers
A
1265 Sewage treatment plant building 15 01-Jan-18 A 18-Jan-18 A AC.Lot 1 Sewage treatment plant building
EXTERIOR A
ARRANGEMENTS 75 31-Dec-17 28-Mar-18 A 28-Mar-18 A, EXTERIOR ARRANGEMENT
A
RIGHT BANK
BAN 75 31-Dec-17 28-Mar-18 A 28-Mar-18 A, RIGHT BANK
1271 Bus parking area 75 31-Dec-17 28-Mar-18 A AC.Lot 1 Bus parking area
A
1273 Maintenance area / crane zone 75 31-Dec-17 28-Mar-18 A AC.Lot 1 Maintenance area / crane zone
A
1272 Fence 25 18-Jan-18 A 16-Feb-18 A AC.Lot 1 Fence
1274 Car parking area 59 18-Jan-18 A 28-Mar-18 A AC.Lot 1 Car parking area
LEFT BANK 60 17-Jan-18 A 28-Mar-18 A 28-Mar-18 A, LEFT BANK
1276 Fence 60 17-Jan-18 A 28-Mar-18 A AC.Lot 1 Fence
1278 Unloading area 47 01-Feb-18 28-Mar-18 A AC.Lot 1 Unloading area
A
1277 Car parking area 34 17-Feb-18 28-Mar-18 A AC.Lot 1 Car parking area
A

Milestone Lot 1 Lot 2 Page 19 of 19


Milestone Lot 2 Lot 3
Milestone Lot 3 Lot 4
Milestone Lot 4 Remaining Work
Lot 1 Critical Remaining Work