Sunteți pe pagina 1din 12

RISK ASSESSMENT

PROJECT NAME: SE-57, CONSTRUCTION OF 10 VILLAS @ GIARDINO VILLAGE


LOCATION: THE PEARL QATAR

LIKELIHOOD
Certain 5 5 10 15 20 25
Probable 4 4 8 12 16 20
Possible 3 3 6 9 12 15
Improbable 2 2 4 6 8 10
Negligible 1 1 2 3 4 5
CONSEQUENCE Slight 1 Minor 2 Significant 3 Severe 4 Major 5
INTOLERABLE (15 TO 25)
Operations must not proceed: alternative methods to conduct this task must be implemented.
INTERMEDIATE (4 TO 12)
Risks should be reduced to as low as reasonably practicable (ALARM). The higher the risk. The more effort must be given to reducing the risk.
This task should be reassessed at regular intervals to evaluate that the existing control measures are adequate.
TOTERABLE (1 TO 4)
This task may proceed with or without additional control measures. But if measures can be implemented to further reduce risk these should be
implemented.
Possible multiple deaths and/or serious structural An event which is certain to occur unless
 MAJOR  CERTAIN
damage immediate controls are applied
Possible death, severe multiple injuries (LTI – An event which is likely to occur unless control
 SEVERE  PROBABLE
Medevac) measures are improved
Possible significant injuries / multiple minor injuries An event which may occur despite existing control
 SIGNIFICANT  POSSIBLE
(Probable LTI) measures
Possible significant injuries (Medical treatment/first An improbable event, but could occur it control
 MINOR  IMPROBABLE
Aid) measures are disregarded
Possible slight/no potential risk of injuries(Possible
 SLIGHT  NEGLIGIBLE A highly unlikely event.
first Aid)
Any number 15 or above is intolerable and the task must not commence until alternative methods have been introduced. Any number 4 to
12 risks are deemed as tolerable, risks must have been reduced to as low as reasonably practicable (ALARM). Additional control measures
may be required and the tasks should be re-assessed at regular intervals. Numbers 1 to 4 are tolerable, but risks should be reduced further
if easily achievable.

Page 1 of 12
ACTIVITY: DEMOLITION OF REINFORCED CONCRETE SLAB - COLUMN - BEAM - PLINTHS

ACTIVITIES POTENTIAL Who or RISK CONTROL MEASURES Residua Risk


HAZARDS What RATING l Risk Response
might be S L R C S L RR Owner
harmed R

Task 1 : Mobilization of Materials , Manpower Equipment for Demolition


1. Permit, gate pass Unauthorized SEC, 3 4 1  Ensure that all personnel are having UDC gate pass 3 1 3 Timekeeper
& certificates personnel cause Workers 2 to avoid penalty from Client. / document
to penalty from assigned  All required documents for gate pass purpose to be controller,
Client submitted in advance. Safety
Misunderstanding  Full Work Pack (Adequate Work Permit, Method officer, Site
of the plan due to Statement, Risk Assessment, Drawings, etc...) shall Engineer,
wrong be approved and available to be consulted. Supervisor
implementation  All documents shall be placed in the corresponding
work pack shed near place of works
 Necessary work permit shall be taken from SEC HSE
department before starting the job.
 Ensure that a job will be carried out as per
approved drawing and specification.
2. Communication Poor Workers 3 4 1  Ensure that a communication on site will be 3 1 3 Safety
communication assigned 2 provided by radios and cellular phones (if the officer, Site
Cellular phone doesn't work in all areas, radios will Engineer,
be preferred). Supervisor
3. Provision of safe Slips, trips and fall Workers 3 5 1  Ensure to have defined, clear/unobstructed access 3 1 3 Safety
access/egress to Obstructed assigned 5 walkways and free from any type of obstructions. Officer /
the work location. walkways  Audible & relevant warning signs must be displayed Supervisor
or posted.
 Ensure to provide isolation zone and relevant safety
controls.
 STARRT and or RAMS discussed to all persons
involved in the task prior to works commencing.

Page 2 of 12
 Trained, competent and authorized Supervision will
be present at all times to ensure employees /
workers are following the Safe working procedures
Poor planning at all times.
 Ensure appropriate planning arrangement for
coordination, responsibilities and authority of
management personnel during the progress of the
work.
 Ensure to apply a PTW for all activity related to
ddemolition and hot works activity.
 Ensure the use of suitable plant and equipment
 Ensure a proper arrangements for delivering,
stacking, storing and movement of materials and
tools
4. Manual handling Slip Trip & Fall Workers 3 5 1  Avoid manual handling where possible 3 1 3 Safety
Back injury assigned 5  Ensure STARRT and/or RAMS are discussed with the Officer /
Sharp objects work group prior to works commencing Supervisor
Heavy objects.  If manual handling cannot be avoided, automation,
Hand injury mechanization and the use of lifting and transport
Musculoskeletal equipment should be considered (e.g. conveyors,
disorders hoists, cranes, vacuum lifting devices, lift tables,
Cuts, abrasions pallet trucks, lift trucks, barrows, trolleys).
and fractures However, attention should be paid to ensure that
new work risks are not created (e.g. through noise,
or hand-arm vibration).
 Heavy or frequent manual handling tasks should be
carried out by several people or, if possible, the
amount that is handled should be reduced or the
load split into smaller ones
 The rate of manual handling should not be set by a
machine, supervisor or colleagues. The time taken
to carry out manual handling tasks should be
extended by taking breaks, or by alternating them

Page 3 of 12
with other tasks so that the muscles have time to
recover
 Employees are provided with the correct lifting /
handling techniques
5. Work during Heat stress in Assigned 3 5 1  Comply with Qatar Regulation regarding Summer 3 1 3 Safety
extreme weather/ Summer worker 5 Working Hours. Officer /
climate conditions. Dehydration  Ensure to regularly check the heat/humidity index, Supervisor
Heat Stroke measure of humidity levels and adjust the
Heat Stress work/rest cycles accordingly.
Muscle cramps  Provision of insulated flasks to all operatives to be
Fainting filled with cool water.
Feeling Sick  Job rotation among operative to reduced exposure
Over fatigue time.
 Take plenty of water,
 Do urine test for dehydration.
 Take rest underneath the shed as per heat stroke
prevention procedure.
 Lay the person flat or head down in a cool and open
place, loosen clothing. Call the emergency if
necessary.
 Advise to sit down and lie down.
 Always carry the personal water bottle with water
while working on site.
 Ensure adequate and cool drinking water always
available in the site.
 Provide adequate rest shelter.
 Ensure that heat index is updated at all the times.
 All people must be trained for heat stress training.
 Buddy system must be applied.
 STARRT and/or RAMS discussed to all persons
involved in the task prior to works commencing
 Trained, Competent and Authorized Supervision
will be present at all times to ensure

Page 4 of 12
employees/workers follow safe working procedures
at all times.
 SEC will follow summer working hours to meet
Ministerial Decision No. 16 of 2007, Ministry Of
Labour – Notification, In reference to the
ministerial decision No. 16 of the year 2007,
determining working hours in bare sites in summer.
 Kindly note that, working hours from 15th of June
till 31st of August, shall not exceed 5 hours in the
morning, and not exceeding 11:30am and shall not
start in the evening period before 3:00pm.
 Any employer must fix time table for daily working
hours, in clean place, readable by the workers and
recognized by Safety Inspectors, while visiting work
site.
 Any establishment violate this decision shall be
closed for one month by an order from the
Minister.

Task 2 : Coring and cutting work

1. Plant movement Injuries / fatalities Assigned 3 5 1  Enclose the area by hoarding or fences 3 1 3 Safety
clearance caused by contact worker 5  Always signal intention when operating. Officer /
with the  Keep a minimum of 10m away from the equipment Supervisor
equipment  Conduct daily tool box meeting to instruct the
workers not to enter the working radius unless
positive communication shall been established and
equipment power terminated.
 Provide “DANGER” signage. Banksman for all
vehicle movement and will always be placed in a
safe position.
 Close supervision must be maintained.
 Pre-task briefing on TMP and work methodology.

Page 5 of 12
 Before swinging, banksman & signal man will be
there and the area shall be barricaded & ensure
that it is clear of anyone who is not involved in this
process
 Segregate vehicular and pedestrian access
2. Coring and cutting Contact with Assigned 3 5 1  Ensure a proper close supervision by the 3 1 3 Safety
operation coring machine, worker 5 Supervisor/Foreman during work task activity Officer /
flying debris, noise  Ensure that all working areas are free from any Supervisor
and respiratory hazardous materials
problem  All tools and equipment to be inspected and color
coded by the HSE department prior to use.
 All personnel using tools and equipment shall be
trained by HSE department.
 Cables should be routed properly to avoid any
damage to the cable
 Install barricading and Caution signs along the area
 Use of protective goggles/ visor helmets by
machine operator
 Exclusion zone around the working area to allow
authorized entry only
 Wear appropriate PPE especially earplugs and dust
mask during activity.
Risk to other Assigned 3 5 1  Work area should be delineated off from Un- 3 1 3 Safety
personnel worker 5 Authorized personnel & signs posted Officer /
 All personnel must use caution when in or around Supervisor
saw cutting areas
 Proper PPE shall be worn by adjacent personnel, as
required by their proximity to the work task.
Injury from Assigned 3 5 1  All connections, mountings, guards & controls on 3 1 3 Safety
improper set up worker 5 the equipment must be inspected prior to use. Officer /
or operation.  Ensure there has been a Penetration Permit briefing Supervisor
& permit is signed & on site.
 All operators of this equipment shall be trained on
that piece of equipment.

Page 6 of 12
 Operator must wear proper PPE. (Face shield,
safety glasses & hearing protection minimum).
Exposure to silica Assigned 3 5 1  Ensure half face respirators are required for core 3 1 3 Safety
based product worker 5 drilling into concrete. Officer /
 Ensure a water suppression during coring to avoid Supervisor
spreading of silica dust
3. Stability of Uncontrolled Assigned 3 5 1  Demolition to be conducted remotely using high 3 1 3 Safety
structural frame collapse of worker 5 reach demolition plant. Officer /
relies upon in- adjacent beams  Total exclusion zone to be established around villa Supervisor
plane rigidity and column perimeter to protect workforce and the others.
created by slab, sections.  Ensure full sight line maintained using stepped
column, beam and approach to demolition
plinths.  Stand-off demolition machine from side elevation.
 Remove floors one at a time to avoid excessive
loading from debris.
 Work in a pre-determined sequence towards shear
walls.
 Maintain total exclusion zone around villa
perimeter.
 Clear all demolition debris from floors as it arises
Heavy structural Assigned 3 5 1  Pulverize structural elements in situ and reduce in 3 1 3 Safety
sections due to worker 5 size prior to lifting clear of the building. Officer /
falling sections  Maintain shear walls within villa and commence Supervisor
cause failure of demolition from “free ends” working towards
precast sections points of fixity at each level.
below.
Task 3 : Use of tools and equipment
1. Using portable Hair or clothing Assigned 3 5 1  Loose clothing to be kept clear of moving parts of 3 1 3 Safety
tools becoming worker 5 power tools. Officer /
entangled in  Operatives shall be trained in the correct use of Supervisor
moving parts portable tools.

Page 7 of 12
Eye injuries from  Suitable eye protection to be worn where there is a
dust, swarf or foreseeable risk of eye injury.
other fragments  Suitable RPE to be worn where there is a
foreseeable dust hazard.
Wrist and hand  Tools must be used in accordance with
injuries due to manufacturer’s instructions.
tool jamming or  Qualified persons will test all portable electrical
binding equipment at recommended regular intervals.
Hand/Arm  Select power tools with lowest vibration level.
Vibration  A tool producing high levels of vibration to have
Syndrome (HAVS) anti-vibration handles to reduce the risks Hand/Arm
Vibration Syndrome (HAVS).
Air/hydraulic lines  Noise Assessment required where deemed
becoming necessary.
detached or  A safe working platform is required when using a
bursting power tool (in preference to equipment such as a
step ladder).
Electrocution / Assigned 3 5 1  All power feeds, electrical, pneumatic or hydraulic, 3 1 3 Safety
electric shock worker 5 to comply with European or British Standards and Officer /
maintained in good condition. Supervisor
 Where practicable only 110v electrical tools will be
used.
 Portable tools shall only be used in well-lit and
ventilated areas
Task 4 : Using Mobile Crane (Lifting of Slab)

1. Movement of General Assigned 5 4 2  Operator must secured with valid Qatar Driving 4 1 4 Supervisor
mobile crane worker 0 License and Third party certificates. Operator
Operator Riggers must have valid Third Party Certificates.
 Mobile Crane to approved by certified by Third Party.
 STARRT CARD, Permit to Work and Lifting Plan signed
by Lifting Supervisor.
 Lifting zone to be isolated.

Page 8 of 12
 No Unauthorized lift shall be permitted.
Overturned Assigned 5 4 2  Ensure that ground is level and firm 4 1 4 Engineers
worker 0  Ensure to follow a lifting plan and the lifting Foremen
Operator supervisor is always present Operator
 Lifting plan shall be communicated to workforce Safety
properly Officer
Rigger
Failure to lifting Operator 5 4 2  All lifting equipment is to be certificated and 4 1 4 Engineers
equipment Workers 0 inspected regularly. Foremen
resulting to Property  A copy of certification/ third party certificate is to be Operator
damage the damage retained on site for record keeping and reference. Safety
property/death or  Qualified Slinger / Signaller/Rigger/Operator to carry Officer
injury out visual inspection prior to use Rigger
 Discuss/Quarantined all damaged parts of
equipment.
Falling materials Operator 5 4 2  All lifts are to be carried out by competent trained 4 1 4 Engineers
resulting to Workers 0 qualified slinger/signaller. Foremen
damage the Property  Competent Rigger, Operator Operator
property/death or damage  All lifts are to be carried out as directed in the lifting Safety
injury assessments and schedule of common lifts Officer
 Isolate the lifting area. Rigger
 Lifting plan should be provided.
 Third party certificate for lifting equipment.
Heavy loads Operator 5 4 2  Visual assessments are to be made by competent 4 1 4 Engineers
resulting to failure Workers 0 personnel to ensure the correct lifting equipment is Foremen
of lifting Property used for the lift and that the crane is able to lift the Operator
equipment and damage weight of the load at the required radius Safety
machinery  All lifts are to be carried out as directed in the lifting Officer
assessments and schedule of common lifts Rigger
 Lifting plan.
 Competency of Rigger/operator.
 Area isolated.

Page 9 of 12
Swinging of loads Operator 5 4 2  Tag lines shall be attached to load before lift 4 1 4 Engineers
potential to Workers 0 commences. One tag line each end allow for full Foremen
contact with Property control of load. Personnel instructed never to wrap Operator
nearby structures damage tag lines around hand, always hold with palm of Safety
and plants and or hand. Officer
due to heavy  Competent Rigger/operator. Rigger
winds  Ensure load balanced or not.
 Close supervision.
Failure of hoisting Operator 5 4 2  Competent riggers shall attach load to lifting 4 1 4 Engineers
due to unsecured Workers 0 equipment ensuring correctly connected. Load Foremen
loads Property will be secured to trailers with ratchet straps. Operator
damage  Third inspection for Webbing Slings, Safety
Hooks/Hooks equipment. Officer
 Isolate the area. Rigger
 Close Supervision.
Hooking of master Operator 5 4 2  Competent riggers shall attach slip to main block 4 1 4 Engineers
link sling to crane Workers 0 ensuring correctly connected. Also to be ensured the Foremen
main block Property safety latch is in good condition. Operator
resulting to damage  Third party inspection certificate for the sling to be Safety
unsecured loads, submitted and visual inspection to be done by the Officer
slips of loads or assigned rigger. Rigger
damage sling  Close supervision.
Task 5 : Night Works ( If Required )
1. Inadequate Could lead to trip Assigned 3 5 1  Task lighting shall be provided in order to ensure 3 1 1 Safety
Illumination slip or other injury worker 5 adequate lighting levels are achieved inspector /
 Lux Surveys shall be conducted in order to verify Supervisor
lighting level
2. Use of tower lights Electrical hazard, Assigned 3 5 1  Only competent electrical person can allowed to
spillage, fire and worker 5 operate the tower light.
hand and body  Drip tray must be provided in tower lights using at
injuries the site.

Page 10 of 12
 Ensure appropriate earth ground must be installed
and connected to tower light as per manufacturer
guidelines.
 Ensure adequate pre inspection / maintenance has
been carried out.
3. Work at night Fitness to work at Assigned 3 3 9  All night shift personnel will be offered a free health 3 1 1 Site Nurse,
night shift worker assessment before they start working nights and on Safety
a regular basis after that (a follow-up examination inspector /
by a health nurse should be provided where Supervisor
necessary)
lack of proper Assigned 3 5 1  Ensure that all personnel will be required to attend 3 1 1 Site Nurse,
sleep, worker 5 specific toolbox talks prior to working at night Safety
Workers on the  All night and shift workers will be provided with inspector /
night shift end sufficient information, instruction and training to Supervisor
up tired and ensure their health and safety whilst undertaking
worn down, tasks
developing
fatigue and
irritability.
Increased levels Assigned 3 3 9  SEC will ensure that employees on night work do 3 1 1 Site Nurse,
of tiredness and worker not work more than on average 48 hours a week Safety
fatigue, calculated over a successive 17 week reference inspector /
Development of period Supervisor
stress on the
 SEC will ensure that night workers’ normal working Engineer
body
hours do not exceed more than an average of eight
hours in each 24 hour period as calculated over a
successive 17 week reference period.
 Site Engineer shall review the safe systems of work
to ensure they take into account night and work.
 Project Manager will review existing safe systems of
work for specific activities to ensure that they have
adequately addressed the additional psychological
and physiological hazards.

Page 11 of 12
Task 6 : Emergency Procedure and Response
1. Emergency Poor Assigned 3 3 9  In Case of any emergency all work to be 3 1 1 Safety
procedure & Communication worker stopped ,shut down all running equipment & inspector /
Response Machineries and reported to muster point Supervisor
 Proper communication prior to emergency
evacuation shall be well circulated and discuss
Improper
access/Egress to all personnel at site.
 All access and ingress shall be clear to any
obstruction and available at all times.
 All access and ingress shall be properly marked
to know where the exact location of muster
point is.
 All workforces shall know the muster point
location
Emergency
 Emergency numbers shall be posted and clear
Numbers.
of instruction in case of emergency.

Prepared by Sub con.: HSE Manager: Reviewed by: Approved by:

Signature: Signature: Signature: Signature:


Francis Tan Engr. Ahmed Zakaria Engr. Tamer Ali
Date: 14 June 2018 Date: 14 June 2018 Date: 14 June 2018 Date: 14 June 2018

Page 12 of 12

S-ar putea să vă placă și