Documente Academic
Documente Profesional
Documente Cultură
LIST OF ITEMS
ROAD WORKS
Item No 2.1 : Subgrade Filling
Subgrade filling (With material from outside source)
material Cost Cost
Notes & Comments for Item No 2.1:
Material Cost from Outside source Cum 100.00 #REF! #VALUE! Material Cost - Rs.
243/cum i) The Rate Analysis has done for 100cum
Lead (Considering 8 Km) Cum 100.00 -
Equipment Cost ii) Rs. 5.5/- per cft is the gravel cost
Dozer Hr 1.00 #REF! #VALUE!
iii) The Lead considered 8km
Grader Hr 3.00 #REF! #VALUE!
Water Tanker Hr 4.00 #REF! #VALUE! BOQ:
Vibrator Roller Hr 2.00 #REF! #VALUE!
Filling of Subgrade gravel with approved materials obtain
Equipment Cost for land/Barrow pit outside including all lifts and lead transpor
Diesel Charges Ltr #REF! #REF! #VALUE! Levelling work - in layers of 150mm thick loose, breaking cloads dressing
Rs.86/cum line, curves, grade and section, watering the earth to O.M
Dozer Operator cost Hrs 1.00 #REF! #VALUE!
vibromax roller capacity of 8 to 10 tone for compacting the
Grader Operator cost Hrs 3.00 #REF! #VALUE! requirements as per specification 305-2 table 300-2. MOR
Water tanker Operator cost Hrs 4.00 #REF! #VALUE! 305
1 of
vibromax roller capacity of 8 to 10 tone for compacting the
requirements as per specification 305-2 table 300-2. MOR
305
Vibrator Operator cost Hrs 2.00 #REF! #VALUE!
Manpower Cost
Semi-skilled Day 0.50 #REF! #VALUE!
Mazdoor Day 1.00 #REF! #VALUE!
Supervision Charges -
Site Supervisor Day 0.60 #REF! #VALUE!
RS. 10/cum
Surveyor Day 0.15 #REF! #VALUE!
Engineer Day #REF! #VALUE!
Total cost for 100 Cum subgrade
#REF!
work
Cost per cum / 100 #REF! 325
Over Head & Other operational
%age #REF!
costs
Total Item No 2.1 Per cum #REF! Top
Item No 2.3 : WMM (Considered 360 Cum of WMM laying) Notes & Comments for Item No 2.3:
Item No 2.6 : Tack Coat (considering 10 sqm) Notes & Comments for Item No 2.6:
Emulsion MT 0.00315 #REF! #VALUE! 3 Kg per 10 Sqm
i) The Rate Analysis has done for 10sqm
Contractor charges for supply of ii) The rate application taken as 0.3kg per sqm incl. wasta
Sqm 10 3.50 35.00
aggregate, mixing and laying.
BOQ:
Cost of 1 sqm of #REF! Providing and applying Tack coat with bitumen emulsion
Over Head & Other operational granular Base including clearing of road surface and spra
%age #REF!
costs Sqm using mechanical means. MORTH Specification-503
Total Item No 2.1 Per Sqm #REF! Top #REF!
Item No 2.7: SDBC Laying Notes & Comments for Item No 2.7:
Contractor charges for supply of i) The Rate Analysis has done for 1 cum
1 Cum 1 3,500.00 3,500.00
aggregate, mixing and laying. ii) The Bitumen content considered 115kg/cum
Bitumen (60/70 grade - Includes iii) Material (excl. Bitumen) and laying contractor rate (Rs.
transportation and any handling MT 0.12075 #REF! #VALUE! quotation for SDBC from the contractor
2 charges) BOQ:
Cost of 1 Cum of Premix #REF! Providing and laying hot mix hot laid Semi Densed Bitum
Over Head & Other operational compacted thickness with 4.5 % bitumen content by weig
%age #REF!
costs surface with specified graded crusher aggregates for the
Total Item No 2.1 Per cum #REF! Top loading of aggregate, heating of stone aggregates and bit
drum mix type of hot mix plant transporting the hot mix to
material with sensor Paver finisher to the required grade,
Item No 2.8: Kerb construction power roller and vibratory roller to achieve the desired de
Materials (for 1 Rm) should
Notes & beComments
60/70). MORTH Specification-511
for Item No 2.7:
Concrete blocks of 0.5 mtrs length Cum 0.1035 #REF! #REF!
i) The Rate Analysis has done for 1 Rm
Transportation Cost for 30 Rm
kerb (with a lead of 4 km) considering 26 days and
Tractor Hour rental Charges Hr 1.50 #REF! #VALUE!
ii) The 1cum mortor considered for 50rm of kerb
8 hrs
Diesel consumption for 3 tractors Lts #REF! #REF! #VALUE! iii) The mix considered as PCC 1:3:6
Tractor Operator Salary Hr 1.50 #REF! #VALUE!
BOQ:
Transportation cost for 1 Rm kerb #REF! Providing and fixing Concrete Kerbs of size 150 X 500 m
Manpower for Shifting and placing
of blocks
Mazdoor Day 0.01 #REF! #REF! For curing
Mazdoor Day 0.04 #REF! #REF! For loading and
Site Supervisor Day 0.01 #REF! #VALUE! unloading
4 of
Item No 2.9: Provifing of PCC (1:3:6)
Material Cost Notes: PCC
Cement Kg 180.00 #REF! #VALUE!
i) The Rate Analysis has done for 1 cum
Fly Ash Kg 50.00 #REF! #VALUE!
Water Ltr 130.46 #REF! #VALUE! BOQ:
Providing and laying in position in-situ cement concrete o
20 mm Agg. MT 0.76 #REF! #VALUE! unit cement, 3 units sand, 6 units coarse aggregates) of tr
10 mm Agg. MT 0.48 #REF! #VALUE! stones for foundation and bedding formwork, compacting
River Sand Cum 0.55 #REF! #VALUE!
Shuttering Sqm 0.60 300.00 180.00
Equipment Cost
Considering 1 Cum of
RMC Hr 0.30 #REF! #VALUE! concrete
Disel Charges Ltr #REF! #REF! #VALUE!
RM-800 Operator Cost Hrs 0.30 31.00 9.30
Manpower Cost
Mason Day 0.15 #REF! #VALUE!
Mazdoor Day 1.76 #REF! #VALUE!
Site Supervisor Day 0.11 #REF! #VALUE!
Surveyor Day 0.10 #REF! #VALUE!
Cost of Placing of 1 Cum of PCC #REF!
Over Head & Other operational
%age #REF!
costs
Total Item No 2.1 Per cum #REF! Top
Item No 3: Earthwork in back filling / filling with excavated earth (Insitu Materia
Material Cost (Considered 100 Cum for calculation)
Soil (Transport Cost) MT 100.00 104.00 10,400.00
Equipment Cost Notes & Comments for Item No 3:
Dozer Hr 2.67 #REF! #VALUE!
i) The rate analysis done for 1 cum
Water Tanker - 12KL Hr 3.25 #REF! #VALUE!
Vibratory Roller Hr 3.25 #REF! #VALUE! ii) Only dozing and compaction considered on
existing surface
Diesel Ltr #REF! #REF! #VALUE!
Dozer Operator cost Hrs 2.67 #REF! #VALUE!
Water tanker Operator cost Hrs 3.25 #REF! #VALUE!
Vibrator Operator cost Hrs 3.25 #REF! #VALUE!
Manpower Cost
Semi Skilled labor Day 0.50 #REF! #VALUE!
Mazdoor Day 1.50 #REF! #VALUE!
5 of
Site Supervisor Day 1.00 #REF! #VALUE!
Total cost for 100 Cum #REF!
Cost per cum of G6 Material /100 #REF!
Over Head & Other operational
%age #REF!
costs
Total Cost for filling of 1 Cum of
G6 laying (material brought from Per Cum #REF! #REF!
outside)
6 of
Item No 2.1:
gravel cost
8km
7 of
Item No 2.2:
lusive of Fuel.
Item No 2.3:
Item No 2.5:
done for 1 cum
onsidered 108kg/cum
idered revised rate with 5% extra for transportation & Entry tax
Item No 2.7:
done for 1 cum
onsidered 115kg/cum
n) and laying contractor rate (Rs. 3520) considered fron recent
the contractor
done for 1 Rm
s PCC 1:3:6
crete Kerbs of size 150 X 500 mm (of any shape) each piece
10 of
done for 1 cum
Item No 3:
for 1 cum
action considered on
735000
11 of