Documente Academic
Documente Profesional
Documente Cultură
SJVN
POWERING PROGRESS, INNOVATION & EXCELLENCE
The SJVN Ltd ( formerly Satluj Jal Vidyut Nigam Limited –SJVNL) SJVN Limited, a Mini
Ratna, Category-I and Schedule –‘A’ CPSE under administrative control of Ministry of
Power, Govt. of India, was incorporated on May 24, 1988 as a joint venture of the
Government of India (GOI) and the Government of Himachal Pradesh (GOHP). SJVN is now a
listed Company having shareholders pattern of 64.46% with Govt. of India, 25.51% with
Govt. of Himachal Pradesh and rest of 10.03% with Public. The present paid up capital and
authorized capital of SJVN is Rs. 4,136.63 Crore and Rs. 7,000 Crore respectively. The
present Net Worth as on 31.03.2016 is Rs.11063.86 Crore.
Beginning with a single Project and single State operation (i.e. India’s largest 1500 MW
Nathpa Jhakri Hydro Power Station in Himachal Pradesh) the Company has commissioned
projects namely 412 MW Rampur Hydro Power Station in Himachal Pradesh, 47.6 MW
Khirwire Wind Power Project in Maharashtra and 5.25 MW Charnakha Solar Power Plant in
Gujarat. SJVN is presently implementing Power Projects in Himachal Pradesh, Uttarakhand,
Bihar and Gujarat in India besides neighbouring countries viz. Nepal and Bhutan.
Portfolio
The present installed capacity of SJVN is 1,964 MW (comprising of 1912 MW Hydro +
47.6 MW Wind Power + 5 MW Solar Power).
SJVN has expanded its horizons and envisions developing itself into a fully diversified
transnational Power Sector Company in all types of conventional & non-conventional forms
of energy along with Power Transmission. The Company, at present, is implementing (under
various stages of development) 10 Hydro Power Projects totalling 3,200 MW (7 Projects-
1,130 MW in India, 3 Projects of 2,070 MW in neighbouring countries of Nepal & Bhutan),
one 1320 MW Thermal Power Project at Buxar in State of Bihar and 50 MW Sadla Wind
Power Project in Gujarat. SJVN commissioned 86 ckm 400 kV double circuits Indo-Nepal
Cross Border Power Transmission corridor between Dhalkebar (Nepal) and Muzzafarpur
(India) on 17.02.2016 in JV with Power Grid, IL&FS, and Nepal Electricity Authority. The
same was dedicated to nation by Hon’ble Prime Minister of India on 20.02.2016. In addition
to above, Company is engaged in implementation of 400 kV double circuit associated
transmission line of 310 km length for its 900 MW Arun-3 Project in Nepal.
Cabinet Committee on Economic Affairs (CCEA) accorded investment approval on
21.03.2017 to 900 MW Arun-3 Project in Nepal. Naitwar Mori HEP (60 MW ) in
Uttarakhand is in the process of investment decision with all clearances in hand while the
investment decision for pre-construction activities and other statutory clearances in respect
of rest of survey and investigations projects is also in progress
Subsidiaries
SJVN Arun -3 Power Development Company Pvt. Ltd. (SAPDC)–Fully owned
subsidiary incorporated in Nepal for implementation of 900 MW Arun-3 Project in Nepal.
SJVN Thermal Private Limited –Fully owned subsidiary incorporated for execution of
1320 MW Buxar Thermal Power Project in Bihar
Joint Ventures
Cross Border Power Transmission Company Limited (CPTC)-To construct and maintain
86 ckm long, Twin Moose, 400 kV D/C transmission line from Muzaffarpur Nepal
connection point and a bay extension at Muzaffarpur Sub Station.
Bengal Birbhum Coal Fields Ltd - for mining of Coal from the Coal Block allocated to the
six power utilities including Buxar TPP of SJVN.
Financial Performance
The total Income of the Company for the FY 2015-16 was Rs. 2,908.21 Crore and earned
profit after Tax @ Rs. 1,408.48 Crore. SJVN has declared dividend (excluding Dividend
Tax), of Rs. 455.03 Crore. Interim dividend of Rs. 930.74 Crores paid for the FY 2016-17.
Mission
To drive socio-economic growth and optimize shareholders and stakeholders interest
by:
Developing and operating projects in cost effective and socio-environment friendly manner.
Nurturing human resources talent with care.
Adopting innovative practices for technological excellence.
Focusing on continuous growth and diversification.
Objectives
In the pursuit of above mission, the company had set for itself the following corporate
objectives:
Operating and maintaining power stations with maximum performance efficiency.
Establishing and following sound business, financial and regulatory policies.
Taking up of other hydro power projects.
Completion of the new projects allocated to SJVN in an efficient and cost effective manner.
Use of the best project management practices for the project implementation by applying
latest universally accepted Project Management Techniques, and by enabling its Engineers,
to become certified Project Managers through further trainings.
Dissemination of available in-house technical and managerial expertise to other utilities /
projects.
Creating work culture and work environment conducive to the growth and development of
both the organization and the individuals through introduction of participative management
philosophy.
Fulfilling social commitments to the society. Achieving constructive cooperation and
building personal relations with stakeholders, peers, and other related organization.
Striving clean and green project environment with minimal ecological and social
disturbances.
To strive for acquiring Nav Ratna Status.
Beneficiary Project
affected
states people
SJVN Projects
SJVN’s Hydro Projects
Devsari HEP
Devsari HEP with installed capacity of 252 MW is located on River Pinder, on Ganga basin,
in Chamoli district of Uttarakhand. The project is designed as Run of the River project and
has the potential to generate 910.16 MU of electricity in a year.
A Memorandum of Understanding for execution of project was signed with the Government
of Uttarakhand on November 21, 2005. The scheme was cleared by Govt. of Uttarakhand in
October, 2007 and by Standing Technical Committee in April, 2012.
DPR of the project was concurred by CEA in August, 2012. CEA revalidated concurrence of
DPR till 06.08.17. CEA has been requested for further extension of TEC beyond 06.08.17 by
one year. As desired by CEA on 12.09.17, NOC issued by State Govt. on 10.12.17.
Stage-I Forest Clearance (FC-I) was accorded by MOEF on 26.02.18. EAC in its meeting
held on 27.03.18 recommended Environment Clearance (EC).
For the acqusition of pvt. land, payment of land compensation released to State Government
and issuance of notification under section 11 is under process. CEA has vetted the project
cost amount to Rs 2138.67 Cr at Feb,2017 PL on 09.03.2018.
Dhaulasidh HEP
The Dhaulasidh Project with a generation potential of 66 MW is located on River Beas, part
of the Indus basin, in Hamirpur & Kangra districts of Himachal Pradesh. The project is
designed as a Run of the River project with a small live storage that would be utilized for
peaking power during the lean season.
The project holds potential of generating 247.25 million units of electric energy in a 90%
dependable year.
A Memorandum of Understanding for execution of project was signed with the Government
of Himachal Pradesh on 27th October, 2008. Govt. of Himachal Pradesh accorded TEC of
the project on 25.06.2011. Stage-I forest clearance accorded by MoEF, GoI on 06.03.2012
and further extended up to 01.11.2018. Environment clearance accorded on 21.02.2013.
Acquisition of private land as per LAAR Act 2013 is in process. Application for carrying out
SIA study submitted to GoHP on 11.05.17. Fresh revenue papers for SIA study submitted to
GoHP on 04.04.2018.
Construction period of the project is 54 months including infrastructure works.
Kholongchu HEP
Kholongchhu HEP was allocated to SJVN for the preparation of DPR on 22.07.2008. The DPR
for 600MW was approved by CEA and RGoB on 05.11.12 and 23.05.13 respectively.
Kholongchhu HEP with the proposed capacity of 600MW on the river Kholongchu in Bhutan will
generate 2568.88 MU annually.
CCEA approval from GoI received on 28.02.2014. Inter Governmental Agreement between
Royal Government of Bhutan (RGoB) and Government of India (GoI) for implementation of
Kholongchhu HEP was signed on 22.04.14. Hon’ble Prime Minister of India laid the
foundation stone for the Project on 16.06.14. The shareholders agreement between DGPC
and SJVN was signed on 30.09.2014. National Environment Commission (NEC) of RGoB
accorded Environment Clearance on 21.07.2014.
The project is being implemented jointly by SJVN and Druk Green Power Corporation (DGPC)
Bhutan. Joint Venture Company registered as "Kholongchhu Hydro Energy Ltd"(JV of SJVN &
DGPC) in Bhutan on 12.06.2015. Ground Breaking Ceremony of project was held on 18.09.2015
which was graced by His Royal Highness, the Gyaltshab. Bhoomi Poojan for township at Duksum
for residential and non residential buildings held on 13.12.2015.
Concession Agreement is under process of approval with RGoB. Infrastructure works of project
are in progress. Permanent works (30.5 km) of approach roads have been completed. Main Civil
works are under tendering process.
Thermal Project -
Buxar Thermal Power Project - SJVN signed MoU with Bihar State Power Holding
Company Limited (BSPHCL) and Bihar Infrastructure Company (BPIC) on 17.01.13 for
setting up Buxar Thermal Power Plant (2X 660 MW) at village Chausa, Distt. Buxar. SJVN
took over Buxar Bijli Company Private Limited on 04.07.13 and name changed to SJVN
Thermal Private Limited (a wholly owned subsidiary of SJVN Ltd) on 17.10.13. Power
Purchase Agreement (PPA) has been signed with Bihar State Power Holding Company
Limited (BSPHCL) for 85% share of power generation on bus bar rate.
The capacity addition from the Project to the Maharashtra state grid is 47.60MW.The PPA
for power has been signed with MSEDCL at a tariff of Rs 5.81/unit for 53 WEGs and Rs.
5.70/unit for 3 WEGs fixed for a period of 13 years respectively.
Sadla Wind Power Project-The Sadla Wind Power Project with an installed capacity of 50
MW is situated in village Sadla, Taluka Muli, District Surendranagar in the state of
Gujarat.EPC contract was awarded to M/s Inox Wind Limited. Total cost of EPC contract is
Rs. 330.00 crores and Rs. 41.77 crores for Operation and Maintenance contract for 10 years.
The project comprises of 25 Wind Electric Generators. The Project is in advanced stage of
construction and is scheduled to be commissioned during FY 2018-19.
PPA signed with Gujarat Urja Vikas Nigam Limited (GUVNL) for 38 MW on 30.01.2018.
The construction of work is in progress. As on 30.04.2018, out of 25 WEGs, tower
foundations of 16 WEGs and erection of 14 WEGs completed. 2 units (4 MW) have been
commissioned so far.
Solar Power
SJVN has diversified into Solar Power generation with commissioning of its first project in
Charanka Solar Park, Gujarat. The 5 MW Charanka Solar Power Project has been
commissioned on 31.03.2017. An MOU has also been signed between SJVN Limited and
Solar Energy Corporation of India (SECI) on 19.06.2015 to set up 500 MW grid connected
solar power projects. SECI shall facilitate for the development of Solar PV Power Project
and sale of power as well.
Captive Solar Power Plant at NJHPS-Main features of 230KWp, Grid Connected, Solar
Power Plant (Captive Solar Power Plant) at surge shaft of 1500MW NJHPS
Charanka 5 MW Solar PV Power Project
JVN has commissioned its first solar Plant i.e. 5MW Charanka Solar Power Project on
31.03.2017. The project has been developed under REC Mechanism and the PPA for brown
power has been signed with GUVNL on 03.03.2017 for a period of 25 years.
Board of Director
Sh. Nand Lal Sharma
Chairman cum Managing Director
Functional Directors
Director(Finance) Director(Electrical)
Director(Civil)
Action oriented:
HRM focuses attention on action, rather than on record keeping, written procedures
or rules. The problems of employees are solved through rational policies.
Development Oriented:
HRM intends to develop the full potential of employees. The reward structure is
turned to the needs of employees. Training is provided to improve the skill of
employees. Every attempt is made to use their talents fully in the service of
organisational goals.
Continuous Process:
HRM is not a one short deal. It cannot be practised only one hour each day or one
day a week. It requires constant alertness and awareness of human relations and
their importance in every day operations.
Compensation and Benefits: A company can attain its goals and objectives if it can
acclimatize to new ways of providing benefits to the employees. Some of the benefits
given by companies are listed below for our understanding:
1. Working hour flexibility
2. Extended vacation
3. Dental/Medical Insurance
4. Maternal/Paternal Leave
5. Education Reimbursement for children
Ensuring Legal Compliance: To protect the organization this function plays a crucial
role. The HR department of every organization should be aware of all the laws and
policies that relate to employment, working conditions, working hours, overtime,
minimum wage, tax allowances etc. Compliance with such laws is very much required
for the existence of an organization.
Managerial Functions
1. Planning: This function is very vital to set goals and objectives of an organization. The
policies and procedures are laid down to achieve these goals. When it comes to planning
the first thing is to foresee vacancies, set the job requirements and decide the recruitment
sources. For every job group, a demand and supply forecast is to be made, this requires
an HR manager to be aware of both job market and strategic goals of the company.
Shortage versus the excess of employees for that given job category is determined for a
given period. In the end, a plan is ascertained to eliminate this shortage of employees.
2. Organizing: The next major managerial function is to develop and design the structure
of the organization. It fundamentally includes the following:
1. Employees are grouped into positions or activities they will be performing.
2. Allocate different functions to different persons.
3. Delegate authority as per the tasks and responsibilities that are assigned.
3. Directing: This function is preordained to inspire and direct the employees to achieve
the goals. This can be attained by having in place a proper planning of career of
employees, various motivational methods and having friendly relations with the
manpower. This is a great challenge to any HR manager of an organization; he/she
should have the capability of finding employee needs and ways to satisfy them.
Motivation will be a continuous process here as new needs may come forward as the old
ones get fulfilled.
4. Controlling: This is concerned with the apprehension of activities as per plans, which
was formulated on the basis of goals of the company. The controlling function ends the
cycle and again prompts for planning. Here the HR Manager makes an examination of
outcome achieved with the standards that were set in the planning stage to see if there
are any deviations from the set standards. Hence any deviation can be corrected on the
next cycle.
Advisory Functions
1. Top Management Advice: HR Manager is a specialist in Human Resource Management
functions. She/he can advise the top management in formulating policies and procedures.
He/she can also recommend the top management for the appraisal of manpower which
they feel apt. This function also involves advice regarding maintaining high-quality
human relations and far above the ground employee morale.
2. Departmental Head advice: Under this function, he/she advises the heads of various
departments on policies related to job design, job description, recruitment, selection,
appraisals.
Introduction of topic
Job Satisfaction- Job satisfaction refers to how well a job provides fulfilments of a
need or a want, or how well it serve as a source or means of enjoyments.
Job satisfaction is the degree to which individuals feel positively or negatively about their
job.
There are several theories given which help in evaluating & measuring job satisfaction of
employees at workplace. Some of them are:
- Hierarchy of Needs by Maslow
- Hygiene Theory by Herzberg
These help in understanding the parameters or factors which influence job satisfaction of
employees at workplace.