Sunteți pe pagina 1din 13

Sustainable Energy Technologies and Assessments 16 (2016) 93–105

Contents lists available at ScienceDirect

Sustainable Energy Technologies and Assessments


journal homepage: www.elsevier.com/locate/seta

Original Research Article

Shallow geothermal energy for industrial applications: A case study


S. Focaccia a, F. Tinti a,⇑, F. Monti b, S. Amidei b, R. Bruno a,c
a
DICAM – Department of Civil, Chemical, Environmental and Materials Engineering, University of Bologna, Bologna, Italy
b
Nuovo Pignone S.p.A. – GE Oil&Gas, Firenze, Italy
c
CINIGEO – Italian National Interuniversity Consortium of Georesources Engineering, Rome, Italy

a r t i c l e i n f o a b s t r a c t

Article history: Shallow geothermal energy is of great interest for HVAC (heating, ventilation and air conditioning)
Received 20 October 2015 designers. While increasingly popular in the residential and commercial sectors, shallow applications
Revised 14 March 2016 are still little used in the industrial sector and unfamiliar to policy makers, designers and stakeholders
Accepted 9 May 2016
[1]. Despite this, geothermal applications are feasible for industrial plant for several reasons: operating
at high load factors and supplying energy to a single location, geothermal systems would cut energy
costs, a large slice of overall industrial production costs. This paper presents the results of a feasibility
Keywords:
study carried out for an industrial shallow geothermal project, where the required preheating to the inno-
Ground source heat pumps
Numerical simulation
vative Expanding-Gas-Power-Transformation (EGPT) process was supplied through a Hybrid
Expanding Gas Power Transformation Geothermal-Air Transcritical Heat Pump. Focus was given to modeling the geothermal component to
Sensitivity analysis comply with the heat pump working temperature requirements, integrating this with geostatistics and
numerical simulation of heat/water flows.
Ó 2016 Elsevier Ltd. All rights reserved.

Introduction  Summer cooling of buildings. In summer, underground temper-


atures are lower than the average temperature of air and
A shallow geothermal system (commonly closed loop/open loop superficial water [8].
geoexchange system) allows thermal energy exchange with the  Underground thermal energy storage (UTES). Underground
first 100–200 m of the underground within a specified volume temperatures are lower than the circulating fluid, causing heat
[2]. Shallow geothermal systems are designed to allow operational transfer to the surrounding underground area [9–11].
repeatability during the year, thereby avoiding thermal depletion
of the soil. Low enthalpy geothermal applications in the industrial sector
A so-called geoexchanger, whose temperature level (<100 °C) are still infrequent, temperatures exploited falling mainly into
falls within the range of low enthalpy geothermal systems [3,4], the medium enthalpy range (90 °C < T < 150 °C) [1].
is connected to a heat pump in a system that can be used for dif- The reason for the poor industrial uptake has to do with the
ferent purposes: heating and cooling of buildings, subsurface high temperature requirements of most industrial processes, in
energy storage, production of domestic hot water, de-icing and contrast to the low-temperature requirements of domestic hot
snow melting, conservation and reuse of waste heat from indus- water production. Despite this, certain industrial processes do pre-
trial processes [5]. sent conditions conducive to geothermal applications. These
Heat pumps exploit heat from ambient sources. The warmer the include high load factor operations, single-location load concentra-
source, the higher their efficiency. Given the virtual absence of any tion requirements, and industrial operations where energy is a
seasonal temperature variability, underground sources enhance major production cost item [12].
heat pump capability [6]. Examples of use include: The main recent applications of medium enthalpy reservoirs for
industrial purposes have been the Organic Rankine Cycle (ORC)
 Winter heating of buildings. In winter, underground tempera- production of electrical energy [13,14], the production of heat
tures are higher than the average temperature of air and and cold distributed to final users through pipeline networks
superficial water [7]. (district heating and cooling) [15] and thermal energy storage
applications [16].
⇑ Corresponding author at: via Terracini 28, 40131 Bologna, Italy. Tel.: +39 An application of medium enthalpy geothermal resources with
0512090477. binary Organic Rankine power cycle is described by Hettiarachchi
E-mail address: francesco.tinti@unibo.it (F. Tinti). et al. [17]. Geothermal water is passed through the evaporator that

http://dx.doi.org/10.1016/j.seta.2016.05.003
2213-1388/Ó 2016 Elsevier Ltd. All rights reserved.
94 S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105

heats a secondary fluid, typically an organic working fluid with a Pump [47]. To produce exportable electrical power, the COP of
low boiling point. Vapor generated at the evaporator is used to the heat pump must be higher than 2.0, which depends entirely
drive a turbine. On leaving the turbine, the working fluid is con- on the ambient temperature available and the gas preheating tem-
densed and pumped back to the evaporator, passing through a ser- perature required. The minimum ambient temperature threshold
ies of devices forming a closed loop. By modeling each device, a for system applicability is 0 °C. By exploiting geothermal energy
complete cycle simulation is achieved. alone or with a combination of aerothermal and geothermal
Kalina cycles have been used to generate electricity from energy, the power produced by the system is always higher than
geothermal sources. A notable example is the 2 MWe power plant the power absorbed by the Transcritical Heat Pump, giving rise
in Husavik, Iceland [18]. Started in 2000, the plant utilizes a 124 °C to zero-consumption or even a positive-production process [47].
hot water geothermal source, which cools down to 80 °C, to gener- The pre-feasibility study carried out on a viable application
ate electricity. The geothermal water leaving the plant at 80 °C is investigated the potential integration of EGPT and shallow
used for urban district heating. Medium enthalpy geothermal geothermal energy, and identified preliminary guidelines for the
energy has huge potential as a source of district heating and cool- correct analysis and design of such a system in different climatic
ing and its use is expected to increase [19,20]. Examples in Europe conditions.
include the district heating schemes of Ferrara [21], Southampton
[22], Munich [23] and the Pannonian basin [24]. Many other plants
under construction or recently completed will also increase the Materials and methods
deployment of ORC-based combined heat and power systems
[25,26]. In the case of district heating alone, there are many exam- The following interdependent components must be taken into
ples of shallow low-enthalpy resource schemes linked to heat account when designing a borehole heat exchanger field [48,49]:
pumps. In Paris [27] and Milan [28] water stored in the first aquifer
below the city is used to feed several high-temperature heat  System energy demand (peak power, functioning temperature
pumps linked to the network. In other cases, the heat pump uses and timing).
seawater to provide district heating in Stockholm [29,30], Helsinki  Heat pump appropriate to the energy requirement.
[31] and Tallinn [32].  Underground providing the thermal energy.
Heat pump-based district heating exploits low-enthalpy  Possible GSHP systems providing ambient energy to the heat
geothermal energy through water extraction, i.e. open loop cir- pump and building.
cuits. Reservoirs like aquifers, lakes or even seas are widely pre-
ferred for these applications on account of their favorable flow For relatively small residential applications (generally up to
rates. 30 kW) technical norms allow the use of simplified design meth-
Non-residential applications using geo-exchangers are found in ods, based prevalently on peak heat pump power, the type of
the agricultural and winery sector. There are many examples underground and average yearly working hours. For more complex
around Europe of greenhouses [33–36] and wine cellars [37] oper- and powerful industrial systems, these simplifications are not fea-
ating on closed loop geothermal energy systems. In greenhouses, sible and a detailed analysis must be conducted [50–52].
gas-fired low-temperature heat pumps provide both heating and For the design of a large borehole field with more than 100
cooling and CO2 controlled injection [38]. Dedicated production BHEs, as in the case of industrial projects, the methodology must:
processes in the wine-making sector, such as grape cooling and fer-
mentation cooling, use low-enthalpy geothermal energy [39]. This (a) Assess the hydrogeological site: lithologies, permeability,
energy source is also appearing in innovative processes such as aquifer condition and flow velocity.
freshwater production and desalination [40]. (b) Assess the underground thermal parameters: thermal con-
Finally, other frequent non-residential applications are the ductivity of the different layers, geothermal flow, natural
heating and cooling of industrial sheds and office buildings to temperature gradient.
ensure comfort-zone temperatures for occupants. Eicker and (c) Evaluate the technical feasibility of the various design alter-
Vorschulze provide several examples along with the related energy natives for the geoexchangers and their configurations/dis-
data [41]. posal in the ground.
As regards thermal energy storage applications, shallow
geothermal energy systems have been successfully integrated with As regards the detailed analytical design of borehole heat
solar thermal energy applications for higher storage efficiency [42]. exchanger fields, the ASHRAE American method is one of the most
Several recent central solar heating pilot plants with seasonal heat commonly used (see Italian technical norm UNI 11466:2012 [52]
storage in Central and Northern Europe have proved the suitability and ASHRAE Transactions [48]). The methodology is iterative with
of these systems and confirmed their high energy efficiency poten- the following phases:
tial [43,44]. Moreover, recent studies have also shown their appli-
cability in Southern Europe climates as well. The excess energy 1. Identification of the energy to be extracted from the under-
produced by solar thermal panels in climates with high irradiation ground, based on the equivalent monthly/yearly hours and on
is injected into the ground and then recovered through GSHP, pro- the heat pump load factor.
viding a solution to the overheating problems of solar thermal sys- 2. Choice of the geoexchanger and the connection configuration.
tems [45,46]. 3. Calculation, on the basis of the soil’s thermal properties, of the
Our case study presents an innovative non-residential applica- total length of geoexchangers required to meet thermal needs.
tion of low-enthalpy geothermal energy. It is a pre-feasibility study 4. Iterative analysis to verify the system’s working temperature
of a closed loop shallow geothermal system entirely slaved to a based on the hypothesis made for the chosen geoexchange sys-
new industrial application, the Expanding Gas Power Transforma- tem, both on an annual and decennial basis.
tion (EGPT) process that considerably reduces CO2 emissions in the
natural gas pressure reduction stations. EGPT is an innovative tech- It should be noted that the particular heating requirements of
nique harnessing gas expansion by means of a turboexpander gen- the EGPT process follow seasonality only in part and involve
erator, extracting motive power from the gas flow, whilst the energy consumption mainly by the preheater boiler: higher gas
required preheat is provided by a connected Transcritical Heat consumption during winter, but almost zero take-up during
S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105 95

summer. Such a highly specific process makes simplified calcula- the software has a 3D module that couples heat and mass trans-
tions of underground thermal behavior completely inadequate. port, very important in our case since we had the dual problem
For this reason, it was decided to study the system with a numer- of heat transfer linked to groundwater flow. FEFLOWÒ allowed us
ical modeling approach that allows the dynamic interaction of the to realize as many layers as needed, and upload punctual database
system components. information for each layer (thermal conductivity, thermal capacity,
The numerical analysis consists of: hydraulic conductivity, vertical thermal gradient).
FEFLOWÒ has been widely used to simulate classical borehole
 Geostatistical simulation of thermal conductivity characterizing heat exchanger applications. Appropriate Finite Elements modules
the geothermal reservoir. have been added to the software for efficient formulation of
 Numerical finite element simulation of the behavior of the ther- geothermal heating systems, both for steady state [57,58] and
mal flow inside the geoexchange system in order to evaluate the transient simulation [59]. Comparison with experimental results
effective extractable energy and thermal interference between has shown the model to be quite robust in predicting heat
geoexchangers during prolonged operation. exchange rates for a ground-source heat pump system [60], simu-
lating the aquifer thermal plumes and their effect on the BHE
Geostatistical simulation closed loop applications [61], and modeling the behavior of open
loop applications. FEFLOWÒ can also be used both for specific site
Thermal conductivity is a fundamental parameter for the simulation [62] and as a strategic resource management tool [63].
numerical simulation of the geoexchange system, since it is It has been used as a benchmark for evaluating performances of
directly connected to heat transfer calculations [53]. As in the area other modeling tools [64].
of the prefeasibility study there were no direct field measurements
of the thermal properties of the underground, we used the mean Case study and main calculation
values and variability ranges provided in the literature [50]. The
distribution and spatial variability of thermal conductivity The case study is related to the application of a geo-exchanger
were defined based on several similar cases and used to run system to deliver high efficiency heat to cold, incoming pipeline
geostatistical simulations to generate the parameters required by gas in a pressure reduction station, recovering mechanical energy
a user-defined grid, respecting the value distribution and for the production of power through a turboexpander. The process
variogram model. The geostatistical software used was Geo-MSÒ, is made possible by a Transcritical Heat Pump using CO2 as a refrig-
developed by Instituto Superior Técnico of Lisbon and Gaussian erant that delivers heat to the gas, raising the temperature to
Sequential Simulation was chosen as the geostatistical simulation around 80 °C (depending on the pump manufacturer), and counter-
technique [54]. acting the cooling caused by turboexpansion [65]. Fig. 1 shows a
diagram of the system components and their interaction.
Numerical modeling of underground heat and mass transfer Commercially available transcritical heat pumps have a power
range of 50 kW to more than 1 MW.
In order to evaluate the behavior of large-scale applications, we Table 1 shows an example of EGPT performance at different
used a dynamic simulator of the heat and mass transfer in the ambient reservoir temperatures at a constant preheating of about
underground. For this case we chose the software FEFLOWÒ (Finite 80 °C, supplied by the Transcritical Heat Pump [47].
Element Flow simulator), which has a specific section for modeling In most climates, the use of ambient air for a considerable part
and simulating borehole heat exchangers and allows definition of of the year gives better performance than the underground, where
the hydrogeological modeling of the study area. The numerical temperatures, at limited depth (between 20 and 60 m, neutral
model implemented is based on the Al-Khoury model [55,56], with zone), is practically constant year round and equal to the average
generalized formulations for borehole heat exchangers. In addition, ambient air temperature over the year [66].

Fig. 1. Simplified scheme of the Expanding Gas Power Transformation process. P0, T0: natural gas data before transformation; high pressure, low temperature; P1, T1: natural
gas data after preheating through Transcritical Heat Pump; high pressure, high temperature; P2, T2: natural gas data after depressurization in the Turbo Expander; low
pressure, low temperature.
96 S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105

Table 1 heat exchanger with a Hybrid Transcritical Heat Pump connected


Example of EGPT performance at different ambient temperature values. to the EGPT Process.
Ambient reservoir temperatures (°C) 0 10 20 30 The Heat Pump has the following nominal values (see Table 2).
Gas preheat (kW) [Q] 1015 1015 1015 1015
Heat pump motive input (kW) [A] 305 265 235 210
Heat pump peripherals input (kW) [B] 35 30 25 25 Underground thermal parameters
Existing site electrical load (kW) [C] 10 10 10 10
Total on-site electrical load (kW) [D = A + B 350 305 270 245
Table 3 gives the main lithotype components in the area in
+ C]
Heat pump COP [Q/D] 2.9 3.3 3.8 4.1 question and their thermal conductivity in compliance with Italian
Expander – generator electrical output (kW) 660 660 660 660 norm UNI 11466:2012 [50] and German norm VDI 4640:2010 [52].
[P = Q  g] The parameters necessary for the implementation of the geosta-
Exportable electrical output (kW) [E = P D] 310 355 390 415 tistical simulation were deduced from the above information:
Output loss due to low reservoir temperature 25.3 14.5 6.0 0.0
(%)
1. Distribution – considered a lognormal distribution for the three
lithologies, with a mean equal to the average value of the VDI
norm and a variance equal to 1/12 of the delta between maxi-
The case study presented is located in central Italy, with a typ-
mum and minimum (Fig. 2).
ical Mediterranean climate.
2. Variogram – a nested structure model was considered based on
Based on General Electric calculations, the case study presented
the literature. This comprised a nugget effect and a varying
in this paper shows that if energy losses are to be contained within
range spherical model depending on the lithology (Fig. 3 and
15% with respect to the optimal situation, and if a minimum nom-
Table 4).
inal COP of around 3 is to be obtained, the evaporator of the Tran-
scritical Heat Pump must always register the following minimum
For the geostatistical simulations, a volume of
inlet and outlet temperatures, in a continuous working period of
100 ⁄ 100 ⁄ 200 m3 was considered, based on the assumption that
24 h per day, 365 days per year:
the geoexchangers will not go deeper than 200 m.
 Tin = 8 °C;
 Tout = 3 °C;
Preliminary analytical design
 DT = 5 °C.
The design data for the CO2 heat pump are reported in the fol-
In the ambient context considered by the case study, the under-
lowing table (see Table 5).
ground temperature of the neutral zone during winter (around
Functioning period was decided based on the temperature
14 °C) is definitely higher than the required temperature. In the
trend in the area (analyzed over 10 years, from 2002 to 2011).
summer, however, it is systematically lower than the ambient
Exchange with the underground occurs only when the air temper-
temperature.
ature cannot guarantee the minimum design temperature. The first
It follows that while the limit values are easily met in the sum-
hypothesis for the design was a closed loop application with heat
mer with an air-heating source, in the winter the system may fail
extraction, whose analytical calculation defined the following
on account of low external air temperatures. For this reason, a
parameters:
hydronic system indirectly exchanging heat with the underground,
or directly exploiting heat by confined aquifers is necessary. Given
– Number of vertical Borehole Heat Exchangers (BHEs): 200.
the yearlong heating requirement, the ideal solution is to estimate,
– Depth of boreholes: 150 m.
manage, combine and electronically control the air source and
– Distance between the boreholes: 6 m.
geothermal source operation in order to maximize system effi-
– Borehole disposal: squared grid 13  15 wells.
ciency. In fact, so as to exploit the full natural power present on
– Connections: parallel configuration with direct return on all the
site, the system presented combines ambient air and a geothermal
circuits.
– Inlet temperature of thermovector fluid to boreholes: 3 °C.
– Outlet temperature of thermovector fluid from boreholes: 8 °C.
Table 2
Design data of the Transcritical Heat Pump used in the Italy case study. Preliminary analytical analysis determined a total borehole field
length of 17.320 m. On this basis, it was calculated that 115, cor-
Nominal thermal power 500 kWt
rectly spaced 150 m deep BHEs were sufficient to allow adequate
Required temperature for gas preheating 80 °C
Inlet temperature from the ambient side 8 °C heat exchange between the underground and the thermovector
Outlet temperature to the ambient side 3 °C fluid, for a total extractable power of around 3 kWt for each BHE.
Design nominal COP 3 Assuming the temperature limits imposed by the system
Electric absorption 168 kWe (Tinlet = 3 °C; Toutlet = 8 °C), a field of 200 BHEs could easily meet
Peak power extraction from underground 332 kWt
the heat requirement of the transcritical heat pump (Fig. 4).

Table 3
Thermal conductivity [W/(m K)] of the different lithologies, together with the layer thickness in the case study area. Results of a preliminary geological study.

Lithotypes Thermal conductivity [W/(m K)] Depth [m] Layer thickness [m]
Minimum Average Maximum
Clayey silt 0.40 0.50 1.00 3.50 3.50
Silty sand 0.30 0.45 0.90 4.50 1.00
Saturated gravel 1.80 1.80 1.80 17.00 12.50
Marl-sandstone 1.35 2.20 4.40 152.00 135.00
S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105 97

Fig. 2. Distribution of thermal conductivity for the three lithotypes considered Fig. 3. Variogram model of the thermal conductivity for the three lithotypes: silty
variables: silty sand (a), clayey silt (b) and marl-sandstone unit (c). sand (a), clayey silt (b) and marl-sandstone unit (c).

This preliminary analysis does not, however, take the following Table 4
Characterization of spatial variability of ground thermal conductivity: parameters of
aspects into account:
the variogram models of the three lithotypes: c0 nugget effect, csf sill of the spherical
model, asf range of the spherical model.
 Underground thermal depletion around each BHE due to con-
Lithotypes Variogram parameters
tinuous heat extraction.
 Medium term behavior of each BHE at winter’s end. c0 csf asf
 Thermal interference between BHEs and creation of areas of Clayey silt 0.025 0.035 30
criticality in the center of the borehole field. Silty sand 0.015 0.040 20
 The natural thermal recharge capacity of the underground Marl-sandstone 0.100 0.170 40

when subjected to such continuous heat extraction.


 Long-term behavior (at least 10 years) of the entire borehole
field.
Table 5
For this reason, it was imperative to conduct numerical model- Parameters of the CO2 heat pump.
ing of the 200 BHE field.
Peak extraction power from the underground 332 kWt
The temperature data over one year of the 200 BHE-field simu- Heat pump evaporator outlet temperature 3 °C
lation were then added to the analytical calculations. The results Heat pump evaporator inlet temperature 8 °C
for the two alternatives at constant values of DT (solution a) and Thermovector fluid flow rate 62 m3/h
Tin (solution b) are given below (Figs. 5 and 6). Functioning period 5 months
Daily functioning hours 24 h
Numerical analysis shows how the 200 BHE field at a Available field dimension 100  75 m2
depth of 150 m is unable to meet the thermal requirement of the
98 S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105

transcritical heat pump (both as regards inlet temperature, which


was lower than the limit value of 3 °C at constant DT, and decreas-
ing with time, and delta temperature, which was lower than 5 °C at
constant Tin, and decreasing with time). It follows that the borehole
field must be enlarged, either by increasing the number of BHEs or
increasing the depth of the current number of boreholes. In this
case, the project area in question allows for 208 BHEs maximum.
Given the aim of our study, we did not look further into the ques-
tion of how to improve the performance of the borehole field to
meet the specific industrial project demands.
To avoid any long-term ground freeze risk, common practice in
geothermal applications is to recharge the reservoir during the
summer by inverting the cycle and injecting thermal energy into
the ground. In summer, the moist soil acts as a storage cooling
medium. In many domestic geothermal applications, the pipes
work simultaneously as heat exchangers for space cooling during
the on-peak period and as storage devices in the off-peak period.
Although this solution is very efficient to lower summer energy
Fig. 4. Borehole heat exchanger field composed of 200 BHEs at 150 m depth, in an
consumption, it greatly limits the thermal storage potential of a
available area of 7500 m2.

Fig. 5. Design hypothesis with only heat extraction. Simulation of thermal behavior maintaining a constant temperature difference between inlet and outlet (solution a).

Fig. 6. Design hypothesis with only heat extraction. Simulation of thermal behavior maintaining the thermovector fluid at constant inlet temperature (solution b).
S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105 99

site [67]. In a geothermal industrial application, there is usually no We assumed that the maximum energy extractable from the air
cooling on-peak period, with the result that all the underground was injected in the ground.
thermal energy storage potential can be released. The case study The analytical calculation gave us these parameters for the
took this second hypothesis into account, artificially stimulating system:
taking heat from the external air.
To evaluate the thermal energy extractable from the external – thermal power stored in the ground: 350 kWt;
air, climate data for the area over 10 years (2002–2011) were stud- – inlet temperature of the thermovector fluid in the boreholes in
ied, and the number of summer days (from May to September) injection: 24 °C;
determined when temperatures were statistically over 20 °C – outlet temperature of the thermovector fluid from the bore-
(Table 6). holes in injection: 19 °C;
The temperature of the storage fluid (24 °C) required to ther- – flow rate of the fluid in storage: 62 m3/h;
mally recharge the ground was then defined. – number of vertical BHEs: 200;
Another efficient heat storage alternative could be to reuse the – depth of the boreholes: 150 m;
air after its passage through the Transcritical Heat Pump evapora- – distance between the boreholes: 6 m;
tor. The data relating to this case are given in the following table. – borehole disposal: squared grid 13  15 wells;
As average air temperature from May to September is normally – total needed area: 7.500 m2;
14 °C, and 24 °C only during the summer months (June to August), – connections: parallel configuration with direct return on all the
this solution would only be feasible in summer (see Table 7). circuits;
The advantage of the second alternative is that we could use the – maximum absorption of electricity from the circulation pumps:
exchangers already available in the thermo-hydraulic circuit, while 15 kWe;
in the first case, another exchanger has to be added. – inlet temperature of thermovector fluid to boreholes in extrac-
tion: 3 °C;
– outlet temperature of thermovector fluid from boreholes: 8 °C.
Table 6
Analysis of air temperatures in the summer period over a 10-year period. Again, numerical modeling was performed considering heat
injection prior to heat extraction; the results for one-year opera-
Month Number of days with % of days with Average
T > 20°C T > 20°C temperature (°C) tion are given in Figs. 7 and 8.
May 5 16% 21.1
June 27 90% 23.5 Numerical simulation of thermal flow
July 31 100% 25.7
August 31 100% 24.9 In order to validate the analytical models, the area was modeled
September 15 50% 21.9
and simulated in FEFLOWÒ on the basis of 200 BHEs (in a 6 m grid
configuration, as a compromise solution between thermal interac-
tion between BHE and available space for drilling) in a
Table 7 100  100  200 m3 regular grid field.
Analysis of air-source working system in summer period. The geological strata were assumed to lie parallel. Their specific
Spring Summer
properties of thermal conductivity, thermal capacity, permeability
and undisturbed ground temperature were taken into account.
Thermal power at the evaporator 414.0 kW 414.0 kW
Flow rate 75.0 m3/h 74.0 m3/h
The boundary conditions were the following:
Inlet temperature 19.0 °C 29.0 °C
Outlet temperature 14.0 °C 24.0 °C (a) boundary temperature equal to the undisturbed ground
temperature;

Fig. 7. Design hypothesis with heat extraction and recharge. Simulation of thermal behavior keeping constant temperature difference between inlet and outlet of 5 °C
(solution a).
100 S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105

Fig. 8. Design hypothesis with heat extraction and recharge. Simulation of thermal behavior keeping constant inlet temperature of thermovector fluid of 3 °C (solution b).

(b) constant aquifer depth (6.5 m), with steady velocity of 1. 108 days of heat injection in the ground;
0.054 m/day. 2. 47 days of natural recharge of the ground;
In the first case, the BHE was submitted to continuous heat 3. 150 days of heat extraction from the ground;
extraction for 5 months, maintaining a constant 5 °C difference 4. 60 days of natural recharge of the ground.
between inlet and outlet temperature. Final inlet temperature
was 0.7 °C while outlet temperature was 5.7 °C, too low for our During the first phase, the ground was recharged through the
purpose. injection of 24 °C in the ground, inducing a ground temperature
Although the reservoir was able to provide the constant power variation close to the BHEs. In winter, after 47 days of natural heat
needed for the whole functioning period, the variable inlet and recharge of the ground, the heat extraction was maintained for
outlet temperatures had to be managed since they did not main- 5 months, but the outlet temperature could not be kept at 8 °C.
tain the 3 °C and 8 °C of the hypothesis.
The same BHE, in a second case, underwent heat extraction for Results
5 months and maintained a constant inlet temperature of 3 °C.
However, the reservoir was unable to provide the constant power Numerical simulation allows simulation of long-term borehole
needed to maintain a constant inlet temperature. In fact, at the end field thermal behavior. The results over a 10 year period are pre-
of the 5 months, the outlet temperature had fallen to 7.3 °C, insuf- sented below for both solutions: heat extraction only (solution
ficient to assure the required DT of 5 °C. n°1) and heat extraction and recharge (solution n°2) Figs. 9–12.
The second alternative was simulated with the following It should be noted, however, that simulation has thus far not been
scheme: confirmed by experimental results, the BHE field being a hypothe-

Fig. 9. Design hypothesis with heat extraction only. Simulation of long-term thermal behavior keeping constant temperature difference between inlet and outlet of 5 °C
(solution a).
S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105 101

Fig. 10. Design hypothesis with heat extraction only. Simulation of long-term thermal behavior keeping constant inlet temperature of thermovector fluid of 3 °C (solution b).

Fig. 11. Design hypothesis with heat extraction and recharge. Simulation of long-term thermal behavior keeping constant temperature difference between inlet and outlet of
5 °C (solution a).

Fig. 12. Design hypothesis with heat extraction and recharge. Simulation of long-term thermal behavior keeping constant inlet temperature of thermovector fluid of 3 °C (solution b).
102 S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105

sis at the pre-feasibility study phase. The use of proven robust soft- on test boreholes [68]. Even then, a comprehensive assessment of
ware like FEFLOWÒ is therefore fundamental, there being no exper- underground behavior may not be achieved since TRTs are
imental data available for the specific site. generally performed for a limited period of time and so are not
representative of the entire production process of a borehole field.
Comments to the results In addition, TRTs are usually performed on just a few BHE, a
situation that fails to imitate an entire BHE field.
The results show the effectiveness of summer recharge, which For all these reasons, both the design and TRT phase of any pro-
increases over the long term. ject must be preceded by temperature sensitivity analyses based
Thanks to underground thermal recharge, fluid temperatures on a series of underground thermal parameters. The case study
during heat exploitation increase from 0.5 °C to 1.0 °C, which, espe- included a two-dimensional sensitivity analysis starting from the
cially given the strict EGPT working conditions, can be crucial to underground parameters and covering the borehole field design.
any decision to adopt shallow geothermal reservoir technology to In other words, long-term temperature variation was calculated
meet this type of heat demand. for a range of different equivalent underground thermal conductiv-
The added value of energy storage increases over the long term. ity values for a borehole field of unchanged length and
Although the maximum temperature rise achieved at the outset connections.
does not increase with time, minimum temperatures are, however, The sensitivity analysis shows summer thermal energy storage
damped, in this case never falling below 0.7 °C. to be fundamental. In fact, in the heat-extraction-only configura-
The only negative aspect is the electric power absorption of the tion, solution (b) (keeping constant inlet temperature), an over-
circulation pumps, needed for thermal energy storage, and which estimation of 14% of the underground thermal conductivity
must be included when calculating the energy and economic costs provides an outlet fluid temperature of more than 80% lower than
of operating large borehole fields. In the case examined, the project design. In the heat-extraction-and-recharge hypothesis,
underground thermal recharge was necessary to guarantee the this effect is damped, and the same over-estimation of 14% of
temperature limits required by the specific industrial process. As thermal conductivity gives a temperature deviation of around
a result, the electricity consumption requirement for thermal 40% lower than expected, with a 50% reduction in the risk of failure
energy storage must be included in any return-on-investment cal- (Fig. 14). Solution (a) (keeping constant temperature difference
culations. In this particular case, the energy requirement was esti- between inlet and outlet) gives similar results (Fig. 13). This is
mated at around 92 MWh/y in fact a negligible portion of the total because, on the one hand, low thermal conductivity obstructs heat
electric energy produced by the turboexpander of about 325 kWe transfer, and therefore underground thermal energy exploitation,
with a 500 kWt approx. thermal capacity transcritical heat pump. but on the other, permits higher values of energy storage in the
This electric energy quota completely covers both the peak underground since the underground layers near the borehole
transcritical heat pump power (around 170 kWe, see Table 1) and retain their heat, with limited radial heat transfer occurring.
the peak power of the BHE field circulation pumps (around The calculation results show the importance in non-residential
15 kWe). geothermal applications of applying a probabilistic approach and
In the hypothesis of a 24-h operating turboexpander, there is long-term numerical simulation tools. In fact, when dealing with
perfect contemporaneity between production and consumption, industrial applications, heat requirements do not follow or, only
with an excess power production of around 140 kWe, which consti- partially follow, seasonality, with the result that standard proce-
tutes free electric energy that can be sold on the market. In the case dures for residential heat pump applications are not suitable and
of heat storage, there is no additional electric absorption because can lead to considerable errors or under-estimations of failure
the two possibilities presented – direct use of external air temper- risks. In these types of applications, the underground’s finiteness
ature or cascade use of air source system - both work by means of is all too evident, and the thermal reservoir can be dangerously
the heat exchanger without compression. Using a hybrid combina- depleted if not properly analyzed.
tion of air and ground sources to ensure underground thermal
recharge during summer, the system never allows the temperature
to go below the required 8 °C, with the result that the COP never Discussion
goes below 3. The preliminary energy and economic analysis of
the system is presented in Table 8. It is difficult to produce a universal recipe for calculating the
This preliminary precautionary result may be higher by 20–25% economic attractiveness of the use of ground source applied to
in the event of (mainly summer) ambient temperatures of more the EGPT technology. The factors influencing the validity of the
than 8 °C, while the combined use of ground source and energy investment are:
storage can ensure there are no significant temperature and effi-
ciency drops during the winter. – Local electricity prices and feed-in tariffs.
The uncertainty embedded in this approach is due to the fact – Investment costs for the wells or BHE field, which differ with
that, despite the sophisticated geostatistical tools available, under- the different labor costs in the various countries, and from site
ground thermal properties cannot be known a priori, only esti- to site, on account of geological and hydrogeological variability.
mated. Calculation of exact parameter values requires production – Ambient temperature conditions, which make the use of pure
tests such as the Thermal Response Test (TRT) to be performed air-source more or less feasible.
– Natural gas flow variations at pressure reduction stations, a fac-
tor that also depends on special local/regional energy demand.
Table 8
Minimum energy results for the EGPT system, using hybrid air and ground source For the specific case study presented, the ambient temperature
combination with seasonal thermal energy storage.
does not allow the use of the air source heat pump for the entire
Power (kW) Energy (MWh/y) year, because, for almost 25% of the time, temperatures are below
Turboexpander production 325 2.847 the required limit (Ta < 8 °C). This means that for 25% of the time,
Heat pump consumption 167 1.460 the transcritical heat pump cannot work with aerothermal energy
Circulation pumps consumption 15 92 alone. As an alternative to hybrid ground-air source heat, there are
Exportable electrical output 143 1.295
two other basic hybrid solutions combining an air source:
S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105 103

Fig. 13. Comparison between sensitivity analyses, keeping constant temperature difference between inlet and outlet of 5 °C (solution a): the percentage deviations caused by
potential estimation errors of underground thermal conductivity are compared with the heat extraction only design hypothesis and the heat extraction and recharge design
hypothesis, for both inlet and outlet fluid.

Fig. 14. Comparison between sensitivity analyses, at a constant thermovector inlet fluid temperature of 3 °C (solution b): percentage deviations percentage caused by
potential estimation errors of underground thermal conductivity are compared with the heat-extraction-only design hypothesis and the heat-extraction-and-recharge design
hypothesis, for outlet fluid.

– Preheating the natural gas in other ways and not with a trans- On the other hand, the hybrid ground-air solution presented in
critical heat pump, thereby maintaining the turboexpander of the case study requires the installation of a 200 Borehole Heat
the EGPT process working all year long. This most frequently Exchanger field at 150 m, for a thermal power of 322 kWt with
involves inserting a backup boiler in the circuit, which uses part return temperatures of 8 °C, working practically uninterruptedly
of the natural gas present in the station. For the case study con- for 5 months. This means additional investments ranging from
sidered, the exportable electrical output decreases proportion- 1.500 k€ to 1.800 k€ depending on the specific underground
ally to the natural gas quota used, which was around conditions, which are unknown a priori, and which can only be
1.100 MW h at 80 °C. estimated during pre-feasibility phases.
– Bypassing the entire EGPT system and depressurizing natural The feasibility of the hybrid ground-air solution increases, the
gas through a throttling expansion valve. In this case, the expor- more ambient air temperatures decrease for the following reasons:
table electrical output decreases by 20%.
– Less available optimal aerothermal energy.
In both cases, there is no electrical consumption by the BHE – Natural gas transit through the grids, theoretically, increases
field circulation pumps. because of increased heating needs.
104 S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105

These two facts are in contradiction, because stopping the tur- coupled to shallow geothermal energy systems. Although the sim-
boexpander for long periods causes a major fall off of free power ulation results need to be compared with real experimental data in
production, which otherwise could be significant in the presence order to prove their accuracy, the study proposed could go a long
of huge natural gas consumption for heating. way to defining the appropriate market for EGPT processes and
Since aerothermal energy cannot supply the desired tempera- their very tight operating temperature range.
ture ranges required by EGPT processes for most of the year in
Artic, continental, Atlantic and mountain climates, the hybrid Acknowledgements
ground-air transcritical heat pump would seem very promising.
In contrast, the hybrid ground-air solution would not appear This study was possible thanks to the collaboration between
suitable to Mediterranean, temperate, and generally hot climates Nuovo Pignone – General Electric and CINIGEO – Italian National
where more aerothermal than geothermal energy is employed. Interuniversity Consortium of Georesources Engineering, the lead
The site considered by the case study, in a mountainous zone in author of this paper.
the Apennines in Central Italy, where air temperature can support
the EGPT process for almost 75% of the year, proved a border-line
References
location for this sort of plant, whose investment feasibility must
be assessed in terms of the geological, hydrogeological and [1] Goetzler W, Zogg R, Lisle H, Burgos J. Ground-source heat pumps: overview of
geothermal characteristics of the underground and the possibility market status, barriers to adoption, and options for overcoming barriers. US
of optimal, cost-efficient installing of the wells or geoexchangers. department of energy efficiency and renewable energy geothermal
technologies program.
In this context, the use of appropriate simulation and prediction [2] Rybach L. Shallow systems: geothermal heat pumps. Reference module in
models for the feasibility analysis phase takes on even greater earth systems and environmental sciences. p. 189–207.
importance. [3] D.Lgs. 28 3 marzo 2011 Attuazione della direttiva 2009/28/CE sulla
promozione dell’uso dell’energia da fonti rinnovabili, recante modifica e
successiva abrogazione delle direttive 2001/77/CE e 2003/30/CE.
[4] International Panel for Climate Change (IPCC) Working Group III – Special
Conclusions Report on Renewable Energy) – Chapter 4-Geothermal Energy.
[5] European Geothermal Energy Council – EGEC Geothermal Market Report 2014.
[6] Urchueguía JF, Zacarés M, Corberán JM, Montero Á, Martos J, Witte H.
The case study presents an innovative application of Borehole Comparison between the energy performance of a ground coupled water to
Heat Exchanger (BHE) fields for industrial purposes using a propri- water heat pump system and an air to water heat pump system for heating and
etary power application of General Electric Oil & Gas: the Expand- cooling in typical conditions of the European Mediterranean coast. Energy
Convers Manage 2008;49(10):2917–23.
ing Gas Power Transformation (EGPT) process. A ground heat
[7] Omer AM. Ground-source heat pumps systems and applications. Renewable
source is employed in a hybrid combination with an air source to Sustainable Energy Rev 2008;12–2:344–71.
preheat natural gas in a pressure reduction station by means of a [8] Pahud D, Belliardi M, Caputo P. Geocooling potential of borehole heat
Transcritical Heat Pump, completing a turboexpander-based ther- exchanger systems applied to low energy office buildings. Renewable Energy
2012;45:197–204.
modynamic power production cycle. The borehole field calculation [9] Sanner B, Karytsas C, Mendrinos D, Rybach L. Current status of ground source
methodology presented integrates geostatistical simulation of spa- heat pumps and underground thermal energy storage in Europe. Geothermics
tial parameters and numerical simulation of heat/water table 2003;32(4–6):579–88.
[10] Diersch HJG, Bauer D. Analysis, modeling and simulation of underground
flows. This integrated simulation, normally omitted by conven- thermal energy storage (UTES) systems. Advances in thermal energy storage
tional shallow geothermal projects, becomes indispensable to (a) systems. Methods and applications, 7. p. 149–83.
confirm the analytical design and (b) improve the economic feasi- [11] Hesaraki A, Holmberg S, Haghighat F. Seasonal thermal energy storage with
heat pump sand low temperatures in building projects – a comparative
bility of a proposed plant where the narrow fluid temperature review. Renewable Sustainable Energy Rev 2015;43:1199–213.
ranges risk jeopardizing overall return on investment. [12] Rafferty K. Industrial processes and the potential for geothermal applications.
In fact, in the sort of industrial project considered, stability of Geo Heat Center Bull 2003.
[13] Astolfi M, Romano MC, Bombarda P, Macchi E. Binary ORC (organic Rankine
underground temperature across time is key to the successful cycles) power plants for the exploitation of medium–low temperature geothermal
use of a shallow geothermal source in stand-alone or in combina- sources–part A: thermodynamic optimization. Energy 2014;66:423–34.
tion with an air source to minimize borehole investment costs. [14] Cammarata G, Cammarata L, Petrone G. Thermodynamic analysis of ORC for
energy production from geothermal resources. Energy Procedia 2014;45:1337–43.
Temperature stability must be ensured over time: in order to verify
[15] Ozgener L, Hepbasli A, Dincer I. A key review on performance improvement
this, a long-term underground energy simulation is required, able aspects of geothermal district heating systems and applications. Renewable
to demonstrate the finiteness of the medium and indicate the ideal Sustainable Energy Rev 2007;11(8):1675–97.
borehole design for long-term operations. [16] Xu J, Wang RZ, Li Y. A review of available technologies for seasonal thermal
energy storage. Sol Energy 2013;103:610–38.
Results show that these industrial processes can be advanta- [17] Hettiarachchi HDM, Golubovic M, Worek WM, Ikegami Y. Optimum design
geous when a low-enthalpy shallow geothermal heat source is criteria for an organic Rankine cycle using low-temperature geothermal heat
used, especially in combination with thermal energy storage meth- sources. Energy 2007;32:1698–706.
[18] Mannvit. Electricity from waste heat – distribution of expertise. Published on
ods. In particular, overall system performance is greatly increased PRO-TEM network website; 2010.
by thermal recharge of the underground during non-energy [19] Andrews D, Riekkola AK, Tzimas E, Serpa J, Carlsson J, Pardo-Garcia N, et al.
exploitation periods. Background report on EU-27 district heating and cooling potentials, barriers,
best practice and measures of promotion. JRC Scientific and Policy Reports;
A major drawback is the uncertainty of true thermal properties 2012.
of the ground. The proposed geostatistical simulation of the reser- [20] GeoDH 2014 – Report on Market Development in the Geothermal DH Sector.
voir coupled with numerical simulation of flows are followed by a [21] Giambastiani BMS, Tinti F, Mendrinos D, Mastrocicco M. Energy performance
strategies for the large scale introduction of geothermal energy in residential and
sensitivity analysis providing failure risk due to insufficient knowl- industrial buildings: the GEO.POWER project. Energy Policy 2014;65:315–22.
edge of underground thermal behavior. The analysis shows that [22] Hawkey D, Webb J, Winskel M. Organisation and governance of urban energy
energy recharge could guarantee better performance results: when systems: district heating and cooling in the UK. J Cleaner Prod 2013;50:22–31.
[23] Sanner B, Bussmann W. Current status, prospects and economic framework of
the values of the thermal properties of the underground are over-
geothermal power production in Germany. Geothermics 2003;32(4–
estimated, the under-exploitation of geothermal energy is partially 6):429–38.
compensated by the over-capability of underground thermal [24] Szanyi J, Kovács B. Utilization of geothermal systems in South-East Hungary.
storage. Geothermics 2010;39(4):357–64.
[25] Quoilin S, Van der Broek M, Declaye S, Dewallef P, Lemort F. Techno-economic
Conducted on a wide scale, the analyses proposed could lead to survey of Organic Rankine Cycle (ORC) systems. Renewable Sustainable Energy
design and operating guidelines for similar industrial applications Rev 2013;22(2013):168–86.
S. Focaccia et al. / Sustainable Energy Technologies and Assessments 16 (2016) 93–105 105

[26] Velez F, Segovia JJ, Martin MC, Antolin G, Chejne F, Quijano A. A technical, [47] Amidei S, Byrne J, Monti F, Sikora P. Efficient gas depressurisation via the EGPT
economical and market review of organic Rankine cycles for the conversion of process. GPA Europe conference.
low-grade heat for power generation. Renewable Sustainable Energy Rev [48] Kavanaugh SP, Rafferty K. Ground source heat pumps – design of geothermal
2012;16(2012):4175–89. systems for commercial and institutional buildings. ASHRAE applications
[27] Lopez S, Hamm V, Le Brun M, Schapera L, Boissier F, Cotiche C, et al. 40 years of handbook.
Dogger aquifer management in Ile-de-France, Paris Basin, France. Geothermics [49] Bose JE, Parker JD, Mc Quiston FC. Design/data manual for closed-loop ground-
2010;39(4):339–56. coupled heat pump systems. Atlanta: ASHRAE; 1985.
[28] Sparacino M, Camussi M, Colombo M, Carella R, Sommaruga C. The world’s [50] VDI 4640. Rev. 1 – thermal use of underground. German Association of
largest geothermal district heating using ground water under construction in Engineers; 2010.
Milan (Italy): AEM unified heat pump project. Unterhaching, [51] Koohi-Fayegh S, Rosen MA. Three-dimensional analysis of the thermal
Germany: European Geothermal Congress; 2007. interaction of multiple vertical ground heat exchanger. Int J Green Energy
[29] Bloss WH, Pfisterer F, editors. Advances in solar energy technology, vol. 2015;12(11):1144–50.
1. Pergamon; 1988. p. 3998. [52] UNI 11466:2012 (2012) – Sistemi geotermici a pompa di calore – Requisiti per
[30] Nilsson SF, Reidhav C, Lygnerud K, Werner S. Sparse district-heating in il dimensionamento e la progettazione.
Sweden. Appl Energy 2008;85(7):555–64. [53] Zeng H, Diao N, Fang Z. Heat transfer analysis of boreholes in vertical ground
[31] Riipinen M. District heating and cooling in Helsinki. Paris: International Energy heat exchangers. Int J Heat Mass Transfer 2003;46(23):4467–81.
Agency Workshop; 2013. [54] Fredericks AK, Newman KB. A comparison of the sequential Gaussian and
[32] Hlebnikov A, Siirde A. The major characteristic parameters of the Estonian Markov-Bayes simulation methods for small samples. Math Geol 1998;30
district heating networks and their efficiency increasing potential. Energetika (8):1011–32.
2008;54(4):67–74. [55] Al-Khoury R, Bonnier PG, Brinkgreve RBJ. Efficient finite element formulation
[33] Adaro JA, Galimberti PD, Lema AI, Fasulo A, Barral JR. Geothermal contribution for geothermal heating systems. Part I: steady state. Int J Numer Methods Eng
to greenhouse heating. Appl Energy 1999;64:241–9. 2005;63.
[34] Bakos GC, Fidanidis D, Tsagas NF. Greenhouse heating using geothermal [56] Al-Khoury R, Bonnier PG. Efficient finite element formulation for geothermal
energy. Geothermics 1999;28(6):759–65. heating systems. Part II: transient. Int J Numer Methods Eng 2006;67.
[35] Benli H, Durmusß A. Evaluation of ground-source heat pump combined latent [57] Diersch HJG, Bauer D, Heidemann W, Ruhaak W, Schatzl P. Finite element
heat storage system performance in greenhouse heating. Energy Build 2009;41 modeling of borehole heat exchanger systems part 1. Fundamentals. Comput
(2):220–8. Geosci 2011;37:1122–35.
[36] Firfiris V, Kougias PG, Nikita-Martzopoulou CH, Martzopoulos GG. [58] Diersch HJG, Bauer D, Heidemann W, Ruhaak W, Schatzl P. Finite element
Performance of a covered closed loop shallow geothermal greenhouse modeling of borehole heat exchanger systems part 2. Numerical simulation.
heating system. Acta Hortic 2012;952:457–62. http://dx.doi.org/10.17660/ Comput Geosci 2011;37:1136–47.
ActaHortic.952.57. [59] Bauer D, Heidemann W, Diersch HJG. Transient 3D analysis of borehole heat
[37] Ruiz-Mazarrón F, Almoguera-Millán J, García-Llaneza J, Perdigones A. Energy exchanger modeling. Geothermics 2011;40:250–60.
balance and economic feasibility of shallow geothermal systems for winery [60] Nam Y, Ooka R, Hwang S. Development of a numerical model to predict heat
industry. EGU general assembly 2012, held 22–27 April, 2012 in Vienna – exchange rates for a ground-source heat pump system. Energy Build 2008;40
Austria. p. 4621. (12):2133–40.
[38] De Boever E, Lagrou D, Laenen B. Beknopte wegwijzer, geothermie. België, Geo. [61] Rivera JA, Blum P, Bayer P. Analytical simulation of groundwater flow and land
Power Dutch local handbook. surface effects on thermal plumes of borehole heat exchangers. Appl Energy
[39] Graham J. Rioja winery digs deep for ‘green’ energy. Vineyard & Winery 2015;146:421–33.
management; 2010. [62] Nam Y, Ooka R. Numerical simulation of ground heat and water transfer for
[40] Bundschuh J, Ghaffour N, Mahmoudi H, Goosen M, Mushtaq S, Hoinkis J. Low- groundwater heat pump system based on real-scale experiment. Energy Build
cost low-enthalpy geothermal heat for fresh water production: innovative 2010;42(1):69–75.
applications using thermal desalination processes. Renewable Sustainable [63] Herbert Arthur S, Chillingworth G. Thermal modelling of large scale
Energy Rev 2015;43:196–206. exploitation of ground source energy in urban aquifers as a resource
[41] Eicker U, Vorschulze C. Potential of geothermal heat exchangers for office management tool. Appl Energy 2013;109:94–103.
building climatisation. Renewable Energy 2009;34(4):1126–33. [64] Hecht-Méndez J, Molina-Giraldo N, Blum P, Bayer P. Evaluating MT3DMS for
[42] IEA T44, IEA SHC Task 44/HP38 (2013) – Solar and heat pump systems heat transport simulation of closed geothermal systems. Groundwater
<http://task44.iea-shc.org>. 2010;48(5):741–56.
[43] Sorensen A, Holm L, Jensen NA. Water storages, solar thermal and heat pumps [65] Sikora P. (2011) – System for efficient fluid depressurisation. EP 22642898; US
in district heating. 1st international conference on solar heating, cooling and 8025535.
buildings. Eurosun; 2008. [66] Tinti F, Barbaresi A, Benni S, Torreggiani D, Bruno R, Tassinari P. Experimental
[44] Bauer D, Marx S, Nubbicker-Lux J, Ochs F, Heidemann W, Muller-Seinhagen H. analysis of shallow underground temperature for the assessment of energy
German central solar heating plants with seasonal heat storage. Sol Energy efficiency potential of underground wine cellars. Energy Build 2014;80:451–60.
2010;84:612–23. [67] Zhu N, Hu P, Xu L, Jiang Z, Lei F. Recent research and applications of ground
[45] Reda F, Arcuri N, Loiacono P, Mazzeo D. Energy assessment of solar source heat pump integrated with thermal energy storage systems: a review.
technologies coupled with a ground source heat pump system for residential Appl Therm Eng 2014;71(1):142–51.
energy supply in Southern European climates. Energy 2015;91:294–305. [68] Gehlin S. Thermal response test—in-situ measurements of thermal properties
[46] Flynn C, Sirén K. Influence of location and design on the performance of a solar in hard rock [D]. Sweden: Department of Environmental Engineering, Luleå
district heating system equipped with borehole seasonal storage. Renewable University of Technology; 1998.
Energy 2015;81:377–88.

S-ar putea să vă placă și