Subject: Status of Geo technical reports for structures on the project road
S. Existing Design Type Span arrangement as Span arrangement Status as on 11.10.2010 Remarks
No. Chainage Chainage per schedules proposed by MELTECH
Chappra
1 145.162 MJB 4 x 20 4 x 20 Particle sizes are to be furnished by Soil consultant For Scour depth calculations
bye pass
3 203.700 206.436 MJB 46.36+13x60.63+46.36 46.36+13x60.63+46.36 Corrected soil report is submitted on 23-08-2010 Closed
1 204.884 207.768 Flyover 3x25 3x25 Draft Soil report is submitted on 17-08-2010 Meltech to check and revert back
2 206.700 209.530 Flyover 11x20 Draft Soil report is submitted on 27-08-2010 Meltech to check and revert back
1 203.139 205.871 VUP 1x8 1x8 Draft Soil report is submitted on 14-08-2010 Meltech to check and revert back
2 204.150 207.031 VUP 1x8 1x8 Draft Soil report is submitted on 14-08-2010 Meltech to check and revert back
3 206.298 209.050 VUP 1x8 1x8 Draft Soil report is submitted on 14-08-2010 Meltech to check and revert back
Subject: Status of Geo technical reports for structures on the project road
S. Existing Design Type Span arrangement as Span arrangement Status as on 11.10.2010 Remarks
No. Chainage Chainage per schedules proposed by MELTECH
Shittalpur Awaiting for final soil report with corrections as per the
13 185.921 MNB 1 x 10 1 x 10 Soil report is submitted on 20-09-2010
byepass discussions had with soil consultant
Shittalpur Awaiting for final soil report with corrections as per the
14 187.037 MNB 1 x 40 4x10 Soil report is submitted on 20-09-2010
byepass discussions had with soil consultant
Shittalpur Awaiting for final soil report with corrections as per the
15 194.718 MNB 1 x 20 2x10 Soil report is submitted on 20-09-2010
byepass discussions had with soil consultant
Soil report for pile foundation system is submitted on 07-09-
16 200.400 203.175 MNB 1x46.67 4x11.2 Soil report is required for raft foundation system
2010
Awaiting for final soil report with corrections as per the
17 201.750 204.535 MNB 1x43.65 8.3+25+8.3 Soil report is submitted on 20-09-2010
discussions had with soil consultant
Chappra
1 143.974 ROB 3x26.230 3x26.230 Soil report is submitted on29-09-2010 Closed
bye pass
Chappra
2 150.984 ROB 13.230+26.230+13.230 13.230+26.230+13.230 Soil report is submitted on29-09-2010 Closed
bye pass
Chappra
3 157.860 ROB 26.23+31.23+26.23 26.23+31.23+26.23 Soil report is submitted on29-09-2010 Closed
bye pass
Digwara
4 177.182 ROB 26.23+31.23+26.23 26.23+31.23+26.23 Soil report is submitted on 07-09-2010 Closed
byepass