Sunteți pe pagina 1din 7

Compaction of dune sand backfill by concrete shaft vibrators

S. IDRISMIRZA l
Technical Services Manager, Saudi Arabian Bechtel Company, King Fahd International Airport Project,
P.O. Box 3477, Dammam 31471, Saudi Arabia
Received June 10, 1991
Accepted December 13, 1991

Backfilling is a time-consuming operation at any construction project. Because of construction constraints and to
minimize excavation and backfilling costs, utility trenches are made as narrow as practicable, which precludes the use
of large compactors. The backfill is therefore placed in thin layers and compacted with hand compactors, making backfill-
ing a slow operation. This paper presents the details of development of a fast, effective, and reliable backfill compaction
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Waterloo on 01/28/15

procedure. This method is based on the concept that the sand being a cohesionless material can be easily densified
under its own weight by mere vibrations if the intergranular friction between the sand particles is reduced. The method
allows placement of saturated dune sand backfill in lifts up to 1 m in thickness, and the compaction is achieved by
vibrating the mass by inserting concrete shaft vibrators on a regular grid pattern. The results and analysis of numerous
laboratory experiments and 13 full-scale field test trials which form the basis of this compaction technique are also
included in this paper.
Key words: backfilling, dune sand, intergranular friction, vibrations, concrete shaft vibrators.

Le remblayage est une opCration qui prend du temps sur n'importe quel projet. A cause des contraintes de la con-
struction et pour minimiser les coilts d'excavation et de remblayage, les tranchCes de services sont excavCes aussi Ctroites
que possible ce qui empCche l'utilisation de gros appareils de compactage. Le matkriau de remblayage est alors place
en minces couches et compacte avec des appareils de compactage manuels, faisant du remblayage une operation lente.
Cet article prCsente les dCtails du dCveloppement d'une procedure de compactage rapide, efficace et fiable. Cette mCthode
est basCe sur le concept que le sable Ctant un matCriau pulverulent, peut facilement Ctre densifiC sous son propre poids
par simples vibrations si le frottement inter-granulaire entre les particules de sable est rCduit. La mCthode permet la
mise en place de remblayage de sable de dune saturC en couches allant a 1 m d'kpaisseur, et le compactage est rialis6
For personal use only.

en soumettant la masse a une vibration par l'insertion d'un vibrateur de puits de bCton selon un schCma rCgulier de
grille. Les rksultats et l'analyse de nombreuses expiriences en laboratoire, et treize essais a grande Cchelle sur le terrain
sont prCsentCs dans cet article, et forment la base de cette technique de compactage.
Mots clgs : remplissage, sable de dune, frottement inter-granulaire, frottement, vibrations, puits de biton, vibrateurs.
[Traduit par la redaction]

Can. Geotech. J. 29, 315-321 (1992)

1. Introduction 2. Need for a fast and effective backfill compaction


Backfill placement is generally a time-consuming opera- method
tion on any construction project. To minimize excavation It was recognized that if the specified procedure was
and backfill costs, service trenches and foundation excava- followed the backfilling process would be very slow and the
tions are generally made as narrow as practicable. Therefore, completion of utility and foundation works would be sig-
only hand compactors can normally be used to compact the nificantly delayed. For example, it would take about 3 days
backfill. Since hand compactors cannot effectively compact to place, compact, and test the backfill in a typical excava-
thick soil layers, the backfill is placed and compacted in lifts tion about 100 m long, 1 m wide, and 1 m deep which
up to 10-15 cm in thickness, which makes backfilling a slow required a minimum of 95% compaction. On the other
process. hand, if the backfilling was accelerated by using thicker than
Backfill placement was one of the major works during the specified layers the quality of compaction could suffer.
the construction of the King Fahd International Airport A poorly compacted backfill is likely to consolidate further
(KFIA) project in the Eastern Province of Saudi Arabia. under load and can cause distress to the overlying structures.
The project required excavation and backfilling of hundreds Such distresses had occurred on a previous project in Saudi
of utility trenches, manholes, and structure foundations, Arabia, requiring extensive remedial works.
amounting to over one million cubic metres of compacted Since the project was divided into various subcontracts,
backfill. timely excavation and backfilling in areas where several
The project earthwork specificationstypically required all subcontracts were interfaced was quite critical to the con-
backfill to be placed in layers not exceeding 10 cm in loose struction schedule. Therefore, for expediting the backfilling
thickness, compacted to at least 95% of the maximum operation, the best alternative was to place backfill in thick
density in areas with buildings and pavements and to at least layers, e.g., up to 1 m lifts, and to develop a method that
90% density in other areas, and tested for compliance. would effectively compact these thick layers to the specified
densities.
3. Development of compaction method
'present address: Enka-Bechtel (Joint venture), P.K. Because of its abundance and the shortage of other
68 Kucukesat, Ankara, Turkey. suitable soils, dune sand was the predominant backfill
Printed in Canada / lmprimC au Canada
316 CAN. GEOTECH. J. VOL. 29, 1992

volume of the tank up to esich lift thickness was determined


by filling it with measured quantities of water.
Free-draining sand wrapped in a filter cloth was placed
inside the tank around the outlets to provide drainage from
the tank without loosing any backfill material.
The tank was filled with dune sand up to various lift marks
using a 50 kg bucket. The weight of sand in each bucket
load was measured to determine the total weight of sand
required to fill the tank to a particular lift mark, along with
its initial unit weight and degree of compaction.
After backfilling, the surface of the sand was gently
levelled with a wooden trowel without causing any
densification.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Waterloo on 01/28/15

3.2. Compaction with concrete shaft vibrator


The sand was saturated from the surface by using a mea-
sured quantity of water that was about 14% of the dry
weight of the sand. No efforts were made to verify whether
the sand became saturated throughout its entire mass.
The sand was then vibrated using a concrete shaft vibrator
OUTLETS (Wacker, IREK 05Y), 3.8 cm in diameter, 53 cm in length,
and with a fixed frequency of 200 Hz. The vibrator had a
FIG. 1. Large steel tank used to simulate a trench. metal strip spiralled around the connecting hose to keep it
from flexing. The vibrator was inserted vertically into the
sand almost to the bottom using a grid pattern of approx-
material at the KFIA project. Some physical properties of imately 50 x 50 cm, thereby establishing eight vibration
dune sand are provided in Fig. 2. points for each lift. For 30 cm lifts, a vibration period of
Flooding and water-jetting methods have been used on 25 s was used at each grid point because no further settle-
For personal use only.

other projects to densify sand and clay backfill (American ment in the backfill surface was discernible after this period.
Society of Civil Engineers 1968; Sheta 1977; Meo 1979; and Vibration periods of 35 and 45 s were established for 45 and
Laba 1983), but these methods were not successful at KFIA 55 cm lifts, respectively, based on increase in time propor-
in compacting dune sand to the required densities. There- tionate to approximate volumetric ratios of these lifts with
fore, other methods had to be devised. 30 cm lift. A vibration period of 60 s was arbitrarily selected
It is widely accepted that a cohesionless soil densifies for 100 cm lifts. Excess water was allowed to escape through
under its own weight by vibrations only if its intergranular the bottom outlets during the vibration process.
friction is minimized. Dune sand, being a cohesionless After completion of the vibration process, sand cone den-
material, falls in this category of soil. A simple way to sity tests (ASTM 1985) were performed in the densified
vibrate dune sand in the field is by using concrete shaft backfill at various depths.
vibrators, a process similar to consolidating cement concrete. The above experiment was repeated three times for each
The intergranular friction in dune sand can be easily reduced lift thickness, requiring a total of 12 experiments and 30 sand
by saturating it with water. cone density tests. The test results are presented in Table 1.
A study was therefore conducted in the KFIA laboratory 3.3. Observation and analysis
to evaluate the effectiveness of concrete shaft vibrators in The concrete vibrator generally penetrated the backfill
densifying saturated dune sand. under its own influence, without any significant pushing.
3.1. Excavation and backfill model During vibrations small surface depressions were formed
3.1.1. Excavation (trench) around the vibrator which were mostly filled up by the sand
A trench was simulated in the laboratory by a steel tank, moving in from the vicinity of these depressions when the
approximately 2 m long, 1 m wide, and 1 m deep, with vibrator worked at an adjacent point. During this process
outside bracings to keep it from bulging under the lateral the sand surface continually settled. The average settlements
pressure of the sand backfill. The tank had outlets on one (Table 1) indicated that the sand has significantly densified
side of its base to provide drainage, as shown in Fig. 1. in each case.
The sand cone density results were compared with the
3.1.2. Backfill material maximum dry density (ASTM 1983) of dune sand to deter-
The backfill material was dune sand with grain-size range mine the compaction achieved. As indicated in Table 1, the
shown in Fig. 2. average compaction achieved in 30,45, and 55 cm thick lifts
Prior to backfilling, the natural moisture content, satura- ranged from 95 to 101%, whereas in 100 cm lifts it was 93%.
tion moisture content, gradation, and maximum dry density It was considered possible to improve the compaction level
of the sand were determined. The maximum dry density was in 100-cm lifts by increasing the vibration period. Therefore,
determined by the vibratory table method (ASTM 1983). three additional experiments were conducted with 100 cm
These properties of dune sand are given in Fig. 2. thick lifts. In these, a vibration ~ e r i o dof 90 s was selected
3.1.3. Backfilling operation based on the same criterion as uied for 45 and 55 cm lifts.
The inside of the tank walls was marked at heights of 30, As explained earlier, sand cone density tests were per-
45,55, and 100 cm to represent various lift thicknesses. The formed in the densified backfill at various depths to deter-
MIRZA 317

G R A V E L SIZES S A N D SIZES I
5117 SIZES
COARSE 1 FINE (COARSE ( MEDIUM I FlHL
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Waterloo on 01/28/15

c ' 8 I I I I !
, .
.
.
' . .. I 8 . I
8\
L
:
' 1 , .
, \ I , ,
I
,
I ?
8 I
Lu sot ; I \ " i t ; ' .
For personal use only.

D I A M E T E R IN M l L L l M E T R E S

FIG. 2. Grain-size distribution of KFIA dune sand. Maximum dry density (ASTM 1983) = 1.91 g/cm3; natural moisture content =
0.4-1.8%; saturation moisture content = 14.0%. 1 in. = 25.4 mm.

mine the comaaction achieved. The average compaction in and with a fixed frequency of 200 Hz. In some trials more
each case was over 95%, as indicated in- able 2 . than two vibrators were used to save time.
Based on the compaction time required in the laboratory, At the start of trial 1, the vibrator spacing was kept at
it was estimated that a tv~ical100 m long. 1 m wide. and 50 cm and the vibration ueriod at each point was 90 s, in
1 m deea trench could be backfilled and-bompactedswith line with the laborator;- experiment
- with 100 cm lifts.
concret; shaft vibrators to over 90% compactfon in about Although the 50 cm spacing was found to be adequate in
8 h and to over 95% compaction in about 12 h. In compar- the laboratory, it was fealized that to achieve the equivalent
ison, the s~ecifiedbackfill ~rocedurewould have reauired comaaction in the field a closer spacing would be necessary
2 and 3 days,- - respectively.'
- because of the rather larger surfice area and relatively leis
4. Field trials lateral confinement. ~ e i c ein, all other trials, the vibrator
spacing was arbitrarily reduced to 30 cm, and the vibration
Encouraged with the laboratory test results and to period at each point was proportionately shortened to about
evaluate the practicality and effectiveness of this compaction 35-40 s, based upon approximate ratio of volumes of sand
technique in the field, a program of field trials was initiated. within 50 and 30 cm grids.
For this purpose, 13 locations were selected at the project The vibrator was gently pushed to the bottom of the
site, including excavations for sewer, drainage, and electrical backfill and then was slowly worked up and down a couple
lines and manholes. of times. During vibrations, a hollow space about 10 cm in
4.1. Backfilling and initial saturation diameter and several centimetres in depth was formed
At each location the excavation walls were marked at a around the vibrator which was filled with sand from the
desired height above the bottom up to a maximum of 1.0 m. surrounding area by splashing the water around the vibrator.
Dune sand was dumped in the excavation with a bucket A detailed account of time required in placement, satura-
loader to the marked height. The natural moisture content tion, and compaction of the backfill was maintained for each
of dune sand was determined, which ranged from 0.4 to trial. A reasonably good estimate was also made of the
1.8%. The backfill surface was manually levelled with amount of water used during the saturation and compaction
shovels, and then it was saturated with water using a hose operations by measuring the water levels in the water tankers
connected to a water tanker. before and after each field trial. These data are summarized
4.2. Compaction in Table 3.
The backfill was vibrated using two concrete shaft 4.3. Determination of compaction achieved
vibrators (Wacker, IREK 1, 3Y), each 6.4 cm in diameter After compaction, sand cone density tests were performed
CAN. GEOTECH. J. VOL. 29, 1992

TABLE1. Results of compaction by concrete shaft vibrator


%
'

Yo compaction
achieved by
concrete vibrator
Vibration Initial Average
Lift period at density surface Test depth (cmlb
thickness each point Experiment (% of ASTM settlement
(cm) 6) No. D2049)" (cm) 0 7.5 Avg.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Waterloo on 01/28/15

Test depth (cm)


5 10 Avg.

Test depth (cm)


5 13 30 Avg.

Test depth (cm)


For personal use only.

25 50 71 Avg.
100 60 1 87 7.9 94 90 96 93
2 88 7.6 92 92 96 93
3 88 7.6 94 92 92 93
'See ASTM 1983.
b ~ i n c ethe depth of test holes was 16 cm, the average test depth = test depth + 8 cm.

TABLE
2. Compaction results in 100 cm lifts
in the backfill at various levels to determine the compaction
achieved. The test results are summarized in Table 4. 070 Compaction achieved
The laboratory tests revealed that when dune sand is
dumped in excavations without any compaction, its average '70 density Surface Test depth (cm)
density is about 88% of the maximum. Using this average Expt. prior to settlement
No. vibrations (cm) 0 50 70 Avg.
uncompacted density and the average surface settlement
caused by vibrations, the theoretical compaction was com-
puted for each trial and is included in Table 4.
4.4. Analysis of test results
As evident in Table 4, the frequency of density testing in
most field trials was generally much greater than is normally that a 100 m long, 1 m wide, and 1 m deep excavation can
used on construction projects. The purpose of this intensive be backfilled and compacted to over 95% density in about
density testing was to ensure that the vibration process did 13 h by using a single concrete vibrator. The compaction
not result in random pockets of uncompacted material. time can be reduced proportionately by simultaneously using
The test results indicated that the average compaction in more than one vibrator. The time required to achieve 90%
all trials was 95% or more. Some of the individual tests compaction will naturally be much less than that of the 95%
indicated over 100% compaction. The theoretical compac- compaction.
tion computed from surface settlement exceeded 95% in all The following observations were made from the field trial
measured cases, and this correlated well with the correspond- data.
ing compaction determined from the density tests.
The compaction operation data (Table 3) indicated that Lift Specified Vibrator Vibration time Water
the above compaction was achieved in the following average thickness minimum spacing at each point requirement
time period: placement and initial saturation time = (cm) compaction (Yo) (cm) (s) (~/m~)
1.1 min/m3 of backfill; and vibration time = 6.8 min/m3 100 95 30 35 136
of backfill. Based on these average times, it was estimated
MIRZA

TABLE3. Field placement and compaction operation data ,


Time taken to
place and Time taken
Vibrator saturate sand to vibrate
(min) sand (min)
Field Water Number
trial Depth Volume used Spacing used For 1 m3 per
No. (m) (m3) (gal/m3) (cm) (avg.) Total 1 m3 Total vibrator
1 1.O 36 148 30-50 2.5 45 1.3 105 7.3
2 1.O 50 150 30 2 60 1.2 180 7.2
3 0.65 110 132 30 2 155 1.4 330 6.0
4 1.O 70 159 30 2 80 1.1 275 7.9
nd nd nd
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Waterloo on 01/28/15

5 0.8 95 nd nd nd nd
6 1.O 70 132 30 2 75 1.1 205 5.9
7 0.8 351 110 30 4 350 1.O 595 6.8
8 1.O 45 144 30 2 50 1.1 135 6.0
9 1.O 345 114 30 4 275 0.8 720 8.3
10 1.O 60 nd 30 3 65 1.1 110 5.5
11 0.95 80 125 30 2 80 1.O 210 5.2
12 0.8 120 nd 30 3.5 155 1.3 305 8.9
13 0.9 44 150 25-30 3 40 0.9 105 7.2
Avg . 136 1.1 6.8
NOTE:nd, not determined; 1 gal. = 3.785 412 dm3.

TABLE4. Field compaction test results

FDT performeda
Backfill Average % compaction
For personal use only.

Field surface Theoretical Depth achieved


trial Depth Vol. settlement compaction range Frequency
No. (m) (m3) (cm) (Yo) n (cm) ( m 3 / ~ ~Range
~ ) Avg.
1 1.0 36 8.0 96 10 25-70 4
2 1.0 50 8.4 96 11 0-76 5
3 0.65 110 8.5 99 10 10-45 11
4 1.0 70 8.8 97 10 10-80 7
5 0.8 95 nd nd 11 10-60 9
6 1.0 70 10.0 98 14 10-60 5
7 0.8 351 nd nd 10 10-65 35
8 1.0 45 8.1 96 9 10-60 5
9 1.0 345 nd nd 11 10-80 31
10 1.0 60 10.8 99 6 10-60 10
11 0.95 80 7.8 96 9 10-70 9
12 0.8 120 7.0 96 7 20-60 17
13 0.9 44 nd nd 10 10-65 4
NOTE: nd, not determined.
T D T , field density test (ASTM 1985).

5. Method of dune sand backfill compaction by a bucket loader. (C) Level the backfill with hand shovels.
concrete shaft vibrators (D) Saturate the backfill from the surface. Approximate
The overwhelming conclusion based on the results of water requirement may range from 130 to 150 ~ / of m ~
laboratory experiments and field trials is that the dune sand sand, depending upon natural moisture content of sand.
in lifts up to 1 m in thickness can be effectively compacted (E) Insert concrete shaft vibrator (6.4 cm diameter) into the
with concrete shaft vibrators to over 95% density in a backfill, working it slowly to the bottom. Fill the holes
relatively short time. This method was therefore formalized formed around the vibrators with dune sand by splashing
and included in the project earthwork specifications as a water around the vibrators. Keep the vibrtor tip at least
feasible alternative. 10 cm away from the pipes. (F) For 95% minimum com-
The basic steps of this method are shown in Fig. 3 and paction, use vibrator spacing of 30 cm and vibration period
are summarized here. (A) Install the service pipe in the trench of 35 s at each point. For 90% minimum compaction,
on a properly compacted bedding material. (This step is not vibrator spacing can be increased to 35 cm and vibration
required in excavation for building foundation.) (B) Dump time reduced to 20 s. This is based on the experience on this
dune sand at natural moisture content in the trench (excava- project that the efforts required to achieve 95% compaction
tion) to the desired thickness (up to 1 m maximum) using in dune sand by other compaction methods is about 2.5 times
CAN. GEOTECH. J. VOL. 29, 1992

BACKFILL SURFACE
f L E ~ L Y O W,sHOV.L
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Waterloo on 01/28/15

STEP A STEP B STEP C


INSTALLATION OF D U M P 0ACKF:t.L L L V E L SURFACE
B E D D I N G A N D PIPE WITH ?RONT-EN0 LOADER WITH SHOVELS

T O W A T E R SUPPLY
WATER ( W A T E R TANKER)

CONCRETE SHAFT
VIBRATOR

BACKFILL SURFACE
DURING A N 0 AFTER
COMPACTION
For personal use only.

...................
...................
................... ...................
...................
...................
...................
....................
.................. ...................
...................
...................
STEP D STEP E
SATURATION O? COMPACTION WITH
BACKFILL CONCRETE SHAFT VIBRATOR

BACKFILL

B L D O I N O 1 STEP F
VII3RATOU SPACINO A N 0 T R E N C H L O N C I T U D N A L SECTION

FIG. 3. Compaction of dune sand backfill using concrete shaft vibrators.

that required to achieve 90% compaction. For lift thickness 6. Use of this method at KFIA project
less than 1 m, the vibration time can be proportionately This method was extensively used by all major subcon-
reduced in each case. tractors at the KFIA project for placement of backfill in
Field density tests should be performed to verify the utility trenches, behind retaining walls and utility way
compaction achieved at various depths. structure, and around manholes and structure foundations
MIRZA 321

without any problem and to the requirements of the project This method has the potential for use on other projects
standards. where cohesionless sandy material is to beysed as backfill.
Some of the subcontractors improved the process by
mixing sand with water in a mechanical mixing unit at 8. Acknowledgements
saturation water content (about 14%). This provided a The author gratefully acknowledges the kind permission
continuous feed of saturated dune sand and accelerated the of His Excellency, Said Y. Arnin, Vice President, Civil Avia-
process of backfilling, especially in the case of long and deep tion, and Director, International Airports Projects (IAP),
excavations. Ministry of Defence, Kingdom of Saudi Arabia, to publish
The major excavation and backfilling work at KFIA this paper. Acknowledgement is also due to the officials of
started in early 1985 and was successfully completed at the the IAP and Saudi Arabian Bechtel Company for the
end of 1988. Since then most of the backfilled areas have encouragement and support provided throughout the devel-
been covered with pavements, parking areas, and structures. opment of this method.
Some of the utility lines have been in operation for over
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by University of Waterloo on 01/28/15

2 years. The project has also experienced several rainy American Society of Civil Engineers. 1968. Final report of the
seasons. However, no evidence of surface subsidence or any Committee on Backfilling in Public Rights-of-way. American
other distress has been recorded in the backfilled areas. Society of Civil Engineers, St. Louis section, St. Louis, Mo.
ASTM. 1983. Standard test method for relative density of cohesion-
less soils (ASTM D2049). In 1983 Annual Book of ASTM Stan-
7. Conclusions dards, sect. 4, vol. 04.08. ASTM, Philadelphia. pp. 325-333.
Dune sand can be effectively compacted in lifts up to 1 m ASTM. 1985. Standard test method for density of soil in place by
in thickness with concrete shaft vibrators and without using the sand-cone method (ASTM D1556). In 1985 Annual Book
any other mechanical compactor. of ASTM Standards, sect. 4, vol. 04.08. ASTM, Philadelphia.
By selecting the appropriate type, size, spacing, and num- pp. 275-28 1.
bers of concrete vibrators and saturating the dune sand with Laba, J.T. 1983. Cohesive soil compaction by water jetting.
Canadian Geotechnical Journal, 20: 394-405.
water, the backfill operation can be significantly accelerated. Meo, R. 1979. Water jetting-a comprehensive examination of this
The concrete shaft vibrator technique is reliable and fast method of compaction for cohesive trench backfill. M.A. Sc.
and has provided excellent results at the KFIA project. This thesis, University of Windsor, Windsor, Ont.
technique is especially suitable for compacting sand backfill Sheta, M.A. 1977. Water jetting as a method of compacting native
For personal use only.

in narrow and deep spaces where no mechanical compactor trench backfill. M.A. Sc. thesis, University of Windsor, Windsor,
can be effectively used. Ont.

S-ar putea să vă placă și