SANTOS CONSTRUCTION
STA. BARBARA HOMES, STA. BARBARA, BALIWAG, BULACAN
B. MOBILIZATION
SITE CLEARING 10,000.00
LINE AND GRADE 5,000.00
EARTHWORKS 120 CUM 250.00 30,000.00
EXCAVATION WORKS 20,000.00
TERMITE CONTROL 5,000.00
C. MASONRY
FOUNDATION WORKS
COLUMN FOOTING
1.30 X 1.10 X 30 9.9 CUM 0.00
CEMENT 40 kg 99 BAGS 225.00 22,275.00
SAND 4.95 CUM 1,220.00 6,039.00
GRAVEL 9.9 CUM 1,720.00 17,028.00
16MM DEF BARS 66 PCS 380.00 25,080.00
TIE WIRE 5 KLS 90.00 450.00
COLUMN
.20 X .40 X 9 X 30 21.6 CUM 0.00
CEMENT 40 kg 216 BAGS 225.00 48,600.00
SAND 10.8 CUM 1,220.00 13,176.00
GRAVEL 21.6 CUM 1,720.00 37,152.00
16MM DEF BARS 456 PCS 380.00 173,280.00
10MM DEF BARS 350 PCS 150.00 52,500.00
TIE WIRE 15 KLS 90.00 1,350.00
Page 1
R.E. SANTOS CONSTRUCTION
STA. BARBARA HOMES, STA. BARBARA, BALIWAG, BULACAN
PROJECT: PROPOSED TWO-STOREY BUILDING
LOCATION: TARCAN, BALIWAG, BULACAN
OWNER: DR. JEROME SANTIAGO
ITEM DESCRIPTION QTY UNIT U. PRICE AMOUNT TOTAL
D. BEAMS
FOOTING TIE BEAM
.20 X .40 X 137 LM 10.96 CUM 0.00
CEMENT 40 kg 109.6 BAGS 225.00 24,660.00
SAND 5.48 CUM 1,220.00 6,685.60
GRAVEL 10.96 CUM 1,720.00 18,851.20
16MM DEF BARS 219.2 PCS 380.00 83,296.00
10 MM DEF BARS 183 PCS 150.00 27,450.00
TIEWIRE 37 KLS 90.00 3,330.00
Page 2
SCAFFOLDING 30,000.00
SUBTOTAL 125,000.00 125,000.00
SECOND FLOOR
.10 X 10 X 20 20 CUM 0.00
CEMENT 40 kg 200 BAGS 225.00 45,000.00
SAND 10 CUM 1,220.00 12,200.00
GRAVEL 20 CUM 1,720.00 34,400.00
10 MM DEF BARS 750 PCS 150.00 112,500.00
TIEWIRE 50 KLS 90.00 4,500.00
G. STEEL DECKING
10 X 20 200 LM 500.00 100,000.00
CONCRETE NAIL 3 KL 100.00 300.00
SUBTOTAL 100,300.00 100,300.00
H. CHB WALL 936.8 SQM 0.00
EXT. 5" CHB 387.4 SQM 4,843 PCS 10.00 48,425.00
INT. 4" CHB 549.4 SQM 6,868 PCS 9.00 61,812.00
MORTAR
CEMENT 40 kg 550 BAGS 225.00 123,750.00
SAND 12 CUM 1,220.00 14,640.00
VERT / HOR. BARS 792 PCS 150.00 118,800.00
PLASTERING
2 FACE 158 SQM
Page 3
CEMENT 40 kg 60 BAGS 225.00 13,500.00
SAND 39.6 CUM 1,220.00 48,312.00
K. PAINTING WORKS
INTERIOR / EXTERIOR WALL 729 SQM 0.00 0.00
LATEX PAINT 17.5 TIN 1,870.00 32,725.00
SAND PAPER 20 YRD 180.00 3,600.00
PAINT THINNER 5 GAL 265.00 1,325.00
TINTING COLOR 10 LITER 150.00 1,500.00
Page 4
TRAY 10 PCS 65.00 650.00
BRUSH 10 PCS 60.00 600.00
ROLLER 10 PCS 40.00 400.00
N. CEILING WORKS
10 MM GYPSUM BOARD
10 MM X 1.2 X 2.44 70 PCS 800.00 56,000.00
METAL FURRING
Page 5
DOUBLE FURRING 269 PCS 110.00 29,590.00
CARRYING CHANNEL 120 PCS 120.00 14,400.00
BLIND RIVETS 20 BOXES 600.00 12,000.00
SCREW 10,000 PCS 1.20 12,000.00
Page 6
R.E. SANTOS CONSTRUCTION
STA. BARBARA HOMES, STA. BARBARA, BALIWAG, BULACAN
Page 7
SUBTOTAL 97,200.00 97,200.00
R. STEEL WORKS
STEEL SUN BREAKER 25,000.00
BALCONY RAILING STAINLESS STEEL 25,000.00
STAIR HAND RAILINGS STAINLESS STEEL 25,000.00
SPANDREL CEILING AT EAVES (FRONT) 25,200.00
SUMMARY AMOUNT
A. BUILDING PERMIT 15,000.00
B. MOBILIZATION 70,000.00
C. MASONRY 396,930.00
D. BEAMS 554,002.80
E. FORMWORKS/SCAFOLDING 125,000.00
F. CONCRETE FLOOR SLAB 392,650.00
G. STEEL DECKING 100,300.00
H. CHB WALL 429,239.00
I. STAIRS 17,949.40
J. PLUMBING WORKS 35,095.00
K. PAINTING WORKS 40,800.00
L. ROOF FRAMING WORKS 129,370.00
M. ROOFING WORKS 99,000.00
N. CEILING WORKS 123,990.00
O. ELECTRICAL WORKS 279,270.00
P. TILE WORKS 418,990.00
Q. PLUMBING FIXTURES 97,200.00
R. STEEL WORKS 100,200.00
NOTE: -Application for ELECTRICAL and WATER SUPPLY shall be shouldered and proccessed by the owner.
-Any modifications or changes in MATERIALS / FIXTURES made by the owner will be reflected in the
estimated materials cost.*
Page 8
Prepared and estimated by:
Conforme:
Arch. Roberto E. Santos
Page 9
R.E. SANTOS CONSTRUCTION
STA. BARBARA HOMES, STA. BARBARA, BALIWAG, BULACAN
B. MOBILIZATION
SITE CLEARING 10,000.00
LINE AND GRADE 5,000.00
EARTHWORKS 120 CUM 250.00 30,000.00
EXCAVATION WORKS 20,000.00
TERMITE CONTROL 5,000.00
C. MASONRY
FOUNDATION WORKS
COLUMN FOOTING
1.30 X 1.10 X 0.25 X 30 9.9 CUM 0.00
CEMENT 40 kg 99 BAGS 225.00 22,275.00
SAND 4.95 CUM 1,220.00 6,039.00
GRAVEL 9.9 CUM 1,720.00 17,028.00
16MM DEF BARS 66 PCS 380.00 25,080.00
TIE WIRE 5 KLS 90.00 450.00
COLUMN
.20 X .40 X 9 X 30 21.6 CUM 0.00
CEMENT 40 kg 216 BAGS 225.00 48,600.00
SAND 10.8 CUM 1,220.00 13,176.00
GRAVEL 21.6 CUM 1,720.00 37,152.00
16MM DEF BARS 456 PCS 380.00 173,280.00
10MM DEF BARS 350 PCS 150.00 52,500.00
TIE WIRE 15 KLS 90.00 1,350.00
Page 10
R.E. SANTOS CONSTRUCTION
STA. BARBARA HOMES, STA. BARBARA, BALIWAG, BULACAN
PROJECT: PROPOSED TWO-STOREY BUILDING
LOCATION: TARCAN, BALIWAG, BULACAN
OWNER: DR. JEROME SANTIAGO
ITEM DESCRIPTION QTY UNIT U. PRICE AMOUNT TOTAL
D. BEAMS
FOOTING TIE BEAM
.20 X .40 X 137 LM 10.96 CUM 0.00
CEMENT 40 kg 109.6 BAGS 225.00 24,660.00
SAND 5.48 CUM 1,220.00 6,685.60
GRAVEL 10.96 CUM 1,720.00 18,851.20
16MM DEF BARS 219.2 PCS 380.00 83,296.00
10 MM DEF BARS 183 PCS 150.00 27,450.00
TIEWIRE 37 KLS 90.00 3,330.00
Page 11
SCAFFOLDING 30,000.00
SUBTOTAL 125,000.00 125,000.00
SECOND FLOOR
.10 X 10 X 20 20 CUM 0.00
CEMENT 40 kg 200 BAGS 225.00 45,000.00
SAND 10 CUM 1,220.00 12,200.00
GRAVEL 20 CUM 1,720.00 34,400.00
10 MM DEF BARS 750 PCS 150.00 112,500.00
TIEWIRE 50 KLS 90.00 4,500.00
G. STEEL DECKING
10 X 20 200 LM 500.00 100,000.00
CONCRETE NAIL 3 KL 100.00 300.00
SUBTOTAL 100,300.00 100,300.00
H. CHB WALL 936.8 SQM 0.00
EXT. 5" CHB 387.4 SQM 4,843 PCS 10.00 48,425.00
INT. 4" CHB 549.4 SQM 6,868 PCS 9.00 61,812.00
MORTAR
CEMENT 40 kg 550 BAGS 225.00 123,750.00
SAND 12 CUM 1,220.00 14,640.00
VERT / HOR. BARS 792 PCS 150.00 118,800.00
PLASTERING
2 FACE 158 SQM
Page 12
CEMENT 40 kg 60 BAGS 225.00 13,500.00
SAND 39.6 CUM 1,220.00 48,312.00
K ROOF WORKS
RIBTYPE 200 SQM
0.4MMx1.22Mx20M 200 LM 350.00 70,000.00
WALL FLASHING 5 PCS 250.00 1,250.00
END FLASHING 17 PCS 350.00 5,950.00
TECKSREW 6000 PCS 1.50 9,000.00
TYPE S 800 PCS 1.00 800.00
INSULATION 200 LM 60.00 12,000.00
Page 13
SUB TOTAL 99,000.00 99,000.00
GYPSUM BOARD
10 MM X 1.2M X 2.44M 70 PCS 800.00 56,000.00
METAL FURRING
DOUBLE FURRING 269 PCS 110.00 29,590.00
CARRYING CHANNEL 120 PCS 120.00 14,400.00
BLIND RIVETS 20 BOXES 600.00 12,000.00
SCREW 10,000 PCS 1.20 12,000.00
N PAINTING WORKS
INTERIOR / EXTERIOR WALL 729 SQM 0.00 0.00
LATEX PAINT 17.5 TIN 1,870.00 32,725.00
SAND PAPER 20 YRD 180.00 3,600.00
PAINT THINNER 5 GAL 265.00 1,325.00
TINTING COLOR 10 LITER 150.00 1,500.00
TRAY 10 PCS 65.00 650.00
Page 14
BRUSH 10 PCS 60.00 600.00
ROLLER 10 PCS 40.00 400.00
Page 15
NOTE: ELECTRICAL FIXTURES SHALL BE PROVIDED/SUPPLIED BY THE OWNER
Page 16
30CM X 60CM TILE 266 PCS 180.00 47,880.00
FLOOR 7.5 SQM
30CM X 60CM TILE 45 PCS 180.00 8,100.00
STAIRS*
30CM X 30CM TILE 74 PCS 180.00 13,320.00
S STEEL WORKS
BALCONY RAILING 10M AND STAIRS HAND RAILING 20M
STAINLESS STEEL TUBULAR 1mmX1" 50 PCS 1,075.00 53,750.00
STAINLESS STEEL TUBULAR 1.2mmX2" 10 PCS 1,757.00 17,570.00
2.0 WELDING ROD STAINLESS 10 KLS 400.00 4,000.00
SPANDREL CEILING AT EAVES (FRONT) 25,200.00
STEEL SUN BREAKER 1.2mmX1"X2" TUBULAR, PAINTED
1.2mmx1"x2" TUBULAR 30 PCS 600.00 18,000.00
WELDING ROD 5 KLS 100.00 500.00
Page 17
R.E. SANTOS CONSTRUCTION
STA. BARBARA HOMES, STA. BARBARA, BALIWAG, BULACAN
SUMMARY AMOUNT
A. BUILDING PERMIT 15,000.00
B. MOBILIZATION 70,000.00
C. MASONRY 396,930.00
D. BEAMS 554,002.80
E. FORMWORKS/SCAFOLDING 125,000.00
F. CONCRETE FLOOR SLAB 392,650.00
G. STEEL DECKING 100,300.00
H. CHB WALL 429,239.00
I. STAIRS 17,949.40
J. ROOF FRAMING WORKS 129,370.00
K. ROOFING WORKS 99,000.00
L. CEILING WORKS 123,990.00
M. DOORS AND WINDOWS 45,600.00
N. PAINTING WORKS 40,800.00
O. ELECTRICAL WORKS 279,270.00
P. PLUMBING WORKS 35,095.00
Q. TILE WORKS 418,990.00
R. PLUMBING FIXTURES 97,200.00
S STEEL WORKS 119,020.00
Page 18
NOTE: -Application for ELECTRICAL and WATER SUPPLY shall be shouldered and proccessed by the owner.
-Any modifications or changes in MATERIALS / FIXTURES made by the owner will be added in the
estimated materials cost.*
Conforme:
Arch. Roberto E. Santos
Page 19
H. CHB WALL 936.8 SQM 0.00
EXT. 5" CHB 387.4 SQM 4,843 PCS 10.00 48,425.00
INT. 4" CHB 549.4 SQM 6,868 PCS 9.00 61,812.00
MORTAR
CEMENT 40 kg 550 BAGS 0.00 0.00
SAND 12 CUM 0.00 0.00
VERT / HOR. BARS 792 PCS 150.00 ###
PLASTERING
2 FACE 158 SQM
Page 20
CEMENT 40 kg 60 BAGS 0.00 0.00
SAND 39.6 CUM 0.00 0.00
Page 21
R.E. SANTOS CONSTRUCTION
STA. BARBARA HOMES, STA. BARBARA, BALIWAG, BULACAN
B. MOBILIZATION
SITE CLEARING 10,000.00
LINE AND GRADE 5,000.00
EARTHWORKS 120 CUM 250.00 30,000.00
EXCAVATION WORKS 20,000.00
TERMITE CONTROL 5,000.00
C. MASONRY
FOUNDATION WORKS
COLUMN FOOTING
1.30 X 1.10 X 30 9.9 CUM 0.00
CEMENT 40 kg 99 BAGS 225.00 22,275.00
SAND 4.95 CUM 1,220.00 6,039.00
GRAVEL 9.9 CUM 1,720.00 17,028.00
16MM DEF BARS 66 PCS 380.00 25,080.00
TIE WIRE 5 KLS 90.00 450.00
COLUMN
.20 X .40 X 9 X 30 21.6 CUM 0.00
CEMENT 40 kg 216 BAGS 225.00 48,600.00
SAND 10.8 CUM 1,220.00 13,176.00
GRAVEL 21.6 CUM 1,720.00 37,152.00
16MM DEF BARS 456 PCS 380.00 173,280.00
10MM DEF BARS 350 PCS 150.00 52,500.00
TIE WIRE 15 KLS 90.00 1,350.00
Page 22
R.E. SANTOS CONSTRUCTION
STA. BARBARA HOMES, STA. BARBARA, BALIWAG, BULACAN
PROJECT: PROPOSED TWO-STOREY BUILDING
LOCATION: TARCAN, BALIWAG, BULACAN
OWNER: DR. JEROME SANTIAGO
ITEM DESCRIPTION QTY UNIT U. PRICE AMOUNT TOTAL
D. BEAMS
FOOTING TIE BEAM
.20 X .40 X 137 LM 10.96 CUM 0.00
CEMENT 40 kg 109.6 BAGS 225.00 24,660.00
SAND 5.48 CUM 1,220.00 6,685.60
GRAVEL 10.96 CUM 1,720.00 18,851.20
16MM DEF BARS 219.2 PCS 380.00 83,296.00
10 MM DEF BARS 183 PCS 150.00 27,450.00
TIEWIRE 37 KLS 90.00 3,330.00
Page 23
SCAFFOLDING 30,000.00
SUBTOTAL 125,000.00 125,000.00
SECOND FLOOR
.10 X 10 X 20 20 CUM 0.00
CEMENT 40 kg 200 BAGS 225.00 45,000.00
SAND 10 CUM 1,220.00 12,200.00
GRAVEL 20 CUM 1,720.00 34,400.00
10 MM DEF BARS 750 PCS 150.00 112,500.00
TIEWIRE 50 KLS 90.00 4,500.00
G. STEEL DECKING
10 X 20 200 LM 500.00 100,000.00
CONCRETE NAIL 3 KL 100.00 300.00
SUBTOTAL 100,300.00 100,300.00
H. CHB WALL 936.8 SQM 0.00
EXT. 5" CHB 387.4 SQM 4,843 PCS 10.00 48,425.00
INT. 4" CHB 549.4 SQM 6,868 PCS 9.00 61,812.00
MORTAR
CEMENT 40 kg 550 BAGS 225.00 123,750.00
SAND 12 CUM 1,220.00 14,640.00
VERT / HOR. BARS 792 PCS 150.00 118,800.00
PLASTERING
2 FACE 158 SQM
Page 24
CEMENT 40 kg 60 BAGS 225.00 13,500.00
SAND 39.6 CUM 1,220.00 48,312.00
K ROOF WORKS
RIBTYPE 200 SQM
0.4MMx1.22Mx20M 200 LM 350.00 70,000.00
WALL FLASHING 5 PCS 250.00 1,250.00
END FLASHING 17 PCS 350.00 5,950.00
TECKSREW 6000 PCS 1.50 9,000.00
TYPE S 800 PCS 1.00 800.00
INSULATION 200 LM 60.00 12,000.00
Page 25
SUB TOTAL 99,000.00 99,000.00
GYPSUM BOARD
10 MM X 1.2M X 2.44M 70 PCS 800.00 56,000.00
METAL FURRING
DOUBLE FURRING 269 PCS 110.00 29,590.00
CARRYING CHANNEL 120 PCS 120.00 14,400.00
BLIND RIVETS 20 BOXES 600.00 12,000.00
SCREW 10,000 PCS 1.20 12,000.00
N PAINTING WORKS
INTERIOR / EXTERIOR WALL 729 SQM 0.00 0.00
LATEX PAINT 17.5 TIN 1,870.00 32,725.00
SAND PAPER 20 YRD 180.00 3,600.00
PAINT THINNER 5 GAL 265.00 1,325.00
TINTING COLOR 10 LITER 150.00 1,500.00
TRAY 10 PCS 65.00 650.00
Page 26
BRUSH 10 PCS 60.00 600.00
ROLLER 10 PCS 40.00 400.00
Page 27
NOTE: ELECTRICAL FIXTURES SHALL BE PROVIDED/SUPPLIED BY THE OWNER
Page 28
30CM X 30CM TILE 74 PCS 180.00 13,320.00
S STEEL WORKS
BALCONY RAILING 10M AND STAIRS HAND RAILING 20M
STAINLESS STEEL TUBULAR 1mmX1" 50 PCS 1,075.00 53,750.00
STAINLESS STEEL TUBULAR 1.2mmX2" 10 PCS 1,757.00 17,570.00
2.0 WELDING ROD STAINLESS 10 KLS 400.00 4,000.00
SPANDREL CEILING AT EAVES (FRONT) 25,200.00
STEEL SUN BREAKER 1.2mmX1"X2" TUBULAR, PAINTED
1.2mmx1"x2" TUBULAR 30 PCS 600.00 18,000.00
WELDING ROD 5 KLS 100.00 500.00
Page 29
R.E. SANTOS CONSTRUCTION
STA. BARBARA HOMES, STA. BARBARA, BALIWAG, BULACAN
SUMMARY AMOUNT
A. BUILDING PERMIT 15,000.00
B. MOBILIZATION 70,000.00
C. MASONRY 396,930.00
D. BEAMS 554,002.80
E. FORMWORKS/SCAFFOLDING 125,000.00
F. CONCRETE FLOOR SLAB 392,650.00
G. STEEL DECKING 100,300.00
H. CHB WALL 429,239.00
I. STAIRS 17,949.40
J. ROOF FRAMING WORKS 129,370.00
K. ROOFING WORKS 99,000.00
L. CEILING WORKS 123,990.00
M. DOORS AND WINDOWS 45,600.00
N. PAINTING WORKS 40,800.00
O. ELECTRICAL WORKS 279,270.00
P. PLUMBING WORKS 35,095.00
Q. TILE WORKS 174,370.00
R. PLUMBING FIXTURES 97,200.00
S STEEL WORKS 119,020.00
Page 30
NOTE: -Application for ELECTRICAL and WATER SUPPLY shall be shouldered and proccessed by the owner.
-Any modifications or changes in MATERIALS / FIXTURES made by the owner will be reflected in the
estimated materials cost.*
Conforme:
Arch. Roberto E. Santos
Page 31
Page 32
0.00
TOTAL
BY - OWNER
0.00
Page 33