Pavement Management System Step By Step User Guide
Contents
A. Introduction ............................................................................................................ 5
A.1 Pavement Management System (PMS) .......................................................... 5
A.2 Strategic Planning Analysis Procedure ........................................................... 9
A.3 Programme Analysis Process ........................................................................10
B. Prepare Named Selection for Strategy Planning Analysis .................................11
C. Create and Analyse Homogenous Data Report ..................................................14
C.1 Set Parameters of Confirm (HDM-4 Interface) ...............................................14
C.2 Create Homogenous Data Report ..................................................................17
C.3 Analysis of HDR in Microsoft Excel ................................................................19
C.4 Definition of NSM-SPA...................................................................................23
D. Update HDM-4 Workspace and Export Network and Strategy Input Files ........30
D.1 Update Strategy File ......................................................................................30
D.2 Update Traffic Growth Rate ...........................................................................33
D.3 Update Road User Costs (RUC) ....................................................................35
D.4 Update Construction Costs ............................................................................37
D.5 Export Network and Strategy Input Files ........................................................38
E. Update Network Input File ....................................................................................41
E.1 Prepare Network State Matrix (NSM) Populating Tool - SECTION.................41
E.2 Prepare Network State Matrix (NSM) Populating Tool - TRAFFIC .................45
E.3 Update NSM Attributes ..................................................................................47
F. Identify Optimum Alternative for Each PRS ........................................................50
F.1 Run unconstrained Strategy Analysis of NSM in HDM-4 ................................50
F.2 Assign optimum alternative to PRS ................................................................56
G. Run Strategy Analysis Interface ..........................................................................60
G.1 Set Parameters of Confirm (HDM-4 Interface) – Criteria for NSM-SPA ..........60
G.2 Strategy Analysis Interface ............................................................................61
H. Review Strategy Analysis Interface Outputs ......................................................64
H.1 Check total number of NSM cells ...................................................................64
H.2 Correction of clones length ............................................................................64
H.3 Update of Strategy Input File .........................................................................66
I. Run strategy analysis in HDM-4 and Perform Budget Optimization .................67
I.1 Import revised Strategy Analysis Interface Outputs into HDM-4 .....................67
I.2 Run Strategy Analysis in HDM-4 ....................................................................68
I.3 Perform Budget Optimization .........................................................................71
J. Import HDM-4 result into SETH and prepare SPA visuals .................................74
J.1 Import HDM-4 result into SETH......................................................................74
J.2 Prepare SPA Report visuals for the National Network ....................................74
J.3 Prepare SPA Report visuals per Planning Unit, Region and Road Class .......75
K. Preparation of SPA Report ...................................................................................83
K.1 Analysis of SETH Output ...............................................................................83
K.2 Prepare SPA Report ......................................................................................83
L. Update Budget Optimization in HDM-4 with Defined Budget .............................84
M. Import HDM-4 result into SETH and determine budget per Planning Unit ........85
2
Pavement Management System Step By Step User Guide
3
Pavement Management System Step By Step User Guide
Glossary of Terms
AADT Annual Average Daily Traffic
DPD Development Planning Division
DPWH Department of Public Works and Highways
FY Financial Year
HDM-4 Highway Development and Management (version 4)
HDR Homogeneous Data Report
IMS Information Management Service
IRI International Roughness Index
MYPS Multi-Year Programming and Scheduling Application
NSM Network State Matrix
NSM ID Network State Matrix Identification Code
NSM-SPA Network State Matrix Strategic Planning Analysis
PAGASA Philippines Atmospheric, Geophysical & Astronomical Services Administration
PMS Pavement Management System
PS Planning Service
PRS Planning Road Section
RBIA Road and Bridge Information Application
RTIA Road Traffic Information Application
SD Statistics Division
SETH Strategic Evaluation Tool for HDM-4
SPA Strategic Planning Analysis
TGR Traffic Growth Rate
4
Pavement Management System Step By Step User Guide
A. INTRODUCTION
A.1 Pavement Management System (PMS)
1. The objective of this User Guide is to describe, step by step, the procedure to operate the Pavement
Management System (PMS), which corresponds to the two steps Input Data Preparation and Run
HDM-4 Analysis in the Planning and Programming overall process (see Figure 3 overleaf). The
analysis of HDM-4 output to prepare the Long Term Plan and subsequent programs is covered in the
Planning and Programming Procedures Manual. (See PMS Documentation Map Figure 2).
2. The process actually involves several back and forth between the Confirm (HDM-4 Interface) and
HDM-4 System (see Figure 1 below), and this document was structured to follow this logical
sequence of steps. Therefore, its structure may differ slightly from Figure 3.
Figure 1
PMS System Components
3. The starting point is the creation of HDR. It does NOT require input files exported from HDM-4, but
requires the specification of Network State Matrix (NSM) that represents the national road network
by a small number of representative sections or NSM cells. Currently, NSM is defined by pavement
type, traffic volume, direction, roughness and pavement condition.
4. The main task of Confirm (HDM-4 Interface) at the first stage is to chop the defined national road
network into homogeneous road sections referred to as PRS and produce HDR. HDR summarizes,
PRS by PRS, all relevant information available from Road and Bridge Information Application
(RBIA) and Road Traffic Information Application (RTIA) applicable for running HDM-4. Each PRS
is associated with a unique NSM cell identifier that represents the PRS.
5
Pavement Management System Step By Step User Guide
6
Pavement Management System Step By Step User Guide
Figure 3
Planning and Programming Overall Process
7
Pavement Management System Step By Step User Guide
5. Strategic Planning Analysis (SPA) studies National State Matrix (NSM). HDM-4 workspace must be
configured for the defined NSM by means of network file and strategy file. The strategy file defines a
set of section alternatives for each NSM cell.
6. The configured NSM network file is exported from HDM-4 and populated with the information
contained in HDR by using Excel spreadsheet tools.
7. The populated network file and strategy file that have been exported from the configured HDM-4
workspace are imported to Strategy Analysis Interface of Confirm (along with the user defined
maximum NSMSPA cell length) to prepare HDM-4 input data (i.e., HDM-4 workspace) for SPA.
8. Program Analysis studies individual PRS by Planning Unit (PU). Program Analysis Interface of
Confirm defines the road network as all PRS’s belonging to a given Planning Unit (PU) and prepares
HDM-4 workspace that is populated with section alternatives for each PRS based on the NSM cell
that represents the PRS.
9. The output of HDM-4 strategy analysis are used with the Strategic Evaluation Tool for HDM-4
(SETH) to provide information for decision makers to decide upon the optimal scenario and obtain a
budget per Planning Unit (to be used for the programme analysis).
10. The output of HDM-4 program analysis under the defined budget scenario are then used in the Multi-
Year Programming and Scheduling Application (MYPS) to follow up the implementation of the
works.
8
Pavement Management System Step By Step User Guide
Microsoft Word Analyze SPA output and prepare SPA Report using the
template in Appendix B.
9
Pavement Management System Step By Step User Guide
12. At the end of the Strategic Planning Analysis, an annual budget is decided for the asset preservation
of the national network for the next Financial Year (FY). The objective of the programme analysis is
to translate this budget in a prioritized list of works for each Planning Unit (PU). The Procedure of the
Programme Analysis is described in the flowchart below
Figure 5 -
Programme Analysis Procedure
Tasks Software Description
Set the exclusion settings, then select the appropriate Planning Unit
Confirm (HDM-4 and create the corresponding Named Selection with the queries
Interface) PMS_06, PMS_02 and PMS_03. Then run the Programme Analysis
on this Named Selection. Outputs: PRS_RN_YY_XXXX_01.mdb
and PRS_PRG_YY_XXXX_01.mdb.
HDM-4 Export HDM-4 Programme Analysis in Excel via the “export” tool.
Microsoft Excel Output: PRS_PRG_YY_XXXX_01.xls.
10
Pavement Management System Step By Step User Guide
1. Select the Confirm Enterprise icon from the desktop to launch Confirm.
2. Login to Confirm using your User ID and password.
3. Open the Data Query Qualification form (Reporting > Data Queries) or using the search tool: Ctrl+F,
“queries”:
11
Pavement Management System Step By Step User Guide
7. In Data Query Qualification, set the “Effective Date” (double click on ‘Effective Date) as the RBIA
cut-off date plus one day (to make sure that data entered during the last day is included) then hit
“OK”.
8. Run the query by hitting the “OK” button
9. This will create a selection with all the live road sections of the national network as per the cut-off
12
Pavement Management System Step By Step User Guide
11. Define “Where Selection already exists as “Replace”, then hit “OK”
13
Pavement Management System Step By Step User Guide
2. Open the “General” tab and check that the Maximum NSM length is left blank.
Not relevant at
Maximum NSM section
this stage
length should be left
blank
14
Pavement Management System Step By Step User Guide
4. “Sections” and “Traffic” tabs of HDM-4 Systems Settings should not be changed either as part of the
regular planning procedure.
Not relevant at
this stage
15
Pavement Management System Step By Step User Guide
3. All the other parameters are configured and should not require any change at this stage.
Select the Feature Inventory Tab and review the Inventory Items. This tab lists the features which are
being used and how they are used to determine the homogenous sections. Check that the parameters
follow the PMS interface Configuration Report (2014).
16
Pavement Management System Step By Step User Guide
4. Select the Survey Tab and review the selected items (Ditto previous step).
17
Pavement Management System Step By Step User Guide
4. The Homogenous Data Report exports in a Microsoft Excel spreadsheet the result of the chopping of
the network. It can be “unmerged”, where each row represents a truly homogenous section or
“merged”, where each row represents a Planning Road Section (PRS). The configuration of the
parameters of the chopping are described in the PMS Interface Configuration Report (2014).
5. Set the Effective date at the RBIA cut-off date plus one day (Use the same date as the one defined in
Section B).
6. Select the Named Selection representing the strategy analysis scope of analysis created in Section B.
Merge Box to be
checked
18
Pavement Management System Step By Step User Guide
2. Save the HDR as Excel workbook (xls or xlsx) with the same name, freeze the first row and apply
general filters (Select all and Ctrl + Shift + L) on all columns.
19
Pavement Management System Step By Step User Guide
3. For the above columns, check outstanding values by sorting from largest to smallest, then smallest to
largest. Check if the following RoCond values, corresponding to percentages, exceed 100:
• Edge Break Extent (RCONDA_RC13)
• Wearing Surface (RCONDA_RC48)
• Cracking Extent (Asphalt) (RCONDA_RC10)
• Joint Faulting (RCONDC_RC19)
• Joint Spalling (RCONDC_RC18)
• Cracking (Concrete)(RCONDC_RC16)
4. Check extreme AADT figures against the number of lanes
A 21 HG F G
Pavement type: Traffic/Flow: Traffic: Roughness: Visual Condition:
A: Asphalt 21: 2 lanes 1 VL: Very Low G: Good G: Good
C: Concrete direction LW: Low F: Fair F: Fair
(G: Gravel 22: 2 lanes 2 MD: Medium P: Poor P: Poor
E: Earth) directions HG: High B: Bad B: Bad
42: 4 lanes VH: Very HIgh
2directions
With :
Asphalt and Concrete
AADT Band
Roads
VH Very High AADT > 20,000
HG High AADT > 8,000 & ≤ 20,000
MD Medium AADT > 2,500 & ≤ 8,000
LW Low AADT > 750 & ≤ 2,500
VL Very Low AADT > 0 & ≤ 750
20
Pavement Management System Step By Step User Guide
And
Machine Condition Asphalt and
Band Concrete Roads
G Good IRI > 0 & ≤ 3
F Fair IRI > 3 & ≤ 5
P Poor IRI > 5 & ≤ 7
B Bad IRI > 7
(Visual Condition score is given following a combination of all the defects and cannot be checked as
part of this step)
Select a few NSM_ID and check the corresponding key features (i.e. RPVT_RI34, RNLN_RI21,
RNLN_RI04, RR_RC05):
4. Check that the total length of PRS matches the length of the named selection:
• In the Confirm, open the “Named Selection” module:
21
Pavement Management System Step By Step User Guide
• Search and select the Named selection created in Section B. Selections are sorted by
“name” and not by “code” by default)
Note: A difference of a few meters may appear due to the rounding of the length of each PRS
5. Perform a random check on the column “Exclude_If_True” against the columns Surface Type
(RPVT_RI34) and Environment (RENV_RI07). Exclude_if_True must be “True” when:
• Surface Type is “G” or “E”
• Environment is “UM”
22
Pavement Management System Step By Step User Guide
6. Check if any PRS is longer than the defined maximum length (1,500m). This may happen when both
roughness and RoCond data are missing on a long section. Prepare a list of these sections and report
them to SD.
23
Pavement Management System Step By Step User Guide
4. In the “Pivot Table Fields”, drag and drop “NSM_ID” to the “ROWS” box
24
Pavement Management System Step By Step User Guide
6. In the drop list menu of “Count of SubSection…”, click on “Value Field Settings…”
8. Back in “Pivot Table Fields”, drag and drop “Exclude_if_True” and “AADT(RAAD_RI41)” in the
“FILTERS” box
9. Close the “Pivot Table Fields” window and, in the drop list menu of “Exclude_if_True”, check
“Select Multiple Items” and unselect “True”
10. In the drop list menu of “AADT(RAAD_RI41), check “Select Multiple Items” and unselect “Blank”
25
Pavement Management System Step By Step User Guide
11. Select the two columns of the Pivot Table and copy them
13. Apply a filter on the table: Select all the cells and click on Data > Filter
14. Note the number of rows in the table (make sure not to count the row “Grand Total”)
26
Pavement Management System Step By Step User Guide
• Plot the distribution of NSM cell length by selecting the entire table, then Insert>Insert
Column Chart>Clustered Column
• Increase the size of the graph and identify any break in the “curve” of the distribution of
NSM length. In the example above, such a break occurs between the lengths of 516 km
and 647 km:
• Hence, in the example above, 600km is a more appropriate maximum than 800km.
3. NSM cells whose length is longer than the set maximum will be “cloned” by Confirm (HDM-4
Interface) through the Strategic Analysis module (see section below): New NSM cells with the same
characteristics will be created to distribute the total length into smaller items with a length smaller
than the set maximum.
27
Pavement Management System Step By Step User Guide
1. Calculate the total number of resulting NSM cells by calculating the number of clones to be created.
It can be rapidly estimated with the following formula:
ݐ݃݊݁ܮℎ ܰܵ ܦܫ ܯ
(ݎ݁݃݁ݐ݊ܫ )+1
ݐ݃݊݁ܮ ݉ݑ݉݅ݔܽܯℎ
ୀଵ
2. If the total is smaller than 400, no need to proceed to any change
3. If the total is greater than 400, the appropriate number of cells (Total number – 400) will need to be
removed:
1. The “elimination” of the cells is done by substituting the NSM ID of sections (i.e. PRS) with
another NSM ID. In other words, it is done by merging the NSM cell with another cell
associated to a longer length.
2. Therefore, for each identified cell with a length inferior to the limit, a cell with similar
attributes should be selected, with which the cell will be merged. The following should be
followed to identify the substitution:
a. Sort the column “Total” from “Smallest to Largest
b. Identify the NSM ID of the smallest cells that need to be removed.
c. Example for AHG42BG: Filter the column NSM_ID to select only NSM IDs with the
same 6 first characters (i.e. same pavement type, traffic direction/number of lane,
traffic volume category and roughness).
d. If available, select the NSM ID with the surface condition score (last letter of NSM
ID) in the next category (G > F > P > B). If not available, take the closest one.
28
Pavement Management System Step By Step User Guide
e. If no other NSM ID are available in this selection, repeat Step c. by selecting all
NSM IDs with the same 5 first characters, then repeat step d with the roughness
score.
f. A list as follows should then be transmitted to HDM-4 Interface administrator (IMS),
who will amend the NSMID expression accordingly.
29
Pavement Management System Step By Step User Guide
30
Pavement Management System Step By Step User Guide
4. Verify that the Strategy file is connected to the right network file and vehicle fleet. Analysis period
should remain of 20 years and discount rate of 15%, unless otherwise stated.
5. Go to the “Study Sections” tab and check that all “Sections” are selected (red tick box) and have
“ALL” as Traffic Growth
31
Pavement Management System Step By Step User Guide
7. Each alternative is composed of works standards which are already predefined in the strategy file.
Check that all sections have more than one alternative (base alternative), and correspond to the HDM-
4 Configuration Report (2014).
8. Update Alternatives if needed.
32
Pavement Management System Step By Step User Guide
3. The list of Traffic Growth Rates (TGR) should include a National Average (ALL), used for the
Strategic Planning Analysis, and one set per Region. Select the first Set of TGR and hit the “Edit…”
button.
33
Pavement Management System Step By Step User Guide
4. Update the TGR for each vehicle type and each time period based on values calculated as per the
Procedures Manual for Updating Vehicle Costs and User Costs, Work Unit Costs, Asset Values,
Traffic Growth Rates (2014).
34
Pavement Management System Step By Step User Guide
1. IN HDM-4, Select the file “Philippines12” and hit the “Export” button
4. Update all attributes with the values received from the Statistics Division (SD) as per the Procedures
Manual for Updating Vehicle Costs and User Costs, Work Unit Costs, Asset Values, Traffic
Growth Rates (2014). Note that “EUC” corresponds to “Economic Unit Cost” and “FUC”
corresponds to “Financial Unit Cost”. “FUC” column should be left blank as HDM-4 does not
conduct financial analyses of Road User Costs.
5. Save Changes and close the file
6. In HDM-4, hit the “Import” button and select the file updated in the previous steps
35
Pavement Management System Step By Step User Guide
7. Click “Next” and “Yes” when prompted whether to overwrite existing vehicle fleet
36
Pavement Management System Step By Step User Guide
1. In HDM-4, Select the folder “Work Standards” and hit the “Export” button
4. Select all values by clicking on the top left corner and paste values in a new Microsoft Excel
spreadsheet.
37
Pavement Management System Step By Step User Guide
1. IN HDM-4 workspace, select the network (NSM_Network file) and click on Export:
38
Pavement Management System Step By Step User Guide
2. Create an appropriate folder and save the file under the name NSM_Network_YY_01 with:
• YY: Year of the study
• 01: Sequential number
3. Select the strategy file NSM_Strategy and hit the “Export” button:
39
Pavement Management System Step By Step User Guide
4. Save the NSM_Strategy file in the same folder as the NSM_Network file and under the name
NSM_Strategy_YY_01.mdb.
Where:
o YY: Year of the study
o 01: Sequential number
40
Pavement Management System Step By Step User Guide
2. Go to the HDR-Extract worksheet and clear all the content under the top row (which is protected)
41
Pavement Management System Step By Step User Guide
3. Open the HDR created in Section C.2 in Excel and copy/paste the columns with the corresponding
headers using Paste Special… > Paste Value.
4. Go back to “Introduction” worksheet and in step 3:
• Enter the appropriate Start Year (i.e. the first year of the study period)
• Enter the AADT Year which corresponds to the biggest percentage of traffic data of the
HDR (usually study year minus 2)
• Confirm the option to exclude Gravel and Urban Road (by default it should be yes)
• Confirm whether Rutting is considered as Type A or Type B variable (by default it
should be Type B).
6. Type A variables have been computed based on the imported data from HDR and appear in the cells
highlighted in light yellow. Depending on the relevant attributes of the NSM cells, they have been
sorted in different tables.
7. Look for outliers and any missing data in the tables. If sets of data are considered as biased or non-
representative of the network, default values should be applied (See PMS Configuration Report).
42
Pavement Management System Step By Step User Guide
8. Go to the Type B & C Variables worksheet. These values should only be updated (or reconfirmed)
every 3 to 5 years.
9. Go to SECTIONS worksheet and check that no column includes an error (e.g. #N/A), blank cells
apart from “LINK_ID” and “LINK_NAME” columns, or “no data available”)
43
Pavement Management System Step By Step User Guide
10. Go to the Network Analysis worksheet. Check graphs of the network for visual condition. If the
categories are not representative (e.g., if more than 90% of the roads are scored as “good”), the
Machine Condition Band formula may need to be reviewed.
11. Update Section B of the SPA Report (See Appendix B).
44
Pavement Management System Step By Step User Guide
2. Enter the same AADT Year and as defined in Section E.1 and confirm that the same options for the
exclusion of gravel roads and urban roads have been selected.
3. Go to HDR – Extract tab and. Open the HDR created in Section C.2 in Excel and copy/paste the
columns with the corresponding headers using Paste Special… > Paste Value
45
Pavement Management System Step By Step User Guide
4. Go to Type A variables tab and check the values calculated as the average of AADTs of all PRSs
belonging to the same NSM cell:
5. Go to TRAFFIC tab and check that there is no cell with error (e.g. #N/A) or “no data available”.
46
Pavement Management System Step By Step User Guide
1. Open with Microsoft Access the input file NSM_Network_YY_01.mdb exported from HDM-4 in
Section D.
2. The file is composed of 4 tables. The Tables FILETYPE and ROADNET only include generic
information for HDM-4 purpose and should not be changed. The Table SECTIONS contains all the
information related to the NSM cells.
5. Go back to the NSM Populating Tool_SECTIONS spreadsheet in Excel and copy cells G2:GN481
from the SECTIONS tab and paste them in this table.
6. Click “yes” to the pop-up window. Then save the changes and close the mdb file.
47
Pavement Management System Step By Step User Guide
8. The table shows all the NSM cells in column (the NSM ID is replaced by a serial number) with an
AADT value for each of the 12 vehicles. It is the same as the tab TRAFFIC of the Populating Tool.
9. Copy cells C2:H5761 from the TRAFFIC tab of the NSM Populating Tool_TRAFFIC spreadsheet
and paste them in this table.
10. Click yes to the pop-up window.
48
Pavement Management System Step By Step User Guide
12. Open the NSM_Strategy_YY_01.mbd file extracted in Step D.5. and open the table “Strategy”
• NAME: NSM_Strategy_YY_02
• NETWORK: NSM_Network_YY_02
49
Pavement Management System Step By Step User Guide
1. Import in HDM-4, hit the “Import” button and select the file NSM_Network_YY_02
created in Section E.3.
50
Pavement Management System Step By Step User Guide
51
Pavement Management System Step By Step User Guide
6. In “Study Sections”, check that all the sections are selected and that the traffic growth set is “ALL”
for all NSM cells.
52
Pavement Management System Step By Step User Guide
53
Pavement Management System Step By Step User Guide
54
Pavement Management System Step By Step User Guide
10. Click on the “Export” button and select the following options:
11. Save the Excel Spreadsheet under the name Optimum Section Alternatives (Unconstrained
Budget)_YY_02.xls.
55
Pavement Management System Step By Step User Guide
2. Delete the rows from 1 to 16 and restructure the header to enter in a single row. Apply a filter to mask
empty rows:
3. Insert one column after the Column “Section” with the header “NSM ID”
56
Pavement Management System Step By Step User Guide
4. Open the spreadsheet NSM Populating Tool_SECTIONS used in Section E.1 and open the worksheet
“SECTIONS”. Copy and Paste the columns G and H in a worksheet of the spreadsheet created in Step
1 in the order SECT_NAME, SECT_ID.
5. In the new column “NSM ID” of the worksheet created in step 1, apply a “vlookup” formula on the
table created in step 4 to collect the corresponding SECT_ID.
57
Pavement Management System Step By Step User Guide
9. Hide columns between the column “Location” and the column “NSM_ID”, then all columns after the
column “NSM_ID”
10. Insert a new column named “Optimum Alternative” and apply a vlookup formula in the table created
in step 5 to collect the column “Alternative Desc.”
58
Pavement Management System Step By Step User Guide
11. Repeat the step above to insert a column which collects values from the column “Net Present Value”
of the table created in step 5:
59
Pavement Management System Step By Step User Guide
1. Open Confirm (HDM-4 Interface), and open the HDM-4 System Settings, General tab.
2. Set the maximum NSM length as per Section C.4 (note that in Confirm (HDM-4 Interface), like in
RBIA, lengths are expressed in meters)
Length in
meters
3. The substitution of short NSM cells is done via the Homogenization System Settings > Computed
Columns window. Check that the correct substitutions (if needed) were entered by the HDM-4
Interface administrator (IMS).
60
Pavement Management System Step By Step User Guide
No substitution
required in the
present example
• The NSM_ORIG Compute Column defines the NSM ID to be replaced by the alternative
defined in the NSM_ALT Computed Column. They must be updated together as their content
is related by position.
• The contents of the Computed Columns are structured as follows:
NSM_ORIG = "ORIGINAL_NSM1 , ORIGINAL_NSM2 , ORIGINAL_NSM3 ,….”
NSM_ALT = "ALTERNATIVE_NSM1 , ALTERNATIVE _NSM2 , ALTERNATIVE _NSM3
,….”
• In the following example the first NSM ID in the NSM_ORIG list, “AHG21FF”, would be replaced
by "AHG21FP” and the third NSM ID in the NSM_ORIG list, “CMD22FG”, would be replaced by
“CMD22FF”.
NSM_ORIG = ............... "AHG21FF, AHG21FG ,CMD22FG ,CMD22FP, AHG42PG , AHG42FG"
NSM_ALT = ................. "AHG21FP , AHG21FP , CMD22FF , CMD22FB , AHG42PF, AHG42FF"
61
Pavement Management System Step By Step User Guide
1
Note: The definition of Number of Budget Period and Budget Period Length at this stage only affects the
multiplication of alternatives by the Confirm Interface (refer to the PMS Design Report, 2014 for more
details). Hence, it is not connected to the number and length of budget periods used to perform the
strategy analysis in HDM-4. As the Strategy Input File does not require any multiplication of alternatives,
the Number of Budget Periods is set at 1.
62
Pavement Management System Step By Step User Guide
63
Pavement Management System Step By Step User Guide
3. Check that:
• NSM cells longer than the set maximum have been cloned properly (i.e. there is no more
NSM cells longer than the set maximum)
• Clones have the same properties as original cell
• All cells programmed for substitution have been substituted properly
• The number of NSM cells is smaller than 400.
64
Pavement Management System Step By Step User Guide
3. Sort from “A to Z” the SECT_ID column to make sure that clones are on top of
each other.
4. Copy the SECT_ID and LENGTH cells of all cloned cells and paste them on a new spreadsheet
5. Create a new column named “Corrected Length” and calculate the new length as per the following
procedure:
• If 2 clones only (for example AMD22FG and AMD22FG-1):
(௧ಲಾವమమಷಸ ା ௧ಲಾವమమಷಸషభ )ିଵ
i. Corrected Length of AMD22FG:
ଶ
iii. Corrected Length of CMD22GP-2: Total LengthCMD22GP clones - Corrected LengthCMD22GP - Corrected
LengthCMD22GP-1
6. Replace the values from “corrected length” in the corresponding LENGTH column of the SECTION
table of NSMSPA_RN_YY_01.mdb.
65
Pavement Management System Step By Step User Guide
7. Save and close the mdb file under the name NSMSPA_RN_YY_02.mdb
3. Save and close the mdb file under the name NSMSPA_STR_YY_02.mdb
66
Pavement Management System Step By Step User Guide
67
Pavement Management System Step By Step User Guide
2. Check that:
• The correct road network is assigned
• Tec correct Vehicle Fleet is assigned
• Start Year
• Analysis Period of 20 years (default SETH study period)
• Discount rate of 15% (unless otherwise specified)
68
Pavement Management System Step By Step User Guide
4. Go to “Specify Alternatives”. Check that all sections have works alternatives, corresponding to the
Strategy Input file (perform a random check on a couple of sections).
69
Pavement Management System Step By Step User Guide
• Create a directory for Run Data Export Directory with the name SPA_STR_YY_01
• Check “Exclude annual vehicle data” and “Exclude vehicle period data” (these data will
not be reported in the rundata file, which avoids reaching the Microsoft Access limit of 2
GB).
To be checked
70
Pavement Management System Step By Step User Guide
• Practical Optimum:
Start of Year End of Year Capital Budget
1 1 UCCC6/6
2 2 UCCC6/6
3 3 UCCC6/6
4 4 UCCC6/6
5 6 2*UCCC6/6
7 20 9999999.000000
• 90% Optimum:
Start of Year End of Year Capital Budget
1 1 90%* UCCC6/6
2 2 90%* UCCC6/6
71
Pavement Management System Step By Step User Guide
3 3 90%* UCCC6/6
4 4 90%* UCCC6/6
5 6 2*90%* UCCC6/6
7 20 9999999.000000
• 75% Optimum:
Start of Year End of Year Capital Budget
1 1 75%* UCCC6/6
2 2 75%* UCCC6/6
3 3 75%* UCCC6/6
4 4 75%* UCCC6/6
5 6 2*75%* UCCC6/6
7 20 9999999.000000
• 50% Optimum:
Start of Year End of Year Capital Budget
1 1 50%* UCCC6/6
2 2 50%* UCCC6/6
3 3 50%* UCCC6/6
4 4 50%* UCCC6/6
5 6 2*50%* UCCC6/6
7 20 9999999.000000
2. Select all scenarios and hit the “Perform Budget Optimization” Button
72
Pavement Management System Step By Step User Guide
73
Pavement Management System Step By Step User Guide
74
Pavement Management System Step By Step User Guide
2. Copy and paste the charts to update the SPA Report (See Appendix in Appendix B)
J.3 Prepare SPA Report visuals per Planning Unit, Region and Road
Class
J.3.1 Calculate NSM length per Planning Unit
1. Open the HDR extracted in Section C
2. Go to Insert > Pivot Table (See Section C.4.1)
3. Set the PivotTable Fields as follows:
• Drag and Drop “PLANNING_UNIT” to the “ROWS” box
• Drag and Drop “NSM_ID” in the “ROWS” box (under “PLANNING_UNIT”)
• Drag and drop “SubSections_Length” to the “VALUES” box and change “Count” to
“Sum” in “Value Field Settings”
• Drag and Drop “Exclude_If_True” in the “FILTER” box
• Drag and Drop “AADT(RAAD_RI41)” in the “FILTER” box
75
Pavement Management System Step By Step User Guide
4. Close PivotTable Fields and in the drop list menu of “Exclude_If_True”, check “Select Mupltiple
Items” and uncheck “True”
5. In the drop list menu of “AADT(RAAD_RI41)”, check “Select Multiple Items” and unselect “Blank”
6. Click anywhere in the pivot table and go to Design. Set the following parameters:
• Subtotals > Do not show subtotals
76
Pavement Management System Step By Step User Guide
7. Select the resulting table, copy and paste the values in a new worksheet
8. Create a new column and calculate the total length in kilometers (divide the column “Total” by 1,000)
77
Pavement Management System Step By Step User Guide
9. Copy the column D (Total in km) and paste it over the column “Total” using “Paste Value”
78
Pavement Management System Step By Step User Guide
2. Save the table with the corrected length (per km) under LengthNSM_Reg_YY_01.xls
79
Pavement Management System Step By Step User Guide
4. Save the table with the corrected length (per km) under LengthNSM_Class_YY_01.xls
J.3.4 Prepare Visuals with SETH
1. Open the file SETH_YY_01.xls created in Section J.1.
2. Copy and paste the tables created in Sections J.3.1, J.3.2 and J.3.3 respectively in the worksheets
NSM Length per PU, NSM Length per Region and NSM Length per Class (note that the road
classification system is being updated at the time of this report and the categories will need to be
updated).
3. In the worksheet “Budget Scenario Data”, Select the “Unconstrained Scenario” in the corresponding
box, and Select "Roughness After Works (IRI, m/km)” as Indicator
4. Go to “Output per Region” and select the entire table from the column “Planning Unit”
5. Go to Insert > Insert Scatter (X,Y) or Bubble Chart > Scatter with Straight Lines and Markers
80
Pavement Management System Step By Step User Guide
6. Resize the chart appropriately and change the vertical axis bounds to fit the scale and update chart in
the SPA Report.
81
Pavement Management System Step By Step User Guide
7. Repeat Steps 3 to 6 with the other Budget Scenarios and with “Output per Road Class” worksheet.
8. Note that the worksheet “Output per Planning Unit” is used in the Programme Analysis process to
obtain the capital expenditure per Planning Unit for the defined budget.
82
Pavement Management System Step By Step User Guide
83
Pavement Management System Step By Step User Guide
84
Pavement Management System Step By Step User Guide
3. Go back to the “Main Menu” tab and hit the “Evaluate Scenarios” button.
4. Save the SETH file as SETH_YY_02.xls.
85
Pavement Management System Step By Step User Guide
4. The list of PU in the worksheet “Output per Planning Unit” is the comprehensive list of
Congressional Districts. Therefore some PU may not have any budget allocated, e.g. because their
network is entirely composed of Urban Metropolitan roads. These PU should be discarded from the
study.
5. If HDM-4 does not allocate any budget for the first 6 years, a solution should be discussed by DPD
on a case by case basis.
86
Pavement Management System Step By Step User Guide
1. Open the Homogenisation System Settings tab in the RBIA HDM-4 Interface. In CURRENT_PU,
Select the code of the Planning Unit to be analyzed (See Appendix A for the full list).
2. Check the following settings:
Expression Name Setting/Expression Description
PLANNING_UNIT {RCON_RI01} Sets congressional district as PU
GENERAL_EXCLUSIONS “Y” Exclude all segments outside selected PU
GRAVEL_EXCLUDE “Y” Gravel and Earth roads are excluded
URBAN_EXCLUDE “Y” Urban Metropolitan roads are excluded
3. The other fields should not be changed as part of the regular planning process.
87
Pavement Management System Step By Step User Guide
1. Open the Data Query Qualification and look for the Data Source: PMS_07 – Sections in
Current Planning Unit.
2. Double click on “Named Selection” and select the SPA Named Selection prepared in
Section B. Set the Effective date as per Section B Step 7.
3. Click “OK”. The list of all the PRS included in the selected PU is displayed. Click on the
88
Pavement Management System Step By Step User Guide
4. Define the Code and Name of the Named Selection following instructions from the Appendix G of
PMS Operations Guide, August 2014:
PUXXXX01
Where:
• XXXX: Congressional District Attribute Value Code (Planning Unit)
• 01 Sequential Number
89
Pavement Management System Step By Step User Guide
90
Pavement Management System Step By Step User Guide
91
Pavement Management System Step By Step User Guide
2. Check that the Traffic Growth Rate corresponding to the relevant Region has been applied and that all
the sections are selected.
3. Check that the Maintenance Alternative of the PRS have been properly populated.
92
Pavement Management System Step By Step User Guide
93
Pavement Management System Step By Step User Guide
3. The list of priority works under the Defined budget is given in “Optimised Programme” window.
94
Pavement Management System Step By Step User Guide
95
Pavement Management System Step By Step User Guide
96
Pavement Management System Step By Step User Guide
2. Click on the “Export” button and select “Excel 8.0 (XLS) (Extended) as format and “Disk file”
as Destination:
3. Save the file under the name PRS_PRG_YY_XXX_01.xls in the eponymous folder (i.e. with the
corresponding rundata.mdb file)
4. Open the PRS_PRG_YY_XXX_01.xls file and use the table to prepare the Programme for the
corresponding Planning Unit (Note that the “Surface Class” column refers to the model used in
HDM-4, and therefore is “Bituminous” for all roads. This column should be removed).
97
Pavement Management System Step By Step User Guide
98
Pavement Management System Step By Step User Guide
99
Pavement Management System Step By Step User Guide
100
Pavement Management System Step By Step User Guide
Introduction
1. Strategic Planning Analysis (SPA) clarifies the long term impact of different budget scenarios and
maintenance/rehabilitation policies on the performance of the National Road Network. The
performance that can be analyzed includes the average pavement conditions of the network, costs to
the road agency and the users, and to the society as a whole. Such information is essential in devising
long term and medium term investment and management strategies for road network assets.
2. SPA deals only with the Asset Preservation of the paved National Road Network and does not deal
with Network Development such as paving of gravel roads or construction of new road links.
3. The National Road Network is analyzed through a Network State Matrix (NSM), which is composed
of “cells” representing each category of roads based on their pavement type, traffic flow pattern and
volume, roughness and pavement condition.
4. The role of SPA can be summarized as follows:
• SPA clarifies the relationship between what we can buy with how much we spend
(investment for road asset preservation vs. network performance and user costs), and
facilitates the decision about how much to spend;
• For a given budget scenario, identifies the optimum maintenance strategy (solution catalogue)
for the network;
• Calculates approximate quantities, costs and benefits;
• Identifies the most efficient allocation of resources among planning units (such as Regions or
Districts), or road classes or work categories; and
• Provides guidance for medium-term planning and annual programming.
• SPA is the first step of the Pavement Management process in DPWH. The budget constraints
and maintenance standards defined at this stage will be applied to the program analysis.
5. This report presents the main findings and recommendations of the Strategic Planning Analysis for
the Financial Year 2016, along with the assumptions and hypotheses which were taken to run it.
B. Network Analysis
6. SPA is conducted on the national network, minus the following exclusion (See PMS Operations
Guide):
• Abandoned road sections
• Road sections without following essential data:
a. Traffic data
b. Pavement type data
c. Condition data (Roughness and Surface Condition)
d. Number of lanes
e. Directionality
• Road sections with a Surface Type of ‘Gravel’ or ‘Earth’
• Road sections with an Environment of “Urban (Metropolitan)”
• This was done by preparing a Named Selection in the RBIA with the Data Source:
PMS_01 - All Live Road Sections.
101
Pavement Management System Step By Step User Guide
7. December 15th, 2014 was considered as the cut-off date for RBIA data (and therefore December 16th,
2014 was considered as the “Effective Date” when preparing the Named Selection).
8. This Named Selection was used to run the Confirm (HDM-4 Interface). It was then cut into
homogenous sections (Planning Road Sections, PRS), which are assigned to a cell in the Network
State Matrix (NSM). PRS with the characteristics presented in paragraph 5 are excluded of the
analysis. Table 1 and Figure 6 present the characteristics of the resulting “SPA Network” after
running Confirm (HDM-4 Interface).
9. It can be noticed that 22% of the network of the Named Selection are further excluded of the analysis
(more than 7,000 km). The total length of the network covered by SPA is therefore 25,500
kilometers. Traffic data is missing for 3% of the network, i.e. excluding almost 1,000km. Finally,
concrete roads represent more than 66% of the studied network.
Table 1 -
SPA Network characteristics
Total Length of Named Selection (in km): 32,527
Total Length of Excluded PRS: 7,027
Gravel and Earth roads 4,770
Urban (Metropolitan Roads) 1,272
Traffic Data missing 985
Surface Condition and Roughness missing 0
Total Length of Non Excluded PRS (in km): 25,500
Total length Concrete PRS (in km) 16,719
Total Length Asphalt PRS (in km) 8,781
Figure 6 -
SPA Network characteristics
10. PRS are assigned to NSM cells according to (inter alia) their roughness and surface condition. Two
scores from “Good” to “Bad” are given to each PRS in accordance to their IRI (roughness score) and
a set of thresholds of pavement defects (surface condition score). See PMS Configuration Report -
Homogenization and HDM-4 System Settings for more details.
11. Figure 7 and Figure 8 present the distribution of the roughness and surface condition score for each
pavement type. The following can be observed:
102
Pavement Management System Step By Step User Guide
• 88% of the asphalt network is scored as “fair” or “good”, i.e. with an IRI smaller than 5
• Only 2% of the asphalt network is scored as “bad”, i.e. with an IRI greater than 7.
• 63% of the concrete network is scored as “poor” or “bad”, i.e. with an IRI greater than 5.
• Only 8% of the concrete network if considered as good
• Both the asphalt and concrete network and relatively proportionally distributed among
the four categories of surface condition, which is the objective when defining the scoring
thresholds.
Figure 7 -
Distribution of Roughness Score (in km)
Asphalt Concrete
893 217 1,426
3,638 2,998
5,016
4,199 8,097
Figure 8 -
Distribution of Surface Condition Score (in km)
Asphalt Concrete
2,103 5,978
12. Although the thresholds to determine the surface condition scores were specified so as to distribute
the network among the four categories (and hence differs from the VCI), they provide a relevant tool
to estimate the condition of the pavement. Figure 9 below compares the distribution of roughness
scores against surface condition scores. It can be observed that:
• A significant length of the concrete network (almost 700km) is scored as “good” for its
surface condition, and “bad” for its roughness. This was observed in 2013 and was
explained by inadequate construction methods. This issue was therefore not entirely
addressed in 2014.
103
Pavement Management System Step By Step User Guide
• A significant length of the asphalt network (more than 550 km) is scored as “good” for its
roughness and “bad” for its surface condition. This incoherency is harder to justify, as a
road in poor condition can reasonably be expected to present a high IRI. These roads
require further investigation, and a revision of the thresholds to assign surface condition
scores may be necessary.
Figure 9 -
Distribution of Roughness vs. Surface Condition scores (in km)
Concrete
3,000,000
2,500,000
2,000,000
B
1,500,000
P
1,000,000
F
500,000
G
0
G F P B
Asphalt
2,000,000
1,500,000
B
1,000,000
P
500,000 F
G
0
G F P B
Vertical: Total Length | Horizontal: Surface Condition Score | Depth: Roughness Score
104
Pavement Management System Step By Step User Guide
Table 2 -
Confirm (HDM-4 Interface) Settings
Setting Description
Effective Date 12/16/2014
Named Selection STR15_01
Minimum PRS length (m) 500
Maximum PRS length (m) 1,500
Exclude Gravel (and Earth) Yes
Exclude Urban (Metropolitan) Yes
Maximum NSM length (m) 600,000
Start Year 2016
Number of Budget Periods 1
Budget Period Length (Yrs) 20
Delay Maintenance By (Yrs) 0
HDM-4
14. The following inputs were updated in HDM-4 to run the SPA for FY 2016:
• Vehicle Operating Costs (VOC), Road User Costs (RUC): See Annex 1
• Traffic Growth Rates: See Annex 2
• Capital and Recurrent Construction Costs: See Annex 3
15. The Strategy Analysis in HDM-4 was run with the following parameters:
Table 3 -
HDM-4 Parameters
Setting Description
Start Year 2016
Analysis period 20 years
Optimisation method Maximise NPV
Currency Philippine Peso
Discount rate 15%
105
Pavement Management System Step By Step User Guide
106
Pavement Management System Step By Step User Guide
Figure 10 -
Average Network Roughness Weighted by km
8.0
7.5
7.0
6.5
6.0
IRI
5.5
5.0
4.5
4.0
3.5
3.0
Figure 11 -
Total Financial Road Agency Capital Costs (M PhP)
120,000.0
100,000.0
80,000.0
60,000.0
40,000.0
20,000.0
0.0
107
Pavement Management System Step By Step User Guide
Figure 12 -
Net Present Value of Economic Society Benefits, NPV (M PhP) and Internal Rate of
Return (%)
390,000.0 70.0%
380,000.0
60.0%
370,000.0
50.0%
360,000.0
350,000.0 40.0%
340,000.0 30.0%
330,000.0
20.0%
320,000.0
310,000.0 10.0%
300,000.0 0.0%
Unconstrained Practical 90% Optimum 75% Optimum 50% Optimum
Optimum Optimum
18. Figure 13 below shows the annual financial capital costs for each budget scenario for the planning
period (6 first years), the rest of the study period and the total study period. The annual investment
after the planning period increases in proportion to the constraint applied on the budget during the
first 6 years. For instance, the annual investment between 2022 and 2035 is 25% more important for
the “75% optimum” budget scenario than for the “Practical optimum” budget scenario. As a result,
the average annual expenditure over the entire study period (i.e. the total investment over the 20 year
study period) is almost similar for the “Practical”, “90%” and “75% optimum” budget scenarios.
Figure 13 -
Annual Financial Road Agency Capital Costs (MPhP/year)
40,000.0
35,000.0
30,000.0
25,000.0
20,000.0
15,000.0
10,000.0
5,000.0
0.0
Unconstrained Practical 90% Optimum 75% Optimum 50% Optimum
Optimum Optimum
108
Pavement Management System Step By Step User Guide
19. The recommendation would therefore be to define the annual budget for 2016 and onward within the
range of 75% to 90% of the optimal budget as per HDM-4 analysis, i.e. between 25,600 and 30,600
million Pesos. This would allow a significant improvement of the national network over the next 6
years, while guaranteeing reasonable economic and financial performances.
109
Pavement Management System Step By Step User Guide
Figure 14 -
Average roughness after works (IRI) per Region – Unconstrained Optimum
110
Pavement Management System Step By Step User Guide
Figure 15 -
Average roughness after works (IRI) per Region – Practical Optimum
111
Pavement Management System Step By Step User Guide
Figure 16 -
Average roughness after works (IRI) per Region – 90% Optimum
112
Pavement Management System Step By Step User Guide
Figure 17 -
Average roughness after works (IRI) per Region – 75% Optimum
113
Pavement Management System Step By Step User Guide
Figure 18 -
Average roughness after works (IRI) per Region – 50% Optimum
114
Pavement Management System Step By Step User Guide
Figure 19 -
Distribution of Financial Capital Cost (MPhP) per Region over the first six years of the study (2016 - 2021)
115
Pavement Management System Step By Step User Guide
Figure 20 -
Average roughness after works (IRI) per Road Class – Unconstrained Optimum
Figure 21 -
Average roughness after works (IRI) per Road Class – 100% Optimum
116
Pavement Management System Step By Step User Guide
Figure 22 -
Average roughness after works (IRI) per Road Class – 90% Optimum
Figure 23 -
Average roughness after works (IRI) per Road Class – 75% Optimum
117
Pavement Management System Step By Step User Guide
Figure 24 -
Average roughness after works (IRI) per Road Class – 50% Optimum
Figure 25 -
Distribution of Financial Capital Cost (MPhP) per road class over the first six years of the study (2016 - 2021)
118
Pavement Management System Step By Step User Guide
Annex 1 - Vehicle Operating Costs (VOC) and Road User Costs (RUC)
Insert table
119
Pavement Management System Step By Step User Guide
Insert table
120
Pavement Management System Step By Step User Guide
Insert table
121