Sunteți pe pagina 1din 5

ROCKY CONSTRUCTION COMPANY

Project: MALIK MIJ CHUNXING RESOURCES RECYCLING CO. (PVT) LIMITED,


PLOT # 50/1A, 3M INDUSTRIAL ESTATE, FAISALABAD

1ST RUNNING BILL

Sr. Bill
No. Item # Description Unit Qty
Rate Amount
1 16.2.6 Installation in exact position working piles up to
menthioned in sub item below, inclusive of concrete using
Margalla/Sargodha crush 3/4" down, lawrancepur sand in
1:1.5:3 nominal mix, cement minmum 400 kg/m3,
concrete of cylinder strength min 3750 psi, w/c ratio upto
0.45, and using plasticizer Admixture; driling by rotary
using Bentonite.

a) 600 mm nominal dia 13.5 meter length RM 8869.5 4920 43637940


b) 450 mm nominal dia 13.5 meter length RM 783 3700 2897100
16.2.7 Providing, supply and fix steel reinforcing hot rolled
deformed steel bar grade 60 conforming to ASTM A615 in
pile, steel including vertical bars, spirals, holding rings and
stiffeners etc longitudinal bars in required cut lengths and
staggered laps.

a) 600 mm nominal dia Ton 346.896 120300 41731589


b) 450 mm nominal dia Ton 22.62 120300 2721186

TOTAL: 90987815
Dedcution against cement & steel 38751423
Balance: 52236392
Rebat 11% 5746003
NET PAYABLE AGAINST 1ST RUNNING BILL 46490389
ROCKY CONSTRUCTION COMPANY

Project: MALIK MIJ CHUNXING RESOURCES RECYCLING CO. (PVT) LIMITED,


PLOT # 50/1A, 3M INDUSTRIAL ESTATE, FAISALABAD

1ST RUNNING BILL

Bill
Item # Description Unit Qty
Rate Amount
16.2.6 Installation in exact position working piles up to
menthioned in sub item below, inclusive of concrete using
Margalla/Sargodha crush 3/4" down, lawrancepur sand in
1:1.5:3 nominal mix, cement minmum 400 kg/m3,
concrete of cylinder strength min 3750 psi, w/c ratio upto
0.45, and using plasticizer Admixture; driling by rotary
using Bentonite.

a) 600 mm nominal dia 13.5 meter length RM 8869.5 4920 43637940


b) 450 mm nominal dia 13.5 meter length RM 783 3700 2897100
16.2.7 Providing, supply and fix steel reinforcing hot rolled
deformed steel bar grade 60 conforming to ASTM A615 in
pile, steel including vertical bars, spirals, holding rings and
stiffeners etc longitudinal bars in required cut lengths and
staggered laps.

a) 600 mm nominal dia Ton 346.896 120300 41731589


b) 450 mm nominal dia Ton 22.62 120300 2721186
1.4.1 Structural excavation in soil above sub soil water level for M3 4832 339 1638048
levelling and grading of walls and columns foundation as
shown in drawings and specifications and as per approval
of the engineer.

1.4.2 Structural backfill in foundation and under floor with M3 2623 370 970510
approved suitable excavated soil from BOQ item 1.4.1
including breaking clods, dressing watering, compacting
mechanically in layers not exceeding 225mm thick depth
to 95% modification proctor dry density (MPD) from any
lead and any lift compacted as per specification and as
per approval of the engineer.

2.2.1 Provide and fix steel reinforcement grade 60 deformed


steel bars conforming to ASTM A615, including cleaning,
cutting, bending, placing, binding etc., including provision
and cost of spacers and binder wire, cost of chairs, over
lapsnot shown on drawings etc., in any kind of RCC work
as specified.
a) Reinforcing steel bars of grade 60 (min. 60,000 psi yield Ton 224.98 116000 26097680
strength)
2.4.1 Provide and lay structural cement concrete of 3000 psi
cylinder crushing strength at 28-days using OPC, Chenab
sand and Sargodha crush stone including formwork and
its removal, placing, compacting, finishing and curing
complete in all respects (including screening and washing
of stone aggregate) but excluding the cost of
reinforcement as per specifications.

a) RCC footing / Pile capping using lawrancepur sand and M3 2209.3 12000 26511600
Chenab sand (50:50)

TOTAL: 146205653
Dedcution against cement & steel 62682861
Balance: 83522792
Rebat 11% 9187507
NET PAYABLE AGAINST 1ST RUNNING BILL 74335285

NOTE:
(a) Item # 2.4.1, as per BOQ rates Rs.11420/M 3 with Chenab sand only but consultant
recommended on the drawing Note "Chenab sand with lawerancepur sand (50:50)".
So the rates are revised to Rs.12000/M3.
COMPANY NAME

Project:

CONVEYOR BELT FOUNDATION BOQ

Item # Description Unit Qty

CONVEYOR BELT
SECTION 2-1

16.2 Board Cost in Place R.C.C. Pile

Working Piles
16.2.6 Installation in exact position working piles up to
menthioned in sub item below, inclusive of concrete
using Margalla/Sargodha crush 3/4" down,
lawrancepur sand in 1:1.5:3 nominal mix, cement
minmum 400 kg/m3, concrete of cylinder strength
min 3750 psi, w/c ratio upto 0.45, and using
plasticizer Admixture; driling by rotary using
Bentonite.

a) 600 mm nominal dia 13.5 meter length


16.2.7 Providing, supply and fix steel reinforcing hot rolled
deformed steel bar grade 60 conforming to ASTM
A615 in pile, steel including vertical bars, spirals,
holding rings and stiffeners etc longitudinal bars in
required cut lengths and staggered laps.

a) 600 mm nominal dia

SECTION-1 PRELIMINARIES & EARTHWORKS

1.4 Earth Works


1.4.1 Structural excavation in soil above sub soil water level
for levelling and grading of walls and columns
foundation as shown in drawings and specifications
and as per approval of the engineer.

1.4.2 Structural backfill in foundation and under floor with


approved suitable excavated soil from BOQ item 1.4.1
including breaking clods, dressing watering,
compacting mechanically in layers not exceeding
225mm thick depth to 95% modification proctor dry
density (MPD) from any lead and any lift compacted
as per specification and as per approval of the
engineer.
Item # Description Unit Qty

SECTION-2 CONCRETE WORKS

2.2 Reinforcement for Concrete


2.2.1 Provide and fix steel reinforcement grade 60
deformed steel bars conforming to ASTM A615,
including cleaning, cutting, bending, placing, binding
etc., including provision and cost of spacers and
binder wire, cost of chairs, over lapsnot shown on
drawings etc., in any kind of RCC work as specified.

a) Reinforcing steel bars of grade 60 (min. 60,000 psi


yield strength)

2.4 Structural Concrete


2.4.1 Provide and lay structural cement concrete of 3000
psi cylinder crushing strength at 28-days using OPC,
Chenab sand and Sargodha crush stone including
formwork and its removal, placing, compacting,
finishing and curing complete in all respects
(including screening and washing of stone aggregate)
but excluding the cost of reinforcement as per
specifications.

a) RCC footing / Pile capping using lawrancepur sand


and Chenab sand (50:50)

S-ar putea să vă placă și