WORK SECEDULE

CONTRACTOR: M/S MGH ENGG & CONTROL PVT LTD


Name of Work:

Starting Date:
Completion Date:
Jun Jul Aug Sep Oct Nov Dec Jan
S.NO DISCRIPTION OF WORK
2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1
1 Site Cleaning Layout & Excavation
2 Foundation Preparation
3 Footing
4 Brick work in Sub Structure & Backfill
5 Brick work for Super Structure
6 Shuttering, Steel work
7 Concrete Works for Wall
8 Earth Filling
9 Mud Plaster
10 Plumber work Internal & External
11 Flooring
12 MEP Works
13 Plaster Works
14 MEP Fittings
15 Roof Treatment & External Services.
16 Painting work
17 Finishing work
D

Jan Feb March April May Jun


2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Start date Finish date
20-Jun-17 5-Aug-17
6-Aug-17 12-Aug-17
13-Aug-17 30-Aug-17
25-Aug-17 5-Sep-17
6-Sep-17 12-Sep-17
13-Sep-17 20-Sep-17
1-Oct-17 30-Dec-17
1-Jan-18 20-Jan-18
21-Jan-18 10-Feb-18
15-Sep-17 22-Sep-17
28-Aug-17 26-Sep-17
26-Sep-17 10-Oct-17
5-Oct-17 26-Oct-17
27-Oct-17 12-Nov-17
13-Nov-17 13-Dec-17
28-Nov-17 15-Dec-17
15-Dec-17 15-Feb-18