Operation Management:
Operations management (OM) is defined as the design, operation, and improvement of the
systems that create and deliver the firm’s primary products and services.
Supply Chain Management:
Supply-chain management is a total system approach to managing the entire flow of
information1, materials, and services from raw-material suppliers through factories and warehouses
to the end customer.
Material Resource Planning
A computer-driven production methodology that manufactures products based on an initial
demand forecast. It tends to result in more inventory of all types than a just-in-time (JIT)
production system.
Master Production Schedule (MPS)
Time-phased plan specifying how many and when the firm plans to build each end item.
…………………………………………………………………………………………………………………
Q # 01 (b)
Core Services
Core services are basic things that customers want from products they purchase
Speed
Quality
Flexibility
Price
……………………………………………………………………………………………………………...
Q # 01 (c)
Value-added Services
Value-added services differentiate the organization from competitors and build relationships
that bind customers to the firm in a positive way.
Value-Added Service Categories
Information
Problem Solving
Sales support
Field support
…………………………………………………………………………………………………………….
Q# 2 (a)
Types of Supply Chains
Efficient
aiming at cost efficiencies involving optimization
Risk-Hedging
pooling &sharing resources increasing safety stocks
Responsive
being responsive & flexible mass customization
Agile
being responsive & flexible and pooling inventories
…………………………………………………………………………………………………………………..
Q # 02 (b)
Reasons to outsource
Organizationally-driven
Improvement-driven
Financially-driven
Revenue-driven
Cost-driven
Employee-driven
………………………………………………………………………………………………………………….
Q # 02 (c)
Mass Customization Principles
Principle 1
Modular design, i.e. independent modules that can be assembled into different forms easily
and inexpensively.
Principle 2
Manufacturing & Service presses should be independent modules easy to move rearrange
Principle 3
Process postponement, designing basic product that can easily be customized.
………………………………………………………………………………………………………………
Q # 04 (a)
Pure Project
A pure project is where a self-contained team works full-time on the project
Pure Project: Advantages
The project manager has full authority over the project
Team members report to one boss
Shortened communication lines
Team pride, motivation, and commitment are high
Pure Project: Disadvantages
Duplication of resources
Organizational goals and policies are ignored
Lack of technology transfer
Functional Project
A functional project is housed within a functional division
198+204+198+200
Average Normal Time =
4
800
=
4
= 200 sec
Allowance = 5 %
= 0.05
𝐴𝑣𝑔 𝑁𝑇
Standard Time =
1−𝐴𝑙𝑙𝑜𝑤𝑎𝑛𝑐𝑒
200
=
1−0.05
200
=
0.95
= 210.52 sec