Sunteți pe pagina 1din 6

COIL TUBING DEPLOYED ESP INSTALLATION

TEMBUNGO OFFSHORE PROJECT IN PETRONAS CARIGALI, MALAYSIA

By: Brad Seals, Abdulsalam Alaini, Adel Al Haygana, Anton Shakirov

Abstract: - Increased fluid production and net oil


gain
This paper presents a case study of Alternative - Pressure equalization at the well head
Deployed ESP System Installation performed by - Well optimization and increased oil
PETRONAS & Alkhorayef Petroleum Company reserve recovery
for an Offshore Project in Tembungo within
- No major Capex compared to other
PETRONAS’s Fields in Malaysia, during 2009. types of AL systems
WSP WEST-COIL Deployed Systems represent
innovative technologies and require high However, there was one disadvantage to be
expertise levels and multidisciplinary team considered:
work. In this particular case the downhole
assembly was RIH on coil tubing and fluids were - Some of the platforms do not have
produced through the coiled tubing while sufficient space or electric power
power cable was clamped to the outside of the currently available
coiled tubing (WEST-COIL External Cable Area Maps are shown in the following
System). This configuration makes ESP Figure 1. In Figure 2 the Tembungo Project
installation rigless, faster and requires less platform is presented.
personnel than ESP systems installed on
conventional tubing joints. The utilization of
WEST-COIL results in significant savings,
especially for Offshore Operations. The
successful installation and commissioning of the
Tembungo Project was a result of outstanding
team work managed by PETRONAS. Figure 1 – PETRONAS Carigali Location Map
Introduction:

The WEST-COIL installation @ Tembungo was


undertaken to convert a Gas Lift System to an
ESP System deployed on Coiled Tubing. The
advantages of this solution were found to be as
follows:

- More efficient type of AL systems in


such applications
- Lower operating cost, compared with
Gas Lift
Figure 2 – Tembungo Project Platform
Tembungo Well A9

The Well A9 is a very gassy well. Its production


is comingled from several zones with different
characteristics. Due to this there is no way to
measure production from the separate zones at
the time of production. Due to low inflow, the
first installation was pulled out and a downsized
unit was installed and is successfully producing.

ESP Design:
Figure 4 – Amount of Free Gas at Intake
ESP design was performed using the latest IHS
SubPUMP software. Detailed sensitivity
analyses were performed to overcome the
uncertainties and possible changes in future
well performance.

Fluid Data:

Figure 5 – Pump performance at TDH

The selected equipment was as follows:

UT PUMP 538 SERIES WE 1500


LT PUMP 538 SERIES WE 1500
GPU PRO-MAX 538 SERIES
The following figures present Tembungo Well GAS SEPARATOR 2B ROTARY TYPE
A9 ESP Design considerations. 540 SERIES PROSEAL BB HIGH LOAD
UT 560 SERIES MOTOR 183HP/2414V/46A

Due to the expected high volume of free gas at


the pump intake it was decided to use a Rotary
Gas Separator together with a highly
engineered Gas Processing Unit (GPU). The
Rotary Gas Separator is a device which is
commonly used to separate heavy phase (fluid)
from light phase (gas) whereas the GPU is a high
speed, multistage centrifugal gas processor that
effectively reduces the size of the gas vapor
Figure 3 – Inflow Performance Relationship
bubbles and keeps them in solution, facilitating
their production through the electric
submersible pump without gas locking.

The selected downhole Motor was an XT1 type


to withstand high ambient temperatures up to
325 deg F (163 deg C) and to avoid motor
overheating under low cooling fluid velocity.
The Motor performance curve is presented on
the following Figure 6.
560 XT1 60 HZ Motor
Performance Curves

3600

3500
RPM

3400 90
Eff

3300

80

PF
110

100 70
EFFICIENCY AND POWER FACTOR PERCENT
NAME PLATE AMPS PERCENT

80 Amperage 60

60 50

Figure 7 –Well Completion Diagram

40 40
System Features:
0.2 0.4 0.6 0.8 1 1.2
LOAD FACTOR

 The Coil Tubing 2 7/8 inch, 5400 ft


Figure 6 – 560 Series XT1 Motor Performance length
- To produce fluids and to deploy
Well Completion: downhole assembly

The Final Well Completion proposal was


 Special CT Clamps
developed according to expected flow
- To support and protect ESP power cable
assurance needs as presented on the following
Figure 7.
Figure 10 – Cable Spooler

 CT Wellhead Equipment (Injector Head,


Figure 8 – CT Cable Clamp Goose Neck, Jacking Frame, Coiled
Tubing Reel, Control Cab, Skid Beam
 Auto Flow Valve
System)
- To by-pass the ESP when the well is
- To operate and control the Coil Tubing
naturally flowing and drain the fluid
Installation and Pull-out
when the unit is shut down

Figure 9 – Auto Flow Valve

 DH Sensor Sub Discharge


- To monitor pump Discharge Pressure
Figure 11 –CT Wellhead Equipment
along with the readings from the
standard downhole sensor (Intake  ESP Surface Equipment
Pressure, Intake and Motor - Skid Mounted
Temperature, Vibrations) - Power Generators
- Variable Speed Drive
 Cable Spooler - Transformer
- Electrically powered and hydraulically - Sensor Surface Readout
operated
- SCADA system running stable even at low intake pressures
while daily measurements are showing the gas
factor always at around 1500 scf/bbl (estimated
percent of free gas at intake is over 80%). Most
shutdowns seen on the below diagram are
related to planned servicing of the generators.

A-9 CT Deployed - Pressures Data (March, 2010)


2500

Intake and Discharge Pressure (psi)


2000

1500 Pi
Pd

1000

500

Figure 12 – ESP Surface Equipment Figure 13 – Pressures data


Process Innovations Gas Lift converted to ESP CT
- Jacking frame Summary table of well produced by Gas Lift
- Skidding System which were converted to ESPCT are shown
- Coiled Tubing Stabbing System below. Oil gain at the Well A-9 has been found
- Estimation of Lifting Injector Head around 250 bblpd.
during workover
- GS for Landing and Pulling Hanger
- Split Hanger System saves time

Results

The currently installed string has been running


for over 5 months as of Apr-2010.

The following Figure 13 presents real time


pressure monitoring data taken from the
downhole sensor. As can be seen, the unit is Figure 14 – Oil Gain with CTESP
Conclusions:

 CT Installation requires less space than


conventional joint tubing deployed
installation as there is no workover Rig
required
 CT Wellhead Equipment is more readily
available than Offshore Rigs and as a
result there is less downtime involved
 Savings of up to 30% have been realized
due to reduced workover time
 Significant Oil Gain has been realized
due to Gas Lift conversion to ESP

S-ar putea să vă placă și