Aero Energy LM2500SAC Report

Preliminary Report

19 October, 2012
For

Burak Marine
Aliağa İzmir TURKEY
ESN 560-036
Customer Representative: Burak ALDEMİR
GE Field Service Representative: Adnan LEBLEBİCİ
Mehmet AKIN (Granite)

All technical recommendations and information contained in this report are based on GE manuals that have
been developed and approved for use with GE engines and parts that have been operated and maintained
in accordance with GE technical documentation and recommendations.

GE has no technical knowledge of, nor obligation for, non GE-approved parts and repairs. Accordingly, this
report is not intended to apply to non GE-approved parts and repairs, nor to any parts that may be directly
or indirectly affected by non GE-approved parts and repairs.

Report completed by – Adnan Leblebici


Aero Energy LM2500SAC Report

CONCLUSIONS & RECOMMENDATIONS


The purpose of this visit was to perform a visual and borescope Inspection.
The engine visually was found in satisfactory conditions.
The compressor, combustor and power turbine stage 1 & 6 blades & nozzles were inspected.
This periodic borescope inspection was completed in reference to GEK 97310 Vol I, Chapter 5-3.

Outage Data:

Engine Data:

ESN 560-036 Engine Fired Hours Package Total Hours


Model LM2500PI Engine Fired Starts Package Fired Starts
Trips Total Trips

Report completed by – Adnan Leblebici


Aero Energy LM2500SAC Report

DETAILS AND DATA


Purpose of visit:
This inspection was completed in reference to GEK 97310 Vol I, Chapter 5-3.5.

Daily Activities
Friday, 19 Oct 2012
Units are original packages that were removed and moved to warehouse. Engine was kept at
warehouse almost 1 year without preservation.
HP compressor, combustor and HP turbine borescope ports were removed. Only 1 fuel nozzle were
removed and inspected. Found it in good shape. Feeder tubes are fine. Clearance is correct. HP compressor
was found fairly dirty but no anomaly detected.
T2/PT2 Probe: was secure and no damage, corrosion or obstructions were observed
The inner and outer panels are fully intact with no distortion or other defects noted. No distortion
was visible in the dome plate and the dome plate inner and outer overhangs were fully intact with no cracks
or missing material. Thermal barrier coat was missing from numerous trumpet splash plates in varying
degrees and some slight erosion was noted on the edges of the trumpet splash plates in the area were the
thermal barrier coat is missing.
Found a crack at 6 o’clock position on inner liner, out of limits. See picture. Some erosion and
discoloration was found.
1st stage HPT blades: nothing abnormal was observed on flow path concave side and leading
edges. Some loss of coating was detected.
2nd stage HPT blades: nothing abnormal was observed on flow path concave side and leading
edges.
1st stage HPT nozzles: Cooling holes on HP S1 nozzles are mostly clogged. See picture…
PT was visually inspected. First stage blades as thoroughly as possible without rotating the power
turbine (inspection was made using a flexible borescope through the Pt5.4 ports). No cracking, nicks, dents,
corrosion or erosion was observed.
Both igniters have been removed and inspected. No anomaly found.
Engine external status: engine shows an external dirtiness in general.

Report completed by – Adnan Leblebici 3


Aero Energy LM2500SAC Report

Results:

Engine legs

Report completed by – Adnan Leblebici 4


Aero Energy LM2500SAC Report

Report completed by – Adnan Leblebici 5


Aero Energy LM2500SAC Report

VSV actuator RHS Package roof

VSV torque lever

HP recoup

Report completed by – Adnan Leblebici 6


Aero Energy LM2500SAC Report

T48 probe Fuel pump

Report completed by – Adnan Leblebici 7


Aero Energy LM2500SAC Report

Borescope Pictures
High Pressure Compressor

Midspan Stage 0

Stage 1 Stage 2

Stage 3 Stage 4

Report completed by – Adnan Leblebici 8


Aero Energy LM2500SAC Report

Stage 5, salt residue Stage 6,

Stage 6 Stage 8

Stage 9 Stage 11, nick

Report completed by – Adnan Leblebici 9


Aero Energy LM2500SAC Report

Stage 12 Stage 13

Stage 15 Stage 16

Report completed by – Adnan Leblebici 10


Aero Energy LM2500SAC Report

Combustor

Swirler Coating delamination, swirler (#4 fuel nozzle)

Inner liners A crack found at 6 o’clock position on inner liner

Discoloration carbon build up at swirlers

Report completed by – Adnan Leblebici 11


Aero Energy LM2500SAC Report

HPT

S1 nozzles, cooling holes are clogged S1N

Some dirt/ salt on blades Dirt on shrouds

S1 blades TE

Report completed by – Adnan Leblebici 12


Aero Energy LM2500SAC Report

S2 blades S2 blades, salt residue

Power Turbine

PT Stage 1 PT Stage 1, salt residue

PT Stage 1 PT Stage 1

Report completed by – Adnan Leblebici 13


Aero Energy LM2500SAC Report

GENERAL INSPECTION RECORD GAS TURBINE


IGV and VSV lever arms were found free of side-to-side movement on all stages.

Report completed by – Adnan Leblebici 14


Aero Energy LM2500SAC Report

L&S Pump

Report completed by – Adnan Leblebici 15