Documente Academic
Documente Profesional
Documente Cultură
Situation: You are appointed as a Project Manager for a software development company. The project
charter has already been developed by the project Sponsor and the authority has been given to you.
You have to develop the project management plan. The predefined project scope is to develop a mobile
app. You are in the process of creating the WBS and the lifecycle that involves phases such as
Requirements, Design, Development, Testing, and Deployment. The work packages are:
The activities under each of these work packages are given in this table.
User
Requirements High Level Low Level Modul Modul Test Plan Test Man Inst
Documentation Document Document e1 e2 Document Execution ual aller
Collect Develo Develo Draf Inst
requirements Draft Draft p p Draft Lab setup t all
Unit Unit
Testin Testin Test case Revi
Draft Review Review g g Review execution ew UAT
Hando Hando Base
Review Baseline Baseline ver ver Baseline Results line
Publ
Baseline Publish Publish Publish Reporting ish
Publish
A. Create the Work Breakdown Structure for the above situation.—15 Minutes
The activities in each of these phases will be carried out in a sequence. Requirement is the starting
phase. Once this phase is completed, the design and documentation phase should start. Next is the
development phase. After this phase, first the activities in the HLD phase and then the LLD phase should
be worked on. Module 1 and Module2 under the development phase will happen in parallel. Testing
phase follows the Development phase. Test Execution has to start after the Test Plan document phase.
The Deployment phase begins after the completion of the Testing phase and Documentation phase.