Contract WW 306W – Sewerage Project at Kensington Place – Petit Verger, Pointe aux Sables

Project Brief

1.0 Project Justification

Kensington Place is a housing complex comprising about 110 houses situated in the vicinity of
the Montagne Jacquot Wastewater Treatment Plant. The houses are presently connected to a
poorly performing sewerage system, having as outlet communal septic tanks and leaching fields,
which are saturated. Moreover, the existing sewerage network also shows signs of saturation,
leading to frequent overflow and blockages and associated odour & environmental problems.

Further to complaints received from the inhabitants as well as from the Ministry of Health and
Quality of Life - Bambous Health Office, the WMA carried out an investigation which revealed
that the present wastewater disposal system is no more functioning efficiently.

The prevailing site conditions represent serious health and environmental/health hazards to the
inhabitants.

2.0 Project Particulars

The solution to the recurrent sewerage associated problems would be to construct a new system
of gravity sewers and rising main to discharge into Montagne Jacquot Wastewater Treatment
Plant.

 Region to be sewered: Kensington Place


 Project Objectives: Protection of the environment and improve prevailing on site
conditions
 Number of house connections:110
 Length of gravity sewer: 1400 m
 Length of rising main: 385 m
 Treatment Plant: Montagne Jacquot Treatment Plant
 Scope of the Works Contract:
o Topographical survey to determine best sewer alignment;
o Design and construction of sewer reticulation and house connections at
Kensington Place - Petit Verger, Pointe aux Sables, including construction of
manholes and sewers;
o Design and construction of a lifting station and rising main;
o Trench/road reinstatement;
o Desludging of existing septic tanks/leaching field during the Works;
o Other temporary & ancillary works required during the construction period.
 Status: Invitation for bids was launched on 18 November 2016 and four bids were
received on the closing date of 22 December 2016. Following appraisal of bids and board
approval, the Letter of Acceptance has been issued on 16 February 2017 to Onix Co.Ltd.

1
Kick off meeting was held on 22 February 2017 and contractual procedures are presently
in hand for signature of Contract and issue of notice to commence by 16 March 2017.
 Contract Amount: 73,919,522.90, including VAT
 Expected Start Date: 16 March 2017
 Expected Completion Date:14 August 2018
 End of Defects Liability Period: 13 August 2019

A layout plan of the project area is attached at Annex 1.