Documente Academic
Documente Profesional
Documente Cultură
net/publication/316330422
CITATIONS READS
0 689
2 authors:
All content following this page was uploaded by Riaz Khan on 03 October 2017.
Structural integrity management (SIM) is often defined as After an inspection campaign or post-event inspection, there
the application of qualified standards, by competent people, is a variety of data that is made available to the structural
using appropriate processes and procedures throughout the integrity engineer (SIE). In coming up with a strong strategy,
structures life cycle, to ensure that the structures fitness for one must first evaluate this data for the FFP of the structure
purpose (FFP) is maintained. Structural integrity manage- and develop the remedial actions. SMR is one such reme-
ment systems (SIMS) are often developed within operators dial action; however SMR schemes especially for underwater
as a means of managing their structural risk levels for both activities can be costly and at times hazardous if not prop-
their offshore and onshore facilities. Figure 1 provides a erly managed and executed. To formulate an SMR scheme,
typical risk matrix that is used by operators. These risk it is generally part of the STRATEGY process within SIM
levels are represented in the operator’s risk categorizations (Figures 2 and 3), and its execution is part of the PROGRAM.
based on corporate expectations and generally presented In recent years the growth of computing power and accu-
in a risk matrix. SIMS often goes hand in hand with the racy in developing structural models together with a global
operators understanding of as low as reasonably practicable acceptance of the benefits of performing ultimate strength
(ALARP) principles, which also outlines FFP criteria for analysis for the substructures (Westlake et al., 2006) have
operating regions. In practice, SIMS ensures that risk levels enhanced the decision-making process to determine whether
it is feasible to perform underwater SMR for particular
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
defects. For substructures the ultimate strength analysis or
This article is © 2017 John Wiley & Sons, Ltd. pushover analysis is performed as part of assessment engi-
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition)
neering prior to developing the strategy. The basic assump-
ISBN: 978-1-118-47635-2 tion is that the fixed jacket space frame acts as a system
2 Offshore
High L-1
Consequence
val
in ter
sed
L-2 rea
Inc
L-3
A B C D E
Likelihood High
Figure 1. Typical risk matrix. (Reproduced with permission from O’Connor et al. (2005). © Society of Petroleum Engineers, 2005.)
Detailed work
Evaluation of
Managed system Overall inspection scopes for
structural integrity
for archive and philosophy and inspection
and fitness for
retrieval of SIM strategy and activities and
purpose;
data and other criteria for in- offshore execution
development of
pertinent records service inspection to obtain quality
remedial actions
data
Figure 2. The SIM (structural integrity management) process. (Reproduced with permission from API RP2 SIM (2014). © American
Petroleum Institute, 2014.)
of trusses with some members being redundant, depending Dier (2004) published the results of a joint industry
on the structural configuration and bracing. In the simplest project (JIP) on the Assessment of Repair Techniques for
of the terms, ultimate strength results (nonlinear analysis) Ageing or Damage Structures. This study provides details
are generally presented in the form of a reserve strength on prescribed SMR techniques, advantages of these options,
ratio (RSR) that is the ratio of lateral load at collapse to the and the limitations in using each. This JIP forms the basis
prescribed reference load. This is compared to the acceptance for much of the SMR section of the API RP2 SIM work, and
criteria for the given operating area. If the RSR is greater much of the JIP is referenced in this article due to the compre-
than the acceptance criteria, the jacket structure is generally hensiveness of the study. In this article reference is also made
considered FFP. to a host of well-known industry case studies on SMR to
For topside structures, structural elements are generally reinforce the concepts and application of particular schemes.
assessed on a component level (e.g., members, columns,
joints, etc.). Assessments are generally in the form of linear
static analysis with adherence to acceptance criteria-outlined 2 REMEDIATION AND REPAIR
design codes and standards. Topside defects should be TECHNIQUES
assessed on their importance levels, that is, whether they
form part of a (structural) safety critical element (SCE), 2.1 Remediation and SMR
in such case remediation may require a more elaborate
SMR scheme development. Typical SCEs include, but are Having completed the evaluation of SIM data, the jacket
not limited to, jacket structures, boat landings, helidecks, or the topsides, the full extent of remediation will be only
primary steel, and fire and blast walls. determined after the assessment phase of the SIM process.
Figure 4 provides a simplistic overview of the assessment Initially the main action when considering the SMR options
process as it relates to determining the necessity of an SMR is to determine whether a local SMR option is viable or if
scheme. If none of the identified outcomes are economi- there is need for a more detailed global SMR action required.
cally feasible in meeting the FFP goal, then ALARP may be Local SMR options generally tend to be less costly and
invoked to seek regulatory relief, as an alternative to decom- less complex to install. Global SMR actions are generally
missioning and abandonment. more costly and complex and may require more than SMR
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Remediation and Repair of Offshore Structures 3
Initiator No
Data Evaluation Strategy Program
triggered
Yes
Assessment
Figure 3. The assessment process within SIM. (Reproduced with permission from API RP2 SIM (2014). © American Petroleum Institute,
2014.)
Not
ok
Possible outcome:
Specific inspection
Review findings,
Yes No Load reduction
is it worth refining
analysis/checks? Strengthen/repair
Change operating
procedures
Figure 4. SMR (strengthening, modification, and repair) and the assessment process. (Reproduced with from Dier (2004). Mineral
Management Service/US Government.)
schemes for remediation. Dier (2004) proposed five basic repair work, it might draw from both the intact structure
approaches to SMR work, short of total replacement of the SMR and the damaged structure portion of the diagram. The
facility. These include the following: techniques outlined in Figure 5 will be discussed in more
detail in this section.
1. Remove damage (e.g., grinding out of cracks or removal
of bent/bow members)
2. Reduce loadings 2.2 Selection of SMR techniques
3. Local SMR (where no change in the load path of
the structure occurs when used an SMR scheme, e.g., When choosing an SMR scheme, it is advisable to review as
employing a clamping mechanism around a joint or many options as possible even though one particular option
member) may seem to be the obvious choice. It is important to choose
4. Global SMR by provision of new members. (A change the technique that provides the best scheme based on tech-
of system load path occurs, e.g., by the addition of a new nical, operational, and economic considerations. Figure 6
member) lists all the relevant options of each SMR scheme. Later in
5. Total SMR by tying into a new adjacent structure this section each of these will be discussed in more detail.
When making a final decision on the selection of an SMR
Figure 5 provides the interrelationship of common defect scheme, the following data should be considered as part of
scenarios and appropriate SMR schemes that might be the feasibility study to ensure that the SMR scheme chosen
employed. It should be noted that for various component represents the best solution:
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
4 Offshore
Local SMR Local SMR Local SMR Local SMR Local SMR Local SMR
(1) Grout member (1) Remedial
(1) Remedial grinding, plus
(1) Improve weld (1) Grout member (2) Weld doubler grinding, plus (2), (3) or (4)
(1) Grout member (2) or (3)
– toe grind and/or joint plate over dent
– hammer peen (2) Weld repair
(3) Brace the (2) Grouted sleeve
(2) Nodal clamp (2) Nodal clamp or
(2) Reduce SCFs bowed member, grouted sleeve (3) Nodal clamp or
connect ends of (3) Weld patch grouted sleeve
– grout joint (3) Grouted
brace(s) by: plates
– nodal clamp sleeve (3) Weld doubler
– welding plates (4) Weld doubler
– clamping plates
Global SMR
Provide alternate load paths by introducing new members, connect ends by:
– welding
– clamping
Figure 5. Interrelationship between scenarios, SMR schemes, and SMR techniques. (Reproduced with from Dier (2004). Mineral
Management Service/US Government.)
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Remediation and Repair of Offshore Structures 5
Strengthening/modification/repair techniques
Figure 6. Overview of commonly used SMR techniques. (Reproduced with permission from API RP2 SIM (2014). © American Petroleum
Institute, 2014.)
Figure 7. Deployment of diamond cutting saw for member cutting and removal. (Reproduced with from Dier (2004). Mineral Management
Service/US Government.)
2.2.2 Welding of welding techniques that are generally used. They are the
following:
One of the best SMR techniques that can be used is welding.
The key challenge is when the welding process migrates • Dry Welding at One Atmosphere. This is generally used
to underwater, and there are difficulties in replicating the topside and around the splash zone areas and includes
suitable environment to maintain good quality welding with the use of a cofferdam (Figure 8) or pressure-resistant
the right performance. For SMR, there are three major types chamber to maintain a similar environment as
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
6 Offshore
Figure 8. Cofferdam in position and welder working within cofferdam. (Reproduced with permission from Harris (1986). © Springer,
1986.)
atmospheric. All normal welding processes can be used hydrogen. Dry welding in chambers/cofferdams is gener-
including gas metal arc welding (GMAW), shielded ally restricted to depths up to 50 ft (15 m). Deeper repairs
metal arc welding (SMAW), flux-cored arc welding are technically feasible but become much more costly
(FCAW). due to the need for saturation diving. Robotic welding
• Dry Welding Using Hyperbaric Chambers. The chamber has been used to splice deepwater pipelines, but its use
is typically open to the sea at its base, allowing diver on structures is discouraged by geometric complexity.
access and capturing a bubble of compressed gas at • Wet Welding. For practical purposes only the SMAW
ambient pressure. The main process are GMAW and process is suitable (Figure 9). In this process, the arc is
SMAW although other processes may also be used. operated in direct contact with the water. It has the advan-
Gas composition in the chamber must be controlled tage of not having to use a cofferdam or chamber. It has
to limit the partial pressure of oxygen, nitrogen, and the disadvantage of possibly creating a poorer quality
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Remediation and Repair of Offshore Structures 7
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
8 Offshore
Brace
Toe of weld
Single sided
But weld
Root x
Chord T
Figure 10. Typical toe grinding application. (Reproduced with from Dier (2004). Mineral Management Service/US Government.)
(a) (b)
Figure 11. Weld repair using toe grinding. (a) Mobile exploration and drilling platform. (b) Column–pontoon corner. (Reproduced with
permission from ABS Consulting (2004). © ABS Consulting, 2004.)
a length adjustment to a new or existing member, and The main clamping mechanisms include the following:
providing a means to connect or support a new appurtenance
guide. At its simplest level clamping involves the bolting • Stressed Mechanical (Friction) Clamps. The strength of a
of two plates connected by bolts. In many respects they mechanical connection is obtained from the steel-to-steel
are similar but the essential differences in clamps involve friction that is developed by means of the external
the load transfer capability of each, for example, existing studbolt loads that lead to compressive forces normal
steel with clamp steel and grout or neoprene or whether the to the tubular/clamp saddle interface. These clamps for
interface is prestressed by clamp bolts. Great care must be all purposes should be avoided if the repair is a perma-
taken in the design of clamps. It is recommended prior to nent solution or requires close monitoring to ensure that
design a metrology survey be done to ensure the dimensions the clamp maintains its prestress and functionality over
of the tubulars (members/joints) subjected to any ovaliza- time.
tion due to hydrostatic forces are taken into consideration. • Unstressed Grouted Clamps/Sleeve Connections. An
The general terminology for clamp technology is provided unstressed grouted clamp or sleeve connection comprises
in Figure 12. sleeves, which are placed around a tubular member or
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Remediation and Repair of Offshore Structures 9
Stiffener
Split
Side plate
Stiffener
Figure 12. Clamp terminology. (a) Continuous flange, (b) discontinuous flange. (Reproduced with from Dier (2004). Mineral Management
Service/US Government.)
Figure 13. Post-hurricane Lilli platform stabilization in the Gulf of Mexico. (Reproduced with permission from ABS Consulting (2004).
© ABS Consulting, 2004.)
joint with the annular space so created filled with grout. • Stressed Elastomer-Lined Clamps. Stressed
The bond and interlock between the grout/steel interface elastomer-lined clamps are very similar to stressed
provides the means of load transfer between the tubular mechanical clamps, except that an elastomer lining is
member and the clamp. Unstressed grouted clamps and bonded to the inside faces of the clamp saddle plates, for
connections offer a versatile means for strengthening or example, to accommodate irregularities in the existing
repair of tubular joints and members since they require tube surface.
less accurate offshore surveys than do the mechanical
clamps. Figure 13 shows part of the damage to a drilling platform
• Stressed Grouted Clamps. This form of clamp is a hybrid located at 68 m depth in the Gulf of Mexico and the stress
between a stressed mechanical clamp and an unstressed grouted clamp attached with sleeves to new piles as part of
grouted clamp. The strength of a stressed grouted clamp the SMR scheme. Post-hurricane inspection revealed that a
is obtained from a combination of “plain-pipe” bond and pile was exposed and severed about 6 m below the mudline.
grout/steel friction developed as a result of compressive The repair work involved the installation of stress grouted
radial stresses at the grout/tubular member interface. This clamps at the existing piles. The clamp was connected to
is quite a popular and effective clamping mechanism. The pile sleeves for new pile installation. Several repair options
effects of compressive hoop stress in the base member were considered at the concept stage including guy wires to
should be considered. piles and props attached to undamaged platform. Structural
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
10 Offshore
assessments indicated that more than one template was repair techniques or use in underwater schemes. Dier (2004)
required in addition to severed leg replacement to provide noted that most popular materials for bolting in subsea
sufficient torsional resistance against potential hurricane work are L7 and B7 (1 1∕4% chromium–molybdenum steels)
wave loads. The final SMR scheme included two templates, and have proved themselves with a substantial track record.
a stress grouted clamp and five piles. This case study has Macalloy bar was formerly specified in clamp applications
been published on the BOEMRE (Bureau of Ocean Energy but has fallen out of favor following a number of hydrogen
Management, Regulation, and Enforcement) website (2011) embrittlement failures.
as part of an ABS Consulting publication (2004) on Hurri-
cane Lilli impacts on Fixed Platforms. 2.2.7 Adhesives
2.2.5 Grout filling There are a number of structural resins that are used in SMR
work including acrylic, cyanoacrylic, and urethane products,
For local buckling of tubular sections and growth of dents with epoxy resins being the most commonly used as they
in damaged tubular sections, the process of grout filling cure in the wet. The use of adhesives has had considerable
provides a good repair solution. In many cases grout filling success in the aerospace industry, but their use in the offshore
not only restores the damaged member to original perfor- industry has already been treated with caution. The main
mance but also improves it. Grouting a member may also source of suspicion is that the design of adhesives is not
be part of the preparatory process to another SMR scheme included in codes and standards so its applicability often
such as clamping. A grout-filled joint is one where the chord requires additional research or working together with the
is filled with a cementitious grout material (Figure 14a). The manufacturers to better understand their performance. Bond
chord may be completely filled or, in the case of the piled strength can be adversely affected by contaminants (e.g.,
leg, the annulus between the tubulars is filled (Figure 14b), flash oxidation) and by variable thickness due to a poor fit.
double-skinned joint. Grout filling enhances the strength of Adhesives potentially offer a series of advantages, including
joints and tubular members as it reinforces the chord and their use to joint different types of materials, their application
restricts local shell bending and section ovalization. Grouting in areas where there is limited access, and their properties
is a well-established technique used in the offshore industry largely independent of depth. When selecting a resin the
and is relatively easy to employ. It is highly effective and rela- following are generally considered:
tively cheap compared to other options. Great care should be
taken when employing grout filling to avoid the formation of • Curing period.
voids that may be formed in the joints or members. Addi- • Preparation requirements for the substrates.
tionally, when employing a grouting SMR, one must also • Quality assurance to ensure that the required bond has
consider what this means to the overall global response of the been achieved.
structure. Grout filling might introduce new stiffer sections • Inspectability of joint during service.
that attract loads to unstiffened sections in the vicinity. ISO • Ability to remove the joint if the scheme proves to be
19902 (2007) provides good guidance on the performance of inadequate.
grout-filled joints and sections. • For topside applications consideration should be given to
heat and fire resistance.
2.2.6 Bolted connections
2.2.8 Cold forming
Bolted connections have been used extensively on topside
repair and modifications to existing structures (Figure 15). Using mechanical connectors and swaging techniques in
While used as a modification technique in its own right, SMR work relies on cold forming the steel tubulars. Though
it is also a key component in clamping systems. Bolting not generally popular as SMR schemes, mechanical connec-
is a proven system with key advantages including quick tors and swaging can provide many advantages, in particular
application, no delay time being required to achieve full repair/strengthening situations. Mechanical connectors
strength, easy to fabricate, and readily available key compo- involve the use of grab, twist, and/or gripping devices
nents. Design is available in existing codes and standards and to achieve the mechanical locking of two steel tubulars.
provides great flexibility in it use, including easy removal. Swaging involves forming a structural connection by the
There are in fact some limitations in using bolting systems hydraulic expansion of a steel liner to create an interface
in the splash zone area and underwater. Due to the high lock joint with another tubular.
corrosion environment offshore, it is often required to seek Caisson repairs have been performed on many North
specialist advice when designing bolts for the splash zone Sea platforms due to perforations resulting from internal
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Remediation and Repair of Offshore Structures 11
Grout Chord
Brace
Figure 14. (a) Grout-filled joints and (b) double-skinned grout-filled joints. (Reproduced with permission from Dier (1996). © Society of
Petroleum Engineers, 1996.)
Figure 15. Typical bolting connections for modification work at topsides. (Reproduced with permission from Dier (1996). © Society of
Petroleum Engineers, 1996.)
and external corrosion/erosion and fatigue stress cracking. composite here. Composites are also used as a containment
External access to the damaged regions of caissons is often formwork as in the case of repair work to corroded conduc-
restricted so an alternative solution is provided using the tors. In some cases composites are used as a reinforcing
swaging technique. A liner tube, lowered from the topside plate to bond existing steelwork, for example, strengthening
to bridge the damaged section, is plastically deformed above of beam and column flanges, the reinforcement of webs and
and below the defect area to form a connection between deck plating, and repairs to conductor and riser casings, cais-
the liner and existing caisson reinstating its structural sons tanks, and pipework. There are a variety of suppliers
integrity. The solution provides a cheaper, diverless solution available in the market on a variety of composites for various
to employing external clamps (Figure 16). areas of SMR work.
Figure 17 shows the application of the Syntho-Glass XP, a
high strength fiberglass composite wrap on a 32 inch heavily
2.2.9 Composites
corroded riser on a platform in the South China Sea. The
Generally composites are used in SMR as a mate- application took less than 36 h to complete compared to
rial of choice for the replacement of structural access member removal or replacement that can take a few days, and
members including railings, stairways, and handrails. The costs were considerable less compared to member replace-
fiber-reinforced polymers (FRP) have become a popular ment. In addition, member removal and replacement require
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
12 Offshore
Corrosion
damage to
caisson
Figure 16. Caisson repair using swaged connection in the North Sea. (Reproduced with permission from Oil States Industries (2011). ©
Oil States Industries, Inc.)
(a) (b)
Figure 17. Repair on a 32 inch riser using a composite. (a) Condition before repair, (b) pipe being coated with Syntho-Subsea LV and
Syntho-Glass XT. (Reproduced with permission from Neptune Research, Inc. © 2016.)
the use and mobilization of heavy equipment, which is It must be noted that Table 2 provides reasonable guid-
avoided here, through the use of this composite. Hand lay-up ance to the SIE when selecting a preferred SMR scheme.
of chopped fiberglass in an epoxy matrix has been used for However, other criteria may have to be taken into considera-
corrosion protection in the splash zone since the 1960s. tion as well including the availability of technical expertise,
vessels and equipment, fabrication yards, costs, and so on in
the region/area the SMR work is to be undertaken, prior to
2.2.10 Summary of SMR methods
making a final decision. Moreover, the SMR schemes, espe-
Dier (2004), through an extensive JIP study on the Assess- cially specialist work as clamp design, require using skilled
ment of Repair Techniques for Ageing or Damage Structures, consultants in that area of work (Table 3). Additionally, the
catalogued each repair scheme and its applicability to various JIP also provides a list of advantages and disadvantages
defects. Table 2 summarizes the SMR technique as well as its on proposed SMR schemes, and these are provided within
performance against known defects. Table 4.
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Remediation and Repair of Offshore Structures 13
2.3 Inspection, maintenance, and monitoring mean including the inspection/monitoring techniques
in the operator’s in-service inspection plans (ISIPs) as
As with all SMR techniques, there must be rigorous part of their risk-based underwater inspection or other
procedures in place to monitor the performance of these routine inspections to assess the performance of the SMR
schemes over time. Inspection techniques must be agreed scheme. This performance can be used as lesson learnt
upon by the operator and certifying body (if required) to understand the limitations of particular schemes and to
up front. Once installed/executed, the SMR needs to ensure that they are addressed when choosing future SMR
be monitored as part of the SIMS process. This would schemes.
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
14 Offshore
Nichols and Md Harif (2014) advocated using an online then be grouted with an ultra high performance cementitious
monitoring (OLM) process to monitor the effectiveness of material to stabilize the structure. An OLM instrumenta-
an SMR scheme. Upon performing underwater inspections tion system installed at deck level was used to continuously
on a platform, it was found that one member was severed monitor the structural response of the platform (e.g., natural
and partially detached from one of the jacket legs. Other frequencies and mode shapes) before, during, and after the
members were damaged above and below sea level, together repair process.
with impact damage at the joints. A total of five members The observed changes in structural response provide
were found to be partially damaged. The repairs to the plat- evidence of the improvement in the structural integrity of
form would involve the installation of two new members the platform. Further confidence in the effectiveness of the
and the installation of three specially designed and fabricated repairs can be gained by comparing the changes in structural
clamps to connect the new members and reenforce the weak- response with those predicted using finite element structural
ened joints (Figure 18). The clamps and members would analysis (FESA).
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Remediation and Repair of Offshore Structures 15
Figure 18. Platform A strengthened joints and member computer model and as-built photo. (Reproduced with permission from Nichols
and Md Harif (2014). © Society of Petroleum Engineers, 2014.)
2.4 SMR data within SIM database • It is also recommended to develop a database of SMR
options from global and regional studies to aid the
Due to the variety of options and varying levels of decision-making process, prior to final scheme selection.
complexity for the SMR for both topsides and substruc- • Include inspection/monitoring techniques in operator’s
tures, Nichols et al. (2015) proposed the development of ISIPs to ensure that the performance of SMR schemes
an SMR database/toolkit with a cost estimation module, over time. Modern technology such as OLM has proven
which can be part of the operators SIM database. Global quite effective in monitoring the structural behavior and
case studies on SMR can reside within the SIM database, performance of jacket structures in the implementation
making it easier to access them and aid the decision-making of an SMR scheme.
process prior to selecting an SMR option, and the feasibility
of particular options based on accessibility and availability
of resources and competencies can be based on operating ACKNOWLEDGEMENTS
region requirements.
The authors would like to thank the publishers of the EMOE
for their encouragement to present this article.
3 RECOMMENDATIONS AND
CONCLUSIONS LIST OF ABBREVIATIONS
The following are recommended when developing SMR ALARP (human risk) as low as reasonably
schemes or managing a fleet of aging structures that require practicable
SMR work: API American Petroleum Institute
BOEMRE Bureau of Ocean Energy Management,
• SMR can be a very costly and complex undertaking, Regulation, and Enforcement
especially for underwater repairs. It is critical to find out FCAW flux-cored arc welding
initially whether SMR is required in the first place by FFP fitness for purpose
ensuring that a proper evaluation of the defect/damage FESA finite element structural analysis
is performed or some form of assessment engineering is FRP fiber-reinforced polymer
also done to determine the extent of SMR. ISIP in-service and inspection plan
• Once SMR has been decided upon, it is highly recom- ISO International Standards Organization
mended to consider the feasibility of more than one JIP joint industry project
option depending on operational, regional, resources, and NDE nondestructive examination
technical competency on designing and executing the RSR reserve strength ratio
options. SCE (structural) safety critical element
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
16 Offshore
SIE structural integrity engineer also includes conceptual field development studies, detailed
SIM structural integrity management design, and analyses of both onshore and offshore structures
SIMS structural integrity management system including fatigue, seismic, vessel impact, decommissioning,
SMAW shielded metal arc welding and ultimate strength considerations in a variety of operating
SMR strengthening, modification, and repair regions including the Gulf of Mexico, North Sea, Latin
OLM online monitoring America, Asia, and the Far East. He also serves as a task
UEG Underwater Engineering Group group leader and member of the OGP (ISO 19901-9) Code
Committee for the structural integrity management of fixed
offshore structures. Email: riaz.khan@petronas.com.my
BIOGRAPHICAL SKETCHES Tele: +60132802162 (m).
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2
Remediation and Repair of Offshore Structures 17
Structural A continuous integrity process applied Dier, A.F. (2004) Mineral Management Service (MMS). JIP on the
Assessment of Repair Techniques for Ageing or Damage Struc-
integrity throughout the design, operations,
tures. MSL Engineering Ltd. DOC REF C357R001 Rev 1. Nov
management maintenance, and decommissioning of 2004.
system (SIMS) a platform to ensure a platform is Harris, G. (1986) The Use of Cofferdams for Welded Repair to
safely managed and is fit for its Offshore Structures, Comex Houlder Diving Ltd, Aberdeen.
individual purposes. ISO 19902 (2007) Fixed Steel Offshore Structures, 1st edn, British
Structural risk The cornerstone to successful Standards International, London.
implementation of SIM is the ability Nichols, N.W. and Md Harif, H. (2014) Use of Platform Response
to effectively manage the structural Measurements from On-Line Monitoring (OLM) System to verify
risks associated with the platform the Effectiveness of Structural Repairs & Managing On-going
operations is the adoption of a Structural Integrity. OTC Asia Paper 24947-MS.
risk-based approach to managing the Nichols N.W., Khan, R., Ng, S.M., Lee, L.A., and PETRONAS Cari-
structural integrity for existing gali Sdn Bhd (2015) A Strengthening, Modification and Repair
(SMR) Toolkit for Structural Integrity Management of Ageing
offshore structures. Within this Offshore Structures. SPE Conference, Bali 2015.
context, structural risk is defined as
O’Connor, P.E., Bucknell, J.R., DeFrance, S.J., Westlake, H.S., and
the combination of the likelihood of Westlake, F.J. (2005) Structural Integrity Management (SIM) of
some event occurring during a time Offshore Facilities. Paper OTC 17545. Offshore Technological
period of interest and the Conference.
consequences (generally negative) Oil States Industries (2011) Case Study: Hydra Lok Swaging System.
associated with the event. In http://www.oilstates.com/fw/main/Hydra-LokCAE-Swaging-
mathematical terms, risk can be Systems-227.html (accessed June 2011).
expressed as Thurley, L.S. and Hollobone, T.A. (1981) Handbook of Underwater
Tools. CIRIA/UEG UR18, CIRIA, London.
Risk = Likelihood × Consequence
Structural safety These are structural members within the Westlake H, Puskar, F.J., O’Connor, P.E., and Bucknell, J.R. (2006)
The Role of Ultimate Strength Assessments in the Structural
critical platform that, if are severely damaged Integrity Management (SIM) of Offshore Structures. OTC 18331.
elements or damage goes unmitigated, can lead
(SCEs) to a reduction in the performance of
the structure and may lead to eventual
collapse. FURTHER READING
Ultimate strength Also called a “pushover analysis,” is a
analysis nonlinear measure of the reserve
API RP2A (2000) API Recommended Practice for the “Planning,
strength ratio (RSR) of the jacket
Designing and Constructing Fixed Offshore Platforms”, 21st edn,
structure. It is based on truss action American Petroleum Institute, Washington, DC.
and system strength rather than Dier, A.F. (2003) Mineral Management Service (MMS). JIP on the
component strength. Definition and Reporting of Significant Damage for Offshore Plat-
forms. MSL Engineering Ltd. DOC REF CH161R001 Rev 1. Jan
2003.
Nichols, N.W., Petronas Carigali Sdn Bhd, and Goh, T.K. (2006)
Managing Structural Integrity for Aging Platform. Proceedings for
REFERENCES the Society of Petroleum Engineers (SPE), Adelaide, Australia.
Puskar, F., DeFranco, S., O’Connor, P., Bucknell, J., and Digre,
K. (2010) API RP 2SIM: Recommended Practice for Structural
ABS Consulting (2004) Hurricanes Lili Impacts on Fixed Platform. Integrity Management. Proceedings of the Offshore Technological
https://www.boem.gov/ (accessed June 2011). Conference (OTC) 20675.
API RP2 SIM (2014) Recommended Practice for the Structural Society of Petroleum Engineers (1998) New Technologies in the
Integrity Management of Fixed Offshore Structures, 1st edn, Amer- Reassessment, Strengthening and Repair of Offshore Steel Struc-
ican Petroleum Institute, Washington, DC. tures. Proceedings for the Society of Petroleum Engineers (SPE),
International Petroleum Conference and Exhibition in Mexico.
AWS D3.6M (1999) Specification for Underwater Welding, Amer-
ican Welding Society, Miami, FL.
Dier, A.F. (1996) Background to New Design Manual for Plat-
form Strengthening, Modification and Repair. Paper OTC 8079
presented at the Offshore Technology Conference, Houston, May
1996.
Encyclopedia of Maritime and Offshore Engineering, online © 2017 John Wiley & Sons, Ltd.
This article is © 2017 John Wiley & Sons, Ltd.
DOI: 10.1002/9781118476406.emoe409
Also published in the Encyclopedia of Maritime and Offshore Engineering (print edition) ISBN: 978-1-118-47635-2