Sunteți pe pagina 1din 4

Rig Inspection Checklist

NOTE: The following Rig Inspection Checklists are not a complete listing of requirements. They
were developed to assist employers and workers with training, equipment and documentation
requirements in rigging.

Training Requirements – Rig Inspection Checklist


OHS Regulation/
WC Act
1. Derrick man must be trained and demonstrate proficiency to use 23.39.2 (4)(c)
the emergency escape system installed on the rig; the escape 23.39.3(3)(a)(b)
system must be inspected on a frequency as required by 23.39.3(4)(a)(b)
regulation, by a qualified person and the inspection recorded and
records available.
2. Simulated Derrick rescue once a year and documented 4.14(3)
32.2(2)
3. 2 crew members with “ENFORM RIG RESCUE” training on tower 32.2(1)
at all times

4. All crew members should have “ENFORM FALL PROTECTION” 11.2(6)


training

5. CAODC “FALL PROTECTION MANUAL” on location 11.3(2)

6. Hearing test once a year and within 6 months of being hired 7.8(1)(a)(b)

7. Fit testing for all respirators – SCBA’s and ½ mask respirators 8.40

8. ETS – no smoking in well site shack/camp/vehicles – 4.81


designated safe outside areas only

9. No equipment located under escape buggy line – 50 feet 23.39.2(2)


23.39.3(2)
10. Slings and attachments must be visually inspected each shift and 15.25,15.43(wire rope)
before use / removed from service if defective 15.54 (synthetic)

11. Address hazards when rigging up – working over 3 Meters above 11.2, 11.6
grade / proper anchor points

12. Forklift/Mobile equipment training CSA Standard for lift trucks & 4.3, 16.4, 16.7
Manufacturer’s recommendations

13. Training of workers conducting rigging and slinging operations - 15.2


Definition of qualified - OHS Regulation Part 1 1.1

14. Driver training – GODI – ENFORM Training Program or equivalent 23.22

1
Revised April 2009
Equipment Requirements – Rig Inspection Checklist
OHS Regulation/
WC Act
1. Suitable Self Retracting Lifeline
(a) Floor to Crown 11.5, 11.6
(b) Crown to racking board
(c) Soft line to Retract SALA Block Line when not in use (Reel) –
optional
(d) Additional anchor point and assemblies for working lifelines
2. Equipped with an Emergency escape system from the racking 23.39.1
board that meets the requirements of 23.39.2 or 23.39.3
3. Location of escape equipment to allow unimpeded exit from 4.14(2)
racking board (refer to CAODC RP #9 – Derrick Egress) 23.39.2(1)(a)
4. Fall Restraint system for the roof of the doghouse or any other 11.2
area over 3 meters
5. Rig Rescue Equipment – inspected and maintained in good 11.9
working order
6. Lock-out Station / Board ( locks / tags / scissor hasps) 10.1
10.4
7. 4 – Positive pressure (no donning switch) SCBA on site - 2 units at 23.36
two different locations / 4 spare bottles CSA 94-4
8. Safety chain across “V” door 4.55(a)
9. Cat head spools removed or covered 23.20
10. Crown saver in place / functioned each day 23.49(2)(3)
11. Risk assessment done for eye washing facilities/emergency shower 5.88
12. Oil based mud system – coveralls being cleaned at employers 8.8, 5.85
expense / hand wash/ shower available
13. 15 meter clear area under the end of the escape buggy line 23.39.2(2)
14. Rigging, fittings & slings have Manufacture’s ID / Working Load 15.5(1)
Limit (WLL) attached
15. Stairs with 4 or more risers must have handrails 4.62
16. DST’s, underbalanced drilling & oil based mud systems require 23.43
2 2
L.E.L / H S / O detectors in an enclosed substructure or adequate
ventilation. Size of ventilation openings, mechanical ventilation, and
cold weather provisions
17. Signs under overhead power lines identifying location 19.5
18. Degasser vents lines use appropriate fittings 23.13(1)
19. Exhaust fan in mud mixing room 5.64, 5.65
20. BOP requirements different than Alberta – 1850 Meters and deeper 4.1
require gut line –
**REFER TO Drilling & Production Regulation (Oil & Gas
Commission)
21. Coordination of Multiple Employer workplaces 23.4 & WCA 118
22. Control of Static Electricity-grounding and Bonding 23.6, 5.28
23. Fire hazards – No Smoking or open flames within 25 meters 23.7
24. Control of Ignition Sources – BC Electrical Code 23.8(1)(a)
25. Control of Ignition Sources – Positive Air Shutoffs for Diesel Engines 23.8(1)(b)
23.8(2)
26. Flare Pits & Flare Lines – lighting, safe access 23.9
27. Fire Extinguishers 4 X 40-BC 23.10
28. Air Operating Systems – Alcohol restrictions 23.11
29. Pipelines, fittings & valves – standards, safe work procedures 23.12

2
Revised April 2009
Equipment Requirements (cont’d) – Rig Inspection Checklist
OHS Regulation/
WC Act
30. Hose Connections – design, service 23.13
31. Pumps – positive displacement, PSV 23.14
32. PSV – when required (Boiler & Pressure Vessel Act) 23.15
33. PSV – installation – discharge pressure, valves, restrictions, 23.16
shear pins
34. Pipe Racks – loads, level surface, pins and spacers 23.17
35. Handling Pipe – nubbins, movement, deck pins, loading 23.18
36. Kelly hose – safety lines, clamps, shock hoses 23.19
37. Rigging up – signals, rigging, tag lines, location of worker, winching 23.21
38. Horizontal static line & walkway when derrick is laid down 11.2
39. Steep slopes – engineering, written plan, snubbing & yo-yoing 4.3, 23.23(2)
40. Roads – comply with OHSR – Part 26 23.24
41. Size of work area – emergency response, loads, safely moved 23.31
42. Inspection & Repair – RP’s 1.0/1.0A/2.0/3.0/4.0 – CAODC log book 23.32
43. Rig Moves – lifting points, raising & lowering the derrick 23.33 (2)
44. Manufactures or PEng Identification and Instructions for the 3.3(c),
assembly and disassembly of the drilling or Service rig 14.3(1)(2)(3)
14.12(2)
45. BOPS – installing, slinging 23.37
46. Spudding in – guards in place, platforms/stairways installed, escape 23.38
line
47. Draw works controls – identified, guarded, locking devices 23.40
48. Stabbing boards – dimensions, securing, fall protection 23.41
49. Derrick enclosures – weather, climbing on, exits 23.42
50. Pits & Tanks – sources of ignition, adequate ventilation 23.44
51. Hoisting lines – 5 wraps on the draw works drum 23.48
52. Securing fingers – unsupported ends on the monkey board 23.54
53. Weight indicators – required, safety line 23.56
54. Brakes – tested, automatic feed, hold down chain 23.57
55. Guarding of the rotary table and Kelly 12.2
56. Rotary tongs – preventing uncontrolled movement 23.60
57. Guy lines – installation, testing spec plate, documentation 23.63
58. Drill Stem Testing - requirements 23.64
59. Swabbing at night – lighting, sand line depth meter, flags, wind 23.65
direction
60. Air intakes – 6 meters from rig tank, tank truck loading 23.68
61. Flow piping – anchored, restricted areas, pressure testing 23.69
62. Pressure testing – 10% rule, documentation of tests, bleeding air 23.72
63. Hot oiling – vent line 10 meters from source of ignition 23.73

3
Revised April 2009
Documentation Requirements – Rig Inspection Checklist
OHS Regulation/
WC Act
1. BC WCB – OHS Regulations on site WCA 115(2)(f)
2. CAODC “Fall Protection Manual” on site (fall protection plans) 11.3
3. Accident Reporting Kit WCA 172
4. Derrick climbing procedure posted 11.3
5. Racking board rescue procedures posted 4.13(3)
6. Noise level survey done and posted 7.3
7. Boiler certification on site (BOILER & PRESSURE VESSEL ACT) 4.1
8. Respirable air quality documentation on site – tested every 12 8.37
months CSA Z180.1 M85
9. Fit testing documentation on site 8.44
10. SCBA inspection and maintenance records 8.44
11. List of weights of all items which can be lifted or winched 23.34, 14.36(1)
Critical or Tandem life procedures available followed 14.42(1)(2)(3)
14.42.1(1-5)
12. Emergency Escape system inspection and documentation as per 23.39.2(4)(c)
Requirements of system used i.e.; weekly, monthly or each time 23.39.3(3)(a)(b)
Erected (Manufacturers’ instructions)
13. Simulated derrick rescue performed and documented once a year 4.14(3), 32.2(2)
14. Safe work procedures for all jobs available for all workers 23.5
15. All certification for rig equipment (mast, substructure, BOP’s, etc) 23.32
available on site
16. CAODC log book available on site 23.32(2) (3)
17. Monitoring and Sampling results when drilling with Non-Water Based 5.27(LEL)
Drilling and Completions/Well Servicing Fluids (IRP#14), Exposure 5.48, 5.54, 5.55
Control monitoring conducted and Exposure Control Plan developed (OEL’s)
and implemented according to Industrial Hygiene principals
18. Casing Bowl Welding-Done in accordance with ASME,CSA and API 4.1
Standards, welds NDT tested (dye testing) and pressure tested, 4.3(1)(a)(b)
casing bowl Installation procedures followed and available for review 23.72(1)
Comments:

4
Revised April 2009

S-ar putea să vă placă și