Project Feeder 2 &3 - 13.

8KV Cable Replacement

Subject Cable Termination Procedure on April 1, 2018

Step Procedure Hour Schedule Data/Value To be Executed By GWE Verified By TI Facilities


Verified By Status Verified By Status
Feeder Line De-energization
1 Verify substation incoming voltage (it should be zero)
2 Switch off load break switches of substations (S/S E, Eg, F, H, G)
3 Install LOTO at LBS TI substations (S/S E, Eg, F, H, G)
and draw out Feeder at Team Energy Feeder 2 and 4
Install LOTO at LBS TI substations (S/S M, N, O) and Feeder at 7:00am to 8:00am
4
Team Energy Feeder 2 and 4
5 Draw out LVSG of S/S M, N, O normal breaker
6 Install grounding clusters on Feeder 2 and 4 at cold storage area
7 Label and picture all cables prior to dismantle
Pull-out/Termination of MV cables (SPINE)
8 Open MV termination panel at spine fronting SS-G/H
8:00am to 9:00am
9 Install grounding clusters on main cable termination box
10 Mark cables and terminals before disconnection. Mark/label/picture cables from which terminals it was 9:00am to 10:00am
disconnect one by one. Perform continuity test per cable.
11 Pull-out old Feeder 2 main cable using torque wrench and
record torque values.
10:00am to 11:00am
12
Install new Feeder 2 main cable as per color coding or line numbers (L1-BLK, L2-RED, L3-BLU)
13 Torque bolts/nuts as required
14 Remove grounding clusters
11:00am to 12:00pm
15 Verify main cables resistance (L-L & L-G). It must be infinite.
16 (L1-BLK, L2-RED, L3-BLU)
Pull-out/Termination of MV cables (Sectionalizer Tower).
17 Identify and disconnect old Feeder 2 main cables
Pull-out old Feeder 2 main cables using torque wrench and record torque values. Do not damage 8:00am to 9:00am
18 existing cable (back up) ready for tapping.
19 Install additional horizontal angle bar support with pin insulators. 9:00am to 10:00am
Terminate new Feeder 2 main cables as per color coding or
20 line numbers 10:00am to 11:00am
21 Torque bolts/nuts as required
Remove grounding clusters previously installed on Close MV
22 termination panel at Spine
11:00am to 12:00pm
23 Megger test or Hi-pot Test
24 (L1-BLK, L2-RED, L3-BLU)
Pull-out/Termination of MV cables (Substation N).
25 Open MV termination panel at SS-N
26 Install grounding clusters on Feeder 4 bus 1:00pm to 2:00pm
27 Install pull box at side of SS-N HVL panel.
Mark cables and terminals before disconnection. Mark/label/picture cables from which terminals it was
28 disconnect one by one. Perform continuity test per cable.
2:00pm to 3:00pm
Pull-out old Feeder 4 main cable using torque wrench and record
29 torque values
30 Install new Feeder 4 main cable as per color coding or line numbers
31 Torque bolts/nuts as required
32 Remove grounding clusters 3:00pm to 4:00pm
33 Verify main cables resistance (L-L & L-G). It must be infinite.
34 (L1-BLK, L2-RED, L3-BLU)
Pull-out/Termination of MV cables (Sectionalizer Tower).
35 Identify and disconnect old Feeder 4 main cables
Pull-out old Feeder 4 main cables using torque wrench and record torque values. Do not damage
36 existing cable (back up) ready for tapping. 1:00pm to 2:00pm
Terminate new Feeder 4 main cables as per color coding or
37 line numbers
38 Torque bolts/nuts as required
39 Verify main cables resistance (L-L & L-G). It must be infinite.
Remove grounding clusters previously installed on Close MV 2:00pm to 3:00pm
40 termination panel at SS-N
41 Megger test or Hi-pot Test
42 Close MV termination panel at Spine and SS-N
Remove all scaffoldings and clear all affected areas with 3 man 3:00pm to 4:00pm
43 verification method
44 (L1-BLK, L2-RED, L3-BLU)
Feeder Line Re-Energization
Verify that all points affected by the project is clear and safe for
44 re-energization
Remove LOTO at LBS TI substations (S/S E, Eg, F, H, G) and
45 Feeder at Team Energy Feeder 2
Remove LOTO at LBS TI substations (S/S M, N, O) and Feeder at 4:00pm to 5:00pm
46 Team Energy Feeder 4
Close LBS of SS –H and verify phase sequence of 480V side of transformer or NORMAL power
47 meterterminals 11/12/13. If CW, close LBS of SS-E, Eg, F & G
48 Verify individual phase sequence at SS-H and SS-N
49 System is now ready for load transfer back to normal power source