Documente Academic
Documente Profesional
Documente Cultură
Settlement of Piles
Written Report in Foundation Design (CE513)
Submitted by:
Alvaran, Laurence
Nuñeza, Clark Dane T.
Ong, Ryan Kirby L.
CEIT-02-901P
Submitted to:
Engr. Nestor Competente
Settlement of Piles
Vertical Settlement of Piles
• Estimate of the settlement of a pile can be obtained from a theoretical
analysis based on theory of elasticity
• 80% of the total settlement elastic
• 20% of the total settlement consolidation of soil
Total Settlement
𝑆𝑒 = 𝑆𝑒1 + 𝑆𝑒2 + 𝑆𝑒3
where:
Se = total settlement
𝑆𝑒1 = elastic settlement of piles
𝑆𝑒2 = settlement of pile caused by the load at the pile tip
𝑆𝑒3 = settlement of pile caused by the load transmitted along the
pile shaft
1. Elastic Settlement of Piles
(𝑄𝑤𝑝 + 𝜉 𝑄𝑤𝑝 )𝐿
𝑆𝑒1 =
𝐴𝑝 𝐸𝑝
where:
f f
f
where:
𝑄𝑤𝑝
𝑞𝑤𝑝 = point load per unit area at the pile point; 𝑞𝑤𝑝 =
𝐴𝑝
𝑄𝑤𝑝 𝐶𝑝
b.) 𝑆𝑒2 =
𝐷𝑞𝑝
where:
𝑄𝑤𝑝 = load carried at the pile point under working load condition.
𝑞𝑝 = ultimate point resistance of the pile; 𝑞𝑝 = 𝐶 𝑁𝑐
𝐷 = diameter or width of pile
𝐶𝑝 = an empirical coefficient
Values of 𝑪𝒑
Type of Soil Driven Pile Bored Pile
3. Settlement of Pile caused by the Load Transmitted along the Pile Shaft
𝑄𝑤𝑠 𝐷
a.) 𝑆𝑒3 = (1 − 𝜇𝑠2 )𝐼𝑤𝑠
𝑃𝐿𝐸𝑠
where:
Sample Problem
1. A concrete pile 12m long having a cross section of 0.30m x 0.30m is fully
embedded into a layer of sand C=0. Frictional resistance of pile at working
condition is 240 kN and 100 kN is the point load capacity at working
condition. Allowable working load is 340 kN.
a. Compute for the elastic settlement of the pile.
b. Compute for the settlement cause by the load carried at the pile
point.
c. Compute the settlement of pile caused by the load transmitted along
the pile shaft.
d. Compute the total settlement of the pile.
Solution
a. Elastic Settlement of the Pile
(𝑄𝑤𝑝 +𝜉 𝑄𝑤𝑝 )𝐿 [100+0.60 (240)]12
𝑆𝑒1 = =
𝐴𝑝 𝐸𝑝 (0.30)(0.30)(21 𝑥 106 )
c. Settlement of pile caused by the load transmitted along the pile shaft.
𝐿 12
; 𝐼𝑤𝑠 = 2 + 0.35√ = 2 + 0.35 √
𝐷 0.30
𝐼𝑤𝑠 = 4.21
𝑄𝑤𝑠 𝐷 240 (0.30)
𝑆𝑒3 = (1 − 𝜇𝑠2 )𝐼𝑤𝑠 = (1 − 0.302 )(4.21)
𝑃𝐿𝐸𝑠 4 (0.3)(30000)(12)
𝑺𝒆𝟑 = 0.00638 m = 0.638 mm
d. Total Settlement of the Pile
𝑆𝑒 = 𝑆𝑒1 + 𝑆𝑒2 + 𝑆𝑒3
𝑆𝑒 = 1.55 + 8.59 + 0.638
𝑺𝒆 = 𝟏𝟎. 𝟕𝟕𝟖 𝒎𝒎