STANDARD SPECIFICATIONS

A form shall be constructed to the dimensions indicated on the Drawings and to the height of the
bottom of the bearing plate or pad. Grout shall then be placed, using great care to work the grout
into the form, and filling the form to the top. The exposed surface of the grout shall be given a steel
trowel finish. The form shall remain undisturbed and the grouted area shall be kept damp with no
load for a minimum period of 72 hours.

503.14 Blinding Concrete

a. General. The Contractor shall furnish and install blinding concrete as indicated on the
Drawings, as specified herein and as directed by the Engineer. All concrete placed
below ground level shall have gauge 1000 approved polyethylene sheeting on the
blinding concrete. The polyethylene sheeting shall be returned up the outside faces of
the concrete and suitably sealed.

b. Materials. The blinding concrete shall be constructed of Class K140 concrete and shall
comply with all requirements of Section V, Concrete Works, of these Standard
Specifications.

c. Construction. The construction of all blinding concrete shall comply with the
requirements of Section V, Concrete Works, of these Standard Specifications or as
directed by the Engineer.

503.15 Measurement and Payment

a. General. Measurement and payment for the Items of concrete construction will be as
described herein and as included in the Bills of Quantities. The work included under the
respective Items enumerated in the Bills of Quantities shall include all labour, materials,
tools, equipment and appurtenances to complete the respective Items.

Concrete and related work shall be as specified for measurement and payment
or as a subsidiary obligation to the Items under other Sections of Section V, Concrete
Works, as well as other Sections of the Standard Specifications:

1. Section VI, Storm Water Drainage System

2. Section VII, Water Works

3. Section VIII, Prestressed Concrete Works

4. Section XI, Concrete Pile Foundations

5. Section XII, Metal Works

6. Section XIII, Post-Tensioned Concrete Works

Version 2.0 Section V-3 November 2014