This means in Oracle Primavera P6, the budgeted or planned units for an assignment to that
activity are spread evenly across the duration of the activity or call it as linear distribution
But in site we may not allocate resources evenly to all kind of activity, let me explain brief you
Types of
Method of resource distribution
activities
Curing concrete Evenly distributed over time
Security checks Evenly distributed over time
Uneven distributed, during initial stages of activity, less resources are deployed, as it keep progressing density of
Excavation
allocation will increase and later at the end resources allocation will decrease
Uneven distributed, during initial stages of activity, less resources are deployed, as it keep progressing density of
Footing work
allocation will increase and later at the end resources allocation will decrease
Above table explains well that not all activities are same, and linearly distribution of resources
are not possible for all activities
Here is an example
You can see above, that on initial days i will be using only 5 labours/day and then increased to
15 and at the end I reduced to 5.
So if you are an experienced planner and you have good idea on how resources will be spread
practically, I recommend you to use future period bucket planning over linear distribution
Notes
• You can compare the planned future period resource distribution to actual units and costs
in the Resource Usage Profile, Resource Usage Spreadsheet, Activity Usage Profile,
Activity Usage Spreadsheet, time-distributed reports, and the Tracking window. If you
plan your project work in defined financial periods, after you store period performance,
you can compare the resource distribution you planned to the project’s past period
actuals.
• Activity costs, including earned value and planned value, are calculated using the planned
future period resource distribution you define for activity assignments.