Internal Dates for Sites

AIC Contract Milestones - Line 04 & Line 06

Steel Production Temporary Support Steel Installation


Priority Station
START FINISH START FINISH START FINISH
1 4 E1 6-Apr-17 5-Jun-17 29-Apr-17 20-May-17 21-May-17 20-Jul-17

2 4 B1 17-Apr-17 16-Jun-17 10-May-17 31-May-17 1-Jun-17 31-Jul-17

4 4D1 17-Jun-17 16-Aug-17 10-Jul-17 31-Jul-17 1-Aug-17 30-Sep-17

5 6E'1 17-Jun-17 16-Aug-17 10-Jul-17 31-Jul-17 1-Aug-17 30-Sep-17

6 6H1 17-Aug-17 16-Oct-17 9-Sep-17 30-Sep-17 1-Oct-17 30-Nov-17

3 4 C1 17-Aug-17 16-Oct-17 9-Sep-17 30-Sep-17 1-Oct-17 30-Nov-17

7 6F1 17-Oct-17 16-Dec-17 9-Nov-17 30-Nov-17 1-Dec-17 15-Jan-18

8 6G2 7-Nov-17 6-Jan-18 30-Nov-17 21-Dec-17 22-Dec-17 5-Feb-18

9 6D2 25-Nov-17 24-Jan-18 18-Dec-17 8-Jan-18 9-Jan-18 23-Feb-18

10 6 G1 1-May-18 30-Jun-18 24-May-18 14-Jun-18 15-Jun-18 30-Jul-18