Documente Academic
Documente Profesional
Documente Cultură
QAP-117258-000
PHS SPH
0 14.10.15
QAP-117258-000_Rev (0)_Quality_Plan_ASP_&_RDC.doc
printed on 16/10/15
QUALITY ASSURANCE PLAN Rev : 0
Document No. QAP-117258-000 Date: 14.10.15
Job Number: AF-11-7258 / 00 Page 2 of 32
INDEX
1 PROJECT OVERVIEW
The detailed analysis of the project scope of work comprises the following studies:
Based on the results of the Pre-Feasibility study, ASP/RDC will perform the
topographical route survey on the basis of a field topographical data
collection work. This study will offer the accurate topographical background
and the route alignment to be used in the engineering and design studies
which will be performed in later project phases.
QUALITY ASSURANCE PLAN Rev : 0
Document No. QAP-117258-000 Date: 14.10.15
Job Number: AF-11-7258 / 00 Page 5 of 32
Based on the field verification and desktop analysis data collected for the
best route option, ASP/RDC will describe the pipeline construction
engineering practices methodologies that will be followed by the EPC
contractors for the linear construction work along the route of the jet A1 fuel
pipeline and inside the Muthurajawela tank farm as well.
ASP/RDC will evaluate the environmental and social baseline records along
the selected best option route and alternatives as well, related to: soils,
surface geology, watercourses, ecosystems, land use, residential settlements,
air quality, acoustic environment, landscape, cultural and archaeological
heritage, socioeconomic factors, biodiversity, flora, fauna, industry and
infrastructures. Based on this data evaluation, the environmental and social
impacts will be outlined along with proposals for mitigation measures and an
overall environmental and social management plan.
ASP/RDC will provide three (3) feasibility studies dealing with the following:
ASP/RDC will prepare and issue all the basic design documentation: process
and mechanical design; interconnection piping and pigging facilities; pipeline
crossings design basis; data sheets and material requisitions for the long lead
items: pipes, pumps, tanks, motor operated valves, process equipment and
instrumentation items; typical drawings and design specifications applicable
in the detailed design and construction of the civil, mechanical, piping,
instrumentation, electrical and cathodic protection works.
ASP/RDC will provide training services to CPC’s personnel, in Greece and Sri
Lanka as well, on technical and administrative issues of the project, in order
to constitute them knowledgeable on the pipeline and tank technologies, and
also, on issues of the EPC contract management.
1.2.11 Procurement
Not applicable.
1.2.12 Construction
Not applicable.
QUALITY ASSURANCE PLAN Rev : 0
Document No. QAP-117258-000 Date: 14.10.15
Job Number: AF-11-7258 / 00 Page 7 of 32
1.2.13 Other
Not applicable.
The project scope of work has been identified between ASPROFOS and RDC as follows:
ASPROFOS S.A.
RDC Ltd
All the legislative and regulatory requirements of Sri Lanka’s state regarding
the HSE issues, and in addition, the ones of Greek and EU legislation, shall be
strictly kept by ASP/RDC during the project execution. The compliance of
ASP/RDC with the HSE requirements aims to assure that the risk to working
people (engineers, designers and supervisors, etc.) or damage to the Sri
Lanka’s environment and people’s property, shall be avoided, or at least
eliminated, to the minimum possible level.
Not applicable.
The responsibilities of the parties with the performance of the project are
split as follows:
2 PROJECT ORGANIZATION
Not applicable.
According to the Home Office Organization Chart the assigned Quality Assurance
Correspondence for the project is Dr. Philip-Mark Spanidis from ASPROFOS and his
assistant Mr. Dimitrios Bekos.
2.3.1 Engineering
2.3.2 Procurement
Not applicable.
Not applicable.
Mr. Wasantha Abeysekera from RDC Ltd is the authorized Deputy Project
Manager of the Consortium ASP/RDC for the project.
Not applicable
QUALITY ASSURANCE PLAN Rev : 0
Document No. QAP-117258-000 Date: 14.10.15
Job Number: AF-11-7258 / 00 Page 12 of 32
3 PROJECT PLANNING
Not applicable.
Not applicable.
3.5 Procurement strategy
Not applicable.
3.6.1 Shop
Not applicable.
3.6.2 Field
Not applicable.
Not applicable.
QUALITY ASSURANCE PLAN Rev : 0
Document No. QAP-117258-000 Date: 14.10.15
Job Number: AF-11-7258 / 00 Page 15 of 32
ASP/RDC understands that the risk is a future event that may insert to all project
activities and may create effects on the project objectives: scope, schedule, cost and
quality.
The Project Risk Management of the ASP/RDC Consortium deals with the
establishment of a set of risk management process regarding the planning of the risk
management system, the identification of risks, the qualitative risk analysis, the
quantitative risk analysis, the risk plan responses and the controlling/monitoring of all
the identified project risks.
ASP/RDC Project Risk Management relates to regular reviews for evaluation of the
project risks and decisions to be taken for elimination and/or mitigation of any
identified risks.
In the following Table-2 and Table-3 it is reflected, the qualitative and quantitative views of
the Risk Impact Identification matrices, respectively, on which the outcome of the performed
Risk Analysis is based on.
Impact Classification
Impact Classification
Minimal Risk
Low Risk
Moderate Risk
High Risk
Extreme Risk
The baseline Risk Assessment of ASP/RDC revealed some critical risks. These are
presented on the hereunder Table-4 along with the proposed Response Planning
activities.
QUALITY ASSURANCE PLAN Rev : 0
Document No. QAP-117258-000 Date: 14.10.15
Job Number: AF-11-7258 / 00 Page 17 of 32
4 PROJECT DOCUMENTATION
The basic information for the technical aspects and the project battery limits has been
acknowledged to ASP/RDC during the offer preparation.
(a) For the Jet A1 Fuel Pipeline: ANSI B31.4, ‘’Pipeline Transportation
Systems for Liquid Hydrocarbons and Other Liquids’’ (latest edition)
(b) For the Jet A1 Fuel Tanks: API-650, ''Welded tanks for oil storage''.
4.2.4 Specifications
Not applicable.
a. Contract Agreement
b. Sri Lanka’s legislation
c. Greek and European legislation
d. International Codes and Standards
e. CLIENT’s documentation
Not applicable.
The project documentation will be officially delivered in electronic form (digital files)
following the dates shown in the time schedule where each technical package is
entirely completed, i.e. Pre-Feasibility study, FEED, ITB package, etc.
4.5.10 Procurement
Not applicable.
4.5.11 Construction
Not applicable.
QUALITY ASSURANCE PLAN Rev : 0
Document No. QAP-117258-000 Date: 14.10.15
Job Number: AF-11-7258 / 00 Page 22 of 32
Not applicable.
4.5.13 Certificates
Not applicable.
4.5.14 Permits
Not applicable.
Not applicable.
Not applicable.
4.5.17 Reports
Not applicable.
Not applicable.
Not applicable.
QUALITY ASSURANCE PLAN Rev : 0
Document No. QAP-117258-000 Date: 14.10.15
Job Number: AF-11-7258 / 00 Page 23 of 32
Not applicable.
Not applicable.
Not applicable.
Not applicable.
ASP/RDC will issue specific to the project HSE document presenting the HSE
management system, which will be developed and maintained by ASP/RDC
Consortium in the terms of the project.
ASP/RDC ASP/RDC
Project Control
Project Manager Deputy Project Manager
O. Lathiri
Dr. Philip-Mark Spanidis W. Abeysekera
HSE Manager Process Manager Route Design Expert Civil & Geotechnical Expert EIA Expert
S. Lattas A. Varvakis K. Stamatis U. Goonasekera R. Ellapola
HSE Expert Process Engineer Engineering Geology Expert Surveying, GIS, RS Experts Legal Expert
M. Konstantopoulou C. Chapsias E. Stasinoulias Ms. Eridimane
Mr. Pitawala
Mr. Ovitipana
A1005 KICK-OFF MEETING & SCOPE VALIDAT ION ( SRI L ANKA) 01-Oct-15
Milestone AF-117258/00
Page 1 of 6
SRI LANKA JET A1 FUEL PIPELINE FROM MUTHURAJAWELA TO BIA
KATUNAYAKE & 3 TANKS
A1170 TYPICAL TIME SCHEDULE FOR THE EPC PROJECT 06-Jan-16 20-Jan-16
FRAMEWORK
A1180 PRE-FEASIBILITY STUDY (ROUTING OPTIONS 01-Oct-15 23-Oct-15
EVALUATION)
A1190 FEASIBILITY STUDY FOR JET A1 FUEL PIPELINE FROM 12-Oct-15 11-Dec-15
MUTHURAJAWELA TO BIA KATUNAYAKE & 3 TANKS
A1200 FEASIBILITY STUDY FOR LOGISTIC LINKING VIA PIPELINE 12-Oct-15 11-Dec-15
Milestone AF-117258/00
Page 2 of 6
SRI LANKA JET A1 FUEL PIPELINE FROM MUTHURAJAWELA TO BIA
KATUNAYAKE & 3 TANKS
Milestone AF-117258/00
Page 3 of 6
SRI LANKA JET A1 FUEL PIPELINE FROM MUTHURAJAWELA TO BIA
KATUNAYAKE & 3 TANKS
A1595 TYPICAL D RAWINGS FOR PIPING & MECHANICAL ITEMS 01-Jan-16 29-Jan-16
Milestone AF-117258/00
Page 4 of 6
SRI LANKA JET A1 FUEL PIPELINE FROM MUTHURAJAWELA TO BIA
KATUNAYAKE & 3 TANKS
Milestone AF-117258/00
Page 5 of 6
SRI LANKA JET A1 FUEL PIPELINE FROM MUTHURAJAWELA TO BIA
KATUNAYAKE & 3 TANKS
Milestone AF-117258/00
Page 6 of 6