Konsultan PEMERINTAH PROP.

SUMATERA BARAT Pembangunan Jalan


DINAS PRASARANA JALAN Pantai Purus Cs
Jln. Arau No. 86 Telp. ( 0751 ) 21108 Padang

Tanggal Test : Des 2008


Kontraktor Jns Pekerjaan :
TACK COAT
PT. L M K P - MRM KSO Jns Material :
Lokasi :

JOB MIX FORMULA


TACK COAT

Proportion 25 PPH
( 25 Part of Kerosin per 100 of Bitumen )

Volume Percentase ( % ) Volume ( ltr ) Specific Gravity Weight ( kg )


( ltr ) Kerosin Asphalt Kerosin Asphalt Kerosin Asphalt Kerosin Asphalt

50 10 40 7.89 41.20

100 20 80 15.78 82.40

200 40 160 31.56 164.80

500 0.200 0.800 100 400 0.789 1.03 78.90 412.00

1000 200 800 157.80 824.00

1500 300 1200 236.70 1236.00

2000 400 1600 315.60 1648.00

Approved By, Checked By, Tested By,


Bina Marga Konsultan Konsultan
Tgl Tgl Tgl
Konsultan PEMERINTAH PROP. SUMATERA BARAT Pembangunan Jalan
DINAS PRASARANA JALAN Pantai Purus Cs
Jln. Arau No. 86 Telp. ( 0751 ) 21108 Padang

Tanggal Test : Des 2008


Kontraktor Jns Pekerjaan :
TACK COAT
PT. L M K P - MRM KSO Jns Material :
Lokasi :

CALCULATION OF SPESIFIC GRAVITY


TACK COAT
Proportion 25 pph
( 25 part of kerosine per 100 of bitument

Komposisi campuran tack coat.

1 Bitument = ( 100 / 125 ) * 100 % = 80.00 %


2 Kerosine = ( 25 / 125 ) * 100 % = 20.00 %

Spesific gravity

1 Sp Gr Bitument 60 / 70 = 1.03
2 Sp Gr Kerosine = 0.789

Spesific gravity of mix.

100
80 + 20 = 0.971 gr/cc
1.03 0.789

Composition by volume of total mix.

1 Bitument = 80
x 0.971 = 75.42
1.03

2 Kerosine = 20
x 0.971 = 24.61
0.789

Modification of gravity of mix

1 Bitument = 75 x 1.03 = 77.25

2 Kerosine = 25 x 0.789 = 19.73

Approved By, Checked By, Tested By,


Bina Marga Konsultan Konsultan
Tgl Tgl Tgl
Konsultan PEMERINTAH PROP. SUMATERA BARAT Pembangunan Jalan
DINAS PRASARANA JALAN Pantai Purus Cs
Jln. Arau No. 86 Telp. ( 0751 ) 21108 Padang

Tanggal Test : Des 2008


Kontraktor Jns Pekerjaan :
TACK COAT
PT. L M K P - MRM KSO Jns Material :
Lokasi :

CALCULATION OF SPESIFIC GRAVITY


TACK COAT
Proportion 25 pph
( 25 part of kerosine per 100 of bitument

Komposisi campuran tack coat.

1 Bitument = 75.00 %
2 Kerosine = 25.00 %

Spesific gravity

1 Sp Gr Bitument 60 / 70 = 1.03
2 Sp Gr Kerosine = 0.789
3 Sp Gr Tack Coat ( Gabungan = 0.971 gr/cc.

Rate application of bitument = Untuk jalan baru / licin max. 0,15 ltr/m2
= Untuk jalan lama / berporos max. 0,35 ltr/m2
Temperatur in site = 120 ± 10 0C