CISTERNA:
Tipo de block: 0.20 mt.
Ancho interno: 2.65 ml.
Largo interno: 3.00 ml.
Altura interno: 2.40 ml.
Ancho externo: 3.05 ml.
Largo externo: 3.40 ml.
Altura total: 2.95 ml.
Espesor losa de fondo: 0.20 mt.
Espesor losa de techo: 0.15 ml.
h flotador de cisterna: 0.30 mt.
Espesor de telford: 0.20 mt.
Sobre ancho para excavación: 0.30 mt.
h dentellón de vigas H.A. 0.25 mt.
h viga de amarre perimetral: 0.20 mt.
Capacidad de la cisterna: 4,407 mt.
1.1 REPLANTEO
a Replanteo 1.00 p.a. $2,000.00
TOTAL RD$
TOTAL RD$
TOTAL RD$
TOTAL RD$
TOTAL RD$
.-
il 02, 2019
VALOR
$2,000.00
2,000.00
$9,826.90
$4,125.00
$14,630.68
$3,066.00
31,648.57
$24,671.38
$12,080.21
$16,922.51
36 EXTERIOR
$17,393.36
71,067.46
$49,534.38
$1,931.60
$7,835.32
$2,049.90
$4,044.05
65,395.25
170,111.29
$17,451.26
$19,421.62
$5,000.00
$5,081.67
$6,000.00
52,954.55
223,065.84
LISTADO DE INSUMOS PROMEDIO.-
EQUIPOS DE CONTRUCCION.-
Pala cuadrada "Tramontina" 1.00 unidad $352.64
Pico c/mango "Tramontina" 1.00 unidad $527.22
MADERAS.-
Madera pino americano bruta - 1" x 4" 1.00 pie2 $55.00
Madera pino americano cepillada - 1" x 4" 1.00 pie2 $55.00
COMBUSTIBLES.-
Gasolina regular, fecha: 13-04-2018 1.00 galón $223.20
ALBAÑILERIAS.-
Escoba 1.00 unidad $20.00
AGREGADOS.-
Arena fina (para pañete) 1.00 mt3 $1,000.00
Arena gruesa "Itabo" (de mina) 1.00 mt 3
$900.00
Arena gruesa "Itabo" lavada (de planta) 1.00 mt3 $1,100.00
Gravilla 3/4" @ 1/2" triturada 1.00 mt3 $1,100.00
BLOQUES DE HORMIGON.-
Bloque de 0.20 mts. (8") "Ochoa" 1.00 unidad $35.00
OMEDIO.-
I.T.B.I.S 18.00%
$352.64
$527.22
$5.00
$180.00
$310.00
$55.00
$55.00
$223.20
$20.00
$1,000.00
$900.00
$1,100.00
$1,100.00
$35.00
LISTADO MANO DE OBRA
MANO DE OBRA GENERAL.-
NO. PARTIDA
TARIFA DE ALBANILERIA.-
ALB-001 Trabajador no calificado (TNC)
ALB-002 Trabajador calificado (TC)
ALB-003 Ayudante de albañilería (AY)
ALB-004 Albañil de tercera categoría (AT) - operario
ALB-005 Albañil de segunda categoría (AS) - operario
ALB-006 Albañil de primera categoría (AP) - operario
ALB-007 Maestro de albañilería (MA) - maestro de cada una de las áreas
COSTO
NO. PARTIDA
UNIT. RD$
MUROS DE BLOQUES.-
1 Bloque de 8 x 8 x 16 pulgs. $18.19
2 Llenado de huecos de bloques, bastones a 0.20 mts. $5.46
3 Corte y amarre de varillas en bloques, bastones a 0.20 mts. $2.19
COSTO
NO. PARTIDA
UNIT. RD$
EMPAÑETE Y TERMINACION DE PAREDES Y PLAFONES.-
1 Fraguache con escoba $19.76
2 Pañete pulido sin color $143.55
COSTO
NO. PARTIDA
UNIT. RD$
TERMINACION DE TECHOS E IMPERMEABILIZACION.-
1 Zabaleta en pisos $40.63
2 Fino en techo horizontal sin incluir subida de materiales $114.27
COSTO
NO. PARTIDA
UNIT. RD$
TARIFA DE VARILLA.-
1 Varillas trabajada $289.89
Dinteles y vigas de amarre con altura máxima no mayor de 40 x 20
2 $94.62
cms., (varillas Ø 1/2" Ø 3/4")
COSTO
NO. PARTIDA
UNIT. RD$
TARIFA DE CARPINTERIA.-
VIGAS DE AMARRE.-
1 Encofrado en viga de amarre (0.20 x 0.20) mts., A.T.C. $250.00
LOSAS.-
1 Encofrado de losa (e = 0.13) mts., A.T.C. $260.00
COSTO
NO. PARTIDA
UNIT. RD$
ACARREOS.-
1 Arranque $18.29
2 Regado y nivelado de relleno de reposición $76.00
3 Acarreo de materiales (distancia desde 0.00 kms., hasta 5.00 kms.). $21.34
COSTO
NO. PARTIDA
UNIT. RD$
ACARREOS y SUBIDAS DE MATERIALES-
1 Acarreo interno en bloques de 0.20 mts. $1.38
COSTO
NO. PARTIDA
UNIT. RD$
ANDAMIOS.-
1 Confección de andamios interiores $0.23
COSTO
NO. PARTIDA
UNIT. RD$
LABORES VARIAS.-
1 M.O. mezclado $200.00
E OBRA
NERAL.-
FECHA: 11/28/2017
RESOLUCION
18/2017
UNIDAD DE COMPOSICION VALOR
RENDIMIENTO
MEDIDA BRIGADA RD$/Día
UNIDAD DE
MEDIDA
quintal
ml.
UNIDAD DE
MEDIDA
ml.
mt2
UNIDAD DE
MEDIDA
km.
mt3
mt3n/km.
UNIDAD DE
MEDIDA
unidad
UNIDAD DE
MEDIDA
mt2
UNIDAD DE
MEDIDA
mt3
TARIFA DE EQUIPOS PARA LA
CONSTRUCCION.-
EQUIPOS ALQUILER TARIFA UNIDAD COSTO/DIA COSTO/HORA
Ligadora de 2 fundas $4,000.00 día $4,000.00 $500.00
TARIFA DE EQUIPOS PESADOS PARA LA CON
MOTONIVELADORAS
140 H 165 $2,100.00 $2,478.00
(GREDER)
12 H 140 $1,825.00 $2,153.50
12G-CAT 135 $1,606.70 $1,895.91
GD-37-KOM 125 $1,825.00 $2,153.50
12F-CAT 125 $1,498.55 $1,768.29
120-OG-CAT 125 $1,483.10 $1,750.06
12E-CAT 115 $1,220.47 $1,440.15
14 G 220 $1,767.37 $2,085.50
16 275 $1,944.10 $2,294.04
12-8T-CAT 100 $1,019.63 $1,203.16
CARGADORES
988B-CAT 375 $3,600.45 $4,248.53
FRONTALES
980C-CAT 270 $2,966.21 $3,500.13
980-CAT 235 $2,827.17 $3,336.06
966 G 235 $2,827.17 $3,336.06
966 F 220 $2,600.00 $3,068.00
960 F 200 $2,500.00 $2,950.00
966D-CAT 200 $2,564.53 $3,026.15
966C-CAT 170 $2,240.11 $2,643.33
60C-TEREX 168 $1,992.92 $2,351.65
530-INTER 160 $1,977.47 $2,333.41
950B-CAT 155 $1,884.78 $2,224.04
936 E 135 $1,725.25 $2,035.80
950-CAT 130 $1,637.59 $1,932.36
CARGADORES
W70-KOM 105 $1,498.55
FRONTALES $1,768.29
930-CAT 100 1390.41 $1,640.68
510-INTER 85 $1,235.92 $1,458.39
920-CAT 80 $1,220.47 $1,440.15
MINICBOBCAT 54 $700.00 $826.00
CARGADORES DE
D755-KOM 200 $2,085.62 $2,461.03
ORUGA
977L-CAT 190 $2,023.62 $2,387.87
955L-CAT 130 $1,699.39 $2,005.28
955K-CAT 115 $1,405.86 $1,658.91
COMPACTADORES Y
825C-CAT 310 $2,641.78 $3,117.30
RODILLOS
ESTATICOS 815-CAT 200 $2,209.21 $2,606.87
DW-20A-CAT 300 $1,326.61 $1,565.40
CAT-45BUF 150 $1,251.37 $1,476.62
LISO GALION $250.00 $295.00
MOV-1 Excavación material inservible con retro excavadora (hasta 1.50 mts. de profundidad)
Retro Excavadora, 320-CAT costo/mt3n =
rend. = 35 mt3/hr
Arranque costo/mt3n =
coef. esponj. = 1.15
COSTO UNIT.
TOTAL/P.U.
RD$
mts. de profundidad)
$155.84
$40.25
$21.03
costo/mt3n $217.12
$60.46
$18.29 $91.45
$21.34 $106.70
costo/mt3e $258.61
$352.64 $3.53
$527.22 $5.27
$900.00 $900.00
$76.00 $91.20
$50.00 $50.00
costo/mt3 $1,050.00
LISTADO MANO DE OBRA
ANALISIS DE COSTOS.-
MEZCLAS o MORTEROS.-
UNIDAD DE COSTO
NO. PARTIDA CANTIDAD
MEDIDA UNIT. RD$
$3,568.10
$945.00
$345.20
$210.00
$5,068.30
$3,568.10
$1,155.00
$345.20
$210.00
$5,278.30
$2,002.60
$1,008.00
$338.60
$210.00
$3,559.20
$2,932.60
$910.00
$1,132.20
$226.20
$210.00
$5,411.00
ANALISIS PRECIOS UNITARIOS.-
ANALISIS DE COSTOS.-
HORMIGONES SIMPLE.-
UNIDAD COSTO
NO. PARTIDA CANTIDAD DE
MEDIDA UNIT. RD$
Mano de obra:
1 Albañil de primera categoría (AP) (1) 1.00 hora $170.50
2 Ayudante de albañil (AY) (1) 1.00 hora $92.08
3 Trabajador no calificado (TNC) - peones (4) 1.00 hora $71.58
Sub-total de mano de obra:
Equipos:
1 Ligadora de 2 fundas 1.00 hora $500.00
Sub-total de equipos:
Herramientas: 5% M.O.:
Total de equipos:
costo/mt3
Mano de obra:
1 Albañil de primera categoría (AP) (1) 1.00 hora $170.50
2 Ayudante de albañil (AY) (1) 1.00 hora $92.08
3 Trabajador no calificado (TNC) - peones (4) 1.00 hora $71.58
Sub-total de mano de obra:
Equipos:
1 Ligadora de 2 fundas 1.00 hora $500.00
Sub-total de equipos:
Herramientas: 5% M.O.:
Total de equipos:
costo/mt3
S.-
TOTAL/P.U.
$2,334.30
$572.00
$803.00
$273.25
$3,982.55
$170.50
$92.08
$286.32
$548.90
$313.66
$500.00
$285.71
$27.44
$313.16
$4,609.36
$2,771.40
$561.00
$770.00
$256.10
$4,358.50
$170.50
$92.08
$286.32
$548.90
$313.66
$500.00
$285.71
$27.44
$313.16
$4,985.31
ANALISIS DE COSTOS.-
Hoja No. 1 Fecha:
VALOR
$5,483.85
$2,254.00
$88.20
$284.09
$14.00
$324.97
$8,449.10
$5,483.85
$2,783.00
$108.90
$350.77
$1,734.20
$418.43
$10,879.14
$5,234.58
$3,174.00
$667.00
$150.30
$484.12
$388.40
$10,098.40
78.00 ml.
78.00 ml.
78.00 ml.
$5,483.85
$3,096.15
$4,129.50
$282.74
$2,365.50
$6,250.00
$864.31
$22,472.05
ANALISIS PRECIOS UNITARIOS.-
ANALISIS DE COSTOS.-
ANALISIS ALBAÑILERIA.-
UNIDAD COSTO
NO. PARTIDA CANTIDAD DE
MEDIDA UNIT. RD$
ANDAMIOS.
AND-1 Andamios interiores.
1 Madera pino americano bruta - 1" x 4" 0.182 pie2 $55.00
2 M.O. confección de andamios interiores 1.00 mt2 $0.23
3 Herramientas (5%) 5.00 % $0.51
costo/mt2
OS.-
TOTAL/P.U.
$10.01
$0.23
$0.51
$10.75
ANALISIS PRECIOS UNITARIOS.-
ANALISIS DE COSTOS.-
ANALISIS ALBAÑILERIA.-
UNIDAD DE
NO. PARTIDA CANTIDAD
MEDIDA
MUROS DE HORMIGON.-
MUR-1 Muros de block 0.20 mts. c/cruce Ø 3/8" @ 0.20 mts. B.N.P. (sin serpentinas).
1 Bloques de 0.20 mts. (8") "Ochoa", + 4% desp. 13.00 unidad
Acero estructural Ø 3/8" x 20' - G40° + 0.40 mts., solape
2 0.089 quintales
y traslape
3 Alambre galvanizado #18 - (2 libras/qq) 0.178 libras
4 Mezcla 1:3 0.039 mt3
5 Hormigón simple Fc' = 140 kg/cm2 (con ligadora) 0.089 mt3
6 M.O. colocación en bloques de 8 x 8 x 16 pulgs. (8") 13.00 unidad
M.O. llenado de huecos de bloques, bastones a 0.20
7 13.00 unidad
mts.
M.O. corte y amarre de varillas en bloques, bastones a
8 13.00 unidad
0.20 mts.
9 Acarreo de block 8" "Ochoa" 13.00 unidad
10 Herramientas (5%) 5.00 %
TERMINACION DE SUPERFICIE.
TER-1 Pañete en muros y H.A. - pulido (interior).
1 Madera pino americano cepillada - 1" x 4" 0.033 pie2
2 Mezcla 1:1.5:5 (pañete) 0.022 mt3
M.O. pañete en muros interiores, maestriado y a plomo.
3 1.00 mt2
(pulido)
4 M.O. andamios interiores 1.00 mt2
5 Herramientas (5%) 5.00 %
COSTO UNIT.
TOTAL/P.U.
RD$
rpentinas).
$35.00 $455.00
$2,300.00 $204.70
$45.00 $8.01
$5,068.30 $197.66
$4,609.36 $410.23
$18.19 $236.41
$5.46 $70.92
$2.19 $28.46
$1.38 $17.94
$80.57 $402.85
costo/mt2 $2,032.18
$55.00 $1.82
$5,411.00 $119.04
$143.55 $143.55
$10.75 $10.75
$13.76 $13.76
costo/mt2 $288.91
$20.00 $0.20
$3,559.20 $28.47
$19.76 $19.76
$10.75 $10.75
$2.95 $2.95
costo/mt2 $61.93
$5,278.30 $52.78
$40.63 $40.63
$4.67 $4.67
costo/ml. $98.08
$55.00 $0.72
$5,278.30 $369.48
$114.27 $114.27
$24.22 $24.22
costo/mt2 $508.69