Documente Academic
Documente Profesional
Documente Cultură
A dummy activity is a simulated activity of sorts, one that is of zero duration and is
created for the sole purpose of demonstrating a specific relationship and path of
action on the arrow diagramming method. Dummy activities are a useful tool to
implement when the specific logical relationship between two particular activities
on the arrow diagramming method cannot specifically be linked or conceptualized
through simple use of arrows going from one activity to another. In this case, the
creation of a dummy activity, which serves essentially as a form of a placeholder, can
provide exceedingly valuable. Dummy activities should in no cases be allocated any
duration of time in the planning and/or scheduling or project activities and
components.
3. Project Inventory: Living in a world of projects may feel like living in a WHIRL of
projects. Small projects, large projects. Some projects using external resources. Projects
for revenue, and others for cost saving. As projects come and go, how do we keep track
of them? And what do we keep track of?
A project inventory is a list of active projects with information that can include planned
start and finish dates, the name of the project leader, project priorities, budget totals,
project ID numbers and other key project characteristics.
While Project Inventory makes it sound like a complex process, it is simply a list of all active and
planned projects for an organisation. So for Project Inventory you can think “list of projects”. So
the simple objective of the Project Inventory is to capture all of the active and planned projects
in a single list.
Page 1 of 5
Constructing the Project Inventory
The PMO should take the lead on constructing the project inventory. The approach can be:
Pull – ask all of the project teams to submit details of change projects
Push – create a central list and then send to project teams to review and validate
If possible I would lean towards the “Push” approach as it demonstrates that the PMO is trying
to add value by taking on what work it can and then, only asking projects teams where they
cannot complete the task. This will create a positive reaction as opposed to the PMO being seen
as simply making requests of the project teams and offering no support.
The reason this is important is that the project teams should be busy focusing on delivering the
projects. Therefore, a smart PMO will try to avoid making any requests that they can perform
themselves without diverting the attention of the project teams.
Collecting the above information should provide all of the information to give a high level
understanding of the project. With this information, senior management are able to make
decisions on the change portfolio.
Having the information in a spreadsheet, it is possible to total the budget column, sort by
Investment Type, allowing for the cost of mandatory projects to be calculated and compared
against available budget. This then will provide how much budget is available for discretionary
projects.
Page 2 of 5
4. Project Overrun: Project overrun consists of two elements;
Cost Overrun and Time Overrun
A cost overrun, also known as a cost increase or budget overrun, involves unexpected
incurred costs. When these costs in are in excess of budgeted amounts due to an
underestimation of the actual cost during budgeting, they are known by these terms.
Unplanned Costs: Some costs may occur suddenly, e.g. cost due to an accidental damage
Changes in Project Scope: Chang (increase) in scope will warrant extra cost
Unrealistic Cost Estimates: Too little estimates will automatically be overrun.
Inadequate Financing: if financing dries up in the middle of a project, the project may
get delayed and cost may escalate
Lack of Leadership Experience: Ineffective leadership may result in loss of resources,
causing cost escalation.
Lack of funding: Due to unavailability of funds, works may stop and project may get
delayed.
Calamities: Due to natural/other calamities, the duration of project may get lengthened.
Legal compliance: Due to increased legal requirements, project may get delayed.
Shortage of resources: Due to short supply/unavailability of resources (manpower, raw
material, power) project work may get delayed.
Lack of coordination among team members of a project may also lead to delay in
completion.
PERT is an acronym for Program (Project) Evaluation and Review Technique, in which planning,
scheduling, organizing, coordinating and controlling uncertain activities take place. The
technique studies and represents the tasks undertaken to complete a project, to identify the
least time for completing a task and the minimum time required to complete the whole project.
It was developed in the late 1950s. It is aimed to reduce the time and cost of the project.
PERT uses time as a variable which represents the planned resource application along with
performance specification. In this technique, first of all, the project is divided into activities and
events. After that proper sequence is ascertained, and a network is constructed. After that time
needed in each activity is calculated and the critical path (longest path connecting all the events)
is determined.
Definition of CPM
Developed in the late 1950s, Critical Path Method or CPM is an algorithm used for planning,
scheduling, coordination and control of activities in a project. Here, it is assumed that the
Page 3 of 5
activity duration is fixed and certain. CPM is used to compute the earliest and latest possible
start time for each activity.
The process differentiates the critical and non-critical activities to reduce the time and avoid the
queue generation in the process. The reason for the identification of critical activities is that, if
any activity is delayed, it will cause the whole process to suffer. That is why it is named as
Critical Path Method.
In this method, first of all, a list is prepared consisting of all the activities needed to complete a
project, followed by the computation of time required to complete each activity. After that, the
dependency between the activities is determined. Here, ‘path’ is defined as a sequence of
activities in a network. The critical path is the path with the highest length.
11. PERT is best for research and development projects, but CPM is for non-research
projects like construction projects.
12. Crashing is a compression technique applied to CPM, to shorten the project duration,
along with the least additional cost. The crashing concept is not applicable to PERT.
Page 4 of 5
Accounting Break-even Point vs. Financial Break-even Point
There are several differences between accounting break-even point and financial break-even
point.
Accounting break-even point, on the one hand, is the easiest and most common method of
analyzing profits. It is easily calculated by taking the total expenses on a particular production
and computing how many units of the product need to be sold in order to cover the expenses.
Financial break-even point, on the other hand, is more complicated to measure because it
uses different measurements, even though it is the same concept. It doesn’t address a product or
units but a company’s earnings, specifically about how much it needs to earn in order that
its earnings per share are equal to zero. Earnings mean the gross amount of money earned by
the company before taxes and expenses are taken out.
Formula:
Financial breakeven point attempts to find EBIT that results in zero net income. The
relationship between EBIT and net income can be expressed as follows:
Net Income
= EBIT × (1 − Interest Expense) × (1 − Tax Rate) − Preferred Dividends
Financial breakeven point attempts to find EBIT that results in zero net income.
0 = EBIT × (1 − Interest Expense) × (1 − Tax Rate) − Preferred Dividends
Rearranging the above equation, we get the following formula to find the financial breakeven
(i.e. EBIT level that results in zero net income)
Example
You company has $100 million preferred stock issue paying 5% per annum, total interest
expense of $10 million, interest income of $1 million and tax rate of 33%. Calculate your
company’s financial breakeven point.
We need to find the earnings before taxes needed to cover the preferred dividend payments
taxes and interest expense.
Preferred dividends will amount to $5 million (=$100 million × 5%). Net interest expense is $9
million ($10 million - $1 million).
Plugging the above values in the equation for financial breakeven point, we get the following:
(5/1-.33) +9 = 16.58
Page 5 of 5