ESTIMACION
CODIGO : 20132660B
NOTA :
HOLGURAS DE PERT
Tiempo Tiempo
Actv. Duración
optimista pesimista HT HL HI COND.
i-j t ij toi toj t+i t*j
1-2 3 0 3 0 3 0 0 0 C
1-4 42 0 42 0 174 132 0 0 NC
1-8 30 0 71 0 71 41 41 41 NC
2-3 6 3 9 3 9 0 0 0 C
3-5 6 9 15 9 15 0 0 0 C
4-16 0 42 174 174 174 132 132 0 NC
5-6 28 15 43 15 43 0 0 0 C
5-7 14 15 29 15 71 42 0 0 NC
6-8 28 43 71 43 71 0 0 0 C
7-8 0 29 71 71 71 42 42 0 NC
8-9 30 71 101 71 101 0 0 0 C
8-10 30 71 101 71 106 5 0 0 NC
8-11 30 71 101 71 106 5 0 0 NC
9-14 25 101 126 101 126 0 0 0 C
10-14 20 101 126 106 126 5 5 0 NC
10-13 20 101 121 106 126 5 0 0 NC
11-12 20 101 121 106 126 5 0 0 NC
12-14 0 121 126 126 126 5 5 0 NC
13-14 0 121 126 126 126 5 5 0 NC
14-15 23 126 149 126 149 0 0 0 C
15-16 25 149 174 149 174 0 0 0 C
TABLA DE ESTIMACIONES DE TIEMPO
te = (25+112+31)/6 = 28 σ2 = ((31-25)/6)2 = 1
Actividad G
te = (25+112+31)/6 = 28 σ2 = ((31-25)/6)2 = 1
Actividad H
te = (17+80+23)/6 = 20 σ2 = ((23-17)/6)2 = 1
Actividad N
te = (17+80+23)/6 = 20 σ2 = ((23-17)/6)2 = 1
Actividad Ñ
te = (17+80+23)/6 = 20 σ2 = ((23-17)/6)2 = 1
Actividad O
Para Z = + 1.97 se tiene una probabilidad del 94,52 % para el plazo previsto.