Sunteți pe pagina 1din 1

Format No : TPKTI/JBF/SITE -03

FIELD CHANGE NOTICE


Owner: J BF Petroc hemicals Limited Date:

Technip Project No.: 0830 Area I Job details :

Contractor Job No.: Ref. No.: 0830/ FCN/

1 . SUBJECT:

2. REASON FOR CHANGES :

0 Alternate action already taken due to Hold in drawing


0 Owners request
0 Wrong shipment or fabrication by vendor
0 P & ID Field Change Follow-up
0 Obstructed with adjacent foundation I structure due to overlapping
0 Constructability related change notice
0 Wrong Construct ion I installation at site
0 Any Others - Refer enclosed note

3. CONSTRUCT ION STAT US:

0 Before Fabrication 0 Before Installation


0 After Fabrication 0 After Installation
0 Under Fabrication 0 Under Installation

4. Revised IFC Drawing Required - YES/NO


As Build to be Done by (name of Contractor) - I NO

5. DESCRIPTION OF CHANGES :

6.ATTACHMENT:

7. SIGNATURE (Sign/Name/Date) :

INITIATED By I PROPOSED(TP) CHECKED & VALIDATED By (T P) APPROVED BY (JBF)

S-ar putea să vă placă și