Introduction :
ƒ Pressure Test is performed or conducted when
there are new or old operating equipment like
Boilers, Heat Exchangers, Pipe Connections and
other pressure vessels installed.
ƒ All pressure vessels must go through the pressure
test before they are permitted to operate.
ƒ In Malaysia, there are the regulation enforced by
Malaysian Authority under the Department of
Occupational Safety and Health (DOSH).
ƒ There are 2 pressure tests performed :-
Pressure Leak Test
Pressure Strength Test - commonly known
as Hydrostatic Test.
PRESSURE TEST cont :-
Objectives :
ƒ Test Pressure :
ƒ This is manufacturer recommended hydrostatic pressure
Pressure Rating (psi) 150 300 400 600 900 1500 2500
Hydrostatic Test (psi) 450 1100 1450 2175 3250 5400 9000
PRESSURE TEST cont :-
Hydrostatic Test Procedure on Pipes :
7 Open the shut off cock and operate the test pump until
water overflows from the pressure gauge connection
(BLEEDING PROCESS).
8 Fit the pressure gauge.
9 Operate the test pump until the pressure gauge indicates the
specified test pressure.
10Inspect for leaks in the pipeline at the flange joint, as well as
the pipe system in general.
11Release the pressure from the pipeline through the test
pump discharge cock.
12Disconnect the test pump and drain the pipeline through the
shut off cock.
13Remove the blank flanges and dismantle the pipe joints.
PRESSURE TEST cont :-
Hydrostatic Test Procedure on Pipes (cont):
PRESSURE TEST cont :-
Safety Requirements :
ƒ Safety Requirements :-
1Depressurising the equipment after inspection
and the test has been approved must be done by
releasing the pressure slowly through the vent
and drain valves.
2The vent valve needs to be opened to release
pressure and yo admit air when draining to
prevent collapsing of the system by pulling a
vacuum.
3Never leave equipment an attended at any time
when it is under pressure.
4Always wear safety gear when conducting
hydrostatic test.
PRESSURE TEST cont :-
Safety Requirements cont :