Beam Mark: TWM Xray room stump relocation beam GB3 cantilever part

Rebar OK!!
Deflection OK!!
Es = 205 GPa Shear Slab not ok, Provide minimum shear link, R6-200
Beam Length 1.5 m Ec = 25.74296 GPa
b= 200 mm fcu = 30 N/mm2 K' = 0.156 Beam Section maximum capacity,
h= 450 mm fy = 460 N/mm2 Singly Reinforced
H.s = 50 mm Con. Cover = 40 mm Beam Mc = 63.16684 kNm Concrete = 143.8295 kNm
V.s = 25 mm Link = 10 mm (Singly Reinforced Beam)
d= 392 mm fyv = 250 N/mm Opening n Doubly reinforced (max comp bar 2%, ten. bar 4%)
Bar = T 16 100.0 2 0.446804289 % spacing Opening depth from top= 150 mm Available Ten. Bar = 0.026215 %
As Provided 402 mm2 (1 row reinforcement ) max capacity = 420.7127 kNm

Comp Bar = T 0 #DIV/0! 0 Bar spacing = 68 mm


As' Provided 0 mm2 Comp. Bar = #DIV/0! mm
0% 0
0
M= 45 kN.m 0
k= 0.0488078 As' =
z= 0.942458 d 369.4436 As =
As = 278.72953 mm2 bar diameter= 18.83851 mm
As min= 117 mm2

M/bd2 = 1.4642337 N/mm 12 - 100 2


fs = 212.564 N/mm
Mt = 1.4820709

100As'/bd = 0 0.2mm Crack width (Based on 1 layer bar)


Mc = 1 #DIV/0! acr = 64.03 mm
αe = Es/(Ec/2) (0.5 allowance for creep)
= 15.93 mm
Basic ratio 7 x= 129.63 mm
Allowed Span over effective depth ratio = 10.37449615 f s = Ms/(As(d-x/3)
Actual Span over effective depth ratio = 3.826530612 OK!! = 320.8397 N/mm2 < 130N/mm2

V= 48 kN Concrete reduction at maximum shear = 0 mm #DIV/0!


v= 0.6122449 MPa

vc= 0.5403302 OK!! Provide minimum shear link, R6-200

2593.797