Documente Academic
Documente Profesional
Documente Cultură
Department of MBA
I.M.S ENGINEERING COLLEGE, GHAZIABAD
Affiliated to APJ Abdul Kalam technical university, Lucknow
Session-2017-2019
i
CERTIFICATION OF APPROVAL
This is to certify that Ms. /Mr. PRIYANKA Roll No. 1714370028 is a bonafide student of MBA
3rd semester during session 2018-19. The summer training project report entitled “A STUDY
ON IMPACT OF GOODS AND SERVICES TAX {GST} ON REAL ESTATE SECTOR”
has been prepared by him/her in partial fulfillment for the award of degree of Master of Business
Administration of Dr. A.P.J. Abdul Kalam Technical University, Lucknow (formerly UPTU
Lucknow).
ii
DECLARATION FORM
I hereby declare that the Summer Internship Project Work entitled, STUDY ON IMPACT OF
GOODS AND SERVICES TAX (GST) ON REAL ESTATE SECTOR submitted by me,
PRIYANKA, Roll No.. 1714370028, for the partial fulfillment of the master of business
administration (M.B.A) to IMS Engineering College, Ghaziabad is my own original work and
has not been submitted to A.K.T.U. University for the fulfillment of the requirement for any
course of study. I also declare that no chapter of this manuscript in whole or in part is lifted and
incorporated in this report from any earlier / other work done by me or others.
Priyanka
Roll No -1714370028
iii
ACKNOWLEDGEMENT
I would like to express my deepest appreciation to all those who provided me the possibility to
complete this project report. A special gratitude I give to Mrs. Punjika Rathi whose
contribution in stimulating suggestions and encouragement helped me to coordinate my project
especially in completing this report.
I am very thankful for her invaluable guidance, support, and affable & friendly nature. She
guided me at each and every stage of project.
I am equally indebted to my dear Parents; Good friends who always inspired and motivated me
to do something better throughout this project.
At last I would like to thanks to every person to whom I have visited for giving their support and
valuable information, which helps me in completing my project work.
Priyanka
iv
TABLE OF CONTENTS
1. CHAPTER-1
INTRODUCTION 1-41
2. CHAPTER-2
3. CHAPTER-3
4. CHAPTER-4
5. CHAPTER-5
6. CHAPTER-6
FINDINGS 92-93
CONCLUSION 94
7. CHAPTER-7
BIBLIOGRAPHY 97-98
8. CHAPTER-8
ANNEXURE 99-101
CHAPTER-1
INTRODUCTION
1
GOODS AND SERVICES TAX
2
CONCEPT OF GOODS AND SERVICES TAX
Meaning of GST
Clause 366(12A) of the Constitution Bill defines GST as “goods and services tax” means any tax
on supply of goods, or services or both except taxes on the supply of the alcoholic liquor for
human consumption. Further the clause 366(26A) of the Bill defines “Services” means anything
3
other than Goods. Thus it can be said that GST is a comprehensive tax levy on manufacture, sale
and consumption of goods and services at a national level. The proposed tax will be levied on all
transactions involving supply of goods and services, except those which are kept out of its
purview.
HISTORY OF G.S.T.
Atal Bihari Vajpayee, the 10th Prime Minister of India, was the first to recommend the idea of
adopting GST during his time in office, in the year 2000. An Empowered Committee was formed
by the state finance ministers at the time, and their aim was to formulate a structure for GST as
they already had experience in creating State VAT. The Centre as well as the State had
representatives who were urged to examine several different aspects of the proposal so as to
come up with reports on the taxation of services, taxation of inter-state supplies, thresholds, and
exemptions. The Finance Minister of West Bengal at the time, Asim Dasgupta, headed the
The advisory to the Finance Ministry between 2002 and 2004, Vijay Kelkar, led a task force and
sent a report to the Ministry in 2004, highlighting the issues with the then tax structure, adding
During his third term as the Finance Minister of India, P. Chidambaram said in 2005 that the
across India and cover the entire production-distribution chain. As a result, a discussion
4
regarding the same took place in the Budget Session in FY 2005-06, and 1 April, 2010, was set
The advisor to Chidambaram, Parthasarathy Shome, said that preparations by the state to make
reforms may take time, but the deadline to implement the regime was retained at 1 April, 2010,
in the Union Budget 2007-08. Chidambaram confirmed that significant progress was being made
by the states to prepare for the implementation of GST in the Union Budget 2008-09, and the
In 2009, following the appointment of Pranab Mukherjee as the new Finance Minister of India,
an announcement was made regarding the basic framework of GST, and there was still no
change in the deadline. In late 2009, the Empowered Committee, led by Asim Dasgupta,
presented the First Discussion Paper (FDP), explaining in detail the proposed GST reform. The
foundation for GST, however, was laid by the Mission-Mode Project introduced by the
government. The budgetary outlay of the project was Rs.1,133 crore, and it led to the
computerization of commercial taxes in the various states of India. Following this move, GST
The 115th Amendment to the Constitution saw the Government, headed by Congress, put forth
the bill for the implementation of GST. The bill drew protests from the opposition party and was
then sent for detailed scrutiny to a standing committee. The bill was discussed by the committee
in June 2012, and concerns were raised by the opposition party over clause 279B as it provided
extra powers to the Centre. As a result, Finance Ministers of various states along with the
Finance Minister of India held meetings before setting a deadline to resolve the issues by 31
December, 2012.
5
During the Budget Session in 2013, the Finance Minister made an announcement that states will
receive Rs.9,000 as compensation from the government, appealing to state finance ministers to
cooperate with the government so that an indirect tax regime could be implemented. In the same
year, the standing committee that was created to examine the bill, submitted its report to the
parliament, and the regulation was approved by the panel with a few amendments.
Arun Jaitley, the new Finance Minister of India, revealed in his budget speech in February 2015
that GST would be implemented by 1 April, 2016. However, due to disagreements between
states and parties in addition to legal issues, the implementation of the regime was delayed by
over a year, and on 1 July, 2017, the four GST-related bills, viz. Central GST Bill, Union
Territory GST Bill, Integrated GST Bill, and GST (Compensation to States) Bill became Acts.
The GST council, over time, finalized GST rules and rates, and the Government announced that
GST is a consumption based tax/levy. It is based on the “Destination principle.” GST is applied
GST is collected on value-added goods and services at each stage of sale or purchase in the
supply chain. GST paid on the procurement of goods and services can be set off against that
payable on the supply of goods or services. The manufacturer or wholesaler or retailer will pay
the applicable GST rate but will claim back through tax credit mechanism. But being the last
6
person in the supply chain, the end consumer has to bear this tax and so, in many respects, GST
The GST is an indirect tax which means that the tax is passed on till the last stage wherein it is
the customer of the goods and services who bears the tax. This is the case even today for all
indirect taxes but the difference under the GST is that with streamlining of the multiple taxes the
final cost to the customer will come out to be lower on the elimination of double charging in the
system.
7
Let us understand the above supply chain of GST with an example:
8
G.S.T. MODEL
G.S.T.
Tax
9
How is GST Levied?
10
EXAMPLE:
BASIC CONCEPT OF GST:
Importer to wholesaler
Wholesaler to retailers
PRICE 127500 118000
11
Commodities not subsumed in GST:
Custom duty, stamp duty, vehicle tax, excise on liquor, Tax on Sale
and Consumption of Electricity, road tax, entry taxes and toll,
entertainment tax.
12
SGST and IGST are part of GST, Goods and Service Tax. SGST expands as State Goods
and Service Tax and IGST is the short form of Integrated Goods and Service Tax.
Different indirect taxes like State Sales Tax, VAT, Luxury Tax, Entertainment tax (unless it is
levied by the local bodies), Taxes on lottery, betting and gambling, Entry tax not in lieu of
Octroi, State Cesses and Surcharges in so far as they relate to supply of goods and services etc.
are subsumed with SGST. Under IGST, the taxes for movement of goods and services from one
state to another is collected. The tax revenue collected under SGST is meant for State
Government whereas the tax revenue of IGST is shared between State government and Central
CGST and IGST are part of GST, Goods and Service Tax. CGST expands as Central Goods and
Service Tax and IGST is the short form of Integrated Goods and Service Tax. Different indirect
taxes of Central Excise Duty, Central Sales Tax CST, Service Tax, Additional excise duties,
excise duty levied under the medical and toiletries preparation Act, CVD (Additional Customs
duty – Countervailing Duty), SAD (Special Additional Duty of customs) surcharges and cesses
13
are merged with CGST. Under IGST, the taxes for movement of goods and services from one
Major share of tax revenue under CGST is meant for central government where as IGST tax
revenue is shared between State government andCentral government as per the rate fixed by the
authorities.
CGST & SGST are part of GST, Goods and Service Tax.CGST expands as Central Goods and
Service Tax and SGST is the short form of State Goods and Service Tax. Different indirect taxes
of Central Excise Duty, Central Sales Tax CST, Service Tax, Additional excise duties, excise
duty levied under the medical and toiletries preparation Act, CVD(Additional Customs duty –
Countervailing Duty), SAD (Special Additional Duty of customs) surcharges and cesses are
merged with CGST. Under SGST, the taxes like State Sales Tax, VAT, Luxury Tax,
Entertainment tax(unless it is levied by the local bodies), Taxes on lottery, betting and gambling,
Entry tax not in lieu of Octroi, State Cesses and Surcharges in sofar as they relate to supply of
14
goods and services etc. are subsumed. The major share of tax revenue under CGST is meant for
Exempted categories – 0
GST Council:
It will constitute union minister of state in charge of revenue and minister in charge of
finance or taxation or of any other field nominated by state governments. The 2/3rd
a. Taxes, surcharge, cess of central and states which will be integrated in GST.
g. Provision with respect to special category states especially north east states.
15
It may also work as Dispute Settlement Authority for GST.
The Council would consist of 2/3rd representation of states and 1/3rd representation of
the Centre. The GST Council will take all decisions regarding tax rates, dispute
resolution, exemptions and so on. Recommendations of the GST Council (75% votes)
GSTIN:
Next number shows the entity number of the same PAN holder in a state.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
States PAN Entity code
Code /Check digit
16
IMPACT OF GST ON REAL
ESTATE SECTOR
17
Impact of GST on real estate sector-
VAT, Registration Charges, Stamp Duty Charges vary from state to state
Under the erstwhile indirect tax regime, CENVAT Credit on inputs used for the construction of a
18
Taxability of Real Estate Transactions under GST
Tax Tax
Credit
above)
19
On resale properties Not applicable – Not
available
On Land purchase and sale Not applicable. As per Schedule III, sale of land is – Not
Contract
Contract to Government
Authorities
general public
contract – Affordable
20
Housing
* NOTE: The homes purchased under the Credit-Linked Subsidy Scheme (CLSS) attracts 12%
GST rate. The applicable rate will be 8% after cutting the 1/3rd amount towards the cost of land.
Impact on Buyers:
Under the earlier tax regime, buyers had to pay VAT, Service tax, Registration charges & Stamp
duty on purchase of properties under construction. Also since VAT, Registration charges &
Stamp duty were state levies, prices of properties varied from state to state. Moreover,
developers had to pay various duties like sales tax (CST), custom duty, OCTROI etc. for which
Under GST, a single tax rate of 12% is applicable on properties under construction while GST is
not applicable on completed or ready to sale properties which was the case in previous law.
In the short-term, buyers may stick to “wait and watch” approach to gain more understanding on
Also, in the long term, GST will a positive impact on buyers if the benefit of input tax credit
21
Impact on Developers / Builders / Contractors
Under the previous tax regime, developers had to bear Excise duty, VAT, Customs duty, Entry
taxes etc. on raw materials / inputs and Service tax on various input services like approval
charges, architect professional fees, labor charges, legal charges etc. ITC was not available for
duties like CST, Customs duty, Entry Tax etc. This would impact the pricing and subsequently
Under GST, developers’ construction costs are significantly reduced as multiple taxes are
subsumed and due to the availability of input tax credit. Also, reduction in cost of logistics will
On the downside, developers have to do multiple calculations to arrive at ITC in order to pass it
on to the buyers. Hence, in most cases, they can pass on the ITC only during the final stages.
This lack of transparency on ITC, may affect the developers since buyers may resort to “wait and
And, in the erstwhile laws, a large portion of expenditure remained unrecorded in the books.
Under GST, availability of credit on inputs and cloud storage of invoicing has reduced under
recording of expenditure.
The impact on the allied services like labor, material suppliers, service suppliers etc. depends on
the increase or decrease in the tax levied on these goods and services. This will have a
22
For example, earlier cement was taxed at an effective rate of 27-31 percent which will now be
taxed at 18 percent. Increase in cement prices will result in consequential increase in the overall
cost of construction.
GST Rates for some of the goods relating to the construction industry are given below:
Sand 5%
Steel 18%
Paint 18%
Cement 18%
23
GST REGISTRATION & GST
RETURN
24
GST REGISTRATION -
1) Every person who is liable to be registered under Schedule III of this Act, shall apply
for registration in every such State in which he is liable within 30 days from the date of which he
becomes liable to registration, in such manner and subject to such conditions as may be
prescribed.
2) Not withstanding anything contained in sub-section (1), a person having multiple business
verticals in a State may obtain a separate registration for each business vertical, subject to such
3) A person, though not liable to be registered under Schedule III, may get himself registered
voluntary, and all provisions of this Act, as are applicable to a registered taxable person, shall
4) Every person shall have a Permanent Account Number issued under the Income Tax Act,1961
(43 of 1961) in order to be eligible for grant of registration under subsection (1), (2) or (3).
5) Where a person who is liable to be registered under this Act fails to obtain registration, the
proper officer may, without prejudice to any action that is, or may be taken under this Act,
25
6) The registration or the Unique Identity Number, shall be granted or, as the case maybe,
rejected after due verification in the manner and within such periods as may be prescribed.
7) A registration or an Unique Identity Number shall be deemed to have been granted after the
period prescribed under sub-section (7), if no deficiency has been communicated to the applicant
registration under the CGST/SGST Act shall be deemed to be a rejection of application for
9) The Central or State Government may, on the recommendation of the Council, by notification,
specify the category of persons who may be a exempted from obtaining registration under this Act.
26
GST registration page-
27
Amendment of Registration-
a) Every registered taxable person shall inform the proper officer of any changes in the
manner and within such period as may be prescribed. The proper officer may, on the
reject amendments in the registration particulars in the manner and within such period as
may be prescribed, provided that approval of the proper officer shall not be required in
b) The proper officer shall not reject the request for amendment in the registration
particulars without giving a notice to show cause and without giving the person a
c) Any rejection or approval of the amendments under the CGST/SGST Act shall bedeemed
28
GST RETURN
29
GST RETURNS-
Every registered taxable person shall, for every calendar month or part thereof, furnish, in such
form and in such manner as may be prescribed, a return, electronically, of inward and outward
supplies of goods or services, input tax credit availed, tax payable, tax paid and other particulars
as may be prescribed within 20 days after the end of such month:
Provided that a registered taxable person paying tax under the provisions of Section 8 of this Act
shall furnish a return for each quarter or part thereof, electronically, in such form and in such
manners may be prescribed, within 18 days after the end of such quarter:
Every registered taxable person, who is required to furnish a return under sub-section (1) shall
pay to the credit of the appropriate Government the tax due as per such return not later than the
last date on which he is required to furnish such return.
A return furnishes under the sub-section (1) by a registered taxable person without payment of
full tax due as per such return shall not be treated as a valid return for allowing input tax credit in
respect of supplies made by such person. Every registered taxable person shall furnish a return
for every tax period under sub-section (1), whether or not any supplies of goods or services have
been effected during such tax period.
Note: Subject to the provisions of Section 25 and 26, if any taxable person after furnishing a
return discovers any omission or incorrect particulars therein, other than as a result of scrutiny,
audit, inspection or enforcement activity by the tax authorities, he shall rectify such omission in
the return to be filed for the month or quarter, as the case may be, during which such omission is
noticed subject to the payment of interest, where applicable and as specified in the Act:
30
Types of GST Returns
31
1) What is GSTR-1?
GSTR-1 is a monthly return that should be filed by every registered dealer by the 10th of the
following month. It is the first or the starting point for passing input tax credit to the dealers. It
contains details of all outward supplies i.e. sales.
GSTR-1 has to be filed by "all" taxable registered persons under GST. However, there are certain
dealers who are not required to file GSTR-1, instead are required to file other different GST
returns as the case may be. These dealers are E-Commerce operators, Non-Resident dealers and
Tax deductions. It has to be filed even in cases where there is no business conducted during the
reporting month.
The Suppliers need to log in to the GSTN portal with the given User ID and Password, following
these steps:
Search for "Services" and then click on Returns, followed by Returns Dashboard.
In the Dashboard, the dealer has to enter the financial year and the month for which the return
needs to be filed Click on Search after that.
After this, he will have the option either to prepare online or to upload the return.
The dealer will now Add invoices or upload all invoices directly.
Once the entire form is filled up, the dealer shall then Click on Submit and validate the data
filled up.
32
With the data validated, dealer will now click on FILE GSTR-1 and proceed to either
E-Sign or digitally sign the form.
Another confirmation pop-up will be displayed on the screen with a yes or no option To the
return.
Once yes is selected, an Acknowledgement Reference Number (ARN) is generated.
2. What is GSTR-2?
It is mandatory to file a GST Return for each and every entity registered under the GST Act.
Even in case where there are no inward supplies during the tax period, NIL return for that period
is required to be filed.
In case of failure to file the return within due period, the tax payer is penalized with the late fees
of INR 100 per day up to a maximum limit of INR 5,000/-
33
When to file GSTR-2?
Every registered taxable person is required to furnish details of Inward Supply for a tax period
i.e. the end of the relevant month.
This return has to be filed by the recipient of (goods/services) supplies within 15 days from the
end of the relevant tax period.
However to facility the ease of payment and return filing for small and medium scale
Businesses with annual aggregate turnover up to Rs.1.5 crores, it has been decided in the 22nd
GST Council meeting dated 06th October 2017, that such tax payers shall be required to file
quarterly returns in Form GSTR 1,2 and 3 and pay taxes only on quarterly basis, starting from
the third quarter of this financial year, i.e. October to December 2017.
3) What is GSTR-3?
GSTR-3 is a return to be filed on monthly basis (compounding and ISD taxpayers are
exceptions). GSTR-3 is more like a pooled version of GSTR-1 and GSTR-2. The form captures
the information of outward and inward supply information at aggregate level which will be auto
populated through GSTR-1, GSTR-1A and GSTR-2.It will comprise of the entire turnover
related details, including, local sales turnover, export sales turnover, exempted local sales
turnover, turnover except GST and taxable turnover. A taxpayer just has to validate this prefilled
information and make modifications if required.
4) What is GSTR-4?
Compounding taxpayers would have to file a quarterly return called GSTR-4. Taxpayers
otherwise eligible for the compounding scheme can opt against the compounding and file
monthly returns and thereby make their supplies eligible for ITC in hands of the purchasers.
Compounding taxpayer will also file a simple Annual return (GSTR-9)
34
5) What is GSTR-5?
Non –Resident Taxpayers would have to file GSTR-1, GSTR-2 and GSTR-3 returns for the
period for which they have obtained registration. The registration of Non–Resident taxpayers
will be done in the same manner as that of Regular taxpayers. Non-Resident Taxpayers would be
required to file GSTR-5 return for the period for which they have obtained registration within a
period of seven days after the date of expiry of registration. In case registration period is for
more than one month, monthly return(s) would be filed and thereafter return for remaining
period would be filed within a period of seven days as stated earlier.
6) Annual Return
Every registered taxable person, other than an input service distributor, a deduct or under Section
37, a casual taxable person and a non-resident taxable person, shall furnish an annual return for
every financial year electronically in such form and in such manner as may be prescribed on or
before the thirty first day of December following the end of such financial year. Every taxable
person who is required to get his accounts audited under sub-section (4) of section 42 shall
furnish, electronically the annual return along with the audited copy of the annual accounts and a
reconciliation statement, reconciling the value of supplies declared in the return furnished for the
year with audited annual financial statement, and such other particulars as may be prescribed.
Every registered taxable person required to keep and maintain books of account or other records
under sub-section (1) of section 42 shall retain them until the expiry of sixty months from the last
date of filing of Annual Return for the year pertaining to such accounts and records: Provided
that a taxable person, who is a party to an appeal or revision or any other proceeding before any
35
Appellate Authority or Tribunal or Court, whether filed by him or by the department, shall retain
the books of account and other records pertaining to the subject matter of such appeal or revision
or proceeding for a period of one year after final disposal of such appeal or revision or
proceeding, or for the period specified undersub-section (1), whichever is later.
Every registered person shall keep and maintain, at his principal place of business, as mention in
the certificate of registration, a true and correct accounts of production or manufacture of goods,
of inward or outward supply of goods and services, of stocks of goods, of input tax credit
availed, of output tax payable and paid, and such other particulars as may be prescribed in this
behalf:
Provided that where more than one place of business is specified in the certificate of registration,
the accounts relating to each place of business shall be kept at such places of business concerned:
Provided further that the registered person may keep and maintain such accounts and other
particulars in the electronic form in the manner as may be prescribed.
The Commissioner may notify a class of taxable persons to maintain additional accounts or
documents for such purpose. Every registered taxable person whose turnover during a financial
year exceeds the prescribed limit shall get his accounts audited by a chartered accountant or a
cost accountant and shall submit to the proper officer a copy of the audited statement of
accounts, the reconciliation statement under sub-section (2) of section 30 and such other
documents in the form of manner as may be prescribed in this behalf.
Every registered taxable person required to keep and maintain books of account or other records
under sub-section (1) of section 42 shall retain them until the expiry of sixty months from the last
date of filing of Annual Return for the year pertaining to such accounts and records: Provided
that a taxable person, who is a party to an appeal or revision or any other proceeding before any
Appellate Authority or Tribunal or Court, whether filed by him or by the department, shall retain
the books of account and other records pertaining to the subject matter of such appeal or revision
36
or proceeding for a period of one year after final disposal of such appeal or revision or
proceeding, or for the period specified under sub-section (1), whichever is later.
37
KEY FEATURES OF GST MODEL
38
Key Features of The GST Model-
2. Inter-State Transactions and the IGST Mechanism: The Centre would levy and
collect the Integrated Goods and Services Tax (IGST) on all inter-State supply of goods and
services. The IGST mechanism has been designed to ensure seamless flow of input tax credit
from one State to another. The inter-State seller would pay IGST on the sale of his goods to the
Central Government after adjusting credit of IGST, CGST and SGST on his purchases (in that
order). The exporting State will transfer to the Centre the credit of SGST used in payment of
IGST. The importing dealer will claim credit of IGST while discharging his output tax liability
(both CGST and SGST) in his own State. The Centre will transfer to the importing State the
implies that all SGST collected will ordinarily accrue to the State where the consumer of the
4. Computation of GST on the basis of invoice credit method: The liability under
the GST will be invoice credit method i.e. cenvat credit will be allowed on the basis of invoice
5. Payment of GST: The CGST and SGST are to be paid to the accounts of the central and
states respectively.
39
6. Goods and Services Tax Network (GSTN):A not-for-profit, Non-Government
Company called Goods and Services Tax Network (GSTN), jointly set up by the Central and
State Governments will provide shared IT infrastructure and services to the Central and State
7. INPUT TAX CREDIT (ITC) SET OFF: ITC for CGST & SGST will be taken for taxes
8. GST on Imports: Centre will levy IGST on inter-State supply of goods and services. Import
books of account for a ailment, utilization or refund of Input Tax Credit of CGST, SGST and
IGST.
10. Administration of GST: Administration of GST will be the responsibility of the GST
Council, which will be the apex policy making body of the GST. Members of GST Council
comprised of the Central and State ministers in charge of the finance portfolio.
11. Goods and Service Tax Council: The GST Council will be a joint forum of the Centre and
the States. The Council will make recommendations to the Union and the States on important
issues like tax rates, exemption list, threshold limits, etc. One-half of the total number of
40
Benefits of GST: -
To Traders: -
To Government: -
41
CHAPTER-2
COMPANY PROFILE
42
ABOUT COMPANY
43
ABOUT COMPANY
government (Ministry of Railways) under the Companies Act, 1956 on 28th April, 1976
originally under the name Indian Railways Construction Company Limited, is the leading
turnkey construction company in the public sector known for its quality, commitment and
consistency in terms of performance. Ircon has wide spread operations in several states in
constructions activities and services in the infrastructure sector. However, Railways and
Highways Construction, EHP sub-station (engineering and construction), and MRTS are
IRCON operates not only in highly competitive environment but also in difficult terrains
and regions in India and abroad and is an active participant in prestigious nations building
projects. IRCON has so far completed more than 300 infrastructure projects in India and
more than 100 projects across the globe in more than 21 countries.
44
The Company has a long standing reputation as a sectoral leader in Transportation
Infrastructure amongst the public sector construction companies in the Country with
known for its quality, commitment and consistency in terms of its performance.
airport construction, commercial complexes, as well as to metro works. It has been one of
the few construction companies in the public sector to have earned substantial foreign
exchange for the Country and paid dividend without fail every year to the Government.
The Company has executed many landmark construction projects in the last 41 years both
in India and abroad. In India, in particular, it has also been undertaking projects even in
difficult terrains and disturbed regions. The Company has so far completed more than
120 projects in more than 24 countries across the globe, and 376 projects in India. The
Health and Safety Management Systems, a Schedule ‘A’ public sector company, and a
45
LEGAL STATUS AND AUTONOMY
The Company, a legal entity separate from the Government, is legally, functionally, and
enterprise, does not receive any budgetary or financial support from the Government, nor
the Ministry of Railways and the Department of Public Enterprises under the Ministry of
Heavy Industries and Public Enterprises monitors its performance through a system of
Government can issue and does issue guidelines to regulate and bring about some
uniform pattern in the functioning of the Company as a public sector company. However,
no Government department has any supervisory authority to exercise control over the
Company which is managed and run under the superintendence, control, and direction of
BUSINESS ENVIRONMENT
India is not only among the world’s fastest growing major economies, but also one of the
few economies enacting major structural reforms. Indian economy registered a growth of
7.1% for the financial year 2016-17 in the backdrop of two major domestic development
46
viz. demonetization of two highest denomination notes in November 2016, and
To make this growth rate consistent and enduring, the government continues with its
development projects, export growth etc. A total allocation of Rs. 3,96,135 crore for
Company. The historic step of merger of the Railways Budget with the General Budget
would facilitate multi-modal transport planning between railways, highways, and inland
waterways.
VISION
organization comparable with the best in the field covering the entire spectrum of
MISSION
abroad.
47
ii. To earn the global recognition by providing high quality products and services in
times and in conformity with the best engineering practices as well as good
FINANCIAL PROFILE
The operating income of the company has registered an increase of 24% from Rs. 2419
crore in 2015-16 to Rs. 2995 crore in 2016-17, though profit before tax has decreased by
12% from Rs. 602 to Rs. 532 crore during the corresponding period. Indian project has
IRCON has allotted bonus shares in January 2017 in the ratio of 4:1 i.e. bonus (equity)
shares for every one equity share held by the shareholders thereby increasing the paid up
No. Decrease
(In %)
turnover
48
3 Operating income from 327 409
Indian projects
7%
4%
14%
BOARD OF DIRECTORS
As on 31st March 2017, the strength of Board of Directors was nine comprising four whole-time
directors, two government nominated directors, and three independent directors. The details are
as follows:
49
Director Finance 01.05.2016
OPERATIOAL PROFILE
During 2016-17, IRCON has completed four projects, two in India and one each in
Bhutan and Bangladesh. Ircon is having pan India presence through more than 24
projects across various states of India. In addition, the company executing projects in
50
The product mix of IRCON is varied and includes signaling projects, electrical sub-
stations, and road over bridges, buildings, road projects from NHAI, apart from railway
The mode of execution of some of these projects is EPC whereas road projects from
NHAI are being executed through wholly owned subsidiary companies (WOS) formed
for this purpose, and coal connectivity projects are being executed through joint venture
companies formed as a strategic alliance with other PSUs, Ircon’s equity stake in such
Ircon had four subsidiary companies viz. IrconISL, IRSDC, IrconPBTL, and IrconSGTL
as on 31 March 2017. After the close of the year, one wholly owned subsidiary (WOS)
company by the name IrconDHHL got incorporated on 11th May 2017, whereas IRSDC
ceased to be a subsidiary company after transfer of 1% equity stake (out of 51% held by
IRCON) to RLDA. The present status of IRSDC is joint venture Company having 50:50
corporate governance under the DPE Corporate Governance Guidelines, and other legal
51
requirements. During the year, your Company has spent an amount of Rs. 5.89 crore
towards Corporate Social Responsibility (CSR) initiatives. The CSR initiatives, aimed at
differently abled, environment, infrastructure development, etc. To keep pace with new
developments in the area of CSR, IRCON has revised its CSR and Sustainability policy
in May 2017.
OPERATIONAL PERFORMANCE
IRCON has completed two projects (one in Bhutan and another in Bangladesh) during
Bhutan
1. The turnkey project for dismantling of existing 66/33/11 KV sub-station and Design,
2x20 MVA, 66/33 KV sub-station including all associated works at Paro in Bhutan
Bangladesh
2. The project for construction of 2nd Bhairab Railway Bridge with Approach Rail
52
Company and AFCONS viz. IRCONAFCONS JV, at a revised value of Rs. 265
Bangladesh
Physical work has been completed in July 2017. The work is scheduled to be
2. Construction of Embankment, Track, all civil works, major & minor bridges
(Except Rupsha) & culverts and implementation of EMP against Package WD1
under the project Construction of Khulna-Mongla Port Rail Line for Bangladesh
Railway, at a value of Rs. 971 crore (USD 147.80 million). The physical progress
up to July 2017 is10%. The work was commenced in March 2016 and is
land and non issuance of drawings for bridges and buildings by the client.
53
Algeria
double line has been revised to Rs. 1944 crore (converted in INR). Though the
project was awarded in 2008, but it was suspended by the client in January 2009
The completion time has been extended by client up to 10th May 2018.The
amendment and were later negotiated with the client, which hampered the cash
flow and project progress. Eventually, the mode of payment to the local sub-
contractors and revision of the price were negotiated by a high level committee in
July 2016 paving the way for smooth progress of the project. Lack of sufficient
funds with the client is likely to affect the completion period of the project.
South Africa
Power Supplies Switching Stations and Signalling Systems for Majuba Rail
54
Project, South Africa, for Eskom Holdings SOC Limited, at a value of Rs. 346
crore (Rand 663 million, Rand 1 = 5.212). The work has been secured in
November 2015. During the operation of contract, Foreign Currency issue arose
which has been resolved. The work is in progress and likely to be completed by
In March 2017, following two projects at a total value of Rs. 178 crore got completed
55
1. Construction of Corridor-III of East-West Corridor between Gevra Road to
between Gevra Road to Penra Road in the State of Chhattisgarh, for Chhattisgarh
(JCRL), at an estimated project cost Rs. 1365 crore as per approved DPR.
Rail Coal Connectivity Project(s), for Mahanadi Coal Railway Limited (MCRL),
5. Akhaura – Agartala Rail Link project, for North Frontier Railway, at an estimated
project cost of Rs. 574 crore as per approved DPR, out of which Rs. 211 crore
56
6. Additional work of Design, Drawing and Construction of External Development
After the close of the year 2016-17, IRCON secured following projects in India
HHP locomotives, for East Coast Railway, at a value of Rs. 61.75 crore.
2. Katni Grade Seperator / by pass line (21.50 Km) Project, for West Central
57
4. Railway electrification work for Katni-Singrauli, for East Central Railway, at
for East Central Railway at an estimated project cost of Rs. 305.90 crore.
COMPLIANCES:
1) Official language:
During the year, various novel and encouraging initiatives have been undertaken for
a) Pledge by all employees to work in Hindi completely on every last Monday of the
month.
b) First ever “Rajbhasha Sanghosthi” was held in Corporate Office which is now
Committee and workshops for effective use of the Unicode system and official
58
language are being conducted. Bilingual facility has been introduced for computer
systems and mobile phones used by officials of the Company. Officers and staff
the annual program of the Official Language Department. Bilingual formats have
been made available at Ircon’s internal website for use by the employees. A
As per the requirements of the RTI Act, necessary updated information including the
names of Appellate Authority, Central Public Information Officer, State Level Public
Information Officer and Assistant Public Information Officer are posted on Ircon’s
website. Queries received are replied within the stipulated time. The queries are usually
in the nature of service matters, related to finance, contract, and projects. The details of
RTI cases have been forwarded to the Ministry of Railways for publication on the
basis. During the year, out of 204 applications / appeals received 191 applications
59
PERSONNEL DEVELOPMENT
Cordial and harmonious industrial relations prevailed in the Company during the year. The total
manpower strength as on 31 March 2017 stood at 1495, which included 1183 regular employees,
47 deputationists, and 265 employees on contract (including service contract). 1004 employees
of the Company were technically and professionally qualified. The total number of women
employees was 68. There were a total of 241 scheduled caste / scheduled tribe employees as on
IRCON has been continuously taking steps for building capacity of its human resource through
training in functional and general management areas, contract & arbitration, leadership,
information technology, as well as soft skills. External faculty is arranged wherever required and
officials are nominated for workshops, seminars, etc. with reputed institutes. During the year
2016-17, a total 912 man-days training was imparted to officials of Ircon through workshops,
Ircon has various schemes for staff welfare like educational scholarships, one-time educational
grant for admission to professional degrees and diploma courses, educational awards to
assistance for marriage of daughters and dependent sisters of group ‘C’ and ‘D’ employees, etc.
An award was introduced for meritorious wards of Ircon employees who secured gold medal in
office, yoga classes are also conducted for overall well-being of the employees. Other facilities
60
like immediate financial assistance and guidance are being provided to employees and their
family members in case of any medical exigency, lump sum exgratia payment to family
IRCON aims to provide congenial and safe working atmosphere to women employees. The
Company has a complaints committee for prevention of sexual harassment at work place.
Further, provision pertaining to prohibition of sexual harassment has also been incorporated in
Ircon Conduct, Disciplinary, and Appeal Rules. No complaints relating to sexual harassment has
been received by the Company during the year. The Company, on International Women’s day,
arranged one workshop during the year, exclusively for women employees for creating
awareness on health related issues. Inter-project Quiz programmes and Debate competition were
conducted for the employees of Ircon. Winning team and the runners up were awarded cash prize
Quality Management System (QMS) has been successfully sustained and continually improved
since 1996 when the Company as a whole was first certified for ISO-9002-1994 by TUV
Suddeutschland Private Limited (TUV). Your Company has continued the certification and
sustained the system as per latest revised code ISO 9001:2015 (by periodical re-certification
audit after expiry of every three years). Latest re-certification audit has been conducted in March
61
2017, whereby the Company has been re-certified by TUV for a period of another three years i.e.
up to June 2020.
During the year, the Company has started working on development of mobile phone / web based
video library, and for this purpose two topics have been identified viz. Construction of
format. The mobile / internet based application on personal safety and safety in construction has
Environmental friendly equipment such as solar panels has been installed and are being installed
at various offices / projects. Waste water is recycled at Corporate Office through Sewage
Treatment Plant (STP), and the same is used for horticulture work. STPs are also being
constructed at Noida, Guru Gram, and MFC buildings. LED lights, sensor lights and sensor taps
are being used in Corporate Office to conserve electricity and water. Various environment
friendly steps like use of fly ash brick instead of clay brick, rain water harvesting arrangements,
sensor controlled Cromium Plate (CP) fittings, use of latest version of fecade glass (glass in
building) to make the building sustainable etc. are being taken up across various offices / projects
of the Company. Monitoring of water usage and waste water, ambient air quality and noise
quality is also being carried out at various construction sites. The Company is emphasizing on
providing clean environment by initiating indoor air quality monitoring in the Corporate Office
building. Tree plantation is also undertaken by corporate office and project offices.
62
TECHNOLOGY ABSORPTION AND UPGRADATION
Supervisory Control and Data Acquisition System (SCADA) for energy management have been
made operational at Rail Coach Factory, Rae Bareli. Further, the Company has constructed all
sub-station buildings in DMRC with latest energy efficient and environmental friendly
For the first time in Indian Railways, Overhead Equipment (OHE) design for Railway
Electrification Project is being carried out by using Drone camera for picking the coordinates and
Geographical Information System (GIS). The OHE layout plans are then prepared with the help
of AutoCAD. Ircon has also planned for use of Drone Camera for Katni Singrauli Doubling
project.
A concept paper on adoption of Semi High Speed on existing routes was presented in IPWE
63
RESEARCH AND DEVELOPMENT
IRCON does not undertake any pure research project but takes the help of consultants and firms
to innovate and to develop methods and techniques to execute projects in a cost effective
manner, with requisite quality, to enhance the technological competence and efficiency.
With an objective to enable IT facility in all domain, efforts were directed towards enhancement
of SAP ECC 6.0 based Finance-Controlling module to incorporate additional functionalities like
fixed asset accounting for calculation of depreciation as per Indian Income Tax Act, Bank
Reconciliation System, FOREX reporting in Functional currency, local currency and reporting
reports for quarterly and annual financial statements as per schedule III of the Companies Act,
2013; implementation of E-recruitment system on SAAS model with functionalities like on-line
submission of application with payment gateway, generation of admit card and communication
through SMS / e-mail with the applicants, conducting online written test, instant publication of
64
results; installation of video conferencing system for conducting review meetings with Project
Heads, training, promotion interviews etc.; hiring data centre services for SAP ERP application
to gain enhanced efficiency, security, and flexibility for capacity augmentation; revamping
To reduce paper usage and transparent working, use of IT has been enhanced in all the
functional domains.
AWARDS
1. India Pride Awards 2015-16 instituted by Dainik Bhaskar for ‘Excellence in Public
award was presented by Mr. VenkaiahNaidu, Hon’ble Union Minister for Urban
Development to Mr. Mohan Tiwari, former Chairman & Managing Director, Ircon, at a
2. Dun & Bradstreet Infra Awards 2016, in the category of “Best Infrastructure
Project: Setting up of Rail Coach Factory, Rae Bareli at Lalganj (U.P.) Phase-I
Project”. The award was presented by Mr. Mansukh L. Mandaviya, Hon’ble Minister of
State for Transport & Highways to Mr. M.K. Singh, Director Finance, Ircon, at a
65
3. Governance Now 4th PSU Awards 2016 in the category of “HR Initiative
(Miniratna I)”. The award was presented by Mr. Ram Villas Paswan, Hon’ble Union
Minister for Consumer Affairs, Food and Public Distribution, to Ms. Anupam Ban,
General Manager/HRM, Ircon, at a function held in New Delhi on 23rd December 2016.
(CIDC) in the category of Best Construction Project for Railways Coach Factory,
Rae Bareli. The award was presented to Mr. S.K. Chaudhary Chairman & Managing
Director; Mr. Deepak Sabhlok, Director Projects; Mr. Dwarika Prasad, Executive
Director (Rae Bareli);, and Mr. A.K. Goyal, Executive Director (Projects); at a function
5. As per Dun & Bradstreet India’s Top PSUs 2016 Certificate released on 22nd August
66
SOME OF THE ON-GOING MAJOR PROJECTS IN INDIA
Rs. In
Crore
No. Revised
value
Railway
2 Setting up of new Rail Coach Factory at Rae Bareli, including additional 2973
3 Design and Construction of Civil, Building and Track Works of Vaitarna- 2116
5 Sivok-Rangpo New Rail Line Project, for North Frontier Railway. 1339
a) Bihar (Phase – I & II), for Ministry of Railways and Government of (Bihar)
Bihar 618
67
c) One RoB on State owned Road (other than NHs) in Bihar through its
Development Department.
lane from Km. 4.200 to Km. 55.250 and Two-Lane with paved shoulder
from Km. 55.250 to Km. 163.500 of NH-15 on BOT (Toll) basis in the
Subsidiaries companies
IrconISL, a wholly owned subsidiary of Ircon, was incorporated on 30th September 2009
Complexes (MFCs), etc., to provide facilities and amenities to users of Indian Railway
68
System, and to carry on the business of hire purchasing, leasing of all kinds of moveable
and immoveable properties, to provide consultancy for all kinds of engineering projects
including providing maintenance, support, and all kinds of services including social
welfare measures, etc. During the year 2016-17, IrconISL has executed consultancy
project of Ministry of External Affairs (MEA) for preparation of feasibility report and
Detailed Project Report (DPR) for Bridge Project in Myanmar, and preparation of DPR
During the year, IrconISL had achieved an operating income of Rs. 40.98 crore, and
earned profit before tax of Rs. 20.81 crore and profit after tax of Rs. 12.36 crore.
IRSDC, a subsidiary company of Ircon and JV Company with Rail Land Development
Authority (RLDA), was incorporated on 12th April 2012 and obtained a Certificate of
Commencement of Business on 9th May 2012. The main objects of IRSDC is to develop /
re-develop the existing / new railway station(s) which will consist of upgrading the level
the station buildings, platform surfaces, circulating area, etc., to better standards so as to
serve the need of the passengers in India, and commercial development of land/ air space.
The equity participation of Ircon and RLDA in IRSDC is in the ratio of 51:49
respectively.
69
IRSDC has been entrusted with development of 13 stations located at Chandigarh, Habibganj
(Bhopal), Shivaji Nagar (Pune), Bijwasan (New Delhi), Anand Vihar (Delhi), Surat and
Gandhinagar (Gujarat), and SAS Nagar (Mohali) Punjab, Gandhinagar (Jaipur), Amritsar,
(i) Chandigarh Railway Station - proposal sent to Railway Board for taking up re-
(ii) (ii) Habibganj Railway Station - contract for redevelopment of this station has
Corporation;
(iv) Bijwasan and Anand Vihar Railway Station - bidding process is in advance
stage;
Transportation Hub through a Joint Venture Company and pooling of land by the
70
(vi) Gandhinagar Railway Station - work taken up through a JV company between
EPC mode;
(vii) SAS Nagar Mohali Railway Station - found to be unviable and has been
Vehicle on 30th September 2014, and has obtained approval for, commencement of
business of widening and strengthening of the existing Bikaner & Phalodi Section to four
lane from 4.200 km to 55.250 km and Two Lane with paved shoulder from 55.250 km to
163.500 km of NH-15 on Build, Operate, and Transfer (BOT) (Toll) basis in the State of
Rajasthan, in accordance with the terms of the Concession Agreement signed with
Vehicle on 12 May 2015 and has obtained approval for commencement th of business from
71
the Registrar of Companies on 27 May 2015. The main objects of IrconSGTL is to carry on
the business of four laning of Shivpuri-Guna section of NH-3 from 236.00 km to 332.1 km
on Build, Operate, and Transfer (BOT) (Toll) basis on Design, Build, Finance, Operate and
Transfer ‘DBFOT’ pattern under NHDP Phase-IV in the State of Madhya Pradesh and other
ancillary works relating thereto, in accordance with the terms of the Concession th
Agreement, signed with the NHAI on 15 June 2015. In terms of the concession agreement,
IrconSGTL rd attained financial close on 23 November 2015 i.e. date of execution and
signing of the loan agreement with Ircon for a value of Rs. 722.11 crore. Other conditions set
Date viz. signing of Escrow Agreement (between IrconSGTL, Ircon, Indian Overseas Bank,
and NHAI) and Substitution Agreement (between NHAI, the IrconSGTL, and Ircon) were
completed on 4 December 2015. th NHAI had declared 25 January 2016 as the appointed
date for commencement of construction, with construction period of 910 days, for which
Ircon has been appointed as EPC contractor. The Commercial Date of Operations would be
notified after completion of construction (scheduled in July 2018) and issue of completion
certificate by NHAI for operationalization of toll plaza and levy of toll fees. The
Construction work is progressing as per the schedule except for delay on account of no
availability of encumbrance free land. Financials of IrconSGTL: The authorized share capital
of IrconSGTL is Rs. 150 crore and its subscribed and paid-up share capital is st Rs. 150 crore
as on 31 March 2017. During the year, IrconSGTL has made two Rights issue of equity
shares of Rs. 80 crore subscribed by Ircon in July 2016 (Rs. 50 crore) and October 2016 (Rs.
30 crore). During the year, IrconSGTL had achieved revenue from operations (operating
turnover) of Rs. 294.12 crore, and earned profit before tax of Rs. 0.61 crore and profit after
72
tax of Rs. 0.39 crore. 5. Ircon Davanagere Haveri Highway Limited (IrconDHHL) After the
close of the year, your Company has formed another wholly-owned subsidiary company by
the name ‘Ircon Davanagere Haveri Highway Limited’ (IrconDHHL) on 11 May 2017,
maintenance and management of National Highway No. 48 (Old NH-4) including the section
National Highway No. 48 (Old NH-4) in the State of Karnataka by six-laning thereof on
design, build, finance, operate and transfer basis. IrconDHHL has signed the concession
agreement with NHAI on 19 June 2017. IrconDHHL is yet to submit relevant documents to
NHAI to achieve financial close. Execution of the project would be taken up after achieving
financial close and intimation of appointed date by NHAI. Financials of IrconDHHL: The
authorized share capital of IrconDHHL is Rs. 5 crore and its subscribed and paid-up share
After the close of the year, your Company has formed another wholly-owned subsidiary
company by the name ‘Ircon Davanagere Haveri Highway Limited (IrconDHHL) on 11 May
2017, pursuant to conditions of award of Davanagere Haveri Project in the State of Karnataka
maintenance and management of National Highway No. 48 (Old NH-4) including the section
73
National Highway No. 48 (Old NH-4) in the State of Karnataka by six-laning thereof on
design, build, finance, operate and transfer basis. IrconDHHL has signed the concession
agreement with NHAI on 19 June 2017. IrconDHHL is yet to submit relevant documents to
NHAI to achieve financial close. Execution of the project would be taken up after achieving
financial close and intimation of appointed date by NHAI. Financials of IrconDHHL: The
authorized share capital of IrconDHHL is Rs. 5 crore and its subscribed and paid-up share
A joint venture company called ‘Ircon-Soma Toll way Private Limited’ (ISTPL) was
1incorporated on 19th April 2005, with 50% equity participation by both Ircon and Soma
project for four laning of Pimpalgaon-Dhule section of NH-3 from km 380 to km 265 in
Maharashtra for NHAI. The BOT project for four laning of Pimpalgaon-Dhule section
got completed in 2010-11 and accordingly, ISTPL is earning toll on the entire stretch of
118.158 km. Financials of ISTPL: The authorized share capital of ISTPL is Rs. 130 crore
and its subscribed and paid-up share capital is Rs. 127.74 crore (Ircon’s share being Rs.
63.87 crore) as on 31stMarch 2017. During the year, ISTPL has achieved operating
turnover of Rs. 153.34 crore as compared to Rs. 157.23 crore achieved during the
74
previous year, and earned profit after tax of Rs. 11.69 crore against profit of Rs. 5.91
A joint venture company called ‘Chhattisgarh East the Railway Limited’ (CERL) was
development of coal connectivity corridor i.e. East Corridor (length 180 Km) in the State
7thMay 2013.
The CERL has signed concession agreement on 12thJune 2015 with Ministry of
Railways, for Chhattisgarh East Railway Corridor - Phase I in the State of Chhattisgarh
(Total 104.157 km). Phase I of the project is being implemented for Build, Own, Operate,
and Transfer (BOOT) model for PPP projects. Detailed Project rd Report (DPR) has been
approved on 3rd May 2016 by Zonal Railways viz. South Eastern Central Railway with
75
Financial closure is in progress and likely to be completed by 30thSeptember 2017. The
project progress is infringing due to stay by National Green Tribunal (NGT) payment of
67% disbursement has been completed by State Revenue officials and balance as
Financials of CERL:
The authorized share capital of CERL is Rs. 400 crore and its subscribed and paid-up
share capital.
A joint venture company called ‘Mahanadi l is Rs. 306 crores (Ircon’s share being Rs.
Coal Railway Limited’ (MCRL) was incorporated on 31stAugust 2015, with equity
respectively, with the main object to build, construct, operate, and maintain identified rail
corridor projects that are critical for evacuation of coal from mines in the State of Odisha.
MCRL has signed project execution agreement with Ircon on 19thApril 2016. Angul-
Balram-Jharpada new rail corridor has been identified by the Company for
implementation. Feasibility Report has been submitted to East Coast Railway (ECoR) on
76
8th August 2016 and DPR has been submitted to ECoR on 18th July 2017 and forwarded
to Railway Board on 20th July 2017 for approval. Land acquisition process is in progress.
Financials of MCRL:
The authorized, subscribed, and paid-up share capital of MCRL is Rs. 5 lakhs as on 31st
March 2017.
A joint venture company called ‘Jharkhand Central Railway Limited’ (JCRL) was
Limited, Ircon, and Govt. of Jharkhand in the ratio of 64:26:10 respectively, with the
main object to build, construct, operate, and maintain identified rail corridor projects that
are critical for evacuation of coal from mines, in the State of Jharkhand.
JCRL had signed project execution agreement with Ircon on 28th March 2016. Railway
Board on 6th April 2016 has granted in-principle approval for project transferring Broad
Gauge Single Railway Line connecting Shivpur to Kathautia from km 41.5 to km 90.7 in
the State of Jharkhand, having a total route length of 49.2 km and track length of 68.7 km
estimated cost of Rs. 1400 crore. Orders for acquisition of private and Government land
acquisition have been issued and environmental clearances are under process. Feasibility
/ initial viability estimation and Detailed Project Report (DPR) are in the process of
finalization.
77
Financials of JCRL:
The authorized share capital of JCRL is Rs. 100 crore and its subscribed and paid-up
A joint venture company called ‘Chhattisgarh East West Railway Limited’ (CEWRL)
for development of coal connectivity corridor i.e. East-West Corridor (length 135 Km) in
the State of Chhattisgarh. CEWRL had obtained the Certificate for Commencement of th
Business on 7 May 2013. Detailed Project Report (DPR) was approved by Zonal
Railways viz. South Eastern Central Railway in July 2015. Land acquisition proceedings
are in process. Concession Agreement is yet to be signed between CEWRL and Ministry
authorized share capital of CEWRL is Rs. 1110 crore and its subscribed and paid-up
share capital is Rs. 504 crore (Ircon’s share being Rs. 131.30 crore) as st on 31 March
78
6) Bastar Railway Private Limited (BRPL)
During the year 2016-17, a joint venture company called ‘Bastar Railway Private
Limited’ (BRPL) was the incorporated on 5 May 2016, with equity participation by
NMDC Limited, Ircon, Steel Authority of India Limited and Chhattisgarh Mineral
43:26:21:10 respectively, with the main object to build, construct, operate and maintain
Rowghat to Jagdalpur (via Narayanpur, Kondagaon) new railway line, in the State of
Agreement for BRPL has been signed th on 20 January 2016. As per the Articles of
Association of the Company, Ircon is the implementation agency for the project and
project th execution agreement was signed on 19 July 2017. Detailed Project Report
(DPR) has been submitted to South East Central Railway in July 2017 for approval.
Financials of BRPL: The authorized share capital of BRPL is Rs. 5 crore and its
subscribed and paid-up share capital is Rs. 4.55 st crore (Ircon’s share being Rs. 1.18
79
CHAPTER-3
80
BACKGROUND OF THE STUDY
Dr. R. Vasanthagopal (2011) studied and stated that adopting GST against current
complicated indirect tax system in India will be a great step in blooming Indian economy.
Panda and Ratel (2015) analyzed the impact of GST (goods and services tax) on Indian
tax scenario. They have detailed brief description of the historical Indian taxation system
and its tax structure. Then the need arose for the change in the tax structure from earlier
to GST model. GST has been discussed in detail in this paper by the author as the
background, silent features and the impact of GST in the present tax scenario in India.
Dani S (2016) a research paper on an Impact of Goods and Services Tax (GST) on Indian
economy stated that GST would impact negatively on the real estate market. It would add
Shrikant Paranjapee (2017), president of CREDAI Pune Metro, maintains that “The
impact of the GST on property prices will be difficult to gauge at this stage because of
the lack of clarity on abatement for land value. In a product, where the major raw
material is not covered by the GST, the tax input benefit will be hard to calculate or
justify. Only the market forces, the ready reckoned rates and time, will decide whether
and how much benefit will be passed on by the developers to the purchasers.”
81
CHAPTER-4
RESEARCH METHODOLOGY
82
OBJECTIVE OF THE STUDY
The general objective of the study is to get practical insights of Goods and Services Tax.
83
Data collection
For the preparation of this report secondary source of data is used. The data are collected from
secondary source.
Websites
Newspaper
While preparing this report I took help from company staff and group discussion with friends.
84
CHAPTER- 5
ANALYSIS
85
Comparative statement of balance sheet for the financial year 2016-17 & 2017-2018
Sr. Particulars 2017 2018 Increase/Decr Percentage
No ease change
Assets
1 Non-current assets
a.) Property 137.0 133.58 (3.50)
8 2.55
b.) Capital work-in - 0.98 0.98
progress 0.98
c.) Investment property 307.3 358.67 51.33
4 16.70
d.) Other tangible 1.21 0.83 (0.38) 31.40
Assets
e.) Financial assets
i Investment 973.1 984.52 11.37
5 1.17
ii Loans 339.8 806.34 466.50
4 137.27
iii Other 100.3 2729.4 2,629.08
3 1 2,620.43
g.) Defered tax assets 161.0 150.88 (10.17)
5 6.31
h.) Other non-current 403.6 141.07 (262.53)
assets 65.05
86
v Loans 84.77 1.87 (82.90)
97.79
vi Others 659.6 624.73 (34.95)
8 5.30
c.) Current Tax Assets 1.72 29.09 27.37
1,591.28
d.) Other Current 526.3 1114.8 588.49
Assets 7 6 111.80
4 Liabilities
i Non-current
Liabilities
a) Financial liability
i) Borrowings 3203.0 3,203.08
- 8 3,20308
ii) Trade payables 0.45 0.46 0.01
2.22
ii) Other Financial 210.1 321.47 111.36
Liabilities 1 53.00
b) Provisions 76.18 75.28 (0.90)
1.18
c) Other Current 1711. 883.45 (828.31)
Liabilities 76 48.39
87
Total non-current 1998. 4483.7 2,485.24
liabilities 5 4 124.36
ii Current Liabilities
a) Financial Liabilities
i) Trade Payables 363.7 512.86 149.11
5 40.99
ii) Other financial 687.2 942.66 255.38
liabilities 8 37.16
b) Other current 1968. 2737.2 768.79
liabilities 49 8 39.05
c) Provisions 297.9 265.32 (32.61)
3 10.95
d) Current tax liability 23.83 14.13 (9.70)
40.70
3. The Fourth column may be added for giving percentages of increase or decrease.
88
INTERPITATION
The comparative balance sheet of the company reveals that during 2018 the
1) non- current assets of the company like property has been decrease of 3.5 crore i.e.
2.55%, capital work-in progress has been increase of .98 crore i.e. 98%, investment
property has been also increase of 51.33 crore i.e. 16.70% , all the financial assets have
also been increase, deferred tax asset has been decrease of 10.17 crore i.e. 6.31% and
the other non –current asset have also been decrease of 262.57 crore i.e. 65.05%. So as a
result total non-current assets has been increase during the year 2018 as compare to the
2) It also reveals that during the 2018 inventories of the company has been increase of
1.4crore i.e. 1.004%, financial asset as investment has been decrease of 33.74crore i.e.
13.5%, trade receivables has been increase of 249.09 crore i.e. 58.65%, Cash & cash
equivalent has been increase of 130.9 cr i.e. 9.39%, other bank balance has been
decrease 188.06cr i.e. 5.76%, loans have been decrease of 82.94cr i.e. 97.84% and
others financial asset have been decrease of 34.95cr i.e. 5.29%, the current asset of the
company have also been increase of 27.37cr i.e. 1591.27%,and the other current asset
has been increase of 588.49cr i.e. 111.80%. So as a result total current assets have been
89
So the comparative balance sheet of IRCON of financial year 207-18 reveals that the total
assets of the company have been increase of 3540.32cr i.e. 38.61% during the year 2018 as
3) On the other side total equity of the company during the year 2018 have decreased of
75.86cr i.e. 1.98%. This table also reveals that during this year in liability the non-
current liability like borrowings has been increase of 3203.08cr i.e. 320308%, trade
payables has also been increase of .01cr i.e. 2.22%, other financial liabilities have
increased of 111.36cr i.e. 53%, but the provisions have decreased of 0.9cr i.e. 1.18%,
and the other non-current liability have also been decreased of 82.31cr i.e. 48.38%. So
as a result the total non-current liability has been increased of 2485.24cr i.e. 124.35%
4) On the other hand the current liability of the company during the year 2018 includes
financial liability like trade payables has been increased of 149.11cr i.e. 40.99%, other
financial liability has also been increased of 25.38cr i.e.37.15%. Other current liability
has been increased of 768.79cr i.e. 39.05%. The provisions have decreased of 32.61cr
i.e. 10.94%. The current tax liability has been decreased of 9.7cr i.e. 40.70. So the total
90
So the comparative balance sheet of IRCON of financial year 207-18 reveals that the total
Equity & Liability of the company have been increase of 3540.32cr i.e. 38.61% during the
91
CHAPTER-6
FINDINGS, CONCLUSION,
SEGGESTIONS AND
LIMITATIONS
92
FINDINGS
During the research I found that after the implementation of Goods and Services Tax in India:
The overall financial position of the company is satisfactory because company’s assets,
equity and liability has been increase of 1:1 ratio during the financial year 2018 as
IRCON is not only getting their projects in India but also outside the India, which is a
good indicator for the company. As a result company will become NAVRATNA in
upcoming years.
93
CONCLUSION
The Goods and Services Tax (GST), a revolutionary tax reform rolled out on the 1st
of July 2017, has effectively replaced the previous Gordian Knot of multiple taxes
like VAT, central excise duty, commercial tax, service tax, Octroi, etc. It has made
India a 'tax-neutral' nation - and while it evoked a response best described as 'mixed'
This is natural, as the unitary tax compliance system has simplified the home buying
process - and with the passage of Input Tax Credit (ITC), there may not be a
However, even almost a year after GST implementation, the only real clarity that
exists for property buyers is on the prevailing GST rate of 12% on under-construction
projects. There is still confusion about the amount of rebate that a prospective
homebuyer is entitled to on the back of the pass-over of ITC. The confusion is not
only about the percentage of ITC but also on the mode and tranche of the rebate.
The company’s financial position has also been increase or become better during the
94
SUGGESTIONS & RECOMMENDATIONS
After analyzing the data, I would like to give some suggestions that are:
In real estate sector, there is confusion about the integration of input tax credit. So it
According to company’s balance sheet of financial year 2017-18, the borrowings have
Company’s total equity has been decrease during the year 2018 so they will have to
95
LIMITATIONS OF THE STUDY
Just like any other study, present study is also not exempt from limitations, foremost data is
collected from IRCON International Ltd. on branch and the findings may represent the all
branches of the IRCON GROUP. Further this study concentrates the all branches it may
have their own dynamics and may different results for different branches.
There can be even being the printing mistakes by which the fake result could be generated.
There are few data which kept confidential and they are basically available to the higher
executives.
Authenticity of the data cannot be proved as it was received through informal meetings and
interviews.
Appointments with the higher executive were one of the major problems.
96
CHAPTER-7
BIBLIOGRAPHY
97
BIBLIOGRAPHY
https://www.avalara.com/in/en/blog/2017/09/impact-gst-indian-real-
estate-sector.html
https://blog.mygov.in/editorial/why-gst/
https://www.gst.gov.in
https://www.gstn.org
https://www.gstcouncil.gov.in
https://www.cbec.gov.in
https://www.financialexpress.com
https://www.wikipedia.com
https://www.cleartax.com
https://www.ircon.org
98
CHAPTER-8
ANNEXURE
99
ANNEXURE:-
100
101