Sunteți pe pagina 1din 1

Project Name:

Date of Name of
Inspection: Inspector:
Weather
Contractor:
Conditions:
Site
Completed By:
Information:

CONSTRUCTION CHECK LIST


Reference Conformance/
Action
Check When Item Task Name Non- Description Condition/Remarks/Comments
Needed?
Inspected Number Conformance?
Framing
Wall Studs (size, height, and spacing per code)

All bearing points and point loads are supported


properly (proper number of jacks under girders,
beams down to the foundation, etc)
There is no significant moisture remaining in the
wood framing
Fasteners and hardware for pressure
preservative and fire-retardant treated wood
shall be of hot dipped galvantized steel, stainless
steel, silicon bronze, or copper.
All hangers and or ledger strips are in place and
fastened correctly
Lumber size and grade agrees with the structural
notes
Protection from wood decay
Headers are installed and are properly sized and
supported per code.
Insulation Inspection
All mechanical trade inspections are complete
All small holes in area requiring fireblocking are
stuffed with unfaced insulation
All side walls and floors are properly attached
with correct R value
All insulation baffles are in place
Check for voids at electrical boxes, wires, and
pipes
Thermal envelope complete
Secure insulation in floor assemblies to subfloor
surface
Slab
Beams clear of debris and water
Nominal 4 inches concrete depth top of pads
Live and dead ends protected according to ACI
Manual
Piers installed per plans/passed pier inspection

Proper beam depth and width per Engineer plans


Cables and rebar placed per approved plans
Brick/Wall Ties
Clean mortar from behind brick
Moisture barrier for OSB
Brick ties properly spaced
Brick to be 4' height for inspection