Documente Academic
Documente Profesional
Documente Cultură
Page 1 of 44
1 Introduction
1.1 Objectives
The Ancillary Services Procurement Plan (ASPP) has been developed to inform the
electric power industry participants how NGCP, through its System Operator,
will undertake its responsibilities to provide Ancillary Services to the Philippine
Grid, in coordination with the Market Operator, as required by the Electric Power
Industry Reform Act of 2001 (EPIRA), the Implementing Rules and Regulations
of Republic act No. 9136 (the IRR), the Philippine Grid Code, OATS Rules and the WESM
Rules.
1.2 Glossary
Active Power - The time average of the instantaneous power over one period of
the electrical wave measured in Watts (W) or multiple thereof. For AC circuits or
Systems, it is the product of the root-mean-square (RMS) or effective value of the
voltage and the RMS value of the in-phase component of the current. In a three
phase System, it is the sum of the Active Power of the individual phases.
Automatic Generation Control (AGC) - The regulation of the power output of Generating
Units in response to a change in system Frequency, so as to maintain the Power System
Frequency within the predetermined limits.
Available Capacity - the dependable capacity, modified for equipment limitation at any
time.
Energy Storage System – is a set of technologies where energy is stored during times
when production exceeds consumption and the stored energy are used at times when
consumption exceeds production.
Page 2 of 44
Dependable Capacity - the maximum capacity, modified for ambient limitation for a
specified period of time, such as a month or a season.
Dispatch Instructions – Refers to the instruction issued by the System Operator to the
Generators with Scheduled Generating Units and to the Generators whose Generating
Units will provide Ancillary Services to implement the final Dispatch Schedule in real time.
Dispatch Schedule (Market base) - The target loading levels in MW for each schedule
Generating Unit or scheduled Loads and for each Reserve facility for the end of that trading
interval determined by the Market Operator through the use of a market dispatch
optimization model.
Dispatch Schedule (Non-Market base). The target loading levels in MW for each
scheduled Generating Unit or scheduled Loads and for each Reserve facility as determined
by the System Operator.
Excess capacity - For a generator, excess capacity is the available output capacity
in MW while it is supplying the scheduled energy, Primary, Secondary and Tertiary reserve
dispatched by the System Operator or under contract (i.e.: available capacity less
scheduled energy, Primary, Secondary and Tertiary reserve). Excess capacity = available
capacity - (scheduled energy + scheduled AS reserves).
Frequency – as defined in the Philippine Grid Code with a nominal value of 60Hz
Governor Control Mode (GCM) - A generating unit operating under the control of a
governor which has been calibrated to control the output of the generating unit to
set levels of frequency, voltage or other parameter, without the need for external
control signals.
Page 3 of 44
National Grid Corporation of the Philippines (NGCP) - The entity which in
2009 has been awarded the concession to operate, maintain and expand the
Philippine electricity Grid, in accordance with NGCP Franchise (RA9511), or asotherwise
approved under Philippines law from time to time.
Open Access Transmission Service Rules (OATS Rules) – The set of rules that govern
the implementation of the Open Access Transmission Services as approved by the ERC.
Philippine Grid Code (PGC or Grid Code) – The set of rules, requirements, procedures,
and standards to ensure the safe, reliable, secured and efficient
operation, maintenance and development of the high-voltage backbone Transmission
System and its related facilities.
Qualified Interruptible Loads - A load that is tested, certified and monitored by the System
Operator to provide Tertiary Reserve Ancillary Service.
Qualified Generating Unit – A Generating Unit tested, certified and monitored by the
System Operator to provide specific types of Ancillary Service.
Reaction Time - The elapsed time from the occurrence of a disturbance until the time the
ancillary service provider begins to respond.
Reactive Power Capability Curve - A diagram which shows the Reactive Power capability
limit versus the Real Power within which a Generating Unit is expected to operate under
normal conditions. Refer to Attachment 4 for an example.
Saturation Time – The elapsed time from the occurrence of a disturbance until the time
the ancillary service provider reaches the required reserve capacity.
Sustainability - The elapsed time from the saturation point until the time for which the
ancillary service provider must maintain the appropriate reserve capacity.
Page 4 of 44
TransCo - The National Transmission Corporation of the Philippines, which is
currently the owner of the electricity transmission assets of the Philippine Grid.
Under Frequency Relays (UFR) - An electrical relay that operates when the Power
System Frequency decreases to a preset value.
Wholesale Electricity Spot Market (WESM) – The electricity market established by the
DOE pursuant to Section 30 of the Act.
Where terms are not defined in this ASPP reference should be made to the EPIRA,
IRR, Grid Code or WESM Rules.
This document covers the definition of the types of Ancillary Services (AS) necessary for
the reliable operations of the Grid, the manner of procurement by the System Operator, the
level of Ancillary Services requirement, the process of certifying Qualified Generating Units
and Qualified Interruptible Loads which the System Operator can contract and/or schedule
for provision of Ancillary Services, and the process for control, monitoring Ancillary
Services provider’s performance and the obligation for payments.
The cost recovery mechanism for the provision of scheduled Ancillary Services is defined
in separate documents, which are subject to due process and approval by the ERC.
All Ancillary Services can be grouped under one of the following three (3) major
categories:
FCAS are used (by the System Operator) to maintain the frequency on the
electrical system, at any point in time, close to sixty (60) cycles per second.
There are three (3) types of reserve under Frequency Control as specified
by the PGC.
•
• Primary Reserve Ancillary Service (PRAS)
• Secondary Reserve Ancillary Service (SRAS)
• Tertiary Reserve Ancillary Service (TRAS)
Page 5 of 44
These types of FCAS will be defined in Section 2 of this plan.
BSAS are used to recover the Power System from total or partial system
blackout by starting and synchronizing with the Power System without an
external power supply.
The following AS will be provided by Qualified Generators, Energy Storage System and
Qualified Interruptible Loads in the Philippine Grid. These AS are essential in maintaining
power quality, reliability, and security of the Philippine Grid.
2.1 PRAS – are FCAS capacities from qualified Generating Units and Energy Storage
System that are allocated to stabilize the system Frequency and to cover the loss or
failure of a Synchronized Generating Unit or a transmission line or the power import
from a single circuit interconnection.
2.2 SRAS - are FCAS capacities from qualified Generating Units and Energy Storage
System that are allocated to restore the system frequency from the quasi-steady
state value as established by the Primary Reserve back to the nominal frequency of
60 Hz. This type of service should also be used to provide supply demand balance
during small frequency deviations.
2.3 TRAS - are FCAS capacities from qualified Generating Units, Energy Storage
System and Interruptible Loads that are readily available for dispatch in order to
replenish the Secondary Reserve and to cover variation of VRE generations. This
type of service should also be used in maintaining the Frequency at a pre-
established value and/or returning the Frequency to 60Hz in case the Primary and
Secondary Reserve are not adequate or already exhausted.
Page 6 of 44
2.5 BSAS - The need for this AS arises when an event or significant incident will result
in a Partial or Total System Blackout. This is the ability of a generating unit, without
assistance from the Grid or other external power supply, to recover from a shutdown
condition to an operating condition in order to energize the Grid and assists other
generating units to start.
3 Technical Requirements
This section of the plan sets out the arrangements which the System Operator will
follow for contracting or procurement of each category of Ancillary Services from Service
Providers. On the other hand, the Service Provider shall use reasonable efforts, in
accordance with good industry practice, to ensure that the plant and equipment meet the
technical specification as per Philippine Grid Code requirement.
NGCP, as the System Operator, has certified numerous Service Providers. These Service
Providers meet the performance criteria as evaluated based on the result of the capability
tests.
Included in this plan are the tabulated summaries of Performance Measures & Criteria with
its monitoring scheme and the Accredited Service Providers for each category of ancillary
services, once testing and certification has been performed by NGCP.
3.1.1 The Generating Units or Energy Storage System providing Primary Reserve as
an Ancillary Service shall be capable of operating in Governor Control mode
with sufficient headroom.
3.1.2 The Generating Units or Energy Storage System providing Primary Reserve as
an Ancillary Service shall be certified and contracted by the System Operator.
3.1.3 The Generating Units or Energy Storage System providing Primary Reserve as
Ancillary Service shall not override its governor control. The Primary Reserve
provider should be able to respond within 5 seconds and deliver its reserve
capacity based on its Ramp-up Rate within 10 minutes which should be
sustainable for at least 30 minutes or as required by the system.
3.1.4 Primary Reserve Service provider shall cover sudden outage or failure of
synchronized generating unit or transmission line links or the power import from
a single circuit interconnection, whichever is larger.
As an illustration, the Figure 3.1 below shows the relationship between Primary Reserve
and Regular Energy Supply:
Page 7 of 44
Figure 3.1: Primary Reserve
Primary
Reserve
Ancillary
Service
Regular
Energy
Supply
3.2.1 Generators and Energy Storage System providing this service shall be
controlled by SO thru AGC with Auto R, Auto A, or Auto E settings in order
to regulate the system frequency. The speed governing system shall be
capable of accepting raise and lower signals or set point signals from the
Control Center of the System Operator. The Secondary Reserve provider
should be able to deliver 90% of the desired generation within 32 seconds
and should be sustainable for at least 30 minutes.
3.2.2 Generating Unit contracted to provide Secondary Reserve shall not override
the AGC mode or AGC setting as set and controlled by SO.
3.2.3 The System Operator thru AGC shall use the Secondary Reserve to restore
the system Frequency from the quasi-steady state value as established by
the Primary Reserve back to the nominal Frequency of 60 Hz.
3.2.4 Where the AGC function of the SO is not fully operational, dispatcher may
instruct the generator to transfer to Manual Control Mode.
3.2.5 The Secondary Reserve, operated thru AGC or manual control, shall be
provided by Generating Units of Energy Storage System, both contracted
and certified by the System Operator.
The capacity of the Generating Unit or Energy Storage System offered for this
service should not be used in the regular energy supply. Figure 3.2 below illustrates
the Secondary Reserve Ancillary Service:
Page 8 of 44
Figure 3.2: Secondary Reserve
Secondary
Reserve
Pmin.
3.3.1 Generating Unit and Energy Storage System providing this service can
either be synchronized, which can respond within 15 minutes, or off-line
provided that it can fully provide the required reserve within 30 minutes
from the receipt of dispatch instruction. The Tertiary Reserve provider
should be able sustain its contributed capacity for at least 60 minutes.
3.3.2 The total Tertiary Reserve may comprise of 50% synchronized with the
Grid and 50% off-line.
3.3.3 The System Operator shall make use of the Tertiary Reserve in cases of:
(a) Unplanned tripping of a Generating Unit or a transmission line
which creates a Generation-Load unbalance;
(b) Unplanned loss of the power import from a single circuit
interconnection;
(c) Unplanned Disconnection of a large Load and/or Load blocks;
(d) Unexpected reduction of VRE Generation or significant errors in its
forecast; or
(e) System Frequency increases above 60.1 Hz or reduces below 59.9
Hz and it is not possible to return it to nominal values with
appropriate use of the Primary and Secondary Reserve.
3.3.4 The System Operator shall use the Tertiary Reserve Service to replenish
the Secondary Reserve.
3.3.5 The Tertiary Reserve shall be provided by Generating Units or Energy
Storage System and Qualified Interruptible Loads contracted by the
Transmission Network Provider and are certified by the System
Operator.
3.3.6 Generators or Energy Storage System providing this service should be
capable of operating thru AGC or Manual mode and shall be monitored
and controlled by the System operator.
3.3.7 The capacity of the Generating Unit or Energy Storage System offered
Page 9 of 44
for this AS should not be part of the regular energy supply. As an
illustration, the Figure 3.3 below shows the relationship between
Tertiary Reserve and Regular Energy Supply of a Generating unit
already supplying energy.
Tertiary
Reserve
Regular
Energy
Supply
Page 10 of 44
and Attachment 2 - Testing, Certification and Accreditation Procedure).
3.4.2 Outside of the above range, but within its Reactive Power Capability
Curve, the generating unit may offer to supply/absorb additional reactive
power to/from the system if the System Operator so requires as an
ancillary service.
3.5.1 Black Start plants must be put on-line and ready to extend power within
thirty (30) minutes upon receipt of dispatch instruction and can sustain the
operation for at least 12 hours.
3.5.2 Black Start and Fast Start capacity shall be:
3.5.2.1 Sufficient at strategic locations to facilitate the restoration of the
Grid to the normal state following a total System blackout.
3.5.2.2 Available at all times to facilitate the goal of a complete system
restoration in twelve (12) hours.
3.5.3 Redundancy of Black Start generation shall be taken into consideration
due to possibility of unit failure to start or transmission facility failures
preventing units from serving their intended loads.
3.5.4 No more than one (1) unit of a Black Start plant with multiple black start
units may be on planned maintenance at any one time.
3.5.5 When a Generating Unit becomes isolated from the Grid, the speed-
governing system shall provide Frequency Control to the resulting island
Grid (asynchronous control).
3.5.6 There shall be at least 50 MW of black start capability available per
Restoration Highway in Luzon, 20 MW for Visayas and 25MW for
Mindanao. However, the maximum Black Start capability shall be
determined by the System Operator, subject to confirmation by the Grid
Management Committee on an annual basis, taking into account the
technical requirement and financial considerations.
The minimum required level for this Ancillary Service is equivalent to the
Contingency Criterion as shown in Table 1 below as prescribed by the PGC 2016
Edition:
Page 11 of 44
Table 1: Frequency Response Obligation
The level of Secondary Reserve on the hourly basis can be computed as follows:
SR h = F h D x 4.0%
Where:
SR h = Secondary Reserve for the hour "h"
F h D = Forecast Demand for the hour "h"
Note: The 4.0% factor should be the minimum amount and this will be adjusted
depending on the requirement to cater VRE output variability in the Grid.
To meet the Grid requirement, there must be enough Tertiary Reserve in each Grid
at any given time, as established by the System Operator. The minimum required
level for this service shall be equal to the Secondary Reserve required level in a
particular Grid in order to arm/bring back the Secondary Reserve in its required
minimum level 15 minutes after receipt of dispatch instructions. Not more than 50%
of Tertiary Reserve shall be allocated to Interruptible Loads during periods where
Sufficient Reserve capacities are available from generators.
The level of Tertiary Reserve on the hourly basis for a particular Grid can be
computed as follows:
TRAS h = SRAS h
Page 12 of 44
is at maximum during peak and off-peak periods. During peak periods, generators
are made to operate at lagging power factor to produce reactive power. While on
off-peak periods, some generators may be required to operate in leading power
factor to absorb reactive power. As such, the reactive power requirement of the
system can only be determined once the dispatch schedule of the generators is
available. In determining the required Voltage Control Ancillary Service for the
system, the System Operator will use a power system simulator (load flow
software).
4.5.2 The system Operator shall determine regularly the best restoration
highways or sub-grids where there are available contracted BSAS provider.
5.1.1 The following Ancillary Services (AS) will be procured by the National Grid
Corporation of the Philippines (NGCP) from various Service Providers in
the Philippine Grid:
5.1.2 NGCP as the System Operator and mandated by the RA 9136 to secure
the Grid shall procure the following Ancillary Service in the least cost
manner:
Page 13 of 44
secondary price cap for reserves approved by the ERC.
5.2.1.3. The actual synchronization time of black start providers are also
monitored using the Alarm/Event subsystem of the
SCADA/EMS.
SO shall prescribe the level of reserve requirement for each Grid based on
the results of assessment and simulation study and shall update the MO
the level of reserve required by each Grid that will be used on their daily
computation.
Page 14 of 44
5.2.3 Scheduling Protocol
Page 15 of 44
implementation procedure. SO may undertake re-dispatch
procedures in the event of the following conditions:
Figure 5.2.5 below shows the process flow for the trading of Ancillary
Services within the WESM as described in this section.
Page 16 of 44
Figure 5.2.5. Trading Process Flow for Tertiary Reserve Ancillary Service
Page 17 of 44
5.3 Qualification and Testing of Service Providers
Aside from the certification, NGCP requires that all certified providers should have fully
functional direct interface with NGCP's SCADA/EMS. This means that relevant real time
data such as; MW, MVAR, KV, Circuit breaker or unit status and mode of control of the
qualified providers are available at the System Operators control centers. All AS capability
tests shall be conducted by the prospective AS providers to show proof to NGCP their
ability to provide AS. Upon evaluation of the test results, NGCP shall issue a certificate
indicating the type of AS, applicable capacity for AS and its validity. The following AS
capability tests will be conducted for all interested prospective AS providers:
Page 18 of 44
5.3.3 Tertiary Reserve Capability Test
5.3.3.2 On the other hand, Interruptible Loads intending to supply this type of
service should prove that their nominated load demand can be dropped
fifteen (15) minutes after receipt of instruction from the System Operator
and should not re-connect that load until instructed by the System
Operator to do so. Refer to the Ancillary Services Testing, Certification
and Accreditation Procedures (Attachment 2) and Ancillary Services
Standard Technical Requirements (Attachment 3).
5.3.6.1 Certified plants that fail in the capability test should endeavor
Page 19 of 44
to correct the deficiency as required in the PGC, within a reasonable
period of time less than sixty (60) days from the date of the failed
test, otherwise these plants may not be allowed to offer their AS in
that annual period.
5.3.6.2 The System Operator will report to ERC the Service Providers that failed
to rectify the deficiencies of the capability test, within the reasonable
period of sixty (60) days.
5.3.6.3 After the failure of the capability test, follow-up testing should be
conducted by the NGCP on a date agreed with the AS provider. Such
date should fall within sixty (60) days of the written request from NGCP
to rectify the reasons for failure.
5.4.1.1 The System Operator will provide a written exception report where the
monitoring of an AS provider demonstrates a breach in its capability
requirements on two consecutive monitoring instances. Such monitoring
to occur at the discretion of the System Operator but should be a minimum
of once per day, on two consecutive days, where an issue is identified.
5.4.1.3 The AS provider can request in writing to the System Operator a delay of
no more than sixty (60) days before the re-test in order to rectify or replace
any control or other equipment which has caused the failure of the
Page 20 of 44
capability monitoring.
5.4.1.4 Re-testing shall occur, on a date agreed between the System Operator
and the AS provider. The scheduling and payment for AS to this AS
provider can only commence once a successful capability test has been
achieved, and the AS has been successfully re-scheduled under the
normal mechanism for scheduling specified elsewhere in the ASPP or
related documents.
5.5.2 Penalties for non-compliance will be included in the statement of accounts at the
end of the billing period.
5.5.3 The Service Providers receive, evaluate and validate the submitted statement of
account prepared by NGCP-and/or the SO and return it for billing settlement.
5.5.4 NGCP and/or the SO shall submit monthly report on Ancillary Services schedule
to ERC no later than the 15th day of the succeeding month.
6.1 SO shall monitor the compliance of Ancillary Services providers based on the approved
Ancillary Services provider schedule using the SCADA system and available meter data.
Penalties for non-compliance will be included in the statement of accounts at the end of
the billing period.
6.2 The Service Providers receive, evaluate and validate the submitted statement of account
prepared by NGCP-and/or the SO and return it for billing settlement.
7 Transitory Provisions
All approved and existing ASPA shall remain in full force and effect until their termination date,
unless the accredited power plant of the AS Provider cannot comply with the technical
requirements provided in the 2016 PGC. Accordingly, the AS categories of the ASPA will be
converted as follows:
Page 21 of 44
However, the AS Provider with an existing ASPA may opt to renegotiate its offer in a new ASPA
that will be filed to the Honorable Commission for approval.”
8 References
Unless otherwise amended and approved by the ERC, the following references are
relevant to interpreting the terminology used in these ASPP.
1. Electric Power Industry Reform Act of 2001, (EPIRA), Republic Act No. 9136.
2. Philippine Grid Code 2016 Edition.
3. Philippine Distribution Code, December 2001.
4. Wholesale Electricity Spot Market (WESM) Rules, 2002.
5. Open Access Transmission Services (OATS) Rules, 2006.
6. Ancillary Services Cost Recovery Mechanism (ASCRM), September 2006.
7. Guide to Ancillary Services in the National Electricity Market, by Australian Energy Market
Operator
8. Reserve Market Arrangements under Section 3.3 of the WESM Rules, administered by
the Market Operator (MO) and the System Operator (SO).
Page 22 of 44
ATTACHMENT
Page 23 of 44
Attachment 1- Certification of Ancillary Service Providers
1.0 PURPOSE
2.0 SCOPE
2.1 This Attachment covers only the certification process including contracting for
Ancillary Service Providers.
3.1.2 Ancillary Services - As defined in the Grid Code and WESM Rules.
3.2 Acronyms
Page 24 of 44
4.0 REFERENCES
Page 25 of 44
5.0 PROCEDURE
START
Page 26 of 44
FLOWCHART RESPONSIBILITY DETAILS
Test
YES
successful?
NO
Transmission
8 Issuance of Provider 8. Issue Certification to ASP
certificate
Page 27 of 44
FLOWCHART RESPONSIBILITY DETAILS
END
Page 28 of 44
Attachment 2 - Ancillary Service Testing, Certification and
Accreditation
1.0 PURPOSE
To establish the guidelines to be used by NGCP for testing plant for certification to provide
Ancillary Services; and for the Issue of Certification/Accreditation as an Ancillary Service
Provider.
2.0 SCOPE
This procedure covers the testing and certification of Ancillary Services Providers for
Primary Reserve, Secondary Reserve, Tertiary Reserve, Reactive Power Support and
Black Start Ancillary Services as required by the Philippine Grid Code.
Page 29 of 44
Frequency at a pre-established value and/or returning the Frequency to 60Hz
in case the Primary and Secondary Reserve are not adequate or already
exhausted.
3.1.9 Frequency – is the number of complete cycles of a sinusoidal current or voltage
per unit time, usually measured in cycles per second or hertz.
3.1.10 Frequency Control – is a strategy used by the System Operator to maintain
the frequency of the Grid within limits prescribed by the Grid Code by the timely
use of Primary Reserve, Secondary Reserve, and Demand Control.
3.1.11 Generator – is an entity authorized by the Energy Regulatory Commission to
operate a facility used in the generation of electricity.
3.1.12 Power Factor – the ratio of Active Power to Apparent Power.
3.1.13 Primary Response – is the automatic response of a Generating unit to
Frequency changes, released increasingly from zero to five seconds from the
time of frequency change, and which is fully available for the next 25 seconds.
The unit operates in a Governor Control mode at dead band setting within +
0.15 Hz.
3.1.14 Reactive Power – the component of electrical power representing the
alternating exchange of stored energy (inductive or capacitive) between
sources and loads or between systems, measured in VAR or multiples thereof.
For AC circuits or systems, it is the product of the RMS value of the voltage and
the RMS value of the quadrature component of the alternating current. In a
three phase system, it is the sum of the reactive power of the individual phases.
3.1.15 Reactive Power Capability Curve – a diagram which shows the reactive
power capability limit versus the real power within which a generating unit is
expected to operate under normal condition.
3.1.16 Reactive Power Support - the injection or absorption of reactive power from
Generators to maintain Transmission System voltages within ranges prescribed
in the code.
3.1.17 Secondary Reserve Ancillary Service – are capacities from qualified
Generating Units and Energy Storage System that are allocated to restore the
system frequency from the quasi-steady state value as established by the
Primary Reserve back to the nominal frequency of 60 Hz. This type of service
should also be used to provide supply demand balance during small frequency
deviations.
3.1.18 Secondary Response – is the automatic response to frequency change which
is fully available 25 seconds from the time of frequency change to take over
from the Primary Response, which is sustainable for at least 30 minutes.
3.1.19 Toolbox Meeting - a brief meeting done before the start of any activity to give
everyone clarity about what needs to be done and why. It is also a way of
dealing with any issues up front, and of improving teamwork through better (2-
way) communication.
3.1.20 Voltage – the electromotive force or electric potential difference between two
points which causes the flow of electric current in an electric circuit.
3.2 Acronyms
3.2.1 ACC – Area Control Center
3.2.2 ACTO – Assistant Chief Technical Officer
3.2.3 AGC – Automatic Generation Control
3.2.4 ASP – Ancillary Service Provider
3.2.5 ASPP – Ancillary Service Procurement Plan
3.2.6 BS – Black Start
3.2.7 DGS – Day-ahead Generation Schedule
Page 30 of 44
3.2.8 FR – Frequency Regulation
3.2.9 LSO – Luzon System Operations
3.2.10 MSO – Mindanao System Operations
3.2.11 MW – Megawatt
3.2.12 MVAR – Mega Volt-Ampere Reactive
3.2.13 MEX – Maximum Excitation Level
3.2.14 NOD – Network Operations Division
3.2.15 OPS – Operations Planning Section
3.2.16 PF – Power Factor
3.2.17 PQA – Power Quality Analyzer
3.2.18 PR – Primary Reserve
3.2.19 PRH – Power Restoration Highway
3.2.20 RCC – Regional Control Center
3.2.21 RPS – Reactive Power Support
3.2.22 RSO – Regional SO
3.2.23 SR – Secondary Reserve
3.2.24 SCADA – Supervisory Control and Data Acquisition
3.2.25 SO – System Operations
3.2.26 TR – Tertiary Reserve
3.2.27 VSO – Visayas System Operations
5.0 REFERENCES
Page 31 of 44
6.0 PROCEDURE
START
Page 32 of 44
A
2. Recommend Test Head, PNPD 2.1 Review and endorse test plan, applicable
Procedure and Instruction Manual/s and schedule.
Schedule for
Approval
3. Approve the AS Head, RSO 3.1 Head, RSO approve the scheduled AS test.
Test Schedule The office of RSO Head shall provide copy
to ACTO-SO and Head-NOD for
information.
4. Conduct Toolbox Head Engineer/ 4.1 Conduct toolbox meeting with all concerned
Meeting with all Representative- groups with the following agenda:
Concerned ASS Plant-
Groups Operations 4.1.1 Schedule of certification test providing
Grid Dispatcher for the required 7-days lead time and
/Plant Electrical taking into consideration the
Maintenance following:
Engineer 1. Inclusion of the schedule in the
(Other NGCP DGS for non-market based
group concerned operation.
if applicable) 2. For market-based operation,
inclusion of the schedule in the
non-security limits as needed.
3. Final schedule shall have the
concurrence of all parties involved.
Page 33 of 44
B 4.1.4 Minutes of meeting shall be properly
recorded and signed by all parties
involved.
5. Conduct the AS Head Engineer / 5.1 Conduct on-site briefing and discussion on
test Lead Engineer, the basic requirements prior to the AS test
ASS/PNPD/RSO such as:
Plant Operations 5.1.2 Electrical technicians to connect the
Grid Dispatcher PQA.
/Plant Electrical 5.1.3 Other technical diagrams, like Power
Maintenance Capability Curve, etc.
Engineer
5.2 ASS shall decide on the sequence of the
test with confirmation from Plant
Operations and Grid Dispatcher.
1. PR AS Test
2. SR AS Test
3. TR AS Test
4. RPS AS Test
5. BS AS Test
6. Sign initial AS Head, ASS- 6.1 AS Test results shall be signed by the
test result PNPD following:
documents Shift In-Charge, 1. Head Engineer, ASS
Plant 2. Shift-In-Charge, Plant
Others (as may 3. Plant Manager (if present)
be applicable) 4. PNPD Head (if present)
Page 34 of 44
C
8. Prepare final Head Engineer, 8.1 Prepare and submit on the 15th working day
Generator AS ASS/PNPD/RSO after the test, the Plant Ancillary Service
test report tests final report.
YES
End
Page 35 of 44
E
13. Clarify with Head Engineer, 13.1 Discuss the test result with the
Generator the ASS/PNPD/RSO Generator that the AS Technical
Final Report requirements were not met.
YES
15. Request to carry- Generator 15.1 The Generator shall request to carry-out a
out a re-test re-test.
(Repeat task 4 – 8).
Page 36 of 44
Attachment 3 – Ancillary Services Standard Technical
Requirements
Page 37 of 44
Accreditation Testing Compliance Monitoring
Performance
Reserve Type Monitoring Monitoring
Measures Performance Criteria Performance Criteria
Scheme Scheme
Adjustment of power 1. NGCP
Actual dispatch
Capacity factor until voltage EMS/SCAD
capability
correction is achieved A & AS Web
• Continuous
Reactive Power 1. PQ Analyzer
monitoring
Support Service Power Factor within Less than 0.85 pf 2. Plant’s DCS Less than 0.85 pf
• Actual
Reactive Power lagging and less than lagging and less than
Dispatch
Capability Curve 0.90 pf leading 0.90 pf leading
2. Dispatcher’s
E-log
Page 38 of 44
Attachment 4 – Generator Reactive Capability Limitation
Page 39 of 44
Attachment 5 – Sample Computations
Note: These are sample computations for the current ASPAs approved by the Energy
Regulatory Commission. Payment computation may change over time when the ERC
approves a different payment mechanism for new ASPAs.
= ℎ + −
Where:
#
ℎ = ℎ × ! "
#
= $ % × ! +& ' ""( − ) *+ , -
= ℎ +
−
Where:
#
ℎ = ℎ × * ! "
#
= $ % × * ! +& ' ""( − ) *+ , -
Page 40 of 44
Scheduled Capacity (SC), kW = 50,000
Undispatched Capacity, kW = 1,000
Generation (dispatched capacity), kWh = 29,760,000
Non-compliant hours, h = 5
WESM Rate, PhP per kWh = 4.00
SR Rate, PhP per kW per hour = 2.25
Variable Rate, PhP per kWh = 1.50
No. of Hours, h = 744
Undispatched Capacity Payment, PhP = 1,674,000.00
Incidental Energy Payment = 111,600,000.00
WESM Revenue = 119,040,000.00
Penalty (PhP) = 281,250.00
SR Payment (PhP) = 1,392,750.00
. = ℎ + −
Where:
#
ℎ = ℎ × . ! "
#
= $ % × . ! +& ' ""( − ) *+ , -
2
* = /*0 # × * !1 − *
#
Page 41 of 44
Rate, PhP per kVAR per hour = 4.00
No. of Hours, h = 8
Payment, PhP = 640,000.00
Penalty (PhP) = 40,000.00
RPS Payment (PhP) = 600,000.00
Note: For Reactive Power Support, the compensable kVAR is the reactive power provided outside
of the required 0.85pf lagging and 0.90pf leading, but within the generating unit’s capability curve.
Note: For Black Start Service, the sample computation is for those with ASPA approvals on a
“per occurrence” payment basis. True cost of generation is paid only when the Black Start
Service plant is dispatched to re-power the Grid.
Page 42 of 44
Attachment 6 – Tertiary Reserve Interruptible Load
Certification Test
1.0 PURPOSE
1.1 To establish the guidelines that NGCP shall use to test the load to be contracted for
Tertiary Reserve - Interruptible Load that can be interrupted manually.
2.0 SCOPE
2.1 This procedure covers the Tertiary Reserve type of Ancillary Service that qualifies
Interruptible Load through manual load dropping to ensure the provision of capacity
which is necessary to respond manually to unexpected loss of Generating Unit.
3.2 Acronyms
4.1 The single line diagram of the load to be dropped which had been submitted to the
System Operation.
4.2 The load profile of the load being offered as Interruptible Load (Tertiary Reserve).
4.3 System at normal condition.
4.4 Approval from the National/Regional Control Center 7 (seven) days to actual date of
testing.
4.5 Utmost safety is a priority. Abort the test if the conditions will affect the normal
operation of the system.
5.0 REFERENCES
Page 43 of 44
7.0 PROCEDURE
START
4. Activate the trip coil Load Control Initiate activation of trip coil of designated
of the designated Room Operator / circuit breaker remotely or manually.
circuit breaker within Engineer - ASS
30 mins. from receipt
of instruction from
NCC.
5. Record the Engineer - ASS Record the readings of the pick-up frequency
activation time and and the corresponding interrupted load
quantity of load recorded in the PQ analyzer and/or in the
interrupted. digital meter.
END
Page 44 of 44